Proposed Revisions to Tech Spec 4.17 Re Shock Suppressors (Snubbers)
ML18139B281
Person / Time
Site: Surry  Dominion icon.png
Issue date: 04/28/1981
From:
VIRGINIA POWER (VIRGINIA ELECTRIC & POWER CO.)
To:
Shared Package
ML18139B280 List:
References
NUDOCS 8105040173
Download: ML18139B281 (44)


Text

ATTACHMENT 1 PROPOSED TECHNICAL SPECIFICATIONS CHANGE SURRY POWER STATION

PART A EXISTING TECHNICAL SPECIFICATIONS PAGES SURRY POWER STATION

4.17 9 14 76 SHOCK SUPPRESSORS (SNU'B~ERSr Applicability Applies to all hydraulic shock !!;Uppressors (snubbers) wh ch are to protect the reactor coolant

  • * -nELETE Ob To the min:1lnum frequency and to be in Table 4.17-l and 4.17-2.

Specification A.

rs whose seal material has been shall be visually inspected.

shall incl~de but no~ necessa;-ily be limit_ed to, inspect ou of the hydraulic-uid re~ervoir, fluid connections, atld lin ge connections to the pip opera :ility in accordance with the Saubbers

. Found I~perable During Inspection or During Inspection Interval 0

1 2

to verify snubber Inspection Interval 18 Months +/- 25%

12 Months+/- 25%

6 Months +/- 25%

Aeendmene Ne. 2S*

~-

  • .:i:.:

l r~-

t B.

c.

D.

e TS 4.17-2 9 14 76

l. 4 124 Days 5,6, 7 DE.LET!=

62 Days

> 8 31 Days The 1:'equired inspection. interval shall not into twc "inacce ible" based on their accessibility

. + 25%

.+/- 25%

+ 25%

These twc

  • y be inspected the above sch seal ma erial are other than ethylene p1:'opylene or that bas been demonstrated to be compatible with th oper ting environment shall be visually 1nspected

. The initial the date of of e.nter~g be assumed schedule.

days.

6 mcnths from For the purpose hedule. into specific ion 4.17-A, it shall inspection a representative sampl hyd aulic snubbers or approximately 10% of the hydra uubbers, vhi.chever 1s less, shall be functionally test operability including verification of lock-up and bleed *

  • \\meeemene Ne, 25

(

C

(

\\.

Basis

  • TS 4.17-3 9 14 76 For each unit: and subsequent unit found inoperable, an additional 10% or 10 hydralic suubbers shall be so tested until no mere failures are found, or all units ba.ve been Snubbers of rated capacity be functioua.lly tested.

DE.LE"TE snubbers are visually aver.all integrity operability.

verification of proper rientation, 8!Jd proper attachment of of snubber protection.

fnversely with the observed snu operable.snubbers time interval for level constant level interval varies The number of in-Inspections performed a new reference point:

inspection. However, the of such early before the original required t e interval has time less 25%) may not be used t:o leng the Any inspection whose result inspection interval will override the previous sched

.Aaaaclaea& Ne, 2.§

  • '?S 4.17-4 9 14 76 Experience ac operating facilities has shewn that surveillance program should_assure an acceptable performance provided that the seal materials 'are enviro1m1ent.

uELE1\\:

containing seal material which has not ting experience, lab tests or analysi erating enviromnent should be (every month until material compatibl is confirmed or an and moisture conditio molded polyurethane exhibits gr it also may be environments.

at reactor facilities and material

  • in many_ snubber locations. Although resistnace to these conditions, tion in *the higher temperature ail~ble to precisely define Lab tests and experience indicate that seal rily ethylene propylene compounds, which are available, give satisfactory the most severe conditions expect din reactor (l)Repo~ H. R. Erickson, Bergen Paterson to K. R. Goller, October 7, 1974,

Subject:

Hydraulic Shock Sway A+restors

.Aaaariaaa1 He, aJ

( )

g 14 7i to further increase the assurance of snubber reliability, functional tests should be performed once each refueling cycle. These tests vill include stroking of the snubbers to verify proper piston move-ment, lock-up and bleed. Ten percent represents an adequate sample for such tests.

should require testing of additio Those suubbe s designated in Tables 4.17-1 and 4.17-2 radiation reas during shutdown or those espe being in high vas previously 50,000 lb. are because of

'"DE. LETE provided operability capacity greater than testing requirements testing such large uni.ts.

(

(

( **.

e RADIATION CATEGORY e

TS 4.17-6 Q 11 79 H

  • High radiation rea only durin periods of reactor operation.

In acceptable r iation work rea during periods of reactor shutdo'Wtl.

N

  • Acceptable radiati rea during period of both reactor operation and shutdo REMOVAL CATEGORY D
  • Difficult to physical ll -

to changes tted to the NRC as part of size,- large component, lead, jacks necessary n areas should

e PART B PROPOSED TECHNICAL SPECIFICATIONS PAGES SURRY POWER STATION

TS 4.17-1 4.17 SHOCK SUPPRESSORS (SNUBBERS)

Applicability Applies to all hydraulic and mechanical shock suppressors (snubbers) which are required to protect the reactor coolant system and safety related systems.

Objective To specify the minimum frequency and type of surveillance to be applied to the hydraulic snubbers in Tables 4.17-1 and 4.17-2 and the mechanical snubbers in Tables 4.17-3 and 4.17-4.

Specification Each snubber shall be demonstrated operable by performance of the following augmented inservice inspection program and the requirements of

  • specification 4 *. 0.

A.

Visual Inspections

1.

The first inservice visual inspection of snubbers shall be performed after four months but within 10 months of commencing power operation and shall include all snubbers listed in Tables 4.17-1, 4.17-2, 4.17-3 and 4.17-4.

If less than two (2) snubbers are found inoperable during the first inservice visual inspection, the second inservice visual inspection shall be performed 12 months

+/- 25% from the date of the first inspection.

Otherwise, sub-quent visual inspections shall be performed in accordance with the following schedule:

2.

TS 4.17-2 No. Inoperable Snubbers Subsequent Visual per Inspection Period Inspection Pe'riod*

0 18 months +/- 25%

1 12 months +/- 25%

2 6 months +/- 25%

3,4 124 days +/- 25%

5,6,7 62 days +/- 25%*

8 or more 31 days +/- 25%

The snubbers may be categorized into two groups:

Those access-ible and those inaccessible during reactor operation.

Each group may be inspected independently in accordance with the above schedule.

B.

Visual Inspection Acceptance Criteria

1.

Visual inspections shall verify:

a.

That there are no visible indicationiii of. damage or impaired operablity,

b.

Attachments to the foundation or supporting structure are secure, and

c.

In those locations where snubber movement can be manually induced without disconnecting the snubber, that the snubber has freedom of movement and is not frozen up.

  • The inspection interval shall not be lengthened more than one step at a time.

e TS 4.17-3

2.

Snubbers which appear inoperable as a result of visual inspections may be determined operable for the purpose of establishing the next visual inspection interval, providing that the cause of the rejection is clearly established and remedied for that particular snubber and for other snubbers that may be generically susceptible and the affected snubber is functionally tested in the as found condition and determined operable per Specification 4.17-D or 4.17-E, as applicable.

3.

When the fluid port of a hydraulic snubber is found to be uncovered, the snubber shall be determined inoperable and cannot be determined operable via functional testing for the purpose of establishing the next visual inspection interval.

All snubbers connected to an inoperable common hydraulic fluid reservior shall be counted as inoperable snubbers.

C.

Functional Tests

1.

At least once per 18 months during shutdown, a representative sample of 10% of the total of each type of snubber used in the plant shall be functionally tested either in place or in a bench test.

2.

For each snubber that does not meet the functional acceptance criteria of Specifications 4.17-D or 4.17-E, an additional 10%

of that type of snubber shall be functionally tested.

3.

The representative sample selected for functional testing shall include the various configurations, oper~ting environments and the range of size and* capacity of snubbers.

e TS 4.17-4

4.

At least 25% of the snubbers in the representative sample shall include snubbers from the following three categories:

a.

The 'first snubber away from each reactor vessel nozzle

b.

Snubbers within 5 feet of heavy equipment (valve, pump, turbine, motor, etc.)

c.

Snubbers within 10 feet of the discharge from a safety relief valve.

5.

Snubbers identified in Tables 4.17-1, 4.17-2, 4.r7-3 and 4.. 17-4 as "Especially Difficult to Remove" or in "High Radiation Zones.

During Shutdown" shall also be included in the representative sample.* Tables 4.17-1, 4.17-2, 4.17-3 and 4.17-4 may be used jointly or separately as the basis for the sampling plan.

6.

In addition to the regular sample, snubbers which failed the previous functional test shall be retested during the next test period.

If a spare snubber has been installed in place of a failed snubber, then both the failed snubber (if it is repaired and installed in* another po~ition) and the spare snubber. shall be retested.

Test results of these snubbers may not be included for the re-sampling.

7.

Snubbers of rated capacity greater than 50,000 lb. need not be functionally tested.

  • Permanent or other exemptions from functional testing for individual snubbers in these categories may be granted by the Commission only if a justifiable basis for exemption is presented and/or snubber life destructiv~ testing was performed to qualify snubber operability for all design conditions at either the completion of their fabrication or at subsequent date.

e e

TS 4.17-5

8.

If a~y snubber selected for functional testing either fails to lockup or fails to move, i.e., frozen in place, the cause will be evaluated and if caused by manufacturer or design deficiency all snubbers of the same design subject to the same defect shall be functionally tested~

This testing requirement shall be indepen-dent of the requirements stated above for snubbers not meeting the functional test acceptance criteria.

9.

For the snubber(s) found inoperable, an engineering evaluation shall be performed on the components which are supported by snubber(s).

The purpose of this engineering evaluation shall be to determine if the components supported by the snubber(s) were adversely affected by the inoperability of the snubber(s) in order to ensure that the supported component remains capable of meeting the* des*igned service.

D.

Hydraulic Snubbers Functional Test Acceptance Criteria

1.

The hydraulic snubber functional* test shall verify *that:

a.

Activity (restraining action) is achieved within the specified range of velocity or acceleration in both tension and compression.

b.

Snubber bleed, or release rate, where required, is within the specified range in compression and tension.

For snubbers specifically required to not displace under continuous load, the ability of the snubber to withstand load without displace-ment shall be verified.

e TS 4.17-6 E.

Mechanical Snubbers Functional Test Acceptance Criteria

1.

The mechanical snubbers functional test shall verify that:

a.

The force that initiates free movement of the snubber rod in either tension or compression is less than the specified maximum drag force.

Drag force shall not have increased more than 50% since the last functional test.

b.

Activity (restraining action) is achieved within the specified

.range of velocity in both tension and compression.

c.

Snubber release rate, where required, is within the specified range in compression and tension.

For snubbers specifically required not to displace under continuous load, the ability of the snubber to withstand load without displacement shall be verified.

