NRR E-mail Capture - Three Mile Island Nuclear Station, Units 1 and 2 - Acceptance of Requested Licensing Action License Amendment Request to Modify the Emergency Plan for POST-SHUTDOWN and Permanently Defueled Condition
ML18096A053
Person / Time
Site: Three Mile Island  Constellation icon.png
Issue date: 04/05/2018
From: Justin Poole
Plant Licensing Branch 1
To: Mascitelli F
Exelon Generation Co
References
L-2018-LLA-0073
Download: ML18096A053 (2)


Text

NRR-DMPSPEm Resource From: Poole, Justin Sent: Thursday, April 5, 2018 11:55 AM To: Mascitelli, Francis J:(GenCo-Nuc); Bonnett, Frederick Paul:(GenCo-Nuc)

Cc: Danna, James

Subject:

THREE MILE ISLAND NUCLEAR STATION, UNITS 1 AND 2 - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: LICENSE AMENDMENT REQUEST TO MODIFY THE EMERGENCY PLAN FOR POST-SHUTDOWN AND PERMANENTLY DEFUELED CONDITION

SUBJECT:

THREE MILE ISLAND NUCLEAR STATION, UNITS 1 AND 2 - ACCEPTANCE OF REQUESTED LICENSING ACTION RE:

LICENSE AMENDMENT REQUEST TO MODIFY THE EMERGENCY PLAN FOR POST-SHUTDOWN AND PERMANENTLY DEFUELED CONDITION By letter dated March 19, 2018, Exelon Generation Company, LLC submitted a license amendment request for Three Mile Island Nuclear Station, Units 1 and 2. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 410 hours17.083 days <br />2.44 weeks <br />0.562 months <br /> to complete. The NRC staff expects to complete this review by March 2019. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me.

Justin C. Poole Project Manager NRR/DORL/LPL I U.S. Nuclear Regulatory Commission (301)415-2048 1

Hearing Identifier: NRR_DMPS Email Number: 274 Mail Envelope Properties (Justin.Poole@nrc.gov20180405115400)

Subject:

THREE MILE ISLAND NUCLEAR STATION, UNITS 1 AND 2 - ACCEPTANCE OF REQUESTED LICENSING ACTION RE: LICENSE AMENDMENT REQUEST TO MODIFY THE EMERGENCY PLAN FOR POST-SHUTDOWN AND PERMANENTLY DEFUELED CONDITION Sent Date: 4/5/2018 11:54:43 AM Received Date: 4/5/2018 11:54:00 AM From: Poole, Justin Created By: Justin.Poole@nrc.gov Recipients:

"Danna, James" <James.Danna@nrc.gov>

Tracking Status: None "Mascitelli, Francis J:(GenCo-Nuc)" <Francis.Mascitelli@exeloncorp.com>

Tracking Status: None "Bonnett, Frederick Paul:(GenCo-Nuc)" <Frederick.Bonnett@exeloncorp.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 2831 4/5/2018 11:54:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: