ML18101A363

From kanterella
Jump to navigation Jump to search
Safety Insp Repts 50-272/94-21 & 50-311/94-21 on 940912-16 & 1019-21.Violations Noted.Major Areas Inspected:Review IST Program & Procedures,Pump Testing & Valve Testing
ML18101A363
Person / Time
Site: Salem  
Issue date: 11/30/1994
From: Dempsey D, Eugene Kelly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML18101A360 List:
References
50-272-94-21, 50-311-94-21, NUDOCS 9412060151
Download: ML18101A363 (12)


See also: IR 05000272/1994021

Text

DOCKET/REPORT NOS:

LICENSEE:

FACILITY:

DATES:

INSPECTORS:

APPROVED BY:

SCOPE AND FINDINGS:

9412060151 941130

PDR

ADOCK 05000272

G

PDR

U. S. NUCLEAR REGULATORY COMMISSION

REGION I

50-272/94-21

50-311/94-21

Public Service Electric and Gas Company

Salem Nuclear Generating Station, Units 1 & 2

Hancocks Bridge, New Jersey 08038

September 12-16, 1994, & October 19-21, 1994

Douglas Dempsey, Reactor Engineer

Joseph Colaccino, NRR

Oou~~i'3tor"'"tngi neer

Systems Section

Division of Reactor Safety

Systems Section .

Division of Reactor Safety

This inspection evaluated compliance with NRC

regulations, American Society of Mechanical Engineers

(ASME) Code requirements, and commitments made in the

licensee's approved inservice testing program.

The

licensee's resolution of anomalies identified in

previous NRC Safety Evaluations also was reviewed.

Two violations of NRC requirements were identified

involving failure to test certain safety system check

valves within the periodicity specified by the ASME

Code, and failure to assure that conditions adverse to

quality are identified and corrected promptly.

Two

unresolved items were opened involving technical

review of changes to pump and valve test acceptance

criteria, and inadequate or incomplete cold shutdown

justifications. Two previous unresolved items were

closed. The executive summary provides additional

assessment .

EXECUTIVE SUMMARY

SALEM IST INSPECTION

The IST program at Salem Units 1 and 2 was reviewed to verify conformance with

the American Society of Mechanical Engineers Boiler and Pressure Vessel Code

and NRC requirements. Overall, the program satisfied the requirements, in

that the pumps and valves in the systems selected for review generally were

being tested properly, and the test results were evaluated and trended

appropriately.

An initiative to use spectrum analysis to assess the condition

of pump bearings exceeded Code requirements and contributed to safe operation

of the facility.

However, several program shortcomings indicative of weak management oversight

were identified during the inspection.

For example,* certain safety system

check valves were not tested in accordance with the Code or program

commitments (VIO 50-272 and 50-311/94-21-03); several requests for relief from

Code test requirements were not updated to reflect the responses to program

anomalies which were identified in an NRC safety evaluation; and cold shutdown

justifications often were documented incompletely.

In addition,

clarifications to some cold shutdown justifications, provided during the

inspection, did not adequately justify postponement of the tests specified by

the Code.

(URI 50-272 and 50-311/94-21-02)

Although the Quality Assurance organization performed comprehensive and

critical program audits, followup of audit findings by the line organization

were not always effective in assuring that conditions adverse to quality were

corrected. The failure to reconfirm pump vibration reference data following

corrective maintenance was cited because remedial action for two previous

similar audit findings was not adequate to prevent recurrence. A second

example of inadequate corrective action was identified during review of an

unresolved item (URI 50-311/94-13-01) involving recurring unexpected

actuations of a safety injection pump discharge relief valve during

surveillance testing (VIO 50-311/94-21-04).

An unresolved item (50-272 and 50-311/94-21-01) was opened regarding review of

changes to the baseline data sheets for safety-related pumps.

The data sheets

contain the acceptance criteria for IST surveillances. While the levels of

review appeared to be adequate from a technical standpoint, it was not

apparent to the inspectors that the administrative review requirements of the

technical specifications were being met.

