ML18067A689

From kanterella
Jump to navigation Jump to search
Insp Rept 50-255/97-08 on 970524-0707.Violations Noted.Major Areas Inspected:Operations,Maint,Engineering & Plant Support
ML18067A689
Person / Time
Site: Palisades 
Issue date: 09/05/1997
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML18067A687 List:
References
50-255-97-08, 50-255-97-8, NUDOCS 9709230082
Download: ML18067A689 (18)


See also: IR 05000255/1997008

Text

U.S. NUCLEAR REGULATORY COMMISSION

Docket No.:

License No.:

Report No.:

Licensee:

Facility:

Location:

Dates:

Inspector:

Approved by:

9709230082 970905

PDR

ADOCK 05000255

G

PDR

REGION Ill

50-255

DPR-20

50-255/97008(DRP)

Consumers Power Company

212 West Michigan Avenue

Jackson, Ml 49201

Palisades Nuclear Generating Plant

27780 Blue Star Memorial Highway

Covert, Ml 49043-9530

May 24 through July 7, 1997

P. Prescott, Resident Inspector

Bruce L. Burgess, Chief

Reactor Projects Branch 6

EXECUTIVE SUMMARY

Palisades Nuclear Generating Plant

NRC Inspection Report 50-255/97008

This inspection reviewed aspects of licensee operations, maintenance, engineering and

plant support. The report covers a 6-week period of resident inspection.

Operations

A plant procedure that allowed operations with steady state indicated reactor

thermal power greater than the licensed limit was identified as a violation. This

-procedure had previously been modified by the licensee to no longer allow the

steady state operation above the licensed limit. While no actual operation of the

unit of greater than the licensed limit was identified, the potential for such

operation had existed.

(Section 01 .2)

Ttie inspectors noted good operations performance during a CCW system spurious

relief valve lift. Operator identification and resolution of the event was prompt and

thorough. However, the inspectors identified a weakness in the initial operability

evaluation, which was subsequently addressed. The relief valve was subsequently

gagged closed until repairs could be initiated. (Section 01 .3)

Maintenance

The inspectors observed a weakness in communications in that neither system

engineering nor l&C personnel informed the operators of a grounding problem that

could occur during performance of the loop one T-ref maintenance activity, nor

were the alarms that could be received in the control room reviewed with the

operators. The inspectors noted these oversights were corrected in the loop two

phase of the maintenance activity. (Section M1 .2)

The inspector discussed an improper post maintenance test on valve CV-0733, and

indicated that this was another example of a negative trend observed in the quality

of post maintenance testing. The PMTs reviewed appeared to have been written to

verify the initial problem was repaired, not that the component continued to meet

its design function following maintenance. The licensee is currently reviewing the

PMT process. (Section M1 .3)

--- ---

-*-

2

~*

Engineering

The inspectors, in followup to a potentially generic issue, determined that the

licensee's administrative and design features that pertained to part length (P-L)

control rods provide sufficient controls such that a reactor power excursion due to

a stuck or mispositioned P-L control rod would be highly unlikely. Also, the

licensee's fuel vendor had reviewed and determined that a P-L control rod event

was bounded by a dropped or ejected control rod scenario in the current fuel cycle

analysis ~eport. (Section E1 .1)

Plant Support

The inspectors determined that the post maintenance critique did not fully address

.other available options to reduce dose during evaporation cleaning activities.

Critique meeting participants characterized the evaporator cleaning as a low dose

job (less than or equal to 10 mrem) when in fact the licensee had expended

approximately 350 mrem for a job that may not have been required. The inspectors

concluded that the evaporator cleaning job did not have the proper emphasis placed .

on ALARA planning. (Section R 1. 1)

3

REPORT DETAILS

Summary of Plant Status

The plant operated at essentially 99.6 percent power for the entire inspection report

period. July 7, 1997, marked the 138th day of continuous power operation.

I. Operations

01

Conduct of Operations .