F.

Snubber Service Life Monitoring

1.

A record of the service life of each snubber, the date at which the designated service life comlliences and the installation and maintenance records on which the designated service life is based shall be maintained as required by Specification 6.5.B.9.

2.

Concurrent with the first inservice visual inspection and at least once per 18 months thereafter, the installation and maintenance records for each snubber listed in Tables 4.17-1, 4.17-2, 4.17-3 and 4.17-4 shall be reviewed to verify that the indicated service life has not been exceeded or will not be exceeded prior to the next scheduled snubber service life review.

If the indicated service life will be

Bases TS 4.17-7.

exceeded prior to the next scheduled snubber service life review, the snubber service life shall be reevaluated or the snubber shall be replaced or reconditioned so as to extend its service life beyond the date of the next scheduled service life review.

This reevaluation, replacement or reconditioning shall be indicated in the records.

All snubbers are required operable to ensure that the structural integri-ty of the reactor coolant system and all other safety-related systems is maintained during and following a seismic or other event initiating dynamic loads.

Snubbers excluded from this inspection program are those installed on nonsafety-related systems and then only if their failure or failure of the system on which they are installed would have no adverse effect on any safety-related system.

The visual inspection frequency is based upon maintai~ing a constant level of snubber protection to systems.

Therefore, the required inspec-tion interval varies inversely with the observed snubber failures and is determined by the number of inoperable snubbers found during an inspec-tion.

Inspections performed before that interval has elapsed may be used as a new reference point to determine the next inspection.

However1 the results of such early inspections performed before the original required time interval has elapsed (nominal time less 25%) may not be used to lengthen the required inspection interval.

Any inspection ~hose results require a shorter inspection interval will override the previous schedule.

TS 4.17-8 When the cause of the rejection of a snubber is clearly established and remedied for that snubber and for any other snubbers that may be gener-ically susceptible, and verified by inservice functional testing, that snubber may be exempted from being counted as inoperable.

Generically susceptible snubbers are those which are of a specific make or model

_____________________ and have the same design features directly relate~ __ to rejection of the snubber by visual inspection, or are similarly located or exposed to the same environmental conditions such as temperature, radiation, and vibra-tion.

When a snubber is found inoperable, an engineering evaluation is per-formed, in addition to the determination of the snubber mode of failure, in order to determine if any safety-related component or system has been adversely affected by the inoperability of the snubber.

The engineering evaluation shall determine whether or not the snubber mode of failure has imparted a significant effect or degradation on the supported component or-system.

To provide assurance of snubber functional relaibility, a representative sample of the installed snubbers will be functionally tested during plant shutdowns at 18 month intervals.

Observed failures of these sample snubbers shall require functional testing of additional units.

Hydraulic snubbers and mechanical snubbers may each be treated as a different entity for the above surveillance programs.

TS 4.17-9 The service life of a snubber is evaluated via manufacturer input and information'through consideration of the snubber service conditions and associated installation and maintenance records (newly installed snubber, seal replaced, spring replaced, in high radiation area, in high tempera-ture area, etc...

).

The requirement to monitor the snubber service life is included to ensure that the snubbers periodically undergo a performance evaluation in view of their age and operating conditions.

These records will provide statistical bases for future consideration of snubber service life.

The requirements for the maintenance of records and the snubber service life review are not intended to affect plant operation.

TS 4.17-10 LEGEND Accessibility Category A= Accessible I= Inaccessible Radiation Category H = High radiation area only during periods of reactor operation.

In acceptable radiation work area during period of reactor shutdown.

N = Acceptable radiat_ion work area during periods of reactor operation and shutdown.

Removal Category D = Expecially difficult to remove R = *Can be removed

  • Snubbers may be added to and deleted from safety related systems without prior License Amendment to Tables 4.17-1, 4.17-2, 4.17-3 and 4.17-4 provided that a revision to Tables 4.17-1, 4.17-2, 4.17~3 and 4.17-4 is included in the next License Amendment request.
    • Modifications to the "Radiation Category" column due to changes in high radiation areas may be made without prior License Amendment provided that a revision to Tables 4.17-1, 4.17-2, 4.17-3 and 4.17-4 is includ~d with the next License Amendment request.

I TABLE 4.17-1 UNIT #1 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL e SYSTEM HARIC HO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY Main Steam 1-SHP-HSS-IA 5"

5" Mech. Equip. Room-Service Bldg.

FP-IB A

N D

Hain *steam 1-SHP-HSS-IB 5"

5" Mech. Equip. Room-Service Bldg.

FP-IB A

N D

Main Steam 1-SHP-HSS-2A 5"

5" Steam Line From A Generator At Top Of Crane Wall FP-lA I

H D

Hain Steam 1-SHP-H9S-2B 5"

5" Steam Line From A Generator At Top Of Crane Wall FP-lA-I H

D Main Steam 1-SHP-HSS-3A 3-\\"

5" Steam Line From A Generator At Top Of Crane Wall FP-IA I

H D

Main Steam 1-SHP-HSS-3B 3-\\"

5" Steam Line From A Generator At Top Of Crane Wall FP-lA I

H D

Main Steam 1-SHP-HS6-4A 3-\\"

5" Steam Line From A Generator At.Top Of Crane Wall FP-lA I

H D

Main Steam 1-SHP-HSS-4B 3-\\"

5" Steam Line From A Generator

  • At Top Of Crane Wall FP-lA I

H D

Hain Steam 1-SHP-HSS-5A 2-\\"

5" Steam Line From A Generator At Top Of Crane Wall FP-lA

,I H

D Main Steam 1-SHP-HSS-5B 2-\\"

5" Steam Line From A Generator At Top Of Crane Wall FP-lA

I H

D Hain Steam 1-SHP-HSS-6A 2-\\"

5" Steam Line* From A Generator At rop Of Crane Wall FP-lA I

H D

Main Steam 1-SHP-HSS-6B 2-\\"

5" Steam Line From A Generator At Top Of Crane Wall FP-lA I

H D

Main Steam l-SHP-HSS-7 8"

5" Steam Line From A Generator H

C/J At Top Of Crane Wall FP-lA I

H D

Main Steam 1-SHP-HSS-8 8"

5" Steam Line From A Generator

+'"

At Top Of Crane Wall FP-IA I

H D

1--'

Hain Steam 1-SHP-HSS-9 10" 5"

C Main Steam Line FP-lA

  • 1 H

D

-..J I

1--'

1--'

I TABLE 4.17-1 UNIT f/1 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL -

SYSTEM HARK NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY Hain Steam 1-SHP-HSS-10 10" 5"

C Hain Steam Line FP-lA I

H D

Hain Steam 1-SHP-HSS-11 8"

5" B Hain Steam Top Of CW

(

FP-lA I

H D

Hain Steam 1-SHP-HSS-12 8"

5" B Hain Steam Top Of CW FP-lA I

H D

Hain Steam l-SHP-HSS-13A 4"

5" B Hain Steam Top Of CW FP-lA I

H D

Hain Steam 1-SHP-HSS-14A 5"

5" Mech. Equip. Room-Service Bldg.

FP-1B A

N D

Hain Steam 1-SHP-HSS-14B 5"

5" Mech. Equip. Room-Service Bldg.

FP-lB A

N D

Hain Steam 1-SHP-HSS-15 4"

5" Safeguards FP-lB A

N D

Hain Steam l-SHP-HSS-16 4"

5".

Safeguards FP-lB A

N D

Hain Steam l-SHP-HSS-17 4"

5" Safeguards' FP-IB A

N D

Hain Steam 1-SHP-HSS-18 4"

5" Safeguards FP-lB A

N D

Hain Steam 1-SHP-HSS-19 4"

5" Safeguards FP-lB A

N D

Hain Steam 1-SHP-HSS-20 4"

5" Safeguards FP-lB A

N D

Hain Steam l-SHP-HSS-21 4"

5" Mech.. Equip. Room-Service Bldg.

FP-IB A

N D

Hain Steam i-SHP-HSS-22 4"

5" Hech. Equip. Room-Service Bldg.

FP-lB A

N D

Hain Steam l-SHP-HSS-23 4"

5" Mech. Equip. Room-Service Bldg.

FP-lB A

N D

Hain Steam 1-SHP-HSS-24 4"

5" Hech. Equip. Room-Service Bldg.

FP-1B A

N D

Hain Steam

  • l*SHP-HSS-25 4"

5" Mech. Equip. Room-Service Bldg.

FP-1B A

N D

e Hain Steam l-SHP-HSS-26 4"

5" Hech. Equip. Room-Service Bldg.

FP-IB A

N D

Hain Steam 1-SHP-HSS-27 6"

5" Safeguards, FP-lB A

N D

Hain Steam 1-SHP-HSS-28 6"

5" Safeguards.

FP-lB A

N D

~

Hain Steam 1-SHP-HSS-29 6"

5" Safeguards FP-1B A

N D

C/J Hain Steam l-SHP-HSS-30 6"

5" Safeguards FP-1B A

N D

+'

Hain Steam 1-SHP-HSS-31 6"

5" Safeguards, FP-lB A

N D

Hain Steam 1-SHP-HSS-32 6"

5" Safeguards*

FP-lB A

N D

Hain Steam l-SHP-HSS-33A 6"

5" Safeguards FP-IB A

N D

I N

TABLE 4.17-1 UNIT #1 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL e SYSTEM HARK NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY Hain*Steam 1-SHP-HSS-33B 6"

5" Safeguards FP-IB A

N D

Hain Steam l-SHP-HSS-34A 6"

5" Safeguards FP-1B A

N D

Hain Steam 1-SHP-HSS-34B 6"

5" Safeguards FP-1B A

N D

Hain Steam 1-SHP-HSS-35A 6"

5" Safeguards FP-IB A

N D

Hain Steam 1-SHP-HSS-35B 6"

5" Safeguards FP-lB A

N D

I Hain Steam l-SHP-HSS-36 1-\\"

6" (11 Safeguards Ground Level Later A

N D

Hain Steam 1-SHP-HSS-37 1-\\"

6" ill Safeguards* Ground Level Later A

N D

Hain Steam 1-SHP-HSS-38 1-\\"

6" Ill Safeguards Ground Level Later A

N D

Hain Steam 1-SHP-HSS-39 1-\\"

6"

  1. 1 Safeguards Ground Level Later A

N D

Hain Feed 1-WFPD-HSS-1 2-\\"

5" Feed Line For A Gen. On Crane Wall FP-2A I

H D

Hain Feed 1.:.WFPD-HSS-2 2-\\"

5" Feed*Line For A Gen. On Crane Wall FP-2A I

H D

Hain Feed 1-WFPD-HSS-3 2-\\"

5" Feed Line For A Gen. On Crane Wall FP-2A I

H D

Hain Feed 1-WFPD-HSS-4 2-\\"

