MONTHYEARML17284A9121999-10-13013 October 1999 Proposed Tech Specs 3.3.6.1,Table 3.3. 6.1-1, Primary Containment Isolation Instrumentation. ML17284A8521999-07-29029 July 1999 Proposed Tech Specs 3.4.9, RHR Shutdown Cooling Sys - Hot Shutdown. ML17284A8491999-07-29029 July 1999 Proposed Tech Specs,Revising SR 3.5.2.2 Re Condensate Storage Tank Water Level ML17284A8461999-07-29029 July 1999 Proposed Tech Specs,Revising Table 3.3.5.1-1, ECCS Instrumentation Items 1.a,2.a,4.a & E.A. ML17284A8421999-07-29029 July 1999 Proposed Tech Specs Revising SR of TS 3.8.4, DC Sources - Operating & SR 3.8.5.1 of TS 3.8.5, DC Sources - Shutdown. ML17333A0021999-04-20020 April 1999 Proposed Tech Specs Section 3.4.11,replacing Existing Reactor Pressure Temp Limit Curves by 000630 ML17292B6341999-04-0707 April 1999 Proposed Tech Specs Modifying MCPR Safety Limits to Allow Continued Power Operation at Plant Following Restart from R-14 RFO ML17292B4881998-12-17017 December 1998 Proposed Tech Specs SR 3.8.1.8,allowing Capability to Manually Transfer Between Preferred & Alternate Offsite Power Sources During Modes 1 & 2 by 990125 ML20198A7051998-11-30030 November 1998 Revs 8 Through 13 to TS Bases & Revs 12 Through 15 of Licensee Controlled Specs ML17284A7181998-08-0505 August 1998 Proposed Tech Specs SR 3.8.4.7,allowing Performance Discharge Test to Be Performed in Lieu of Battery Svc Test for Div 1 & 3,125 Vdc Batteries E-B1-1 & HPCS-B1-DG3 & Div 1,250 Vdc Battery E-B2-1 ML17284A7071998-07-17017 July 1998 Proposed Tech Specs Modifying SR 3.8.4.7 to Allow Performance Discharge Test to Be Performed in Lieu of Battery Svc Test for Div 2,125 Vdc,Battery E-B1-2 ML17292B2831998-03-0909 March 1998 Proposed Tech Specs Establishing Interim SLMCPR for Siemens Power Corp ATRIUM-9X Fuel Applicable to Cycle 14 Only ML17292B1321997-12-0404 December 1997 Proposed Tech Specs Modifying Min Critical Power Ratio Safety Limits ML17292B0281997-08-14014 August 1997 Proposed Tech Specs Revising TS 5.5.6 by Adding Note That Would Extend Interval Requirement to Perform Full Stroke Exercise Testing of TIP-V-6 Until 1998 Refueling Outage ML17292A9691997-08-12012 August 1997 Proposed Tech Specs Supporting Request for Enforcement Discretion for Period of 45 Days from TS Action 3.6.1.3.A Required Actions to Isolate Purge Line & Verify Penetration Flow Path Isolated Every 31 Days ML17292A9421997-07-16016 July 1997 Proposed Tech Specs Adding New Min Reactor Vessel Pressure Versus Reactor Vessel Metal Temp (P/T) Curves,Applicable Up to 12 EFPYs ML17292A8901997-06-0606 June 1997 Revised Tech Spec Page 2.0-1 Modified to Indicate That SLMCPR for ATRIUM-9X Fuel Applies Only to Cycle 13 & Corresponding Bases Pages ML17292A8651997-05-20020 May 1997 Proposed Tech Specs,Requesting Mod of Minimum Critical Power Ratio Safety Limits by 970615 ML17292A7631997-03-24024 March 1997 Rev 7 to Licensee Controlled Specs. ML17292A7621997-03-24024 March 1997 Rev 5 to TS Bases. ML17292A7581997-03-22022 March 1997 Proposed Tech Specs Modifying Response Time Testing SR for RPS Instrumentation,Primary Containment Isolation Actuation Instrumentation & ECCS Actuation Instrumentation ML17292A7531997-03-20020 March 1997 Proposed Tech Specs Re Response Time Testing Requirements ML17292A6591997-01-14014 January 1997 Proposed Tech Specs Reflecting Compilation of TS Change Requests Submitted to NRC in Ltrs Dtd 951208,960709 & 1212 ML17292A6341996-12-12012 December 1996 Proposed Tech Specs Requesting Conversion Based Upon NUREG-1434,rev 1 ML17292A5511996-10-15015 October 1996 Proposed Tech Specs Re Secondary Containment & SGTS to