01.1

General Comments (71707)

01.2

a.

b.

ongoing plant operations. The inspectors considered the conduct of operations to

be good. Specific events and noteworthy observations are detailed below.

Followup on Exceeding Licensed Thermal Power Limits

Inspection Scope (71707)

During this inspection period, the NRC completed its review of enforcement action

(EA)96-092 concerning a February 7, 1996 event at Palisades involving the

potential to exceed rated reactor thermal power limits as indicated by available

control room power monitors. Inspection report 50-255/96002(DRP) provided the *

specific facts and. preliminary analysis of this event. Below is a discussion of the

NRC's review and conclusions concerning the licensee's operation at near full

power.

Observations and Findings

On February 7, 1996, reactor thermal power was indicated to have exceeded the

power stated in the facility's license. This inadvertently occurred during a

delithiation evolution to control primary coolant system chemistry parameters. The

operations shift was aware that, by procedure GOP-12, Revision 12, reactor power

was allowed to reach 100.99 percent. Reactor thermal power is measured by

nuclear instrumentation that is calibrated periodically using a heat balance

calculation. A heat balance calculation provides the best indication of actual

reactor thermal power. Accident analyses presented in the FSAR must meet the

requirements of 10 CFR 50 Appendix K "ECCS Evaluation Models." These analyses

are performed assuming a reactor thermal power of 102 percent in order to allow

for instrument uncertainties. By exceeding licensed thermal power limits, reactor

  • - powe{ during an accident scenario could potentially be outside design bases

.

because the margin of safety derived from assuming a 2 percent instrument error

would be reduced by the higher initial power level at the time of accident initiation .

4

-*

c.

However, the inspectors determined the safety significance of this event was

minimal. Review of subsequent tests and analyses showed that the licensee did

not exceed 1 00 percent power during the nine hour delithiation process. A

calorimetric uncertainty analysis was completed that utilized instrumentation and

indication uncertainties and an ultrasonic flow measurement (UFM) of the feedwater

flow rate was performed. The UFM provided a more accurate indication of actual

feedwater flow, independent of the installed feed water venturies. Due to

feedwater flow rates being the single largest contributor in a calorimetric

calculation; small errors in feedwater flow rates could result in larger differences in

indicated reactor power. Results of the UFM testing revealed that actual power

was 2.2 percent less than the indicated power based on use of the feedwater flow

venturies. The difference was due to a conservative initial venturi calibration and

venturi fouling. Using the UFM results, maximum power level achieved during the

.delithiation process was determined to be 98.2 percent.

NRC has issued guidance that licensees may not operate above the steady state

indicated reactor thermal power limits stated in the license, except in unanticipated

transient conditions. If steady state indicated reactor thermal power exceeds the

licensed limit, the guidance directed licensees to initiate prompt corrective action

within 15 minutes to restore reactor power to less than or equal to the license

power limit.

The inspectors wrote a task interface agreement (TIA) issued to the Office of

Nuclear Reactor Regulation (NRR) to evaluate the adequacy of existing guidance.

The basis for the TIA was that present technology allows c~lculating, almost

instantaneously, reactor thermal power. The current standing guidance to the

industry was developed when calculating reactor thermal power was a one hour or

longer process. Thus under the old technology, the delithiation process and

resultant indicated power level of over 1 00 percent would not have been

immediately detected. Using current technology, almost anytime any evolution

re1ises power above 100 percent, the power excursion would be detected and raise

a question regarding whether or not a licensee should perform a calorimetric

knowing an overpower indication exists.

The response to the TIA stated that the deliberate raising of power above the

licensed limit was inappropriate. Procedure GOP-12, Revision 12, allowed the brief

operation in excess of licensed reactor thermal power. This procedure was

inappropriate to the circumstances and is considered a violation of 10 CFR 50

Appendix B, Criterion V "Instructions, Procedures, and Drawings," (50-255/97008-

01 (DRP)).