The corrective actions implemented in response to a violation (50-272 and

50-311/93-27-01) involving leakage of residual heat removal system hot leg

injection check valves were reviewed, and the item was closed .

ii

DETAILS

1.0

BACKGROUND

Through 10 CFR 50.55a, "Codes and Standards," the NRC requires certain pumps

and valves designed and constructed according to the American Society of

Mechanical Engineers (ASME) Boiler and Pressure Vessel Code to be designed to

enable inservice testing (IST).Section XI, Subsections IWP and IWV, of the

Code provide requirements for testing to assess the operational readiness of

pumps and valves. These requirements are included as surveillance

requirements in plant Technical Specification (TS) 4.0.5, which requires

testing of pumps and valves per ASME Section XI, except where specific written

relief is granted by the Commission.

The purpose of IST is to assess the

operational readiness of pumps and valves, to detect degradation that might

affect component operability, and to maintain safety margins with provisions

for increased surveillance and corrective action.

NRC Generic Letter (GL) 89-

04 provides guidance on meeting the requirements of 10 CFR 50.55a(f),

"Inservice Testing Requirements."

The licensee currently is implementing the second 10-year interval of the IST

program as described in Revision 2 (October 3, 1989) of its program submittal

to the NRC.

The submittal included requests for relief from several Code

requirements, and Public Service Electric and Gas Company's (PSE&G) response

to the regulatory positions contained in GL 89-04, "Guidance On Developing

Acceptable Inservice Test Programs," dated April 3, 1989.

NRC review of the

program entailed verification that the program was based on the applicable

Code edition and addenda, that all appropriate pumps and valves were tested,

and that requests for relief from the provisions of Section XI, Subsections

IWP and IWV were acceptable.

An NRC letter, dated October 9, 1992, forwarded

the safety evaluation (SE) which provided the results of the NRC staff's

review of the Salem IST program.

The SE discussed program anomalies which

were identified during the review and requested additional information

regarding certain relief requests.

PSE&G's response to the items in the SE

was submitted to the NRC on October 12, 1993.

In another SE, dated

April 15, 1994, the NRC staff approved the revised relief requests and

concluded that PSE&G had addressed the program anomalies appropriately.

2.0

INSPECTION DETAILS (TI 2515/114)

The inspectors used NRC Temporary Instruction 2515/114, "Inspection

Requirements for Generic Letter 89-04, Acceptable Inservice Testing Program,"

to assess the current IST programs at Salem Units 1 and 2.

Primarily,

components in the auxiliary feedwater, safety injection, and containment spray

systems were selected for review.

Plant risk and the number of relief

requests and program anomalies identified in the NRc' Safety Evaluation Reports

were considered in the selection of these systems.

2.1

General IST Program Review

IST program documents were reviewed and licensee personnel were interviewed to

verify that program responsibilities were assigned and that requirements were

being implemented effectively.

2

The licensee currently is implementing the second IO-year IST program, which

began on June 30, 1987, and is described in the "Salem Generating Station IST

Program Manual."

The manual specifies program organization and *

responsibilities; the pump and valve testing to be performed pursuant to

Section XI, Subsections IWP and IWV of the Code (1983 Edition through Summer

1983 Addenda), frequency of testing; and requests for relief from Code

requirements. Administrative procedure NC.NA-AP.ZZ-0070(Q), "lnservice

Testing And MOV Testing Programs," Revision 2, establishes personnel

responsibilities and specifies the general requirements for implementing the

IST program.

The program at both units is administered primarily by one full-time IST

Engineer who coordinates the efforts of various implementing departments

(Operations, Maintenance, Planning).

The inspector found that the roles and

responsibilities defined in the two program documents were inconsistent, in

part, and did not always depict current practices accurately.

For example,

the program manual was not updated along with the administrative procedure to

show the change in responsibility for planning and scheduling from the

maintenance manager to the station planning and outage managers; and neither

document reflected the IST Engineer functions have been assumed by the systems

engineers.

With some exceptions, the inspector found that adequate administrative

controls were in place to schedule and track the performance of tests; to

ensure that reference values and acceptance criteria were met; to assure that

reference values were verified or reestablished following component

maintenance or replacement; to perform post-maintenance testing prior to

restoring a component to service; and to analyze and trend test data.

However, the inspector observed, and confirmed through discussions with the

Technical Support Manager and the IST Engineer, that the latter is constrained

by the day-to-day demands of program administration from performing more

programmatic tasks such as general program reviews, updates, and self-

assessments.

As a result, the program deficiencies listed below had been

identified to the licensee during QA audits and NRC program reviews, but

remained uncorrected.