5" Feed.Line For A Gen. On Crane Wall FP-2A I

H D

Hain Feed 1-WFPD-HSS-6 2-\\"

5" Feed Line For A Gen. On Crane Wall FP-2A I

H D

Hain Feed 1-WFPD-HSS-8 2-\\"

5" Containment Operating Level FP-2A I

H D

Hain Feed 1-WFPD-HSS-9 2-\\"

5" Containment Operating Level FP-2A I

H D

Hain Feed

  • 1-WFPD-HSS-10 2-\\"

5" Containment Operating Level FP-2A I

H D --

Hain Feed 1-WFPD-HSS-11 2-\\"

5" Containment Operating Level FP-2A

  • I H

D Hain Feed 1-WFPD-HSS-12 2-\\"

5" Containment Operating Level FP-2A I

H D

Hain Feed 1-WFPD-HSS-13 2-\\"

5" Containment Operating Level FP-2A I

H D

Hain Feed 1-WFPD-HSS-14 2-\\"

5" Containment Operating Level FP-2A I

H D

t-'3 Hain Feed 1-WFPD-HSS-15 2-\\"

5" Containment Operating Level FP-2A I

H D

en Hain Feed 1-WFPD-HSS-16 2-\\"

5" Containment Operating Level FP-2A I

H D

~

Hain Feed 1-WFPD-HSS-17 2-\\"

5" Containment El. 45' Left of Pe~sonnel Hatch FP-2A I

H R

-..J I....

l,)

TABLE 4.17-1 UNIT 111 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEH HARK NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY

~*

Hain Feed l-WFPi>-HSS-18 2-\\"

5" 111 Safeguards First Level From Ground Later A

N D

Hain Feed l-WFPD-Hss...:19 3-\\"

5" f}l Safeguards First Level From Ground Later A

N D

Hain Feed l-WFPD-HSS-20 3-\\"'

5" f}l Safeguards First Level From Ground Later A

N D

Hain Feed l-WFPD-HSS-21 2-\\"

5"

{}1 Safeguards First Level From Ground Later A

N D

Hain Feed l-WFPD-HSS-22 3-\\"

5" Ill Safeguards First Level From Ground Later A

N D

Auxiliary Feed l-WAPD-HSS-140 1-\\"

6" Containment Operating Level FP-2B A

H R

Auxiliary Feed l-WAPD-HSS-141A 1-\\"

6" Containment Operating Level FP-2B A

H R

Auxiliary Feed

- l-WAPD-HSS-141B 1-\\"

6" Containment Operating Level Later A

N R

Auxiliary Feed l-WAPD-HSS-142 1-\\"

6" Containment'Operating Level Later A

N R

Auxiliary Feed l-WAPD-HSS-143A 1-\\"

6" Containment Operating Level Later A

N R

Auxiliary Feed l-WAPD-HSS-143B 1-\\"

6" Containment Operating Level Later A

N R

Auxiliary Feed l-WAPD-HSS-144 1-\\"

6" Ill Safeguards "A" Aux. FW Pump Later A

N R

Auxiliary Feed l-WAPD-HSS-145 1-\\"

6" f}l Safeguards "B" Aux. FW Pump Later A

N R

Auxiliary Feed l-WAPD-HSS-146 1-\\"

6" (Jl'Safeguards "B" Aux. FW Pump Later A

N R

Auxiliary Feed 1-WAPD-HSS-147 1-\\"

6" lll Safegua1;ds "B" Aux. FW Pump Later A

N R

Auxiliary Feed 1-WAPD-HSS-148 1-\\"

6" lll Safeguards "C" Aux. FW Pump Suction Beneath Floor Later A

N R

Auxiliary Feed 1-WAPD-HSS-149 1-\\"

6"

  1. 1 S'Bfeguards First Level From Ground Later A

N R

Reactor Coolant l-RC-HSS-101 1-\\"

6" Pressurize~ Room Relief Line FP-9E I

H D

Reactor Coolant l-RC-HSS-102 1-\\"

6" Basement Ov:erhead-Spray Line FP-9E I

H D

Reactor Coolant l-RC-HSS-103 1-\\"

6" Basement Overhead-Spray Line FP-9E I

H D

Reactor Coolant 1-RC-HSS-104 1-\\"

6" Basement Overhead-Spray Line FP-9E I

H D

1-j Reactor Coolant l-RC-HSS-105 1-\\"

6" Basement Overhead-Spray Line FP-9E I

H D

Cl)

Reactor Coolant 1-RC-HSS-106 1-\\"

6" Basement Overhead-Spray Line FP-9E I

H D

.i:-,

Reactor Coolant l-RC-HSS-107 1-\\"

6" Basement Overhead-Spray Line FP-9E I

H D

f--'

Reactor Coolant l-RC-HSS-108 1-\\"

6" Basement Overhead-Spray Line FP-9E I

H D

'1 I

f--'

.i:-,

TABLE 4.17-1 UNIT Ill SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL e

  • ~

HARK NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY Reactor Coolant 1-RC-HSS-109 1-\\"

6" Pressurizer Room Relief Line FP-9E I

H D

Reactor Coolant 1-RC-HSS-110 1-\\"

6" Pressurizer Room Relief Line FP-9E I

H D

Reactor Coolant 1-RC-HSS-111 1-\\"

6" Pressurizer Room Relief Line FP-9E I

H D

Reactor Coolant 1-RC-HSS-112 1-\\"

6" Pres~urizer Room Relief Line FP-9E I

H D

Reactor Coolant 1-RC-HSS-113 1-\\"

6" Pressurizer Room Relief Line FP-9E I

H D

Reactor Coolant 1-RC-Hss..:114 1-\\"

6" Pressurizer Room Relief Line FP-9E I

H D

Reactor Coolant 1-RC-HSS-115 1-\\"

6" Pressurizer Room Relief Line FP-9E I

H D

Reactor Coolant 1-RC-HSS-116 1-\\"

6" Containment.. "C" Cubicle Under Grating Behind RC Pump Later I

H D

Reactor Coolant l-RC-HSS-117 1-\\"

6" Containment "C" Cubicle Under Grating Behind RC Pump Later I

H D

Reactor Coolant 1-RC-HSS-118 1-\\"

6" Pressurizer Room Relief Line FP-9E I

H D

Reactor Coolant 1-RC-HSS-119 1-\\"

6" Pressurizer Room Relief Line FP-9E I

H D

Reactor Coolant l-RC-HSS-120 1-\\"

6" Pressurizer Room Relief Line FP-9E I

H D

Reactor Coolant l-RC-HSS-121 1-\\"

6" Pressurizer *Room Relief Line FP-9E I

H D

Reactor Coolant l-RC-HSS-122 6"

4" Pressurizer Upper Support FM-52B I

H D

Reactor Coolant 1:-RC-HSS-123 6"

4" Pressurizer Upper Support FM-52B I

H D

Reactor Coolant 1-RC-HSS-124 6"

4" Pressurizer Upper Support FM-52B I

H D

e Reactor Coolant 1-RC-HSS-125 6"

4" Pressurizer 'Upper Support FM-52B I

H D

Reactor Coolant 1-RC-HSS-126 4"

5" B-P Snubber *"A" RCP Holding Assembly FM-53A I

H D

Reactor Coolant 1-RC-HSS-127 4"

5" B-P Snubber "A" RCP Holding Assembly FM-53A I

H D

t--3 Reactor Coolant,

l-RC-HSS-128 4"

5" B-P Snubber "A" RCP Holding Assembly FM-53A I

H D

en

.i:-

Reactor Coolant 1-RC-HSS-129 4"

5" B-P Snubber '."A" RCP Holding Assembly FM-53A I

H D

1--'

Reactor Coolant l-RC-HSS-130 4"

5" B-P Snubber "B" RCP Holding Assembly FM-53A I

H D

Reactor Coolant 1-RC-HSS-131 4"

5" B-P Snubber "B" RCP Holding Assembly FM-53A I

H D

I 1--'

Reactor Coolant 1-RC-HSS-132 4"

5" B-P Snubber "B" RCP Holding Assembly FM-53A I

H D

V1 Reactor Coolant 1-RC-HSS-133 4"

5" B-P Sriubber UB" RCP Holding Assembly FM-53A I

H D

TABLE 4.17-1 UNIT Ill SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL e

SYSTEM HARK NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY I

Reactor Coolant 1-RC-HSS-134 4"

S" B-P Snubber "C" RCP Holding Assembly FH-53A

!I H

D Reactor Coolant 1-RC-HSS-135 4"

S" B-P Snubber "C" RCP Holding Assembly FH-53A I I H

D I

Reactor Coolant 1-RC-HSS-136 4"

S" B-P Snubber "C" RCP Holding Assembly FH-53A i I H

D Reactor Coolant 1-RC-HSS-137 4"

S" B-P Snubber "C" RCP Holding Assembly FH-53A

I H

D Reactor Coolant 1-RC-HSS-138 12" S"

"A" S/G Upper Restraint Casting Snubber FH-SlG

,J H

D Reactor Coolant 1-RC-HSS-139 12" S"

"A" S/G Upper Restraint Casting Snubber FH-SlG

. I H

D Reactor Coolant 1-RC-HSS-140 12" S"

"A" S/G Upper Restraint Casting Snubber FH-516

.I H

D Reactor Coolant 1-RC-HSS-141 1211 S"

"A" S/G Upper Restraint Casting Snubber FH-516

.I H

D Reactor Coolant 1-RC-HSS-142 12" S"

"B" S/G Upper Restraint Casting Snubber FH:.SlG 1

H D

Reactor Coolant 1-RC-HSS-143 12" S"

"B" S/G Upper Restraint Casting Snubber FH-516

I H

D Reactor Coolant 1-RC-HSS-144 12" S"

"B" S/G Upper Restraint Casting Snubber FH-SlG

  • 1 H

D Reactor Coolant l-RC-HSS-145 12" S"

"B" *s/G Upper Restraint Casting Snubber

- FH-516

  • I H

D Reactor Coolant 1-RC-HSS-146 12" 5"

ncn S/G Upper Restraint Casting Snubber FH-516 I

H D

Reactor Coolant 1-RC-HSS-147 t'2" 5"

"C" S/G Upper Restraint Casting Snubber FM-SIG I

H D

Reactor Coolant l-RC-HSS-148 12" 5"

"C" S/G Upper Restraint Casting Snubber FH-516 I

H D

Reactor Coolant 1-RC-HSS-149 12" 5"

ncn S/G Upper Restraint Casting Snubber FH-51G

  • 1 H

D Reactor Coolant 1-RC-HSS-150 12" 5"

"A" S/G Lower Support Ring FH-51G I

H D

e Reactor Coolant l-RC-HSS-151 12" 5"

"A" S/G Loier Support Ring FH-516 I

H D

Reactor Coolant 1-RC-HSS-152 12" 5"

"A" S/G Lower Support Ring FH-51G I

H D

Reactor Coolant l-RC-HSS-153 12" 5"

"A" *S/G Lower Support Ring FH-51G I

H D

Reactor Coolant 1-RC-HSS-154 12" 5"

"B" S/G Lower Support Ring FM-516 I

H D

~

Reactor Coolant' 1-RC-JiSS-155 12" 5"

IIB" S/G Lower Support Ring FH-51G I

H D

C/l Reactor Coolant l-RC-HSS-156 12" 5"

"B" S/G Lower Support Ring FM-516

.I H

D

.p.