In response to NRC concerns, licensee management modified the procedure such

. _ that-it no longer allowed steady state power operation above the licensed limit.

Conclusions

A plant procedure that allowed operations with steady state indicated reactor

thermal power greater than the licensed limit was identified as a violation. In

5

response to concerns from the NRC, licensee management modified the procedure.

While actual operation of the unit greater than the licensed limit was not identified,

the potential for such operation had existed.

01.3

Component Cooling Water (CCW) Relief Valve (RV> Lift During Surveillance

a.

Inspection Scope (71707. 61726 and 37551)

The inspectors observed operations personnel conduct a prejob brief and perform a

right channel surveillance using procedure 00-1, "Safety Injection System."

b.

Observations and Findings

.The purpose of surveillance procedure 00-1 was to demonstrate operability of the

right channel of the safety injection system (SIS) initiation circuitry (SIS actuation

relays and design basis accident (OBA) sequencer) by using the internal testing

capability of the system. One system tested is the component cooling water

(CCW) system. The SIS initiation circuitry signals one of the other two CCW

pumps to start (one normally is already in service). During performance of 00-1 on

June 9, 1997, CCW pump P-528 automatically started as required. This resulted in

an expected increase in CCW system pressure. However, relief valve RV-2108,

which provides thermal over pressure protection for the shield cooling heat

exchanger, subsequently lifted .

The valve did not reseat normally which resulted in an approximately two gpm leak.

No alarms are automatically actuated when relief valve RV-2108 lifts, thus the

operating crew was not immediately aware of the partially open valve. An extra

nuclear shift operator (NSO) was assigned to assist in the control room while the

two normal onshift NSOs performed 00-1. During a routine panel walkdown, the

extra NSO noticed a decrease of approximately 10 percent in the CCW surge tank

level. The extra NSO also noted to the control room supervisor that containment

sump level was trending up. The operators checked the volume control tank level

to verify there was no decrease in level and to ensure that a primary coolant

system leak had not occurred. The operators then concentrated on finding a CCW

leak.

The operators:

Calculated CCW surge tank level loss to determine the rate of decrease;

stopped testing of 00-1;

. *--restored-the plant to normal configuration following the suspension of

surveillance test 00-1 ; and

entered the off-normal procedure for the CCW system due to the apparent

leak.

6

~.

The off-normal procedure was reviewed by operations personnel and the location of

all relief valves on a CCW system drawing were identified. Also, personnel on a

standby list of maintenance and system engineering personnel were notified. A

CCW corrective action team entered containment and identified that RV-2108 for

the shield cooling system had lifted and stayed opened. The valve was

mechanically agitated and it subsequently reseated. Licensee personnel generated a

condition report and an initial operability evaluation was performed. Operators

noted that the available indicators for the relief valve indicated that the valve lifted

early since when the relief valve lifted, CCW pressure was approximately 135 psig

and the setpoint of the relief valve was 150 psig.

The inspectors noted good operator response to the stuck open relief valve and

small CCW leak inside of containment.

The inspectors identified one weakness with the initial operability evaluation.

Initially, the evaluation addressed only the as found leak rate of 2 gpm and failed to

address the potential leak rate of a full open relief valve. If RV-2108 had lifted to

its full capacity of 24 gpm, the inspectors were concerned that the CCW surge tank

makeup capability would be insufficient. System engineering calculated that the

makeup capability of the CCW system was 150 gpm, which would be sufficient to

maintain the CCW system operable should RV-2108 spuriously lift again.

Subsequently, the valve was gaggeo closed to prevent recurrence. Two other relief

valves associated with the CCW system were verified to provide adequate

protection for the shield cooling heat exchanger from over pressure until RV-21 08

can be replaced.

c.