Relief requests were not uniquely identified, and did not

distinguish between relief requests and cold shutdbwn test

frequency justifications, for which no NRC relief is required

Some components were tested as required by the Code, but were not

listed in the program

Component Requirement Review Sheets were not updated to identify

upgraded surveillance procedures

Relief requests were not updated to reflect the licensee's

responses to the anomalies identified in NRC safety evaluations

Cold shutdown justifications frequently were not detailed or

documented adequately

3

The Technical Support Manager acknowledged a need to reduce the IST Engineer's

administrative burden to facilitate the performance of program reviews and

self-assessments.

However, plans to ameliorate the condition were inchoate,

and no specific schedule or action plan was presented during the inspection.

2.2

IST Procedures

IST procedures were reviewed to confirm that instructions were sound

technically, and that components were tested in accordance with the

requirements of ASME Code Section XI and the regulatory positions of GL 89-04;

that appropriate quantitative or qualitative acceptance criteria were

established; and that procedures were reviewed and approved per license

requirements.

IST procedures were revised during the licensee's procedure upgrade program

and uniformly were found to be of high quality. Particularly noteworthy were

the clear, step-by-step processes outlined for performance of post-maintenance

retests, establishment or reverification of baseline values, required actions

for components in the alert and required action ranges, and disposition of

nonconforming conditions or unacceptable test results. Overall, acceptance

criteria were appropriately quantitative and unambiguous.

However, in pump

test procedure Sl-OP-ST.SJ-OOOl(Q), "Inservice Testing - 11 Safety Injection

Pump," Revision 2, safety injection pump discharge check valves ll,12SJ34 and

minimum flow check valves ll,12SJ64 were confirmed closed by verifying that

the safety injection pump discharge pressure gage in the idle loop was

"significantly lower" than the discharge pressure of the pump being tested.

ASME Section XI, Subarticle IWV-3522(a) allows the use of pressure indication

as a means to verify that check valves perform their closure safety function.

The licensee's test did not provide sufficiently definitive assurance (viz.

vague acceptance criteria) that the check valves were closed. The licensee

promptly revised the safety injection pump procedures to provide more

quantitative acceptance criteria.

The acceptance criteria for pumps in the IST program are maintained in a Pump

Test Baseline Data Manual located in the Shift Supervisor's office, rather

than in individual surveillance procedures.

Pump test baseline data sheets

are based directly on the quantities and allowable ranges specified in

Section XI, Tables IWP-3100-1 and IWP-3100-2.

The sheets are prepared by the

IST Engineer, reviewed by a system engineer, and approved by an engineering

supervisor in accordance with procedure SC.TE-TI.ZZ-0028(Q), "Pump Inservice

Testing Results Analysis." Deviations between new and previous pump reference

values are documented either by an engineering memorandum, an engineering

evaluation, or a safety evaluation pursuant to 10 CFR 50.59.

Technical Specifications (TS) 6.8.2 and 6.5.3.2 require procedure changes to

be reviewed independently by a designated Station Qualified Reviewer (SQR) and

approved by the appropriate department head, or, if an "on the spot change",

by two members of the management staff, at least one of whom holds a Senior

Reactor Operator license. The inspector questioned whether review and

approval of changes to the pump test baseline data sheets were consistent with

TS requirements.

The licensee stated that preparation of the data sheets did

not constitute a change in technical content when changed in accordance with

4

procedure SC.TE-TI.ZZ-0028(Q), and that review by an SQR was not required.

This item is unresolved pending further NRC review of the pump test baseline

data sheet approval process.

(URI 50-272 and 50-311/94-21-01)

2.3

Pump Testing

Surveillance procedures and performance records were reviewed for the safety

injection, containment spray, and auxiliary feedwater pumps against ASME

Section XI requirements for IST of pumps.

The test frequencies, quantities

measured, and allowable ranges were consistent with those specified in Article

IWP-3000.

Test instruments were verified to meet th~ accuracy requirements of

Table IWP-4110-1 of the Code.

The licensee properly dispositioned test

results which entered "alert" or "required action" ranges and maintained a

computerized database to trend pump performance.

The inspector noted that following replacement of the #22 auxiliary feedwater

pump impeller in May 1993, the licensee validated pump performance by

comparing differential pressure versus flow rate at only a single point along

the original (1970) pump curve.

The data was taken with the pump operating in

minimum flow recirculation (400*gallons per minute).