Reactor Coolant 1-RC-HSS-157 12" 5"

"B" S/G Lower Support Ring FM-516 I

H D

Reactor Coolant 1-RC-HSS-158 12" 5"

"C" S/G Lower Support Ring FM-516 I

H D

I-'

-..J I

I-'

(j\\

TABLE 4.17-1 UNIT /11 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEM HARK NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY Reactor Coolant 1-RC-HSS-159 1211 5"

"C" _S/G Lower Support Ring FK-510 I

H D

Reactor Coolant 1-RC-HSS-160 12" 5"

ncn S/G Lower Support Ring FK-510 I

H D

Reactor Coolant 1_-RC-HSS-161 12" 5"

"C" S/G Lower Support Ring FK-510 I

H D

Reactor Coolant 1-RC-HSS-162 1211 5"

"A" RCP Lower Support Beam FK-53A I

H D

Reactor Coolant 1-RC-HSS-163 12" 5"

"A" RCP Lower Support Beam FK-53A I

H D

Reactor Coolant 1-RC-HSS-164 1-\\"

6" "A" Loop Room Overhead Later I

H D

Reactor Coolant 1-RC-HSS-165 1-\\"

6" "A'.v Loop Room Overhead Later I

H D

Reactor Coolant

  • 1-RC-HSS-166 1211 5"

"B'.' RCP Lo~er Support Beam FK-53A I

H D

Reactor Coolant 1-RC-HSS-167 12" 5"

"B" RCP.Lower Support Beam Ftf-53A I

H D

Reactor Coolant 1-RC-HSS-168 1-\\"

6" "B" Loop Room Overhead Later I

H D

Reactor Coolant 1-RC-HSS-169 1-\\"

6" HD" Loop Room Overhead Later I

H D

Reacto_r Coolant 1-RC-HSS-170 12" 5"

"C" RCP Lower Support Beam FK-53A I

I.I D

Reactor Coolant 1-RC-HSS-171 12" 5"

"C"*RCP Lower Support Beam FK-53A I

H D

Reactor Coolant 1-RC-HSS-172 4-\\"

2" "A" S/G Upper Support Snubber Bolt FK-51Q I

H D

Reactor Coolant 1-RC-HSS-173 4-\\"

2" "A" S/G Upper Support Snub_ber Bolt FK-51Q I

H D

Reactor Coolant 1-RC-HSS-174 4-\\"

2" "B"-S/G Upper Support Snubber Bolt Ftf-51Q

I H

D Reactor Coolant 1-Rc-uss.: 175 4-\\"

2" "B" S/G Upper Support Snubber Bolt FK.;51Q I

H D

e Reactor Coolant l-RC-HSS-176 4-\\"

2" "B" S/G Upper Support Snubber Bolt FK-51Q I

H D

Reactor Coolant 1-RC-HSS-177 4-\\"

2" "B" S/G Upper Support Snubber Bolt Later I

H D

Reactor Coolant 1-RC-HSS-178 4-\\"

2" "BID S/G Upper Support Snubber Bolt FK-5IQ I

H D

Reactor Coolant 1-RC-HSS-179 4-\\"

2" "B" S/G Upper Support Snubber Bolt FK-51Q I

H D

~

Cl)

Reactor Coolant.

1-RC-HSS-180 4-\\"

2" ncn S/G Upper Support Snubber Bolt FK-51Q I

H D

Reactor Coolant 1-RC-HSS-181 4-\\"

2" "C" S/G Up_per Support Snubber Bolt FK-51Q I

H D

+'

Reactor Coolant 1-RC-HSS-182 4-\\"

2" "C" S/G Upper Support Snubber Bolt FM-51Q I

H D

f-'

Reactor Coolant l-RC-HSS-183 4-\\"

2" "C" S/G Upper Support Snubber Bolt FM-51Q I

H D

-..J.

I f-'

-..J

TABLE 4.17-1 UNIT {II SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEM HARK HO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY e Low Head Safety Containment Basement Hear "A" Injection 1-SI-HSS-19A 5"

5" Accumulator FP-llA I

H D

Low Head Safety Containment Basement Near "A" Injection 1-SI-HSS-19B 5"

5" Accumulator FP-llA I

H D

Low Head Safety Containment Basement Near "A" Injection 1-SI-HSS-20 8"

5" Accumulator FP-llA I

H D

Low Head Safety Containment Basement Near "A" Injection 1-SI-HSS-21A 4"

5" Accumulator FP-llA I

H D

Low Head Safety Containment Basement Near "A" Injection 1-SI-HSS-21B 4"

5" Accumulator FP-llA I

H D

Low Head Safety Containment Basement Near "B" Injection l-SI-HSS-22A 5"

5" Accumulator FP-llA I

H D

Low Head Safety Containment Basement Near "B" Injection 1-SI-HSS-22B 5"

5" Accumulator FP-llA I

H D

Low Head Safety Containment Basement Near "B" Injection 1-SI-HSS-23 8"

5" Accumulator FP-llA I

H D

Low Head Safety Containme~t Basement Near "B" Injection 1-SI-HSS-24A 4"

5" Accumulator FP-llA I

H D

Low Head Safety Containment Basement Near "B" e

Injection 1-SI-HSS-24B 4"

5" Accumulator FP-llA I

H D

Low Head Safety Containment Basement Near "C" Injection 1-SI-HSS-25 8"

5" Accumulator FP-llA I

H D

t-3 Low Head Safety Containment Basement Near "C" Ul Injection l-SI-HSS-26 8"

5" Accumulator FP-llA I

H D

+'"

Low Head Safety Containment Basement Near "C" I-'

Injection 1-SI-HSS-27A 4"

5" Accumulator FP-llA I

H D

-..J Low Head Safety Containment Basement Near "C" I

I-'

Injection 1-SI-HSS-27B 4"

5" Accumulator FP-llA I

H D

00 Low Head Safety Containment Basement Outer Wall Injection 1-SI-HSS-28 1-\\"

6" Near Sump Later I

H D

TABLE 4.17-1 UNIT Ill SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEH HARIC NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY Low Head Safety Injection 1-SI-HSS-100 1-\\"

6" Valve Pit Second.Level FP-60G A

H D

Low Head Safety Injection l-SI-HSS-101 1-\\"

6" Valve Pit Second Level FP-60G A

H D

Low Head Safety.

Injection l-SI-HSS-84 1-\\"

6"

~afeguards Basement FP-5D A

H D

Low Head Safety Injection 1-SI-HSS-86 1-\\"

6" Safeguards Basement FP-5D A

H D

Recirc. Spray 1-RS-HSS-101 1-\\"

6" Containment Aonulus-3' Level FP-13H I

H D

Recirc. Spray 1-RS-HSS-102 1-\\"

6" Containment Aonulus-3' Level FP-13H I

H D

Recirc. Spray l-RS-HSS-103 1-\\"

6" Containment Annulus-3' Level FP-13H I

H D

Recirc. Spray l-RS-HSS-104 1-\\"

6" Containment Annulus-3' Level FP-13H I

H D

Recirc. Spray l-RS-HSS-105 1-\\"

6" Containment Basement Wall Near Sump Later I

H D

Recirc. Spray 1-RS-HSS-106 1-\\"

6" Containment El. 90' in Annulus Outside Pressurizer Later I

H D

Recirc. Spray l-RS-HSS-107 3-\\"

6" Valve Pit Second Level Later A

N D

Coot. Spray l-CS-HSS-01 1-\\"

6"

  1. 1 Safeguards Ground Level on Overhead Later A

N D

Chem. & Vol. Cont.

l-CH-HSS-301 1-\\"

6" Aux. Bldg. '.'C" Charging Pump Cubicle FP-lOZ A

H D

e Chem. & Vol. Coot.

l-CH-HSS-302 1-\\"

6" Aux. Bldg. "C" Charging Pump Cubicle FP-IOZ A

H D

Resi. Heat Remov.

1-RH-HSS-l 2-\\"

5" Containment,, RHR Flat, RHR Pump Support FP-12D I

H D

Resi. Heat Remov.

l-RH-HSS-2 2-\\"

5" Containment, RHR Flat, RHR Pump Support FP-12D I

H D

t-3 C/J Resi. Heat Remov.

l-RH-HSS-3 2-\\"

5" Coot_aioment, RHR Flat, RHR Pump Support FP-12D I

H D

Resi. Heat Remov.

l-RH-HSS-4 2-\\"

5" Containment, RHR Flat, RHR Pump Support FP-12D I

H D

~

Resi. Heat Remov.

l-RH-HSS-5 2-\\"

5" Cootainmeot*Top of RHR HX's A&B FP-12D I

H D

I-"

Resi. Heat Remov.

l-RH-HSS-6 2-\\"

5" Containment.Top of RHR HX's A&B FP-12D I

H D

-...J I

I-"

\\0

TABLE 4.17-l SYSTEM HARK NO.

Resi. Heat Remov.

1-RH-HSS-7 Resi. Heat Remov.

1-RH-HSS-8 ResL Heat Remov.

1-RH-HSS-9 Resi. Heat Remov.

1-RH-HSS-10 Resi. Heat Remov.

1-RH-HSS-11 Resi. Heat Remov.

1-RH-HSS-12 Resi. Heat Remov.

1-RH-HSS-13 Resi. Heat Remov.

1-RH-HSS-14 Resi. Heat Remov.

1-RH-HSS-15 Resi. Heat Remov.

1-RH-HSS-17 Resi. Heat Remov.

1-RH-HSS-18 Resi. Heat Remov.

1-RH-HSS-19 Resi. Heat Remov.

1-RH-HSS-20 Resi. Heat Remov.

1-RH-HSS-21 Resi. Heat Remov.