Conclusions

The inspectors noted good operator performance during identification and response

to the spurious lift of a CCW relief valve. Operator identification and response to

restore CCW system integrity was prompt and thorough. However, the inspectors

identified a weakness in the initial operability evaluation, which .was subsequently

addressed. The relief valve was subsequently gagged closed until repairs can be

initiated.

II. Maintenance

M 1

Conduct of Maintenance

M 1 . 1 General Comments

a.

Inspection Scope !62707 and 61726)

The inspectors observed all or portions of the following work activities:

Work Order No:

24711110

Dirty waste "B" evaporator; open/inspect and hydrolaze

7

24711266

CV-3223, SOC HXH E-60A inlet valve; open/inspect

PCV and replace internals

24711268

. CV-321 2, SOC HXH E-608 inlet valve; open/inspect

PCV and replace internals

24711416

CV-3055, inlet valve to SOC HXH; open/inspect PCV

and replace internals

24711267

CV-3224, SOC HXH E-60A outlet valve; open/inspect

PCV and replace internals

24514371

Install new program for PCS Loop one revised T-ref

curve in transmitter TYT-0100 per SC-95-099

24612597

Install new program for LIC-01 OA pressurizer level

controller for revised T-ref curve on loop one

24612508

CV-0511 turbine bypass valve; replace tubing and

fittings downstream of CA-0390

24513316

Diagnostic testing of CV-0511

24514370

Install new program for PCS loop 2 revised T-ref curve

in transmitter TYT-0200 per SC-95-099

24612596

Install new program for LIC-0101 B pressurizer level

.~

~

controller for revised T-ref curve on loop two

~

24612911

Charging pump P-55A; install new pump body and head

24712354

Hydrolaze drain line to equipment drain tank T-80

Surveillance Activities

SOP-2

. Surveillance for Auxiliary Feedwater valves CV-

0727 and CV-0749 following PPAC FWS034

SOP-8 ATT 2

Testing of Main Turbine Valves/Protective Trips

00-1

Safety Injection System (Right Channel With

Standby Power)

00-1

Safety Injection System (Right Channel Without

Standby Power)

00-19

lnservice Test Procedure - HPSI Pump and ESS

Check Valve Operability Test

8

-*

b.

Observations and Findings

The inspectors concluded that the work performed during maintenance and

surveillance activities was professional and thorough. All work observed was

performed with the work package present and in active use. Work packages were

comprehensive for the task and post maintenance testing requirements were

adequate. The inspectors frequently observed supervisors and system engineers

monitoring work practices. When applicable, work was completed by adhering to

the appropriate radiation control practices.

c.

Conclusions

In general, the inspectors observed good procedure adherence, maintenance and

.radiation worker practices. Specific observations are detailed below.

M1 .2 Poor Communications During T-ref Controller Maintenance

a.

Inspection Scope (61726 and 71707)

The Inspectors observed portions of scheduled maintenance on transmitters TYT-

0100 and TYT-0200. The temperature reference (T-ref) curve had changed and the

licensee intended to change the electronic program constants to reflect the revised

curve.* In addition to observing the transmitter work, the inspectors also reviewed

the associated work package and observed the post maintenance test. Also

observed were maintenance activities for the pressurizer level controller LIC-0101 A

and LIC-0101 B, which provided a revised pressurizer level setpoint curve. The

pressurizer level setpoint curve was revised to reflect a revised Tave for 100 percent

power.

b.

Observation and Findings

As noted in section 01.2 of this report, the licensee had identified conservative

errors in the measured flow rates of the main feedwater system. Following the

identification of these errors, l&C personnel adjusted feedwater flow

instrumentation and other power measuring instruments. As the unit power was

adjusted, Tave and T-ref were also adjusted.

