Monthly Operating Rept for Oct 1993 for Salem Unit 2.W/ 931115 Ltr
ML18100A713
Person / Time
Site: Salem PSEG icon.png
Issue date: 10/31/1993
From: Shedlock M, Vondra C
Public Service Enterprise Group
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9311190330
Download: ML18100A713 (8)


Text

e PS~G Public Service Electric and Gas Company P.O. Box 236 Hancocks Bridge, New Jersey 08038 Salem Generating Station November 15, 1993 U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555

Dear Sir:

MONTHLY OPERATING REPORT SALEM NO. 2 DOCKET NO. 50-311 In compliance with Section 6.9.1.6, Reporting Requirements for the Salem Technical Specifications, the original copy of the monthly operating reports for the month of October 1993 are being sent to you.

Average Daily Unit Power Level Operating Data Report Unit Shutdowns and Power Reductions Safety Related Maintenance 10CFR50.59 Evaluations Operating Summary Refueling Information Sincerely yours, General Manager -

Salem Operations RH:pc cc: Mr. Thomas T. Martin Regional Administrator USNRC Region I 631 Park Avenue King of Prussia, PA 19046 Enclosures

________ 8_""".1.:-Z.B.4 __________ _

9311190330 931031  !~

PDR ADOCK 05000311 u **

R PDR

/~~~eople 95-2189 (SM) 12-90

... ~ AVERAGE DAILY UNIT POWER~VEL Docket No.: 50-311 Unit Name: Salem #2 Date: 11-10-93 Completed by: Mark Shedlock Telephone: 339-2122 Month OCTOBER 1993 Day Average Daily Power Level Day Average Daily Power Level (MWe-NET) (MWe-NET) 1 1116 17 677 2 1117 18 727 3 1102 19 939 4 1102 20 1090 5 732 21 1110 6 740 22 1124 7 731 23 1131 8 821 24 1129 9 975 25 1124 10 976 26 1132 11 955 27 1102 12 503 28 1136 13 0 29 1128 14 292 30 1170 15 675 31 1183 16 704 P. 8.1-7 Rl

. .,, OPERATING DATA REPO~

Docket No: 50-311 Date: 11/10/93 Completed by: Mark Shedlock Telephone: 339-2122 Operating Status

1. Unit Name Salem No. 2 Notes
2. Reporting Period October 1993
3. Licensed Thermal Power (MWt) 3411
4. Nameplate Rating (Gross MWe) 1170
5. Design Electrical Rating (Net MWe) 1115
6. Maximum Dependable Capacity(Gross MWe) 1149
7. Maximum Dependable Capacity (Net MWe) 1106
8. If Changes Occur in Capacity Ratings (items 3 through 7) since Last Report, Give Reason NA
9. Power Level to Which Restricted, if any (Net MWe) N/A
10. Reasons for Restrictions, if any NONE This Month Year to Date Cumulative
11. Hours in Reporting Period 745 7296 105649
12. No. of Hrs. Rx. was Critical 745 4722.11 68487.71
13. Reactor Reserve Shutdown Hrs. 0 0 0
14. Hours Generator On-Line 708.1 4539.21 66097.67
15. Unit Reserve Shutdown Hours 0 0 0
16. Gross Thermal Energy Generated (MWH) 2156220 14760808.8 159856498.6 Gross Elec. Energy Generated (MWH) 715810 4949340 69656828
18. Net Elec. Energy Gen. (MWH) 682993 4699925 66285901
19. Unit Service Factor 95 62.2 62.6
20. Unit Availability Factor 95 62.2 62.6
21. Unit Capacity Factor (using MDC Net) 82.9 58.2 56.7
22. Unit Capacity Factor (using DER Net) 82.2 57.8 56.3
23. Unit Forced Outage Rate 5 13.2 22.3
24. Shutdowns scheduled over next 6 months (type, date and duration of each)

NONE

25. If shutdown at end of Report Period, Estimated Date of Startup:

NA 8-l-7.R2

UN IT SHUTDOWN AND POWER REDUCT IONS REPORT MONTH OCTOBER 1993 DOCKET NO.