Notwithstanding that the

comparison satisfied the minimum requirement of Section XI, Subarticle IWP-

3111, the inspector considered that additional measurements taken at

progressively higher flow rates would have provided a greater level of

confidence in pump performance.

The licensee consulted the pump manufacturer,

who stated that the new impeller differed from the original only in material,

and that the original performance curve remained valid for the refurbished

pump.

The inspector discussed this with the Technical Support Manager, who

stated that pump performance would be validated at higher flow rates when a

suitable opportunity occurred.

In reviewing test data for the safety injection pumps, the inspector found

that the licensee uses spectrum analysis to assess the condition of the pumps

in the IST program.

The licensee also trends vibration levels for drivers as

well as pumps.

The inspector concluded that the licensee was utilizing

vibration data effectively, and that the monitoring program exceeded Code

requirements.

2.4

Valve Testing

Test frequency, methods, acceptance criteria, and corrective actions for

several types of valves in the selected systems were reviewed and found to be

satisfactory with the exceptions noted below.

The appropriate containment

isolation valves listed in TS Table 3.6-1 for both units were included in the

IST program as Category A or A/C valves.

As documented in the IST program,

these valves are leak rate tested pursuant to 10 CFR 50, Appendix J, in lieu

of Subarticles IWV-3421 through 3425 of the Code.

The inspector identified

several Unit 1 pressure isolation which are not listed in TS Table 4.4-4.

However, all pressure isolation valves at Unit 1 were verified to be included

in the IST program as Category A or A/C valves and tested per procedure

Sl.OP-ST.SJ-0020(Q), "Periodic Leakage Test - RCS Pressure Isolation Valves,"

Revision 3.

The licensee stated that a revision to the TS table which adds

5

the missing valves currently is being reviewed.

The inspector reviewed

completed work order packages for valves 11-14SJ139 and 11-14SJ144, verified

that the valves were tested individually, and concluded that the test results

were satisfactory.

Procedures and maintenance records for power-operated valves were assessed

against the stroke time criteria of Section XI, Subarticles IWV-3413(b} and

3417, and Position 6 (rapid-acting valves} of Generic Letter 89-04, as

applicable. Subarticles IWV-3411 and 3412(a} require Category A and B valves

to be exercised at least once every three months unless operation is not

practical during power operation. Valves which cannot be exercised during

power operation are to be specifically identified by the licensee and full-

stroke exercised during cold shutdowns.

The inspector evaluated several cold

shutdown justifications and verified on the basis of the program

documentation, that most of the valves could not practically be exercised

during power operation. However, several examples of inadequate cold shutdown

justifications were identified.

Accumulator outlet isolation valves ll-14SJ54 and 21-24SJ54 were

exercised on a cold shutdown frequency.

However, the valves were

not listed, and no cold shutdown justification was included, in

the IST program beyond a simple statement in a Component

Requirement Review sheet that the valves are required by TS to be

open.

The justifications in the program documents for RHR heat exchanger

outlet valves 11SJ45 and 12SJ45 were inconsistent. The basis

stated in the relief request was that opening the valves during

power operation would allow the refueling water storage tank to

backflow into the containment sump, while the Component

Requirement Review Sheet stated that the valves could not be

exercised'because they were interlocked with the SJ44 valves.

RHR supply to containment spray header valves 11CS36 and 12CS36

were tested during cold shutdown to avoid spraying down the

containment.

The inspector was unable to conclude from the program documents that the

licensee was justified in not testing the valves listed above at the frequency

prescribed by the Code. This issue is unresolved pending review of additional

information from the licensee.

{URI 50-272 and 50-311/94-21-02)

The inspector identified that charging pump suction check valves ISJ3 and 2SJ3

were partial-stroke exercised during cold shutdowns and full-stroke exercised

during refueling outages.

The safety function of the valves is to open to

permit the flow of borated water from the refueling water storage tanks to the

reactor coolant system.

10 CFR 50.55a{f) requires IST of certain ASME Code 1,

2, and 3 valves per Section XI of ASME Code except where specific written

relief has been granted by the Commission.

The tests performed by the

licensee deviate from the requirements of Section XI, Subarticles IWV-3521 and

3522, which state that check valves are to be exercised at least once every

three months unless such operation is impractical during power operation. If

6

only limited operation is practical during power operation, the valve shall be

partial-stroke exercised during power operation and full-stroke exercised

during cold shutdowns.