The first portion of the maintenance activity involved removal of the loop one

transmitter TYT-0100 to have its program upgraded and then reinstalled after

testing. TYT-0100 was unplugged from the control room panel and a digital

programmer was connected. When the programmer was turned on and TYT-0100

was plugged back in an AC ground fault alarm occurred on preferred AC power bus

.. 'l~10, which powers TYT-0100. The TYT-0100 showed no sign of having AC

power applied. Also, digital T.v. indicator Tl-0111 and temperature recorder TR-021

both showed a 15° F increase. At this point, the control room operators suspended

the job and entered the proper annunciator response procedure. The inspectors

observed good command and control of control room operations.

9

The ground fault was evaluated and the required procedural actions completed.

The operators then allowed removal of transmitter TYT-0100. The ground was no

longer observed on the Y-10 bus. The original TYT-01 00 transmitter unit was

replaced with a new unit. The inspectors learned from discussions with the system

engineer that similar events had occurred with the same model transmitters in five

previous instances. The inspectors had attended the prejob brief and this potential

problem was not discussed. The inspectors also noted that the operations

personnel were not present for the prejob brief. Prior to commencing work, neither

the system engineer nor instrumentation and control (l&Cl technieians briefed

operations of this potential problem. During this evolution, the inspectors discussed

with plant management concerns that operators are briefed on expected alarms

prior to commencement of work .

. Prior to work on the second Tave loop, the inspectors discussed with operations that

LIC-0101 B was a suspect unit and that the scope of the job was to only reprogram

the unit. The operators performed a prejob brief for the loop two work activity with

the operations shift, l&C technicians, their supervisor, and the system engineer.

The inspectors noted the brief was thorough. During the brief, the system engineer

identified to operations that LIC-0101 B was a suspect unit. The original scope of

the work package was to simply reprogram the unit and not replace the unit or the

power supply. The operators suggested that it would be prudent to take care of

the potential power supply problem now rather than simply reinstall the unit. The

system engineer agreed and the power supply was replaced after proper work order

revisions were completed.

c.

Conclusions

The inspectors observed that neither system engineering nor l&C personnel

informed the operators of a potential problem that could occur during performance

of the T-ref maintenance activity, nor were potential alarms reviewed with

operations. The inspectors noted these oversights were corrected in the second

phase of the maintenance activity.

M-1.3 Adequacy of Post Maintenance Test (PMTI Requirements

a.

Inspection Scope 62707

The inspectors observed portions of maintenance performed for turbine bypass*

valve CV-0511 and portions of the testing conducted on condensate fast makeup

valve, CV-0733.

The PMT history for the CV-0733 valve was also reviewed.

b.

Observations and Findings

The intent of the work order for CV-0511 was to replace a mix of copper and

stainless steel instrument air lines and fittings with new stainless steel. Part of the

work order required removal of certain solenoid valve (SVs). The SVs were to be

de-terminated and the wire-nutted connections replaced with lugged connections.

10

In the inspectors' review of the PMT operability requirements for CV-0511, CV-

0511 was to remain isolated from the main steam system during valve timing tests.

Also, the PMT required the verification of no air leakage on the replaced instrument

air lines. The inspectors were concerned this would be an inadequate PMT of CV-

0511 , in that fill the SVs would not be verified as functional. The SVs for the

bypass valve quick opening and loss of condenser vacuum functions would not be

tested. The turbine bypass valve is important to plant safety. The valve passes up

to 4.5 percent steam flow with the reactor at full power. The FSAR states that the

turbine bypass valve is one of the systems utilized for taking the plant to hot

shutdown. The valve is also discussed in the Technical Specification Basis Section 2.2. The TS basis states that additional assurance is provided by the

bypass valve in preventing the nuclear steam supply system pressure from

exceeding safety limits.

The inspectors observed the PMT for the condensate fast makeup valve. The 12

inch valve supplies condensate makeup from storage tank T-2. The valve opens on

a low-low hotwell level signal. A pressure control valve (PCV) was repaired and

operators attempted to stroke CV-0733. The valve failed to stroke. The PCV was

adjusted to increase air pressure and the valve was mechanically agitated.