UNIT NAME Salem #2 DATE 11/10/93 COMPLETED BY Mark Shedlock' TELEPHONE 339-2122 METHOD OF SHUTTING LICENSE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION 1 2 NO. DATE TYPE (HOURS) REASON REACTOR REPORT # CODE 4 CODE 5 TO PREVENT RECURRENCE 039 10-05-93 F 87.40 A 5 ----------- HB VAL VEX MAIN STEAM SAFETY RELIEF VALVES 040 10-10-93 F 42.33 A 5 ----------- HC HTEXCH CONDENSER TUBE PROBLEMS 041 10-12-93 F 36.90 B 1 ...................... CH zzzzzz STEAM GENERATOR CHEMISTRY 1 2 3 4 5 F: Forced Reason Method: Exhibit G - Instructions Exhibit 1 - Same S: Scheduled A-Equipment Failure (explain) 1-Manual for Preparation of Data Source B-Maintenance or Test 2-Manual Scram Entry Sheets for Licensee C-Refuel ing 3-Automatic Scram Event Report CLER) File D-Requlatory Restriction 4-Continuation of (NUREG-0161)

E-Operator Training & License Examination Previous Outage F-Administrative 5-Load Reduction G-Operational Error (Explain) 9-0ther H-Other (Explain)

SA~ETY RELATED MAINT,ANCE

  • MONTH: - OCTOBER 1993 DOC. NO:

UNIT NAME:

50-311 SALEM 2 DATE: NOVEMBER 10, 1993 COMPLETED BY: R. HELLER TELEPHONE: (609)339-5162 WO NO UNIT EQUIPMENT IDENTIFICATION 930828100 2 NO. 24 SAFETY INJECTION ACCUMULATOR LEVEL INDICATION FAILURE DESCRIPTION: 2LI934D READS LOW - INVESTIGATE 930828101 2 VALVE 2CV181 FAILURE DESCRIPTION: BORIC ACID TO BLENDER ISOLATION VALVE LEAKS BY - INVESTIGATE 931016094 2 23 CHARGING PUMP FAILURE DESCRIPTION: 23 CHARGING PUMP SUCTION STABILIZER BLADDER LEAKS - REPAIR 931022152 2 NO. 24 SAFETY INJECTION ACCUMULATOR LEVEL INDICATION FAILURE DESCRIPTION: INDICATOR 2LT935D/24 ACCUMULATOR LEVEL APPROXIMATELY 12%

DIFFERENCE WITH INDICATOR 2LT934D

~O~F~50.59 e

EVALUATIONS Docl. NO: 50-311

  • MONTH: - OCTOBER 1993 UNIT NAME: SALEM 2 DATE: NOVEMBER 10, 1993 COMPLETED BY: R. HELLER TELEPHONE: (609)339-5162 The following items were evaluated in accordance with the provisions of the Code of Federal Regulations 10CFR50.59. The Station Operations Review Committee has reviewed and concurs with these evaluations.

ITEM

SUMMARY

NONE FOR THE PERIOD

~*

.* ~

SALEM GENERATING STATION MONTHLY OPERATING

SUMMARY

- UNIT 2 OCTOBER 1993 SALEM UNIT NO. 2 The Unit began the period operating at full power and continued to operate at full power until October 5, 1993, when power was reduced to 70% to support design modifications in the 500KV switchyard. The unit was restored to 90% power on October 8, 1993, and continued to operate at that level until October 12, 1993, when it was removed from service to clean up the secondary system due to a chemistry excursion which had occurred after #23 heater drain pump was replaced and returned to service. The Unit was returned to service on October 13, 1993, and commenced a power escalation. The Unit was held at approximately 65%

power from October 14-19, 1993, for a station power transformer outage. These activities were completed and the Unit returned to 100%

power on October 19, 1993. The Unit continued to operate at essentially full power throughout the remainder of the period.

-' ~ ,,M

.*~EF)J~LING -

INFORMATION

-MONTH: - OCTOBER 1993 Docil NO:

UNIT NAME:

DATE:

50-311 SALEM 2 NOVEMBER 10, 1993 COMPLETED BY: R. HELLER TELEPHONE: (609)339-5162 MONTH OCTOBER 1993

1. Refueling information has changed from last month:

YES X NO

2. Scheduled date for next refueling: SEPTEMBER 24, 1994
3. Scheduled date for restart following refueling: NOVEMBER 22. 1994
4. a) Will Technical Specification changes or other license amendments be required?:

YES NO NOT DETERMINED TO DATE ~=X~-

b) Has the reload fuel design been reviewed by the station Operating Review Committee?:

YES NO ~--=X'--~

If no, when is it *scheduled?: OCTOBER 94

5. Scheduled date(s) for submitting proposed licensing action:

N/A

6. Important licensing considerations associated with refueling:
7. Number of Fuel Assemblies:
a. Incore 193
b. In Spent Fuel Storage 464
8. Present licensed spent fuel storage capacity: 1170 Future spent fuel storage capacity: 1170
9. Date of last refueling that can be discharged to the spent fuel pool assuming the present licensed capacity: March 2003 8-l-:-7.R4