Reflect Revised Secondary Containment Drawdown & post- Accident Analyses Results ML17292A5411996-10-10010 October 1996 Proposed Tech Specs Requesting Addition of Section 2B(6) Re Storage of Byproduct,Source & Special Nuclear Materials ML17292A4501996-09-0606 September 1996 Proposed Tech Specs,Containing Corrections to Factual Statements & Proposed Info to Clarify Evaluations ML17292A4111996-08-0909 August 1996 Proposed Tech Specs,Revising TS Section 6.3 Re Unit Staff Qualifications,By Changing Operations Manager Qualification Requirements Associated W/Operations Knowledge from Meeting Ansi/Ans N18.1-1971 ML17292A3561996-07-0909 July 1996 Proposed Tech Specs,Revising Rev a, Including Changes in Vol 7.Proposed Rev Does Not Change Conclusion of NSHC or Environ Assessment Provided Rev a ML20107M3391996-04-24024 April 1996 Proposed Tech Specs,Modifying TS to Support Cycle 12, Scheduled to Begin Subsequent to Spring 1996 Outage ML17292A1511996-04-22022 April 1996 Proposed Tech Specs,Supplementing TS That Describes Administrative & Editorial Changes to Section 6.0, Administrative Controls. ML17291B2801996-03-19019 March 1996 Proposed Tech Specs Re Containment Leakage Testing ML17291B2491996-02-26026 February 1996 Proposed Tech Specs,Submitting Revised Copy of TS Bases Which Include Minor Changes & Clarifications Made Per Requirements of 10CFR50.59 ML17333A0201996-01-19019 January 1996 Proposed Tech Specs Re Primary Containment Leakage Testing ML17291B0941995-10-26026 October 1995 Proposed Tech Specs,Replacing Existing Reactor Recirculation Flow Control Sys W/Adjustable Speed Drive Sys ML17291A9911995-08-16016 August 1995 Proposed Tech Specs Page 3/4 4-4,incorporating Surveillance Notes in Front of Surveillances 4.4.1.2.1 & 4.4.1.2.2 for Jet Pump Operability to Clarify That Notes Apply to Each Surveillance ML17291A8441995-06-0606 June 1995 Proposed Tech Specs Section 6.0, Administrative Controls. ML17291A8401995-06-0606 June 1995 Proposed Tech Specs Index,Deleting Ref to Bases Pages ML17291A8371995-06-0606 June 1995 Proposed Tech Specs Section 6.9.3.2,adding Ref to Three TRs Describing Analytical Methods That May Be Used in Determining Reactor Core Operating Limits for Reload Licensing Applications ML17291A7561995-04-25025 April 1995 Proposed Tech Specs,Adding RWCU Sys High Blowdown Containment Isolation Trip Function & Associated LCO & SRs to Tables 3.3.2-1,3.3.2-2 & 4.3.2.1-1 ML17291A6541995-02-10010 February 1995 Proposed Tech Specs,Modifying Surveillance Acceptance Criteria from 10% to 20% for Individual Jet Pump diffuser- to-lower Plenum Differential Pressure Variations of Individual Jet Pump from Established Patterns ML17291A4811994-10-31031 October 1994 Proposed Tech Spec Relocating Safety/Relief Valve Position Indication Instrumentation Requirements ML17291A4781994-10-31031 October 1994 Proposed Tech Spec 3/4.1.3.1, Reactivity Control Sys. ML17291A4451994-10-12012 October 1994 Corrected Proposed TS Bases 3/4.2.6, Power/Flow Instability. ML17291A4221994-09-26026 September 1994 Proposed Tech Specs,Reflecting Use of Siemens Power Corp Staif Code for Stability Analysis,Per Ieb 88-007,Suppl 1 ML17291A3981994-09-18018 September 1994 Proposed TS Table 3.6.3-1 Re Primary Containment Isolation Valve Requirements ML17291A3191994-08-0808 August 1994 Proposed Tech Specs 4.0.5 Re Guideliness for Inservice Insp & Testing Program ML17291A2171994-07-12012 July 1994 Proposed Tech Specs for Relocation of TS Tables for Instrument Response Time Limits ML17291A2221994-07-0808 July 1994 Proposed TS W/Regard to Control Rod Scram Insertion Testing Under Emergency Circumstances ML17291A1561994-06-23023 June 1994 Proposed Tech Specs Re Supporting Hydrostatic Testing 1999-07-29