However, the valve still failed to stroke. The valve maintenance supervisor stopped

further testing until the situation could be reviewed. At the end of the inspection

period, the valve had not been stroked. Licensee maintenance personnel are

evaluating options to stroke the valve.

The licensee, in reviewing post maintenance and interviews with personnel, found

that the actuator for CV-0733 had been overhauled in February 1997. After

completion of the overhaul, it was found that CV-0733 had not been stroked even

though the PMT cover sheet recommended it. The licensee wrote a condition

report which requires a root cause analysis (referred to as a level two condition

report).

In the previous inspection report (IR) (50-255/97006(DRP)), the inspectors

identified a concern with PMT of the P-55A charging pump. Also, detailed in the

same IR were problems of PMT with P-88 Auxiliary feedwater pump. The

inspectors discussed with the licensee the continued weaknesses noted in the area

of post maintenance testing.

c.

Conclusions

The licensee reviewed the test requirements and decided to stroke the valve and

declare CV-0511 inoperable but available pending testing of the SVs and associated

control circuitry for the loss of vacuum and turbine trip features. The licensee

---discussed -the adequacy of the testing requirements with the work order planning

group. The licensee is currently reviewing the best method to stroke CV-0733.

The inspectors discussed the negative trend in post maintenance testing with the

licensee. The PMTs appeared to have been written to verify the initial problem was

repaired, not that the component continued to meet its design function following

11

maintenance. In response to NRC questions, regarding the PMT program, the

licensee is currently reviewing the PMT process.

Ill. Engineering

E1

Conduct of Engineering

E1 .1

Review of Part-Length Control Rod Transient Analyses

a.

Inspection Scope (37551 >

The inspectors reviewed the applicability to Palisades of a generic NRC concern

with part-length (P-L) control rods. Specifically, the concern involved the fuel

.vendor's elimination of two transient analysis events from the fuel cycle-by-cycle

analysis normally performed for the Combustion Engineering (CE) plants that have

the core protection calculator (CPC) digital protective systems.

To assess the applicability of this concern to the licensee and to verify any

necessary corrective actions the inspectors held discussions with reactor

engineering and operations department personnel. In addition, the inspectors also

reviewed licensee plant procedures, Technical Specifications (TS), the Final Safety

Analysis Report and operator training guides.

b.

Observations and Findings

The issue involved not addressing certain control rod misoperation events. The two

accident analysis of interest involved P-L control rod deviations while in the control

deadband during startup and the slip of a P-L control rod from 50 percent inserted

to 90 percent inserted. NRC review of this issue concluded that a single P-L control

rod deviation within the deadband and the P-L control rod slip are an anticipated

operational occurrence (AOO). An'AOO is an event in which plant conditions may

be present for this event once in the life of the plant. Therefore, it must be

evaluated each cycle under all conditions allowed by TS.

The inspectors found several distinctions in plant configuration and administrative

controls that make the two events in question highly unlikely at Palisades.

( 1)

Palisades has 20 shutdown, 21 regulating and 4 P-L control rods. The P-L

control rod drive mechanisms (CRDMs), unlike the other CRDMs at

Palisades, has a short drive shaft in place of a clutch. The CROM motor and

brake cannot be uncoupled from the control rod without disassembly. As a

result, P-L ,control rods cannot drop into the core on a reactor trip, unlike

--- other CE plants with the digital protective systems ..

(2)

At Palisades, the rods in question are not used for flux shaping during power

operations. Licensee TS require P-L control rods to be completely withdrawn

from the core (except for control rod exercises and physics tests).

Administratively, P-L control rods are not exercised. Also, a P-L control rod

12

is considered inoperable if it is not fully withdrawn from the core and cannot

be moved by .its operator. By TS, if more than one control rod or P-L control

rod becomes misaligned or inoperable, the reactor shall be placed in the hot

shutdown condition within 1 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br />. The licensee placed these restrictions

on P-L control rods since it had been previously demonstrated on other CE

plants that design power distribution envelopes could, under some

circumstances, be violated by using P-L control rods.

