Reply to Notice of Violation (NRC Investigation Report No. 1-2017-011)
ML18150A274
Person / Time
Site: Pilgrim
Issue date: 05/30/2018
From: Anthony Dimitriadis
NRC/RGN-I/DRP/PB5
To: Brian Sullivan
Entergy Nuclear Operations
Dimitriadis A
References
EA-17-143, OI 1-2017-011
Download: ML18150A274 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSLYVANIA 19406-2713 May 30, 2018 EA-17-143 Mr. Brian Sullivan Site Vice President Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508

SUBJECT:

PILGRIM NUCLEAR POWER STATION - REPLY TO NOTICE OF VIOLATION (NRC INVESTIGATION REPORT NO. 1-2017-011)

Dear Mr. Sullivan:

The U.S. Nuclear Regulatory Commission (NRC) is in receipt of Entergys letter dated March 29, 2018 (ML18117A1631) which responds to our February 27, 2018, letter and NRC Notice of Violation (ML18052B084). That letter cited Entergy for being in violation of a condition of Pilgrims NRC license as specified in the facility technical specifications. Specifically, the letter and Notice of Violation describe the failure to comply with the applicable procedure when Pilgrim staff did not properly implement a surveillance test of the reactor core isolation cooling (RCIC) system on March 27, 2017. The staff performing the RCIC steam line high temperature surveillance test deliberately failed to perform concurrent verification of installation of an electrical connection as required by the procedure to ensure they were manipulating the proper component, resulting in inadvertently isolating the high-pressure coolant injection system and rendering it unavailable for 33 minutes. The NRC will review the implementation of your corrective actions during a future inspection to determine their adequacy and that full compliance has been achieved and maintained.

1 The designation in parentheses refers to an Agencywide Documents Access and Management System (ADAMS) Accession Number. Documents referenced in this letter are publicly available using the Accession Number in ADAMS

B. Sullivan 2 This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Anthony Dimitriadis, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket No. 50-293 License No. DPR-35 cc: Distribution via ListServ

B. Sullivan 3

SUBJECT:

PILGRIM NUCLEAR POWER STATION - REPLY TO NOTICE OF VIOLATION (NRC INVESTIGATION REPORT NO. 1-2017-011) dated May 30, 2018 DISTRIBUTION: (via e-mail)

DPelton, DRP MGray, DRP ADimitriadis, DRP LCline, DRP PBoguszewski, DRP MHardgrove, DRP ECarfang, DRP, SRI BPinson, DRP, RI BBickett, ORA MMcLaughlin, ORA DOCUMENT NAME: G:\DRP\BRANCH5\+++Pilgrim\Pilgrim HPCI isolation NOV Acknowledgment Letter - final.docx ADAMS Accession No: ML18150A274 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/ORA RI/DRP MMcLaughlin via NAME MHardgrove ADimitriadis email DATE 05/09/18 05/17/18 05/30/18

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION I 2100 RENAISSANCE BOULEVARD, SUITE 100 KING OF PRUSSIA, PENNSLYVANIA 19406-2713 May 30, 2018 EA-17-143 Mr. Brian Sullivan Site Vice President Entergy Nuclear Operations, Inc.

Pilgrim Nuclear Power Station 600 Rocky Hill Road Plymouth, MA 02360-5508

SUBJECT:

PILGRIM NUCLEAR POWER STATION - REPLY TO NOTICE OF VIOLATION (NRC INVESTIGATION REPORT NO. 1-2017-011)

Dear Mr. Sullivan:

The U.S. Nuclear Regulatory Commission (NRC) is in receipt of Entergys letter dated March 29, 2018 (ML18117A1631) which responds to our February 27, 2018, letter and NRC Notice of Violation (ML18052B084). That letter cited Entergy for being in violation of a condition of Pilgrims NRC license as specified in the facility technical specifications. Specifically, the letter and Notice of Violation describe the failure to comply with the applicable procedure when Pilgrim staff did not properly implement a surveillance test of the reactor core isolation cooling (RCIC) system on March 27, 2017. The staff performing the RCIC steam line high temperature surveillance test deliberately failed to perform concurrent verification of installation of an electrical connection as required by the procedure to ensure they were manipulating the proper component, resulting in inadvertently isolating the high-pressure coolant injection system and rendering it unavailable for 33 minutes. The NRC will review the implementation of your corrective actions during a future inspection to determine their adequacy and that full compliance has been achieved and maintained.

1 The designation in parentheses refers to an Agencywide Documents Access and Management System (ADAMS) Accession Number. Documents referenced in this letter are publicly available using the Accession Number in ADAMS

B. Sullivan 2 This letter will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely,

/RA/

Anthony Dimitriadis, Chief Reactor Projects Branch 5 Division of Reactor Projects Docket No. 50-293 License No. DPR-35 cc: Distribution via ListServ

B. Sullivan 3

SUBJECT:

PILGRIM NUCLEAR POWER STATION - REPLY TO NOTICE OF VIOLATION (NRC INVESTIGATION REPORT NO. 1-2017-011) dated May 30, 2018 DISTRIBUTION: (via e-mail)

DPelton, DRP MGray, DRP ADimitriadis, DRP LCline, DRP PBoguszewski, DRP MHardgrove, DRP ECarfang, DRP, SRI BPinson, DRP, RI BBickett, ORA MMcLaughlin, ORA DOCUMENT NAME: G:\DRP\BRANCH5\+++Pilgrim\Pilgrim HPCI isolation NOV Acknowledgment Letter - final.docx ADAMS Accession No: ML18150A274 Non-Sensitive Publicly Available SUNSI Review Sensitive Non-Publicly Available OFFICE RI/DRP RI/ORA RI/DRP MMcLaughlin via NAME MHardgrove ADimitriadis email DATE 05/09/18 05/17/18 05/30/18