[Table view] Category:TECHNICAL SPECIFICATIONS & TEST REPORTS
MONTHYEARML17284A9121999-10-13013 October 1999 Proposed Tech Specs 3.3.6.1,Table 3.3. 6.1-1, Primary Containment Isolation Instrumentation. ML17284A8761999-08-27027 August 1999 Replacement Page 9 of 9 to Attachment 4 of Procedure 13.10.6 ML17284A8491999-07-29029 July 1999 Proposed Tech Specs,Revising SR 3.5.2.2 Re Condensate Storage Tank Water Level ML17284A8421999-07-29029 July 1999 Proposed Tech Specs Revising SR of TS 3.8.4, DC Sources - Operating & SR 3.8.5.1 of TS 3.8.5, DC Sources - Shutdown. ML17284A8461999-07-29029 July 1999 Proposed Tech Specs,Revising Table 3.3.5.1-1, ECCS Instrumentation Items 1.a,2.a,4.a & E.A. ML17284A8521999-07-29029 July 1999 Proposed Tech Specs 3.4.9, RHR Shutdown Cooling Sys - Hot Shutdown. ML17333A0021999-04-20020 April 1999 Proposed Tech Specs Section 3.4.11,replacing Existing Reactor Pressure Temp Limit Curves by 000630 ML17292B6341999-04-0707 April 1999 Proposed Tech Specs Modifying MCPR Safety Limits to Allow Continued Power Operation at Plant Following Restart from R-14 RFO ML17292B5731999-03-0101 March 1999 ODCM for WNP-2 ML17292B4881998-12-17017 December 1998 Proposed Tech Specs SR 3.8.1.8,allowing Capability to Manually Transfer Between Preferred & Alternate Offsite Power Sources During Modes 1 & 2 by 990125 ML20198A7051998-11-30030 November 1998 Revs 8 Through 13 to TS Bases & Revs 12 Through 15 of Licensee Controlled Specs ML17284A7181998-08-0505 August 1998 Proposed Tech Specs SR 3.8.4.7,allowing Performance Discharge Test to Be Performed in Lieu of Battery Svc Test for Div 1 & 3,125 Vdc Batteries E-B1-1 & HPCS-B1-DG3 & Div 1,250 Vdc Battery E-B2-1 ML17284A7071998-07-17017 July 1998 Proposed Tech Specs Modifying SR 3.8.4.7 to Allow Performance Discharge Test to Be Performed in Lieu of Battery Svc Test for Div 2,125 Vdc,Battery E-B1-2 ML17284A6431998-05-29029 May 1998 Revised Plant Procedure Sys for Site Wide Procedures, Replacing Pages Located in Manual W/Pages in Package ML17292B2831998-03-0909 March 1998 Proposed Tech Specs Establishing Interim SLMCPR for Siemens Power Corp ATRIUM-9X Fuel Applicable to Cycle 14 Only ML17292B2591998-01-31031 January 1998 Offsite Dose Calculation Manual. ML17292B1321997-12-0404 December 1997 Proposed Tech Specs Modifying Min Critical Power Ratio Safety Limits ML17292B0281997-08-14014 August 1997 Proposed Tech Specs Revising TS 5.5.6 by Adding Note That Would Extend Interval Requirement to Perform Full Stroke Exercise Testing of TIP-V-6 Until 1998 Refueling Outage ML17292A9691997-08-12012 August 1997 Proposed Tech Specs Supporting Request for Enforcement Discretion for Period of 45 Days from TS Action 3.6.1.3.A Required Actions to Isolate Purge Line & Verify Penetration Flow Path Isolated Every 31 Days ML17292A9421997-07-16016 July 1997 Proposed Tech Specs Adding New Min Reactor Vessel Pressure Versus Reactor Vessel Metal Temp (P/T) Curves,Applicable Up to 12 EFPYs ML17292A8901997-06-0606 June 1997 Revised Tech Spec Page 2.0-1 Modified to Indicate That SLMCPR for ATRIUM-9X Fuel Applies Only to Cycle 13 & Corresponding Bases Pages ML17292A8651997-05-20020 May 1997 Proposed Tech Specs,Requesting Mod of Minimum Critical Power Ratio Safety Limits by 970615 ML17292A8301997-03-31031 March 1997 Wppss WNP-2 RPV Surveillance Matls Testing & Analysis. ML17292A7621997-03-24024 March 1997 Rev 5 to TS Bases. ML17292A7631997-03-24024 March 1997 Rev 7 to Licensee Controlled Specs. ML17292A7581997-03-22022 March 1997 