UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION I
631 PARK AVENUE
KING OF PRUSSIA, PENNSYLVANIA 19406
DEC ~ 5 197g
Docket No. 50-311
-.
Public Service Electric & Gas Company
ATTN:
Mr. T. J. Martin
Vice President
Engineering and Construction
80 Park Place
Newark, New Jersey 07101
Gentlemen:
Subject:
Inspection 50-311/78-46
This refers to the inspection conducted by Mr. A. Toth of this office on
November 20-22, 1978, at the Salem Nuclear Generating Station, Unit 2,
at Hancocks Bridge, New Jersey, of activities auth6rized by NRC License
No. CPPR-53 and to the discussions of our findings held by Mr. Toth with
Mr. E. Meyer of your staff at the conclusion or the inspection, and to a
subsequent telephone discussion between Mr. Toth and Mr. Meyer on November
27' 1978.
Areas examined during this inspection are described in the Office of
Inspection and Enforcement Inspection Report which is enclosed with this
letter. Within these areas, the inspection consisted of selective
examinations of procedures and representative records, interviews with
personnel, and observations by the inspector.
Based on the results of this inspection, it appears that one of your
activities was not conducted in full compliance with NRC requirements,
as set forth in the Notice of Violation, enclosed herewith as Appendix
A.
This* item of noncompliance has been categorized into the levels as
described in our correspondence to you dat~d December 31, 1974.
This
notice is sent to you pursuant to the provisions of Section 2.201 of the
NRC
1 s
11 Rules of Practice,
11 Part 2, Title 10, Code of Federal Regulations.
Section 2.201 requires you to submit to this office, within thirty (30)
days of your receipt of this notice, a written statement or explanation
in reply including:
(1) corrective steps which have been taken by you
and the results ~chieved; (2) corrective steps which will be taken to
avoid further items of noncompliance; and (3) the date when full compliance
will be achieved .
7 90313 0 :<. f.*1
Public Service Electric & Gas
Company
2
In accordance with Section 2.790 of the NRC's "Rules of Practice," Part
2, Title 10, Code of Federal Regulations, a copy of this letter and the
enclosed inspection report will be placed in the NRC's Public Document
Room.
If this report contains any information that you (or your contractor)
believe to be proprietary, it is necessary that you make a written
application within 20 days to this office to withhold such information
from public disclosure.
Any such application must be accompanied by an
affidavit executed by the owner of the information, which identifies the
document or part sought to be withheld, and which contains a statement
o*f reasons which addresses with specificity the items which will be
considered by the Commission as listed in subparagraph (b)(4) of Section
2.790.
The information sought to be withheld shall be incorporated as
far as possible into a separate part of the affidavit.
If we do not
hear from you in this regard within the specified period, the report
will be placed in the Public Document Room.
Should you have any questions concerning this inspection, we will be
pleased to discuss them with you.
Enclosures:
Sincerely,
Robert T. Carlson, Chief
Reactor Construction and Engineering
Support Branch
1.
Appendix A, Notice of Violation
2~
Office of Inspection and Enforcement Inspection
Report Number 50-311/78-46
cc w/encls:
E. N. Schwalje, Manager - Quality Assurance,
Engineering and Construction Department