In a SE dated October 2, 1992, the NRC denied a relief

request to full-stroke exercise the valves during refueling outages, but

granted interim relief to permit the licensee to evaluate the practicality of

testing the valves during cold shutdown.

The licensee responded to the SE on

October 12, 1993 by withdrawing the relief request and stating that the valves

would be tested during cold shutdowns.

The inspector concluded that since

October 12, 1993, valves 1SJ3 and 2SJ3 were not tested in accordance with ASME

Code Section XI during cold shutdowns. This is the first example of a

violation of 10 CFR 50.55a(f}.

On being informed of the discrepancy described above, the licensee determined

on October 17, 1994, that check valves 1PR25 and 2PR25 also were not being

tested in accordance with the Code or as committed to the NRC in its SE

response.

The valves are located in the common discharge line of the

emergency core cooling system relief valves and function to permit flow from

the relief valves to the pressurizer relief tank.

Per Position 2 of GL 89-04,

the NRC SE granted relief from the test frequency and method requirements

Subarticles IWV-3521 and 3522, and authorized the licensee t9 partial-stroke

exercise the valves quarterly, and disassemble and inspect the valve internals

each refueling outage.

However, since October 9, 1992, the licensee has not

disassembled and inspected the valves. This is the second example of a

violation of 10 CFR 50.55a(f}. In support of an interim determination of

operability, the licensee relied, in part, on records of successful partial

flow tests which were performed per procedure Sl.OP-ST.ZZ-0003(Q}, "In Service

Testing - Miscellaneous Valves." The inspector verified through review of

test data that the partial-stroke exercise tests had been performed

satisfactorily. The inspector concluded that these deviations from the Code

test requirements were significant in that, in combination with the other

program deficiencies described above, they indicated poor licensee followup of

program commitments and weak management oversight of the IST program.

Consequently, the violations of 10 CFR 50.55a(f} will be cited.

(VIO 50-272

and 50-311/94-21-03}

Generic Letter 89-04, Position 2, states that check valves which are

disassembled and inspected in lieu of full-stroke exercising must be partial-

stroke exercised, if possible, after reassembly.

Several relief requests to

disassemble and inspect check valves were granted by the NRC in the IST

program SE with this proviso.

The inspector reviewed procedure NC.NA-AP.ZZ-

0050(Q}, "Station Testing Procedure," Revision 2, and observed that it

contained detailed retest instructions which are correlated explicitly with

ASME Code,Section XI requirements.

The inspector also verified throug~

review of work order packages, that the licensee partial-stroke exercised the

check valves following reassembly.

However, the inspector noted that the

quality of documentation for the retests varied considerably.

In most cases,

retest documentation consisted of a "sat" notation in the work order, while in

a few instances the original disassembly work order and test procedure were

referenced.

The licensee acknowledged the inconsistencies and agreed that

improved documentation of retests was warranted .

7

Test records and work order packages of pressurizer and steam generator Code

safety valves were reviewed and setpoints were verified to have been adjusted

within a tolerance of plus or minus 1.0 percent in accordance with the TS.

The inspector noted that for scheduling convenience, the licensee tests all of

its Code safety valves one time every five years. This practice takes

advantage of an ambiguity in the requirements in the 1983 Edition of Section

XI, Table IWV-3510-1, which provides a testing schedule for groups of valves

that should be tested every refueling outage.

The inspector determined that

Section XI Interpretation XI-1-89-25 of Subarticle IWV-3511 does not require a

minimum number of safety valves to be tested each refueling outage, and

concluded that the licensee's schedule was acceptable.

2.5

Evaluation of Anomaly Responses

The NRC SE for the Salem IST program contained a list of 19 anomalies where

inconsistencies and omissions in the program were noted.

The inspector

evaluated the anomaly responses contained in the licensee's submittal dated

October 12, 1993, and found, with two exceptions, that the responses had been

implemented satisfactorily. Anomaly No. 9 involved testing of check valves

1SJ3 and 2SJ3, which is discussed in Section 3.4 above.

Anomaly No. 15 stated

that some relief requests that were granted to permit full-stroke exercising

of check valves during refueling outages did not document adequately the

justification for not performing the tests during cold shutdowns, and that the

relief requests should be revised to provide this information.

In response,

the licensee stated that justification would be provided where valves were not

being tested per the ASME Code.

The inspector noted that the relief requests

for valves 11-14SJ139 and ll-14SJ144 were not updated to reflect the

licensee's statement, but verified that the valves were being tested as

required.

The inspector concluded that this was another example of lack of

followup and weak program oversight by licensee management.

3.0

IST PROGRAM AUDITS AND SELF-ASSESSMENTS

The licensee's quality assurance organization performs audits of the IST

program approximately every other year.

The reports of audit numbers90-011

(October 1990);91-012 (September 1991); and 93-012 (December 1993) were

reviewed.

The 1990 and 1993 audits were performed with the assistance of a

technical specialist from outside of the company, and focused on compliance

with license requirements (Section XI of the ASME Code), and broader

performance factors such as interdepartmental coordination and communication,

training, management support, and self-assessments. The inspector found the

audits to be comprehensive and self-critical. Audit findings (as opposed to

recommendations) were tracked via the licensee's action request system, and

the quality assurance organization was aggressive in insisting on timely

closeout of items.

Notwithstanding the above, the inspector found several recurring indications

of weakness in IST program implementation involving pump vibration reference

values following corrective maintenance.

ASME Code Section XI, Subarticle

IWP-3111 requires that when a reference value or set of values may have been

affected by repair of a pump, a new reference value or set of values must be

determined, or the previous values reconfirmed, by an IST run prior to, or

8

within 96 hours0.00111 days <br />0.0267 hours <br />1.587302e-4 weeks <br />3.6528e-5 months <br /> of returning the pump to normal service.

In audit 90-011, the

licensee identified that this requirement had not been met following repair of

an auxiliary feedwater pump in November, 1989. This was recognized as a

repeat of a similar finding in a 1988 program audit.

In spite of actions

taken in 1991 to prevent recurrence, the 1993 auditors found that new

reference values were not taken (or previous values reconfirmed) following

replacement of thrust bearings in the #21 component cooling water pump in July

1993.

The inspector considered two common elements detailed in the audit

reports to be significant.

Audit 93-012 stated that the operations department had no specific

direction for a method of transmitting completed IST data to the

technical department.

The IST Engineer stated that in 1993 he did

not routinely receive test data. Audit 90-11 noted a lack of

procedure controls to ensure that pump and valve test data is

transmitted to the IST Engineer.

Audit 93-012 stated that the knowledge level of IST program

requirements was not consistent among personnel with program

responsibilities, and that operators lacked specific training on

the IST program and administrative procedures.

Corrective actions

recommended in the auxiliary feedwater pump action request in

audit 90-011 included training and indoctrination of operations

personnel on IST program requirements. This item was closed in

audit 91-011 .

The inspector noted that the actions implemented in response to the 1993 audit

finding did not include consideration of why the previous corrective actions

had not been effective in preventing recurrence of the event.

The licensee failed to establish new vibration reference values, or to

reconfirm old reference values following corrective maintenance on the #21

component cooling water pump on July 6, 1993, despite identification of and

corrective action for similar occurrences identified in quality assurance

department audits in 1988 and 1990. This is the first example of a violation

of 10 CFR 50, Appendix B, Criterion XVI, "Corrective Action," which requires

measures to be established to assure that the cause of a significant condition

adverse to quality are taken to preclude repetition.

The inspector observed that the licensee has not performed any self-

assessments of the IST program, and learned in discussions with the IST

Engineer and the Station Technical Support Manager that, despite a strong

recommendation from the technical specialist in the 1993 audit, there are no

plans to do so at this time. In addition, the inspector learned that the

licensee does not plan to implement a new (Summer, 1994) requirement in

administrative procedure NC.NA-AP.ZZ-0070(Q) to perform a biannual review of

IST program submittals to evaluate the need for updated submittals to the NRC.

Finally, the inspector was informed that in anticipation of the resources

which will be required, the licensee does not intend to update or revise

extensively the present IST program prior to the third ten-year test interval

which is scheduled for June 30, 1997.

9

4.0

PREVIOUSLY-IDENTIFIED ITEMS

4.1

(Closed)

URI 50-311/94-13-01 Safety Injection Pump Discharge Relief

Valve Leakage

This item involved recurring leakage through safety injection pump discharge

relief valve 22SJ39 during surveillance testing of safety injection pumps on

March 31 and June 22, 1994. This relief valve is one of three whose safety

function is to protect the safety injection system from overpressure due to

reactor coolant system {RCS) backleakage through the injection line check

valves.