Proposed Tech Specs Modifying Response Time Testing SR for RPS Instrumentation,Primary Containment Isolation Actuation Instrumentation & ECCS Actuation Instrumentation ML17292A7531997-03-20020 March 1997 Proposed Tech Specs Re Response Time Testing Requirements ML17292A6591997-01-14014 January 1997 Proposed Tech Specs Reflecting Compilation of TS Change Requests Submitted to NRC in Ltrs Dtd 951208,960709 & 1212 ML17292A6341996-12-12012 December 1996 Proposed Tech Specs Requesting Conversion Based Upon NUREG-1434,rev 1 ML17292A6161996-11-19019 November 1996 Rev 1 to WNP-2 IST Program Plan (Pumps & Valves) 2nd Interval (941213-041212). ML17292A5511996-10-15015 October 1996 Proposed Tech Specs Re Secondary Containment & SGTS to Reflect Revised Secondary Containment Drawdown & post- Accident Analyses Results ML17292A5411996-10-10010 October 1996 Proposed Tech Specs Requesting Addition of Section 2B(6) Re Storage of Byproduct,Source & Special Nuclear Materials ML17292A4501996-09-0606 September 1996 Proposed Tech Specs,Containing Corrections to Factual Statements & Proposed Info to Clarify Evaluations ML17292A4111996-08-0909 August 1996 Proposed Tech Specs,Revising TS Section 6.3 Re Unit Staff Qualifications,By Changing Operations Manager Qualification Requirements Associated W/Operations Knowledge from Meeting Ansi/Ans N18.1-1971 ML17292A3561996-07-0909 July 1996 Proposed Tech Specs,Revising Rev a, Including Changes in Vol 7.Proposed Rev Does Not Change Conclusion of NSHC or Environ Assessment Provided Rev a ML17292A7241996-05-31031 May 1996 Offsite Dose Calculation Manual. ML17292A2741996-04-25025 April 1996 Rev 0 to UT-WNP2-208V0, Exam Summary Sheet. ML20107M3391996-04-24024 April 1996 Proposed Tech Specs,Modifying TS to Support Cycle 12, Scheduled to Begin Subsequent to Spring 1996 Outage ML17292A1511996-04-22022 April 1996 Proposed Tech Specs,Supplementing TS That Describes Administrative & Editorial Changes to Section 6.0, Administrative Controls. ML17291B2801996-03-19019 March 1996 Proposed Tech Specs Re Containment Leakage Testing ML17291B2491996-02-26026 February 1996 Proposed Tech Specs,Submitting Revised Copy of TS Bases Which Include Minor Changes & Clarifications Made Per Requirements of 10CFR50.59 ML17333A0201996-01-19019 January 1996 Proposed Tech Specs Re Primary Containment Leakage Testing ML17291B1751995-12-31031 December 1995 Reactor Power Uprate Startup Test Rept, for WNP-2. W/951215 Ltr ML17291B0941995-10-26026 October 1995 Proposed Tech Specs,Replacing Existing Reactor Recirculation Flow Control Sys W/Adjustable Speed Drive Sys ML17291A9911995-08-16016 August 1995 Proposed Tech Specs Page 3/4 4-4,incorporating Surveillance Notes in Front of Surveillances 4.4.1.2.1 & 4.4.1.2.2 for Jet Pump Operability to Clarify That Notes Apply to Each Surveillance ML17291A9591995-07-28028 July 1995 Operations Instructions OI-23,Rev a to, Human Performance Improvement Program. ML20087E2831995-07-26026 July 1995 Performance Enhancement Strategy 1995 ML17291A8401995-06-0606 June 1995 Proposed Tech Specs Index,Deleting Ref to Bases Pages ML17291A8371995-06-0606 June 1995 Proposed Tech Specs Section 6.9.3.2,adding Ref to Three TRs Describing Analytical Methods That May Be Used in Determining Reactor Core Operating Limits for Reload Licensing Applications ML17291A8441995-06-0606 June 1995 Proposed Tech Specs Section 6.0, Administrative Controls. 1999-08-27
[Table view] |
Text
PLANT SYSTEMS ULTIMATE HEAT SINK LIMITING CONOITION FOR OPERATION Da<676 3.7.1.3 The ultimate heat sink consisting of two separate spray ponds shall be OPERABLE with:
Dmtmn o.