1-RH-HSS-22 SIZE STROKE 2-\\"

5" 2-\\"

5" 1-\\"

6" 1-\\"

6" 1-\\"

6" 1-\\"

6" 1-\\"

6" 1-\\"

6" 1-\\"

6" 1-\\"

6" 1-\\"

6" 1-\\"

6" 1-\\"

6" 1-\\"

6" 1-\\"

6" UNIT Ill SUPPRESSOR DATA GENERAL LOCATION Containment Top of RHR HX's A&B Containment Top of RHR HX's A&B Containment, RHR Flat, RHR Pump Disch. Line Containment, RHR Flat, RHR Pump Disch. Line Containment, RHR Flat, RHR-Pump Disch. Line Containment, RHR Pump Suction, Basement Containment, RHR Pump Suction, Basement Containment, RHR Pump Suction, Basement Containment, RHR Flat, Outlet Of "B" IIX Containment, "A" Loop Room Near HOV 1700 Containment, "A" Loop Room Near HOV 1700 Containment, RHR Flat, Near HOV 1701 Containment, RHR Flat, Near HOV 1701 Containment, Basement Near HOV 1720 A&B Containmen~, Basement Near HOV 1720 A&B PRINT (11448-)

FP-12D FP-12D FP-12D FP-12D FP-12D FP-12D FP-12D FP-12D FP-12D FP-12D FP-12D FP-12D FP-12D FP-12&

FP-12&

ACCESS!-

BILITY CATEGORY I

I I

I I

I I

I I

I I

I I

I I

RADIATION REMOVAL CATEGORY CATEGORY H

D H

D H

D H

D H

D H

D H

D H

D H

D H

D H

D H

D H

D H

D H

D 00

~

I-'

I N

0

TABLE 4.17-1 UNIT Ill SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL

~

tfARK NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY Resi. Heat Remov.

1-RH-HSS-23 1-\\"

6" Containment, Basement Near HOV 1720 A&B FP-I2E I

H D

Resi. Heat Remov.

1-RH-HSS-24 1-\\"

6" Containment, Basement Under RHR Flat FP-12E I

H D

On Return Line Resi. Heat Remov.

1-RH-HSS-25 1-\\"

6" Containment, Basement Under RHR Flat FP-I2E I

H D

On Return Line Resi. Heat Remov.

1-RH-HSS-26 1-\\"

6" RHR Flat Later I

H D

Resi. Heat Remov.

1-RH-HSS-27 1-\\"

6" RHR Flat Later I

H D

Resi. Heat Remov.

1-RH-HSS-28 1-\\"

6" RHR Flat Later I

H D

Resi. Heat Remov.

1-RH-HSS-100 1-\\"

6" Containment 15' Level On RV-1721 FP-3DD I

H D

Discharge Line.

Resi. Heat Remov.

1-RH-HSS-lOlA 1-\\"

5" Containment, Basement On RHR Letdown Line FP-3DD A

N D

Resi. Heat Remov.

1-RH-HSS-lOIB 1-\\"

5" Containment*, Basement On.RHR Letdown Line FP-3DD A

N D

Resi. Heat Remov.

l*RH-HSS-102 1-\\"

5" Containment, Basement On RHR Return FP-3DD I

N D

HD-HOV-1720A Resi. Heat Remov.

1-RH-HSS-103 2-\\"

5" Containment, El. 3' "A" Cubicle Later I

N D

Resi. Heat Remov.

1-RH-HSS-104 2-\\"

5" Containment El. 3' "A" Cubicle Later I

N D

Resi. Heat Remov.

l-RH-HSS-105 1-\\"

6" Containment Basement On Overhead Later I

H D

Under RHR Flat Component Cooling l*CC-HSS-65 2-\\"

5" Aux. Bldg. Basement In Overhead FP-16J A

N D

Unit 1 Side, Component Cooling l*CC*HSS-331 2-\\"

5" Aux. Bldg.. Basement In Overhead FP-16J A

N D

Unit 1 Side

~

C/)

.i:--

I-'

-..J I

N I-'

TABLE 4.17-1 UNIT Ill SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEM HARK NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY Cbmponent Cooling 1-CC-HSS-332A 2-1:t" 5"

Aux. Bldg. Basemep.t In Overhead FP-16J A

N D

Unit l Side Component Cooling l-CC-HSS-332B 2-1:t" 5"

Aux. Bldg. Basement In Overhead FP-16J A

N D

Unit 1 Side Component Cooling 1-CC-HSS-340A 2-\\"

5" Aux. Bldg. Basement In Overhead FP-16J A

N D

Unit 1 Side Component Cooling 1-CC-HSS-340B 2-\\"

5" Aux. Bldg. Basement In.Overhead FP-I6J A

N D

Unit I Side Component Cooling l-CC-HSS-341 2-\\"

5" Aux. Bldg. Basement In Overhead Later A

N D

Unit 1 Side Component Cooling 1-CC-HSS-356A 2-\\"

5" Aux. Bldg. Basement Unit.2 Side FP-16J A

N D

Component Cooling l-CC-HSS-356B 2-\\"

5" Aux. Bldg. Basement Unit 2 Side FP-16J A

N D

Component Cooling 1-CC-HSS-60A 2-\\"

5" Aux." Bldg. Basement Component FP-16J A

N D

Cooling Pumps Component Cooling l-CC-HSS-330 2-1:t" 5"

Aux.. Bldg. Basement Component FP-16J A

N D

Cooling Pumps Diesel Exhaust 1-EE-HSS-01 2-\\"

6"

  1. 1 Emergency Diesel Outside On Roof of Bldg.

Later A

N R

Blowdown 1-WGCB-HSS-01 2-\\"

5" Blowdown Line A Cubicle FP-3H I

H D

Blowdown 1-WGCB-HSS-02 2-\\"

5" Blowdown Annulus (Penetration Area)

FP-3H A

H R

.Blowdown l-WGCB-HSS-03 2-\\"

5" Blowdown An~ulus (Penetration Area)

FP-3H A

H R

f-3 (IJ

+"'

I-'

-...J I

N N

TABLE 4.17-2 UNIT #2 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEM HARK HO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY e Hain steam 2-SHP-HSS-lA 5"

5" Hech. Equip. Room-Service Bldg.

FP-lB A

N D

Hain Steam 2-SHP-HSS-lB 5"

5" Hech. Equip. Room-Service Bldg.

FP-lB A

H D

Hain St~am 2-SHP-HSS-2A 5"

5" Hain Steam Top Of Crane Wall FP-lA I

H D

Hain Steam 2-SHP-HSS-2B 5"

5" Hain Steam Top Of Crane Wall FP-lA I

H D

Hain Steam 2-SHP-HSS-3A 3-".i" 5"

Hain Steam Top Of Crane Wall FP-lA I

H D

Hain Steam 2-SHP-HSS-3B 3-".i" 5"

Hain Steam Top Of Crane Wall FP-lA I

H D

Hain Steam 2-SHP-HSS-4A 3-\\"

5" Hain Steam Top Of Crane Wall FP-lA I

H D

Hain Steam 2-SHP-HSS-4B 3-".i" 5"

Hain Steam, Top Of Crane Wall FP-lA I

H D

Hain Steam 2-SHP-HSS-5A 2-".i" 5"

Hain Steam Top Of Crane Wall FP-lA I

H D

Hain Steam 2-SHP-HSS-5B 2-".i" 5"

Hain Steam Top Of Crane Wall FP-lA I

H D

Hain Steam 2-SHP-HSS-6A 2-\\"

5" Hain Steam Top Of Crane Wall FP-lA I

H D

Hain Steam 2-SHP-HSS-6B 2-".i" 5"

Hain Steam Top Of Crane Wall FP-lA I

H D

Hain Steam

. 2-SHP-HSS-7 2-".i" 5"

Hain Steam Top Of Crane Wall FP-lA I

H D

Hain Steam 2-SHP-HSS-:8 6"

5" Hain Steam Top Of Crane Wall FP.:.lA I

H D

Hain Steam 2-SHP-HSS-9 10" 5"

Hain Steam Top Of Crane Wall FP-lA I

H D

Hain Steam 2-SHP-HSS-10 10" 5"

Hain Steam Top Of Crane Wall FP-lA I

H D

Hain Steam 2-SHP-HSS-ll 8"

5" Hain Steam Top Of Crane Wall FP-lA I

H D

Hain Steam 2-SHP-HSS-12 8"

5" Hain Ste~m Top Of Crane Wall FP-lA I

H D

e Hain Steam 2-SHP-HSS-13 4"

5" Hain Steam Top Of Crane Wall FP-IA I

H D

Hain steam 2-SHP-HSS-14A 5"

5" Hech. Equip. Room-Service Bldg.

FP-lB A

H D

t-,3 Hai~ Steam 2-SHP-HSS-14B 5"

5" Hech. Equip. Room-Service Bldg.

FP-lB A

N D

C/l Hain Steam 2-SHP-HSS-15 4"

5" Safeguards FP-IB A

N D

.i::-

Hain Steam 2-SHP-HSS-16 4'-'

5" Safeguar~s FP-IB A

H D

Hain Steam 2-SHP-HSS-17 4"

5" Safeguards FP-lB A

N D

-.J I

N w

.TABLE 4.17-2 UNIT /12 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEM HARK NO.

SIZE STROKE GENERAL LOCATION (11548-)

CATEGORY CATEGORY CATEGORY I

Hain Steam 2-SHP-HSS-18 4"

5" Safeguards FP-lB

!A, N

D Hain Steam 2-SHP-HSS-19 4"

5" Safeguards FP-lB IA' N

D Hain Steam 2-SHP-HSS-20 4"

5" Safeguards FP-lB

!A:

N D

Hain Steam 2-SHP-HSS-21 4"

5" Mech. Equip. Room-Service Bldg.

FP-lB

A N

D Hain Steam 2-SHP-HSS-22 4"

5" Hech. Equip. Room-Service Bldg.

FP-lB iA N

D 4"

Hain Steam 2-SHP-HSS-23 5"

Mech. Equip: Room-Service Bldg.

FP-lB

'A N

D

-Hain Steam 2-SHP-HSS-24 4"

5" Mech. Equip. Room-Service Bldg.

FP-lB A'

N D

Hain Steam 2-SHP-HSS-25 4"

5" Mech: Equip,. Room-Service Bldg.

FP-IB A

N D

Hain Steam 2-SHP-HSS-26 4"

5" Mech. Equip. Room-Service Bldg.