The leakage was significant because of the potential for reduced and

delayed injection flow to the RCS during a loss of coolant accident, and

depletion of refueling water storage tank inventory via the diverted flow.

Operators first noticed the leakage while testing the No. 21 safety injection

pump on March 31, 1994.

The system engineer was informed verbally of the

condition, but no formal request for engineering assistance was initiated.

When the pump was operated again on April 3, with no apparent valve leakage,

the operators concluded that the safety injection system was operable, and no

further evaluations regarding possible causes or safety impact were performed

until the problem recurred on June 22.

At this time, a formal request for

engineering assistance was made and a troubleshooting plan was implemented.

Ultimately, the leakage was determined to have been caused by relaxation of

the valve operating spring.

The valve was refurbished, satisfactorily bench-

tested, and installed in the system on June 28, and remained seated during

subsequent pump operation.

In Engineering Memorandum 94-117, dated

July 13, 1994, the licensee addressed the safety concerns mentioned above, and

concluded that the safety injection system had been operable while the relief

valve was lifted.

The inspector found the operability evaluation to be technically acceptable,

and this unresolved item is closed. Notwithstanding the outcome, the

inspector also concluded that the final operability determination and action

to prevent recurrence had not been performed in a timely fashion, commensurate

with the potential safety significance of the problem. This is the second

example of a violation of 10 CFR 50, Appendix B, Criterion XVI, "Corrective

Action," which requires conditions adverse to quality to be identified and

corrected promptly.

{VIO 50-311/94-21-04)

4.2

(Closed)

VIO 50-272&311/93-27-01 Corrective Action For Check Valve

Leakage

This violation involved a routine practice of manipulating certain safety-

related valves without an approved procedure.

During the startup of Unit 2 on

December 30, 1993, the NRC noted that valves RH19 and SJSO were positioned

during reactor coolant system {RCS)*pressurization to establish a differential

pressure sufficient to seat the residual heat removal {RHR) system injection

header check valves and to stop backleakage from the RCS to the RHR system.

Other concerns included the licensee's failure to develop a troubleshooting

procedure or to initiate a work order for the activity in accordance with

'

10

administrative directive SC.OP-DD.ZZ-AD46(Q), "Troubleshooting Abnormal Plant

Conditions," (AD-46). Also, the resulting lack of historical data on the

check valves with which to assess potential repetitive failures or the need

for corrective action to precluded recurrence.

The licensee responded to the violation in a letter, dated March 10, 1994, in

which it committed to revising the operations department standing orders to

clarify the application of Directive AD-46 and to issue a procedure for coping

with safety injection and RHR system check valve leakage. The standing orders

and draft Procedure Sl/S2.0P-SO.SJ-0003(Q}, "RCS Pressure Isolation Valves

Check Valve Reseating," were reviewed and found to be acceptable and

consistent with the commitments made in the violation response.

The inspector

also noted that both documents require a work order to be generated, thus

creating a historical trending record of check valve leakage.

Based on these

actions, this violation is closed.

5.0

MANAGEMENT MEETINGS

The inspector met with those principals denoted below on September 16 and

October 21, 1994, to discuss the preliminary inspection findings.

The

licensee acknowledged the findings and conclusions contained in this report

with no exceptions taken.

No proprietary information was reviewed during this

inspection.

J. Fest

s. La Bruna

J. Morrison

M. Morroni

H. Onorato

M. Pastra

M. Pike

F. Thomson

E. Villar

s. Faulkner

F. Kaminski

E. Karpe

H. Onorato

K. Pike

c. Bajwa

c. Marschall

T. Fish

J. White

Assistant to General Manager - Salem Operations

Vice President - Nuclear Engineering

Manager -

Technical Support

Manager - Maintenance Controls

Licensing Engineer

Lead Engineer - General Manager - Salem Operations

Technical Engineer - Reactor and Plant Performance

Manager - Licensing

Licensing Engineer

Senior Staff Engineer

IST Coordinator

Principal Engineer - QA Audits

Licensing Engineer

Technical Engineer - Reactor and Plant Performance

Region I

Senior Resident Inspector

Resident Inspector

Section Chief, Region I, Division of Reactor Projects