Text
Docket Nos. 50-272 and 50-311 Mr. Steven E. Miltenberger Vice President and Chief Nuclear Officer Public Service Electric and Gas Company Post Office Box 236 Hancocks Bridge, New Jersey 08038
Dear Mr. Miltenberger:
e November 2, 1990
SUBJECT:
UNIMPLEMENTED GENERIC SAFETY ISSUES AT THE SALEM GENERATING STATION, UNITS 1 AND 2 (TAC NO. 7599j)
On April 25, 1990 the staff issued Generic Letter 90-04 which requested infor-mation concerning the implementation status of certain generic safety issues (GSis) at your facility. Based on your response to this Generic Letter, dated July 2, 1990 and supplement dated July 13, 1990, our own records and discussions with your staff, we have updated our database on GSI implementation status. The results of this effort were presented to the Commission at a meeting on October 25, 1990.
The enclosure to this letter summarizes the staff's understanding of the current status of those GSis which remain unimplemented at Salem 1 and 2.
We appreciate the assistance you provided in responding to Generic Letter 90-04 and we encourage your timely completion of those GSis listed in the enclosure.
Please contact me if you have any questions or comments about the enclosed information.
Sincerely,
/SI James C. Stone, Project Manager Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation
Enclosure:
GSI Summary cc w/enclosure:
See next page DISTRIBUTION:
Docket File NRC PDR Local PDR PDI-2 Reading SVarga WButler MO'Brien PSwetland JRaleigh OGC EJordan ACRS(lO)
RBlough, RI DMiller prlIJ;/)fflh CJILI-2/PM PDI-2/D l b MP.~j~~ f JCStone:tlc WButler j-
~
~V1JW fl I) 190
\\\\ 1zJ9o 0
-96:1. F:>::::()1e::1 *io:L 10:2- ----~
PDR ADOCK 05000272 P
~t,o\\
'-'{\\ '\\\\
BBoger RScholl
I
\\ '-
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D. C. 20555 November 2, 1990 Docket Nos. 50-272 and 50-311 Mr. Steven E. Miltenberger Vice President and Chief Nuclear Officer Public Service Electric and Gas Company Post Office Box 236 Hancocks Bridge, New Jersey 08038
Dear Mr. Miltenberger:
SUBJECT:
UNIMPLEMENTED GENERIC SAFETY ISSUES AT THE SALEM GENERATING STATION, UNITS 1 AND 2 (TAC NO. 75993)
On April 25, 1990 the staff issued Generic Letter 90-04 which requested infor-mation concerning the implementation status of certain generic safety issues (GSis) at your facility. Based on your response to this Generic Letter, dated July 2, 1990 and supplement dated July 13, 1990, our own records and
- discussions with your staff, we have updated our database on GSI implementation status. The results of this effort were presented to the Conunission at a meeting on October 25, 1990.
The enclosure to this letter summarizes the staff's understanding of the current status of those GSis which remain unimplemented at Salem 1 and 2.
We appreciate the assistance you provided in responding to Generic Letter 90-04 and we encourage your timely completion of those GSis listed in the enclosure.
Please contact me if you have any.questions or comments about the enclosed information.
Enclosure:
GSI Summary cc w/enclo-;:-sure:
See next page*
Sincerely,
~r,k-James C. Stone, Project Manager
. Project Directorate I-2 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation
~
~._c::-,:;;;. *-~* - ~
~~~cp--7
GSI NO.
51 75 99 UNIMPLEMENTED GSis AT SALEM 1 AND 2 TITLE PROJECTED IMPLEMENTATION DATE Improving the Reliability 2/91 Salem 1 of Open-Cycle Service 11/91 Salem 2
~later Systems, Salem ATWS Item 2.2.2, Vendor Interface for
'Safety-Related Components RCS/RHR Suction Line.
ValNe Interlock on PWRs Response to GL 90-30 from licensee dated September 24, 1990 To Be Determined ENCLOSURE REMARKS Will be completed at Salem 1 during ninth refueling outage and at Salem 2 during sixth re-fueling outage.
Response is under-going staff review Suction line valve interlocks have been removed at both Salem Units.
By letter dated October 23, 1990, some of the enhance-ments committed to in response to GL 88-17 are being re-
- evaluated by the licensee.
Licensee's revised enhancements and proposed schedule will be forwarded for staff review by December 1990.
J
' \\.
Mr. Steven E. Miltenberger Public Service Electric & Gas Company Salem Nuclear Generating Station cc:
Mark J. Wetterhahn, Esquire Bishop, Cook, Purcell & Reynolds 1400 L Street NW Washington, DC 20005-3502 Richard Fryling, Jr., Esquire Law Department - Tower 5E 80 Park Place Newark, NJ 07101 Mr. L. K. Miller General Manager - Salem Operations Salem Generating Station P.O. Box 236 Hancocks Bridge, NJ 08038 Mr. S. LaBruna Vice President - Nuclear Operations Nuclear Department P.O. Box 236 Hancocks Bridge, New Jersey 08038 Mr. Thomas P. Johnson, Senior Resident Inspector Salem Generating Station U.S. Nuclear Regulatory Co11111ission Drawer I Hancocks Bridge, NJ 08038 Dr. Jill Lipoti, Asst. Director Radiation Protection Programs NJ Department of Environmental Protection CN 415 Trenton, MJ 08625-0415 Maryland People's Counsel American Building, 9th Floor 231 East Baltimore Street Baltimore, Maryland 21202 Richard B. McGlynn, Conmission Department of Public Utilities State of New Jersey 101 Coll111erce Street Newark, NJ 07102 Regional Administrator, Region I U. S. Nuclear Regulatory Co1t111ission 475 Allendale Road King of Prussia, PA 19406 Lower Alloways Creek Township c/o Mary O. Henderson, Clerk Municipal Building, P.O. Box 157 Hancocks Bridge, MJ 08038 Mr. Bruce A. Preston, Manager Licensing and Regulation Nuclear Department P.O. Box 236 Hancocks Bridge, NJ 0.8038 Mr. David Wersan Assistant Consumer Advocate Office of Consumer.Advocate 1425 Strawberry Square Harrisburg, PA 17120 Mr. Scott B. Ungerer MGR. - Joint Generation Projects Atlantic Electric Company P.O. Box 1500 1199 Black Horse Pike Pleasantville, NJ 08232 Mr. Jack Urban General Manager, Fuels Department Delmarva Power & Light Company 800 King Street Wilmington, DE 19899 Public Service Conunission of Maryland Engineering Division ATTN:
Chief Engineer 231--E. Ba~~e Street Baltimore~ ~D 21202-3486 Mr. j. T. Robb, Director Joint Owners Affairs PhiladelJ!bi.a-Electric Company 955 Chesterbrook Blvd., SlA-13 Wayne, PA 19087
-f'".,* '<"'~-~~