- a. A minimum water USGS datum, and level at elevation 432 ft 9 in. Mean Sea L'evel,
- b. A water temperature of less than or equal to 77 F.
- c. A maximum on average sediment depth of less than or equal to 0.5 the floors of the spray ponds.
ft APPLICABILITY: OPERATIONAL CONOITIONS I, 2, 3', 4, 5, and *.
ACTION:
With the requirements of the above specification not satisfied:
In OPERATIONAL CONOITIOH 1,~.2, or 3, be in at least HOT SHUTDOWN within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> and in COLO SHUTDOWN within the next 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />.
w ~~)
- b. In OPERATIONAL CONOITIO(>4 or 5, declare the SW system inoperable and take the ACTION-"r'equired by Specification 3.7.1.1.
(g gc j,0j'~y~Q ~ i'd% mC ihopcnrCb 6 c In QPERATIQNAL coNQITICN *, declare the system inoperable and sprg the ACTION required by Specification 3.7. 1.1. The provisions P'ake of Specification 3.0.3 are not applicable.
- d. With the average sediment depth of either of the spray ponds greater than or equal to 0.5 ft but less than 1.0 ft, the ponds shall be cleaned within 30 days to reduce the average sediment depth to less than or equal to 0. 1 ft.
SURVEILLANCE REOUIREMEHTS 4.7. 1.3 The ultimate heat sink shall be determined OPERABLE at least once per:
- a. 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> by verifying the water temperature and water level to be within their limits.
- b. 92 days by verifying that the average sediment depth in each of the spray ponds is less than or equal to 0.5 ft.
When handling irradiated fuel in he secondarv containment, WASHINGTON NUCLEAR
~
UNIT 2 3/4 7-4 86033i0270 86032i PDR ADOCK 05000397, P PDR
ATTACHMENT I Safet Evaluation of Standi Service Mater Cross-Connection In order to allow for infrequent maintenance of submerged steel structural supports and piping in the ultimate heat sink (UHS) spray ponds, it necessary that we drain the ponds one at a time during a refueling outage.
is The present system design results in the service water (SM) pumps taking suction on one pond, providing cooling water to plant room coolers and essential equipment, returning cooling water to the other pond for spray cooling, and returning water to the pump suction in the first pond via a 30 inch siphon. This mode of operation precludes draining of a pond for maintenance. A design change is planned that will allow the return of water to the pond from which it was drawn., The change involves the cross connection of the return piping via a removable spool piece, and the blockage of the siphon with inflatable plugs. One pond can be drained with this cross connection capability in place.
The safety implications of the cross connection focus in four areas:
I) redundancy requirements of the SW system, 2) UHS water inventory requirements, 3) UHS cooling water temperature limitations, and 4) severe natural phenomena.