The inspectors discussed with reactor engineering potential operator error

scenarios. An operator could move P-L rods, but procedures do not allow it, except

during startup prior to criticality. The operator would have to commit two errors to

move a P-L rod. The operator would have to move the group selector switch for P-

L rods, which gives an alarm, then move the joystick that would move the rod.

This would also give an alarm. These actions would also be contrary to operator

training.

The inspectors reviewed licensee surveillances pertaining to control rod movements.

The procedures did not allow movement of P-L control rods.

c.

Conclusions

The inspectors determined that the licensee's administrative and design features

that pertained to part length (P-L) control rods provided sufficient control such that

a reactor power excursion due to a stuck or mispositioned P-L control rod would be

highly unlikely. Also, the licensee's fuel vendor had reviewed and determined that

a P-L control rod event was bounded by a dropped or ejected control rod scenario in

the current fuel cycle analysis report.

IV. Plant Support

R 1

Radiological Protection

R 1.1

Maintenance Activities and Daily Radiological Work Practices

a.

Inspection Scope (71750 and 83750)

The inspectors observed radiological worker activities during various maintenance

activities detailed in this inspection report, and also monitored radiological practices

during daily plant tours.

b.

Observations and Findings

  • The inspectors' observation of jobs in progress during the maintenance activities.

detailed above revealed that radiation protection technicians were visible at the job

sites. The technicians took appropriate actions and surveys in accordance with

good ALARA practices.

13

c.

Conclusions

The inspectors concluded that radiological practices observed during the

maintenance activities and plant daily walkdowns were adequate. The inspectors

had no concerns. Specific observations are detailed below.

R1 .2 ALARA Planning of "B" Radwaste Evaporator Maintenance

a.

Inspection Scope (71750 and 83750)

The inspectors observed maintenance activities for the opening, inspecting and

cleaning of the B rad waste evaporator.

b.

-Observations and Findings

The inspectors attended meetings and held discussion with ALARA planning,

system engineering and other personnel involved with the B evaporator

maintenance task. The inspectors' main focus was on ALARA practices for

cleaning evaporator internals. A post maintenance critique meeting was also

observed.

The inspectors noted that this job had potential for significant dose accumulation

and that good ALARA planning and interdepartmental communication would be.

required to achieve a low total dose. Maintenance on the evaporator was being

performed because of the overall poor material condition of the-evaporator system.

Auxiliary components were also scheduled for maintenance, besides cleaning

evaporator internals. In addition, operations viewed system performance and

reliability as poor.

,'

Engineering had determined that cleaning evaporator internals would improve

system performance. The method the licensee chose to clean the evaporator was

hydrolazing. Based on past experience, the inspectors questioned why a citric acid

flush of the evaporator was not considered. The licensee responded that although

a citric acid flush was considered, it had not been fully evaluated. The assumption

was environmental engineering would disapprove a citric acid flush because of the

amount of mixed radwaste generated.

After accessing the evaporator internals the licensee began to hydrolaze. Due to

the construction of the evaporator, the licensee found that most of the internals

were not accessible for hydrolazing. At the outset of th_e work, the inspectors

asked system engineering for work specific drawings. System engineering

responded that no drawings were available and the specific vendor was thought to

no long-er exist. -The inspectors, through discussions with the licensee, --*- -

-- ----

found cognizant individuals within the licensee's organization who were

knowledgeable of the vendor and confirmed the inspector's supposition that the

vendor still existed.

14

A contractor engineer had discussed how many evaporator steam tubes could be

plugged. This information was not relayed rad protection to the engineers or

ALARA coordinators planning the job. Although detailed drawings of the

evaporator were not available, vendor personnel responsible for the original

installation relayed important and previously misunderstood operational information

that would have made a detailed inspection of the evaporator internals unnecessary

prior to the planned maintenance.