FP-IB Ai N

D Hain Steam 2-SHP-HSS-27 6"

5" Saft;!guards FP-lB

A N

D Hain Steam 2-SHP-HSS-28 6"

5" Safeguards FP-IB A

N D

Hain Steam 2-SHP-HSS-29 6"

5" Safeguards FP-IB

  • A' N

D Hain Steam 2-SHP-HSS-30 6"

5" Safeguards FP-IB A

N D

Hain Steam 2-SHP-HSS-31 6"

5" Safeguards FP-IB

-A:

N D

Hain Steam 2_.SHP-HSS-32 6"

5" Safeguards '

FP-lB A

N D

Hain Steam 2-SHP-HSS-33A 6"

5" Safeguards FP-lB A

N D

Hain Steam 2-SHP-HSS-33B 6"

5" Safeguards FP-IB A

N D

~

Hain Steam 2-SHP-HSS-34A 6"

5" Safeguards FP-IB A

N D

Hain Steam 2-SHP-HSS-34B 6"

5" Safeguards '

FP-lB A

N D

Hain Steam 2-SHP-HSS-35A 6"

5" Safeguards FP-IB A

N D

t-,3 Hain Steam 2-SHP-HSS-35B 6"

5" Safeguards FI.>-lB A

N D

C/.l Hain Steam 2-SHP-HSS-36 1-\\"

6"

{12 Safeguards Ground Level Later A

N D

~

Hain Steam 2-SHP-HSS-40 2-\\"

5" Near SHP-20*

Later A

N D

Hain Steam 2-SHP-HSS-41 2-\\"

5" Near SHP-20 '

Later A

N D

I Hain Steam 2-SHP-HSS-42 2-\\"

5" Near SHP-20 Later A

N D

N

~

Hain Steam 2-SHP-HSS-43 2-\\"

5" Safeguards Valve Pit, 3rd Floor Later A

N D

Hain Feed 2-WFPD-HSS-l 2-\\"

5" Containment Operating Level FP-2H I

H D

Hain Feed 2-WFPD-HSS-2 2-\\"

5" Containment Operating Level FP-2H I

H D

Hain Feed 2-WFPD-HSS-3 2-\\"

5" Containment Operating Level FP-2H I

H D

Hain Feed 2-WFPD-HSS-4 2-\\"

5" Containment Operating Level FP-2H

,I H

D

TABLE 4.17-2 UNIT #2 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEM HARK NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY Hain Feed 2-WFPD-HSS-5 2-\\"

5" Cootainmeot Operating Level FP-2H I

H D

Hain Feed 2-WFPD-HSS-6 2-\\"

5" Containment Operating Level FP-2H I

H D

Hain Feed 2-WFPD-HSS-7 4"

5" Containment Operating Level FP-2H I

H D

Hain Feed 2-WFPD-HSS-8 4"

5" Containment Operating Level FP-2H I

H D

Hain Feed 2-WFPD-HSS-9 4"

5" Containment Operating Level FP-2H I

H D

Hain Feed 2-WFPD-HSS-10 4"

5" Containment Operating Level FP-2H I

H D

Hain Feed 2-WFPD-HSS-11 2-\\"

5" Containment Operating Level FP-2H I

H D

Hain Feed 2-WFPD-HSS-12 2-\\"

5" Containmen~ Operating Level FP-2H I

H D

Hain Feed 2.:wrpo-HSS-13 2-\\"

. 5" Containment Operating Level Later A

H D

Hain Feed 2-WFPD-HSS-14 2-\\"

5"

  1. 2 Safeguards, 44 Ft. Level Later A

H D

Hain Feed 2-WFPD-HSS-15 3-\\"

5" f/2 Safeguards, 44 Ft. Level Later A

H D

Hain Feed 2-WFPD-HSS-16 3-\\"

5"

  1. 2 Safeguards, 44 Ft. Level Later A

H D

Maio Feed 2-WFPD-HSS-17 3-\\"

5"

(/2 Safeguards, 44 Ft. Level Later A

H D

Hain Feed 2-WFPD-HSS-18 2-\\"

.5"

(/2 Safeguards, 44 Ft. Level Later A

H D

Aux. Feed 2-WAPD-HSS-140 1-\\"

6" Containment Operating Level FP-2B A

H D

Aux. Feed 2-WAPD-HSS-141 1-\\"

6" Containment Operating Level FP-2B I.

H D

Aux. Feed 2-WAPD-HSS-142 1-\\"

6" Containment Operating Level FP-2B

~

H D

e1 Aux. Feed 2-WAPD-HSS-143 1-\\"

6" Containment Operating Level FP-2B A

H D

Aux. Feed 2-WAPD-HSS-144 1-\\"

6"

//2 Safeguaild, Ground Level Later A

N D

Aux. Feed 2-WAPD-HSS-145 1-\\"

6"

  1. 2 Safeguards, Off The Floor Later A

N D

t-3 Compooeot Cooling 2-CC-HSS-357 1-\\"

6"

//2 Cont. Basement Overhead Later I

H D

Cl)

Compooeot Cooling 2-CC-HSS-358 1-\\"

6" (12 Cont. Basement Overhead Later I

H D

.i::-.

Component Cooling 2-CC-HSS-359 1-\\"

6"

  1. 2 Cont. Basement Overhead Later I

H D

Diesel Exhaust 2-EE-HSS-02 1-\\"

6"

  1. 2 Emerg. Diesel Exhaust Later A

N R

-..J Diesel Exhaust 2-EE-HSS-03 1-\\"

6"

  1. 2 Emerg. Diesel Exhaust Later A

N R

I N

\\J1 Containment Spray 2-CS-HSS-IA 2-\\"

5"

  1. 2 Safeguards, 3 Ft. Level Later A

N R

Containment Spray 2-CS-HSS-lB 2-\\"

5" Valve Pit,. 3 Ft. Level Later A

N R

TABLE 4.17-2 UNIT #2 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEM HARIC NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY e Reactor Coolant 2-RC-HSS-100 1-\\"

6" Spray Line-Overhead Cont. Basement FP-9E I

H D

Reactor Coolant 2-RC-HSS-101 1-\\"

6" Spray Line-Overhead Cont. Basement FP-9E I

H D

Reactor Coolant 2-RC-HSS-102 1-\\"

6" In Pressurizer Relief TIC Room FP-9E I

H D

Reactor Coolant 2-RC-HSS-103 1-\\"

6" Spray Line-Overhead Cont. Basement FP-9E I

H D

Reactor Coolant 2-RC-HSS-104 1-\\"

6" Spray Line-Overhead Cont. Basement FP-9E I

H D

React~r Coolant 2-RC-HSS-105 1-\\"

6" Spray Line-Overhead Cont. Basement FP-9E I

H D

Reactor Coolant 2-RC-HSS-106 1-\\"

6" In Pressurizer Relief TIC Room FP-9E I

H D

Reactor Coolant 2-RC-HSS-107 1-\\"

6" Line Above Pressurizer FP-9E I

H D

Reactor Coolant 2-RC-HSS-108 1-\\"

6" Spray Line-Overhead Cont. Basement FP-9E I

H D

Reactor Coolant 2-RC-HSS-110 1-\\"

6" On Pressurizer FP-9E I

H D

Reactor Coolant 2-RC-HSS-146 1-\\"

6" On Pressurizer FP-9E I

H D

Reactor Coolant 2-RC-HSS-112 1-\\"

6" On Line Above Pressurizer FP-9E I

H D

Reactor Coolant 2..:Rc-HSs-113 1-\\"

6" On Line Above Pressurizer FP-9E I

H D

Reactor Coolant 2-RC-HSS-114 1-\\"

6" On. Line,l\\bove Pressurizer FP-9E I

H D

Reactor Coolant 2-RC-HSS-115 1-\\"

6" On Line Above Pressurizer FP-9E I

H D

Reactor Cooiant 2-RC-HSS-116 1-\\"

6" On Line Above Pressurizer FP-9E I

H D

Reactor Coolant 2-RC-HSS-117 1-\\"

6" 0!1 Line Above Pressurizer FP-9E I

H D

Reactor Coolant 2-RC-HSS-it8 1-\\"

6" On Line Above Pressurizer FP-9E I

H D e Reactor Coolant 2-RC-HSS-119 1-\\"

6" On Line ~bove Pressurizer FP-9E I

H D

Reactor Coolant 2-RC-HSS-122 6"

4" Przr. Upper Support Snubber FH-52B I

H D

t-3 Reactor Coolant 2-RC-HSS-123 6"

4" Przr. Upper Support Snubber FH-52B I

H D

Cl)

Reactor Coolant 2-RC-HSS-124 6"

4" Przr. Upper Support Snubber FH-52B I

H D

.i::-

Reactor Coolant 2-RC-HSS-125 6"

4" Przr. Upfer Support Snubber FH-52B I

H D

I-'

-...J I

N O'\\

TABLE 4.17-2 UNIT #2 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL

~

MARK NO.

SIZE STROKE GENERAL LOCATION (11548-)

CATEGORY CATEGORY CATEGORY Reactor Coolant 2-RC-HSS-126 4"

5" B-P Snubber& On "A" RCP Upper Hold. Assy.

FH-53A I

H D

Reactor Coolant 2-RC-HSS-127 4"

5" B-P Snubber!! On "A" RCP Upper Hold. Assy.

FH-53A I

H D

Reactor Coolant 2-RC-HSS-128 4"

5" B-P Snubber& On "A" RCP Upper Hold. Assy.

FH-53A I

H D

Reactor Coolant 2-RC-HSS-129 4"

5" B-P Snubber& On "A" RCP Upper Hold. Assy.

FH-53A I

H D

Reactor Coolant 2-RC-HSS-130 4"

5" B-P Snubber& On "B" RCP Upper Hold. Assy.

FH-53A I

H D

Reactor Coolant 2-RC-HSS-131 4"

5" B-P Snubbers On "B" RCP Upper Hold. Assy.

FH-53A I

H D

Reactor Coolant 2-RC-HSS-132 4"

5" B-P Snubbers On "B" RCP Upper Hold. Assy.

FH-53A I

H D

Reactor Coolant 2-RC-HSS-133 4"

5" B-P Snubber& On "B" RCP Upper Hold. Assy.

FH-53A I

H D

Reactor Coolant 2-RC-HSS-134 4"

5" B-P Snubbers On "C" RCP Upper Hold. Assy.

FM-53A I

H D

Reactor Coolant 2-RC-HSS-135 4"

5" B-P Snubber& On "C" _RCP Upper Hold. Assy.

FM-53A I

H D

Reactor Coolant 2-RC-HSS-136 4"

5" B-P Snubber& On "C" RCP Upper Hold. ABBy.

FM-53A I

H D

Reactor Coolant 2-RC-HSS-137 4"

5" B-P Snubbers On "C" RCP Upper Hold. Assy.

