ND-18-0391, Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.2.03.08c.xlll (Index Number 198)

From kanterella
(Redirected from ML18082A372)
Jump to navigation Jump to search
Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.2.03.08c.xlll (Index Number 198)
ML18082A372
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 03/23/2018
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ITAAC 2.2.03.08c.xiii, ND-18-0391
Download: ML18082A372 (6)


Text

Michael J. Yox 7825 River Road Southern Nuclear Regulatory Affairs Director Waynesboro, GA 30830 Vogtle 3 & 4 706-848-6459 tel 410-474-8587 cell myox@southernco.com Docket Nos.: 52-025 52-026 ND-18-0391 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.2.03.08c.xlll [Index Number 1981 Ladles and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of March 20, 2018, Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.2.03.08c.xlll [Index Number 198] has not been completed greater than 225-days prior to Initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days prior to Initial fuel load.

This notification Is Informed by the guidance described In NEI 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC In Regulatory Guide 1.215. In accordance with NEI 08-01, this notification Includes ITAAC for which required Inspections, tests, or analyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Yox Regulatory Affairs Director Vogtle 3 &4

Enclosure:

Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.2.03.08c.xlll [Index Number 198]

MJY/LRG/amw

U.S. Nuclear Regulatory Commission ND-18-0391 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. D. A. Bost (w/o enclosures)

Mr. M. D. Rauckhorst (w/o enclosures)

Mr. M. D. Meier Mr. D. H. Jones (w/o enclosures)

Mr. D. L. McKinney Mr. M. J. Vox Mr. D. L. Fulton Mr. J. B. Klecha Mr. G. Chick Mr. F. H. Willis Ms. A. L. Pugh Mr. A. 8. Parton Mr. W. A. Sparkman Mr. C. E. Morrow Ms. K. M. Stacy Mr. M. K. Washington Mr. J. P. Redd Ms. A. C. Chamberlain Mr. D. R. Culver Mr. T. G. Petrak Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reouiatorv Commission Mr. W. Jones (w/o enclosures)

Ms. J. M. Heisserer Mr. C. P. Patel Mr. M. E. Ernstes Mr. G. J. Khouri Mr. T. E. Chandler Ms. S. E. Temple Ms. P. Braxton Mr. N. D. Karlovich Mr. A. J. Lerch Mr. C. J. Even Mr. F. D. Brown Mr. B. J. Kemker Ms. A. E. Rivera-Varona Ms. L. A. Kent Mr. P. B. Donnelly Oalethoroe Power Corporation Mr. R. B. Brinkman Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. S. M. Jackson

U.S. Nuclear Regulatory Commission ND-18-0391 Page 3 of 3 Dalton Utilities Mr. T. Bundros Westinahouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. D. Hawkins Ms. J. Monahan Mr. J. L. Coward Ms. N. E. Deangelis Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, inc.

Mr. 8. Roetger, Georgia Public Service Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-18-0391 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-18-0391 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.2.03.08c.xiii [Index Number 198]

U.S. Nuclear Regulatory Commission ND-18-0391 Enclosure Page 2 of 3 ITAAC Statement Desion Commitment 8.C) The PXS provides RCS makeup, boration, and safety injection during design basis events.

Insoections/Tests/Analvses xiii) Inspections will be conducted ofthe surfaces in the vicinity of the containment recirculation screens. The surfaces in the vicinity of the containment recirculation screens are the surfaces located above the bottom of the recirculation screens up to and including the bottom surface of the plate discussed in Table 2.2.3-4, item 8.c.vii, out at least 8 ft, 3 in perpendicular to the front and at least 7 feet to the side of the face of the screens.

Acceotance Criteria xiii) These surfaces are stainless steel.

ITAAC Completion Description Multiple ITAAC are performed to demonstrate that the Passive Core Cooling System (PXS) provides Reactor Coolant System (RCS) makeup, boration, and safety injection during design basis events. Forthis ITAAC, inspections are performed to verify that the surfaces in the vicinity of the containment recirculation screens in the PXS are stainless steel.

The surfaces in the vicinity of the containment recirculation screens in the PXS are defined as the surfaces located above the bottom of the containment recirculation screens up to and including the bottom surface ofthe plate discussed in Vogtle Electric Generating Plant (VEGP)

Combined License Appendix C, Table 2.2.3-4 item 8.c.vii, out at least 8 ft, 3 in perpendicular to the front and at least 7 feet to the side of the face of the screens.

The results of the inspections of the surfaces inthe vicinity of the containment recirculation screens in the PXS as defined above are documented in the Unit 3 and Unit 4 Principal Closure DocumentsXXX and YYY (References 1 and 2, respectively) supporting the Unit 3 and Unit 4 ITAAC 2.2.03.08c.xiii Completion Packages (References 3 and 4, respectively). The inspection confirms that the surfaces in the vicinity of the containment recirculation screens are stainless steel.

The Unit 3 and Unit 4 Principal Closure Documents XXX and YYY (References 1 and 2, respecfully) are available for NRC inspection as part ofthe Unit 3 and Unit 4 ITAAC 2.2.03.08c.xiii Completion Packages (References 3 and 4, respectively).

List of ITAAC Findings In accordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company (SNC) performed a review of all ITAAC findings and associated corrective actions.

This review found there are no relevant ITAAC findings associated with this ITAAC.

U.S. Nuclear Regulatory Commission ND-18-0391 Enclosure Page 3 of 3 References favailable for NRG inspection)

1. Principal Closure Document XXX (Unit 3)
2. Principal Closure Document YYY (Unit 4)
3. Completion Package for Unit 3 ITAAC 2.2.03.08c.xiii [COL Index Number 198]
4. Completion Package for Unit 4 ITAAC 2.2.03.08c.xiii [COL Index Number 198]
5. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"