The inspectors noted in the post maintenance critique a failure to fully investigate

the feasibility of a citric acid cleaning, especially after the problems encountered

with hydrolazing. The total dose expended for the evaporator internals inspection

and cleaning was approximately 350 mrem. The maintenance window to allow for

the reconditioning of the entire B evaporator system was large - at least three

.weeks. Even after the licensee knew the vendor still existed, the job continued as

originally planned without considering the information supplied by the vendor.

c.

Conclusions

The inspectors determined that the post maintenance critique did not fully address

other options available to reduce dose during evaporator cleaning activities.

Critique meeting participants characterized the evaporator cleaning as a low dose

job (less than or equal to 10 mrem) when in fact the licensee had expended

approximately 350 mrem for a job that may not have been required. The inspectors

  • concluded that the evaporator cleaning job did not have proper emphasis placed on

A LARA planning.

V. Management Meetings

X1

Exit Meeting Summary

The inspectors presented the inspection results to members of licensee

management at the conclusion of the inspection on July 7, 1997. No proprietary

information was identified.

15

PARTIAL LIST OF PERSONS CONT ACTED

Licensee

R. A. Fenech, Senior Vice President,

Nuclear, Fossil, and Hydro Operations

T. J. Palmisano, Site Vice President - Palisades

G. B. Szczotka, Manager, Nuclear Performance Assessment Department

D. W. Rogers, General Manager, Plant Operations

D. P. Fadel, Director of Engineering

S. Y. Wawro, Director, Maintenance and Planning

J. L. Hanson, Director, Strategic Business Issues

R. J. Gerling, Design Engineering Manager

A. L. Williams, Acting Manager, System Engineering

T. C. Bordine, Manager, Licensing

J. P. Pomeranski, Manager, Maintenance

D. G. Malone, Shift Operations Supervisor

M. P. Banks, Manager, Chemical & Radiation Services

K. M. Haas, Manager, Training

IP 37551:

IP 61726:

IP 62707:

IP 71707:

IP 71750:

IP 83750:

INSPECTION PROCEDURES USED

Onsite .Engineering

Surveillance Observations

Maintenance Observation

Plant Operations

Plant Support Activities

Occupational Radiation Exposure

ITEM OPENED

50-255/97008-01

VIO

Exceeding licensed thermal power limits

None

ALARA

AOO

AVE

ccw

CE

CFR

CPC

CROM

CV

OBA

DRP

EA

ECCS

FSAR

GL

GPM

GOP

HPSI

HXH

l&C

UC

MREM

Mwt

NRC

NRR

NSO

PCS

PCV

PDR

ITEMS CLOSED

LIST OF ACRONYMS USED

As Low As Reasonably Achievable

Anticipated Operational Occurrence

Average

Component Cooling Water

Combustion Engineering

Code of Federal Regulations

Core Protection Calculator

Control Rod Drive Mechanism

  • Control Valve

Design Basis Accident

Division of Reactor Projects

Enforcement Action

. Emergency Core Cooling System

Final Safety Analysis Report

Generic Letter

Gallons per minute

General Operating Procedure

High Pressure Safety Injection

Heat Exchanger

Instrumentation & Control

Level Instrument Controller


Milli~Rem

Megawatts Thermal

Nuclear Regulatory Commission

Nuclear Regulatory Research

Nuclear Shift Operator

Primary Coolant System

Pressure Control Valve

Public Document Room

..

P-L

PMT

PPAC

RV

SDC

SIS

sv

Tl

TIA

T-ref

TR.

TS

TYT

UFM

VIO

~ --- --- -----

Part-Length

Post Maintenance Test

Periodic & Predetermined Activity Control

Relief Valve

Shutdown Cooling

Safety Injection System

Solenoid Valve

Temperature Indicator

Task Interface Agreement

Temperature - Reference

Temperature Recorder

Technical Specification

Temperature Transmitter

_Ultrasonic Flow Measurement

Violation