FM-'-53A I

H D

Reactor Coolant 2-RC-HSS-138 12" 5"

"A" S/G Upper Restraint Casting Snubber FM-SIG I

H D

Reactor Coolant 2-RC-HSS-139 12" 5"

"A" S/G Upper Restraint Casting Snubber FH-51G I

H D

Reactor Coolant 2-RC-HSS-140 1211 5"

"A" S/G Upp~r Restraint Casting Snubber FM-SIG I

H D

Reactor Coolant 2-RC-HSS-141 12" 5"

"A" S/G Upper Restraint Casting Snubber FM-SIG I

H D

Reactor Coolant 2-RC-HSS-142 12" 5"

"B" S/G Upper Restraint Casting Snubber FM-5IG I

H D

Reactor Coolant 2-RC-HSS-143 12" 51i "B" S/G Upper.Restraint Casting Snubber FH-SlG I

H D

e Reactor Coolant 2-RC-HSS-144 1211 5"

"B" S/G Upper Restraint Casting Snubber FH-SlG I

H D

Reactor Coolant 2-RC-HSS-145 12" 5"

"B" S/G Upper Restraint Casting Snubber FM-SIG I

H D

Reactor Coolant 2-RC-HSS-146 12" 5"

"C" S/G Upper Restraint Casting Snubber FM-SIG I

H D

t-3 Reactor Coolant' 2.;:RC-HSS-147 12" 5"

"C" S/G Upper Restraint Casting Snubber FM-51G I

H D

Cf.l Reactor*coolant 2-RC-HSS-148 12" 5"

"C" S/G Upp~r Restraint Casting Snubber FH-51G I

H D

+'

Reactor Coolant 2-RC-HSS-149 12" 5"

"C" S/G Upper Restraint Casting Snubber FM-51G I

H D

~

Reactor Coolant 2-RC-HSS-150 12" 5"

"A" S/G Lower Support Ring FM-SIG I

H D

'-l I

N Reactor Coolant 2-RC-HSS-151 12" 5"

"A" S/G Lower Support Ring FM-SIG I

H D

'-l Reactor Coolant 2-RC-HSS-152 12" 5"

"A" S/G Lower Support Ring FM-SIG I

H D

Reactor Coolant 2-RC-HSS-153 12" 5"

"A" S/G Lower Support Ring FM-51G I

H D

Reactor Coolant 2-RC-HSS-154 12" 5"

"B" *s/G Lower Suppor_t Ring FH-SlG I

H D

Reactor Coolant 2-RC-HSS-155 12" 5"

"B" S/G Lower Support Ring FM-SIG I

H D

TABLE 4.17-2 UNIT U2 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEM HARK NO.

SIZE STROKE GENERAL LOCATION (11548-)

CATEGORY CATEGORY CATEGORY Reactor Coolant 2-RC-HSS-156 1211 5"

"B" S/G Lower Support Ring FM-516 I

H D

Reactor Coolant 2-RC-HSS-157 12" 5"

"B" S/G Lower Support Ring FM-SIG I

H D

Reactor Coolant 2-RC-HSS-1S8 1211 S"

"C" S/G Lower Support Ring FM-SIG I

H D

Reactor Coolant 2-RC-HSS-1S9 1211 S"

"C" S/G Lower Support Ring FM-SIG I

H D

Reactor Coolant 2-RC-HSS-160 1211 S"

"C" S/G Lower Support Ring FM-SIG I

H D

Reactor Coolant 2-RC-HSS-161 12" S"

"C" S/G.Lower Support Ring FM-SIG I

H D

.Reactor Coolant 2-RC-HSS-162 12" 5"

"A" RCP Lower Support Beam FM-S3A I

H D

Reactor Coolant 2-RC-HSS-163 12" S"

"A" RCP Lower Support Beam FM-S3A I

H D

Reactor Coolant 2-RC-HSS-166 12" S"

"B" RCP Lower Support Beam FM-53A I

H D

Reactor.Coolant 2-RC-HSS-167 12" S"

"B" RCP Lower Support Beam FM-53A I

H D

Reactor Coolant 2-RC-HSS-170 1211 S"

"C" RCP Lower Support Beam FM-S3A I

H D

Reactor Coolant 2-RC-HSS-171 12" S"

"C!' RCP Lower Support Beam FM-S3A I

H D

Reactor Coolant 2-RC-HSS-172 4-\\"

2" "A" S/G Upper Support Snubber Bolt FS-SlG I

H D

Reactor Coolant 2-RC-HSS-173 4-\\"

2" "A" S/G Upper Support Snubber Bolt FS-51G I

H D

Reactor Coolant 2-RC-HSS-174 4-\\"

2" "A" S/G Upper Support Snubber Bolt FS-SlG I

H D

Reactor Coolant 2-RC-HSS-17S 4-\\"

2" "A"*S/G Upper Support Snubber Bolt FS-SlG I

H D

Reactor Coolant 2-RC-HSS-176 4-\\"

2" "B" S/G Upper Support Snubber Bolt FS-51G I

H D

e Reactor Coolant 2-RC-HSS-177 4-\\"

2" "B" S/G Upper Support Snubber Bolt FS-51G I

H D

Reactor Coolant 2-RC-HSS-178 4-\\"

2" "B". S/G UpJ:ler Support Snubber Bolt FS-SlG I

H D

Reactor Coolant 2-RC-HSS-179 4-\\"

2" "B" S/G Upper Support Snubber Bolt FS-SlG I

H D

t-3 Reactor Coolant 2-RC-HSS-180 4-\\"

2" "C" S/G Upper Support Snubber Bolt FS-51G I

H D

Cl)

Reactor *coolant:

2-RC-HSS-181 4-\\"

2" "C" S/G Upper Support Snubber Bolt FS-51G I

H D

~

Reactor Coolant 2-RC-HSS-182 4-\\"

2" "C" S/G Upper Support Snubber Bolt FS-516 I

H D

I-'

Reactor Coolant 2-RC-HSS-183 4-\\"

2" "C" S/G Upper Support Snubber Bolt FS-SlG I

H D

Reactor Coolant 2-RC-HSS-184 1-\\"

6"

/12 Cont. Basement Overhead Later I

H D

I N

00 Reactor Coolant 2-RC-HSS-lBS 2-\\"

S" 112 Cont. Basement Overhead Later I

H R

Reactor Coolant 2-RC-HSS-186 1-\\"

5" 112 Cont. Pzr. Room Later I

H R

Reactor Coolant 2-RC-HSS-187 1-\\"

6" 112 Cont. Pzr. Room Later I

H D

Reactor Coolant 2-RC-HSS-18BA 2-\\"

5" 112 Cont. 55'9" Level Later I

H D

Reactor Coolant 2-RC-HSS-188B 2-\\"

5"

//2 Cont. 55'9" Level Later I

H D

TABLE 4.17-2 UNIT ll2 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEM HARIC NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY Reactor Coolant 2-RC-HSS-189A 4"

5"

{12 Cont. 55 Ft. Level Later I

H D

Reactor Coolant 2-RC-HSS-189B 4"

5"

{12 Cont. 55 Ft. Level Later I

H D

Reactor Coolant 2-RC-HSS-190 1-\\"

6"

{12 Cont. 55 Ft. Level Later I

H D

Safety Injection 2-SI-HSS-19A 5"

5" At "C" Accumulator FP-llB A

H D

Safety Injection 2-S1-HSS-19B 5"

5" At "C" Accumulator FP-llB A

H R

Safety Injection 2-SI-HSS-20 5"

5" At "C" Accumulator FP-llB A

H R

Safety Injection 2-SI-HSS-21 6"

5" At C" Accumilla tor

H D

Safety Injection 2-S1-HSS-22A 5"

5" At "C" Accumulator FP-llB A

H R

Safety Injection 2-SI-HSS-22B 5"

5" At "C" Acc~ulator FP-llB A

H R

Safety Injection 2-SI-HSS-23 8"

5" At "C" Accumulator FP-llB A

H R

Safety Injection 2-SI-HSS-24 6"

5" At "C" Accumulator FP-llB I

H D

Safety Injection 2-SI-HSS-25 8"

5" At "C" Accumulator FP-11B A

H R

Safety Injection 2-SI-HSS-26 8"

5" At "C" Accumulator FP-11B A

H R

Safety InjecUon 2-SI-HSS-27 6"

5" t,t nett Accumulator FP-11B I

H D

Resi. Heat Remov.

2-RH-HSS-l 2-\\"

5" On 2-:RH-P-lB FP-120 I

H D

Resi. Heat Remov.

2-RH-HSS-2 2-\\"

5" On 2-RH-P-lB FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-3 2-'2" 5"

On 2-RH-P-lA FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-4 2-\\"

5" On 2-RH-P-IA FP-12D 1

H D

Resi. Heat Remov.

2-RH-HSS-5 2-\\"

5" On 2-RH-E-lB FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-6 2-".i" 5"

On 2-RH-E-lB FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-7 2-\\"

5" On 2-RH-E-IA FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-8 2-\\"

5" On 2-RH-E-lA FP-12D I

H D

1-'3 Resi. Heat Remov.

2-RH-HSS-9 1-\\"

6" Above 2-RH-i:-IB FP-12D I

H D

Cf.l Resi. Heat Remov.

2-RH-HSS-10 1-\\"

6" Above 2-RH-P-lB FP-12D I

H D

I-'

Resi. Heat Remov.

2-RH-HSS-11 1-\\"

6" Above 2-RH-P-lB FP-12D I

H D

-...J Resi. Heat Remov.

2-RH-HSS-12 1-\\"

6" In Overhead Below RHR Flat FP-12D I

H D

I N

Resi. Heat Remov.

2-RH-HSS-13 l-\\"

6" In Overhead Below RHR Flat FP-12D I

H D

\\.0 Resi. Heat Remov.

2-RH-HSS-14 1-\\"

6" In Overhead Below RHR Flat FP-12D I

H D

TABLE 4.17-2 UNIT #2 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEM HARK NO.

SIZE STROKE GENERAL LOCATION (11548-)

CATEGORY CATEGORY CATEGORY e

Resi. Heat Remov.

2-RH-HSS-15 1-\\"

6" Near 2-RH-E-IB at -3'11" FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-17 2-\\"

5" Back Of "A" Loop Room Near Floor FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-18 2-\\"

5" Back Of "A" Loop Room Near Floor FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-19 2-\\"

5" Unde'r "A" Loop Room Near RHR Flat FP-12D I

H D

Resi. Heat Remov.

2-RH-HS6-20 2-\\"

5" Under "A" Loop Room Near RHR F'lat FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-21 1-1\\11 6"

At Loop Room Level Over RHR Flat FP-12D I

H D

Resi. Heat Remov.

2-RH-HS6-22 1-1\\

11 6"

At Loop Room.Level Over RHR Flat FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-23 1-1\\"

6" Below RHR Flat On 10" Line FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-24 1-1\\11 6"

Below RHR Flat On 10" Line FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-25 1-1\\"

6" Below RHR Flat On 10" Line FP-12D*

I H

D Resi. Heat Remov.

2-RH-HSS-26 1-1\\"

6" Below RHR Flat On 10" Line FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-27 1-1\\"

6" Below RHR Flat On IO" Line FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-28 1-\\"

6" On 12" Discharge From RHR -15'5" El.

FP-12D I

H D

Resi. Hest Remov.

2-RH-HSS-29 1-\\"

6" On 1,211 Discharge From RHR -15' 5" El.

FP-12D I

H D

Resi. Heat Remov.

2-RH-HSS-30 1-\\"

6" 112 Cont. 2 ;Ft. Level 12" Disch. Pipe Later I

H D

Resi. Heat Remov.

2-RH-HSS-31 2-\\"

5" 112 Cont. 2 Ft. Level 12" Disch. Pipe Later I

H D

Resi. Heat Remov.

2-RH-HSS-32 2-\\"

5" "A" Cubicle Later I

H D

Resi. Heat Remov.

2-RH-HSS-33A 1-\\"

6" 112 Cont. RH Flat Overhead Later I

H D -

Resi. Heat Remov.