Redundanc Re uirements The intended use of the cross connection is only during the "star" mode defined in the Technical Specifications, that is, with the reactor shut down, in refueling mode, with the vessel head off and cavity flooded at least 22 feet above the vessel flange. In .this mode the technical specifications require only that one SW division be operable, and that alternate means be shown to be available within one hour is lost.
if that division With one spray pond drained and the siphon plugged with inflatable plugs, it is possible to restore the division associated with the drained pond in a very short time. The water level in the full pond is above the highest point of the siphon, so flow will proceed automatically through the siphon if the inflatable plugs are deflated. Since the siphon plugs can be deflated from the edge of the pond, that flow can be established quickly. Within one hour the previously inoperable division could be brought on line.
UHS Water Inventor Mith one pond drained, the water inventory is approximately half of that normally available. However, the severe heat loads associated with the aesign basis accident can not occur in>the refueling mode and considerably less water is required. An evaluation was done to determine the length of time the water in one pond would last makeup and without2offsite power.
if cooling were requi red without Heat loads associated with previously analyzed accidents were used including diesel generators, decay heat from the core, decay heat from the fuel pool, and from auxiliaries (room coolers, etc.). Design basis drift loss and leakage were assumed. The results of our evaluation indicate that the water inventory of one pond would last over 22 days.
ATTACHMENT I Contd.
While the normal 30 day inventory requirement is not met in this mode of operation, the probability of significant radioactive release is extremely small with the plant shut down in the refueling mode. We would have free movement about the site and have documented experience that with freedom of movement, makeup water can be provided. For example, temporary pipe lines from the river have, in the past, been installed in about 3 days. In addition, one tower makeup pump (12,500 gpm each) can be powered by emergency diesels if piping remains intact.
The 22 day inventory provides adequate time to provide makeup via temporary or installed systems. Long term cooling water supply can be assured.
UHS Coolin Water Tem erature 2
The safety analyses reported in the FSAR were performed under the worst case meteorological conditions and using severe heat loads associated with a design basis accident. In providing the cross-connection during refueling and draining one pond, we have not diminished the heat dissipation capability of the system. Heat dissipation in the sprays is a function of flow rate and meteorological conditions, and the worst case analysis for cooling water temperatures reported in the FSAR used one SW division operable. The effect of the reduction in inventory is a more rapid response to heat load changes. Since the plant is not under-going a rapid transient accident in the case we are evaluating here, the importance of the response time is minimal. The heat loads are relatively stable during the cross connection operation which will be several days after shutdown.
Long term p)ant heat loads during refueling are bounded by those reported in the FSAR for the accident case, and temperature of cooling water would therefore be the same or lower.
Our conclusion is that the maximum temperature reported in the FSAR is bounding for the intended use of the SW cross connection.
Severe Natural Phenomena The major natural phenomena affecting the UHS spray ponds are earthquakes and tornados. If an SSE were to occur during cross-connection use, the operable SW division would continue to serve the plant and the emergency diesel generators. Makeup from the river would potentially be lost due to loss of the Seismic Category II pipe line, but the previous evaluations indicate cooling would continue. Temporary lines could be installed in the 22 days cooling that the inventory would provide. If a tornado were to damage the spray headers or remove some water, the emergency diesel power connection to the tower makeup pumps on the river would assure sufficient cool river water to pryvide essentially once through cooling, the same as described in the FSAR .
ATTACHMENT I Contd.
Conclusion It is our conclusion from the evaluation performed that the cross connection meets safety requirements and that it can be installed when the plant is in refueling mode "star" as described in the Technical Specifications.
Supply System Calculation ME-02-85 "Evaluation of SSl< Cross Connection" FSAR Section 9.2.5
ATTACHMENT II Standby Service Water Flow Paths Cross Connection Locatio Pond B 30" Si Pond A B Pumphouse Division B Return Pump See Detail A A Pumphouse Pump DETAIL A Division B Return O O Grade El. ~
O p ~
O p
C/l Cil Cil U)
I
~
)
I f
CD CD Div. A Return CD Flanged removable Spool Piece and Valve. All piping is 18"P.
NOTE: Nor~ally spool piece cross connection and valve are removed and connections to return line are blind flanged. During outage when draining a pond (plant in mode "*") the spool piece may be installed to allow aligning valves so B return can go to B pond and vice versa for A.
- Division A Return runs underground between ponds.