2-RH-HSS-33B 1-\\"

6"

  1. 2 Cont. RH Flat Overhead Later I

H D

Resi. Heat Remov.

2-RH-HSS-34 1-\\"

6" 112 *Cont. RH Flat Later I

H D

t-3 I

(/) I Resi. Heat Remov.

2-RH-HSS-35 2-\\"

5" 112 Cont. RH Flat Later I

H D

+'

Resi. Heat Remov.

2-RH-HSS-36A 1-\\"

\\, 6" 112 Cont. Basement Near RH Flat Later I

H D

f-'

Resi. Heat Remov.

2-RH-HSS-36B 1-\\"

6" 112 Cont. *Basement Near RH Flat Later I

H D

-..J Resi. Heat Remov.

2-RH-HSS-37 1-\\"

6"

  1. 2 Cont. Ab*ove Sum Later I

H D

I w Resi. Heat Remov.

2-RH-HSS-38 1-\\"

6" 112 Cont. RHR Flat, 2'2" El.

Later I

H D

0 Resi. Heat Remov.

2-RH-HSS-39 1-\\"

6"

/12 Cont. RHR Flat, 2'2" El.

Later I

H D

Resi. Heat Remov.

2-RH-HSS-40 2-\\"

5" 112 C~nt. RHR Flat, 2'2" El.

Later I

H D

Resi. Heat Remov.

2-RH-HSS-102 1-\\"

6" Containment Annulus-13' l" FP-3CC I

H D

Resi. Heat Remov.

2-RH-HSS-103 1-\\"

6" Containment Annulus-13 1 I" FP-3CC I

H D

Recir. Spray 2-RS-HSS-101 1-\\"

6" Annulus 10' Level FP-1'3H I

H D

£*

TABLE 4.17-2 UNIT #2 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEM HARK NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY Recir. Spray 2-RS-HSS-102 1-\\"

6" Annulus 10' Level FP-13H I

H D

Re cir. Spray 2-RS-HSS-103 1-\\"

6" Anniilus 10' Level FP-13H I

H D

Recir. Spray 2-RS-HSS-104 1-\\"

6" Annulus 10' Level FP-13H I

H D

Low Head Safety Injection 2-SI-HSS-100 2-\\"

5" Valve Pit -10" SI Line FP-60H A

N D

Low Head Safety Injection 2-SI-HSS-101 2-\\"

5" Valve Pit -10" SI Line FP-60H A

N D

Low Head Safety Injection 2-SI-HSS-103 1-\\"

6" Safeg!Jards* Valve Pit, 2nd Level Later A

N R

Low Head Safety Injection 2-SI-HSS-104A 2-\\"

5" Aux. Bldg. 13' El. Overhead Later A

H D

Low Head Safety Injection 2-SI-HSS-104B 2-\\"

5" Aux. Bldg. 13' El. Overhead Later A

H D

Reactor Coolant 2-RC-HSS-88A 1-\\"

'6" On Line Above Pressurizer Later I

H D

Reactor Coolant 2-RC-HSS-88B 1-\\"

6" On Line Above Pressurizer Later J

H D

Chem. & Vol. Cont.

2-CH-HSS-303 1-\\"

6" Unit 11211 C CH Pump Cub.

11448 FP-IOZ A

H D

Chem. &_Vol. Cont.

2-CH-HSS-304 1-\\"

6" Unit "2" C _CH Pump Cub.

11448 Fl.'-lOZ A

H D

e Chem. & Vol. Cont.

2-CH-HSS-305 1-\\"

6" (12 Cont. Basement Overhead Later I

H D

Chem. & Vol. Cont.

2-CH-HSS-306A 1-\\"

6" (12 Cont. 1'* 11" Level Later I

H D

t-3 CJ)

Chem. & Vol. Cont.

2-CH-HSS-306B 1-\\"

6" 112 Cont. 1' 11" Level Later I

H D

Chem. & Vol. Cont.

2-CH-HSS-307 1-\\"

6" (12 Cont. 7 Ft. Level Later I

H D

+'

Blowdown 2-WGCB-HSS-01 1-\\"

6" "A" S/G Blowdown Line Annulus FP-3J I

H D

f-"'

Blowdown 2-WGCB-HSS-02 2-\\"

6"

H D

ll Blowdown 2-WGCB-HSS-03 2-\\"

6" nett Loop Room FP-3J I

H D

f-"

TABLE 4.17-2 UNIT 112 SUPPRESSOR DATA SYSTEM HARIC NO.

SIZE STROKE GENERAL LOCATION Blowdown 2-WGCB-HSS-4A 1-\\"

6" Aux. Bldg. Basement Pen. Area.

Blowdown 2-WGCB-HSS-4B 1-\\"

6" Aux. Bldg. Basement Pen. Area.

Blowdown 2-WGCB-HSS-5 1-\\"

6" "A" RCP Cubicle -3' 6" Blowdown 2-WGCB-HSS-6A 1-\\"

6" 112 c*oot. 3' 6" Level, 3" Pipe Blowdown 2-WGCB-HSS-6B 1-\\"

6" 112 Cont. 3' 6" Level, 3" Pipe Blowdown 2-WGCB-HSS-7A 1-\\"

6" IJ2 Side Aux. Bldg., 2 Ft. Level Blowdown 2-WGCB-HSS-7B 1-\\"

6" 112 Side Aux. Bldg., 2 Ft. Level Blowdown 2-WGCB-HSS-SA 1-\\"

6" 112 Side Aux. Bldg., 2 Ft. Level Blowdown 2-WGCB-HSS-8B 1-\\"

6" 112 Side Aux. Bldg., 2 Ft. Level ACCESSI-PRINT BILITY (11548-)

CATEGORY SG Blowdown Later I

SG Blowdown Later I

Later A

Later A

Later A

Later A

Later A

Later A

Later A

RADIATION REMOVAL CATEGORY CATEGORY H

D H

D H

D H

D H

D H

D H

D H

D H

D e

I-'

I u.)

N

Hain Steam TABLE 4.17-3 HARK HO.

l-SHP-HSS-40 SIZE PSA-3 STROKE PSA-3 UNIT #1 SUPPRESSOR DATA GENERAL LOCATION

  1. 1 Safeguards El. 52 PRINT (11448-)

Later ACCESSI-BILITY CATEGORY A

RADIATION CATEGORY N

REMOVAL CATEGORY D

TABLE 4.17-4

  • UNIT #2 SUPPRESSOR DATA ACCESS!-

PRINT BILITY RADIATION REMOVAL SYSTEH HARK NO.

SIZE STROKE GENERAL LOCATION (11448-)

CATEGORY CATEGORY CATEGORY

  • Hain Steam 2-SHP-HSS-1 PSA-3 PSA-3 fJ2 Safeguards El. 27' Below PORV "A" Later A

N D

Hain Steam 2-SHP-HSS-2 PSA-3 PSA-3 112 Safeguards El. 27' Below PORV "B" Later A

N D

,J Hain Steam 2-SHP-HSS-3 PSA-3 PSA-3 112 Safeguards El. 27' Below PORV "C" Later A;

N D

Hain Steam 2-SHP-HSS-4 PSA-3 PSA-3 112 Safeguards Beside "A" PORV Later A

N D

Hain Steam 2-SHP-HSS-5 PSA-3 PSA-3 112 Safeguards Beside "B" PORV Later A

N D

Hain Steam 2-SHP-HSS-6 PSA-3 PSA-3 112 Safeguards Beside "C" PORV Later

. A, N

D Service Water 2-SW-HSS-l PSA-3 PSA-3 SW-Basement Overhead Near 2 RS-E-lC Later A

N R

Recir. & Transfer 2-RT-HSS-lA PSA-3 PSA-3 "A" S/G Cubicle El. 55'0" Later

'I.

H D

Recir. & Transfer 2-RT-HSS-lB PSA-3 PSA-3

. "B" S/G Cubicle El. 55'0" Later I;

H D

Recir. & Transfer 2-RT-HSS-IC PSA-3 PSA-3 "C" S/G Cubicle El. 55'0" Later I

H D

Recir. & Transfer 2-RT-HSS-2A PSA-3 PSA-3 "A" S/G Cubicle El. 54'0" Later I

H D

Recir. & Transfer 2-RT-HSS-2B PSA-3 PSA-3 "B" S/G Cubicle El. 54'0" Later

I N

D Recir. & Transfer 2-RT-HSS-2C PSA-3 PSA-3 "C" S/G Cubicle El. 54'0" Later I

N D

Recir. & Transfer 2-RT-HSS-14A PSA-3 PSA-3 "A" S/G Cubicle El. 3'0" Later

,I H

D I

Recir. & Transfer 2-RT-HSS-15B PSA-3 PSA-3 "B" S/G Cubicle El. 9'0" Later I

H D

Recir. & Transfer 2-RT-HSS-16B PSA-3 PSA-3 Penetration Area El. 10'0" Later I

H D

Resi. Heat Remov.

2-RH-HSS-1 PSA-3 PSA-3 RH-Basement Annulus Near RH-23 Later A

H D

Resi. Heat Remov.

2-RH-HSS-2 PSA-3 PSA-3 On RH Line Beside RH-19 and 20 Later A

H D *-

Reactor Coolant 2-RC-HSS-1 PSA-3 PSA-3 RC-System-18 ft. Level Near Spiral Lad Later I

H D

RC-System-B&C Cubicles -4" Off Floor C/l Reactor Coolant 2-RC-HSS-2 PSA-3 PSA-3 Later I

H D

.i:--

Reactor Coolant 2-RC-HSS-3 PSA"'.'3 PSA-3 RC-"A" Loop Room Overhead Later I

H D

~I Reactor Coolant 2-RC-HSS-4 PSA-3 PSA-3 RC-"B" 15 Ft. Up-Right Side Loop Room Later I

H D

Chem. & Vol. Cont.

2-CH-HSS-l PSA-3 PSA-3 CH - Basement Later I

H D

I.

Chem. & Vol. Cont.

2-cH.:Hss-2 PSA-3 PSA-3 CH - Basemeht Later I

H D

L,,.)

.i:--

TS 6.5-2 B.

Records relative to the following items shall be retained for the life of the plant.

1.

Records of changes made to the plant and pland drawings are described in the FSAR pursuant to 10 CFR 50.59.

2.

Records of new and spent fuel inventory and assembly histories.

3.

Records of plant radiation and contamination surveys.

4.

Records of off-site environmental monitoring surveys.

5.

Records of radiation exposure of all plant personnel, and others as required by 10 CFR 20.

6.

Records of radioactivity in liquid and gaseous wastes released to the environment.

7.

Primary records of inservice inspections including, but not limited to radiographs (of welds which are radiographed), photographs of the scope traces for welds which are tested by ultrasonic techniques, and photographs of the surface of those welds inspected by visual or surface examinations.

8.

Records of Environmental Qualification which are covered under the provisions of paragraph 6.7.

_J