Rev 0 to EOP AP-RCC.3, Dropped Rod Recovery
ML17263A260
Person / Time
Site: Ginna Constellation icon.png
Issue date: 04/21/1993
From: Marlow T
ROCHESTER GAS & ELECTRIC CORP.
To:
Shared Package
ML17263A255 List:
References
AP-RCC.3, NUDOCS 9305140022
Download: ML17263A260 (14)


Text

EOP:

AP-RCC.3 T1TLE:

DROPPED ROD RECOVERY REV:

0 PAGE 1 of 7 ROCHESTER GAS AND ELECTRIC CORPORATION GINNA STATION CONTROLLED COPY NUMBER TECHNICAL REVIEW PORC REVIEW DATE / +~ 9~

LANT SUPERINTENDENT EFFECTIVE DATE CATEGORY 1.0 REVIEWED BY:

qg05140022 500024 PDR ADQCK 0 PDR I

F

EOP:

AP-RCC.3 DROPPED ROD RECOVERY REV:

0 PAGE 2 of 7 A.

PURPOSE This procedure provides the guidance necessary to control the plant during a transient resulting, from a dropped control rod.

B.

ENTRY CONDITIONS/SYMPTOMS 1.

SYMPTOMS The symptoms of dropped control rod are; a.

Annunciator E-28, POWER RANGE ROD DROP ROD STOP

-54/5 SEC, lit, or b.

Annunciator C-14, ROD BOTTOM ROD STOP, lit, or c.

MRPI Indicates control rod(s) on bottom, or

EOP:

AP-RCC.3 TITLE:

DROPPED ROD RECOVERY REV:

0 PAGE 3 of 7 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED CAUTION o

IF AT ANY TIME DURING THIS PROCEDURE, A REACTOR TRIP OR SI OCCURS, THEN E-O, REACTOR TRIP OR SAFETY INJECTION, SHALL BE PERFORMED.

o BANK ROD WITHDRAWAL SHOULD NOT BE PERFORMED UNTIL THE MISALIGNED ROD IS RECOVERED.

NOTE:

A NIS or MRPI dropped rod signal will block AUTO out rod motion.

1 Place Rod Control Bank Selector Switch TO MANUAL 2

Check RCS Tavg STABLE AT PROGRAM Perform the following:

a.

Place EH control in MANUAL.

b. Manually reduce turbine load as necessary to match Tavg and Tref.

3 Verify Annunciator G-15, STEAM DUMP ARMED EXTINGUISHED Verify steam dump valves closed.

IF NOT, THEN place STEAM DUMP MODE SELECTOR switch to MANUAL and close valves.

4 Check Main Generator Load GREATER THAN 15 MW IF load can NOT be stabilized above 15 MW, THEN trip turbine and go to AP-TURB.1, TURBINE TRIP WITHOUT RX TRIP REQUIRED, Step 1.

C+

EOP:

AP-RCC.3 DROPPED ROD RECOVERY REV:

0 PAGE 4 of 7 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED 5 Establish Stable Plant Conditions:

a.

Tavg - TRENDING TO TREF b.

PRZR pressure

- TRENDING TO 2235 PSIG

a. Insert control rods or, if

.necessary, decrease turbine load to match Tavg to Tref.

b. Verify proper operation of PRZR heaters and spray or take manual control of PRZR pressure controller 431K.

IF pressure can NOT be controlled, THEN refer to AP-PRZR.l, ABNORMAL PRESSURIZER PRESSURE.

c.

PRZR level

- TRENDING TO PROGRAM

c. Verify proper operation of charging pump speed controllers or take manual control of speed controllers to control PRZR level.

6 Check REGEN Hx Letdown Indications:

o Annunciator A-4, REGEN HX LETDOWN OUT HI TEMP 395'F-EXTINGUISHED o

REGEN Hx letdown outlet temperature

- STABLE OR DECREASING Adjust charging flow and HCV-142 as necessary to control REGEN Hx letdown outlet temperatures IF REGEN Hx letdown outlet temperature can NOT be controlled, THEN perform the following:

a.

Close all letdown orifice valves (AOV-200A, AOV-200B and AOV-202).

b. Close loop B to REGEN Hx isolation valve (AOV-427).

Ca

EOP:

AP-RCC.3 DROPPED ROD RECOVERY REV:

0 PAGE 5 of 7 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED 7

Check QPTR LESS THAN 1.02 IF QPTR greater than 1.02, THEN computer value should be verified using 0-6.4 to prevent action based on failed computer inputs.

8 Evaluate Control Rod Operability:

a. Verify MRPI indicates rod on bottom a.

Perform the following:

1) Verify all NIS power range channels approximately equal.

IF NOT, THEN defeat failed channel (Refer to ER-NIS.3, PR MALFUNCTION).

b. Direct I&C to locally investigate rod failure c.

Rod failure identified and corrected DROPPED ROD REPAIRED

d. Retrieve dropped rod (Refer to ER-RCC.1, RETRIEVAL OF A DROPPED ROD) 2)

Go to Step 9.

c. Consult Reactor Engineer and Tech Spec 3.10.4.3 for operational concerns.

c~

EOP:

AP-RCC.3 T1TLE DROPPED ROD RECOVERY REV:

0 PAGE 6 of 7 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED 9

Establish Normal Plant Conditions:

a. Verify EH control in AUTO IMP IN
a. IF conditions requiring runback have cleared, THEN place EH in AUTO IMP IN'.

Verify steam dump controller, HC-484, in AUTO at 1005 psig

c. Verify annunciator G-15, STEAM DUMP ARMED - EXTINGUISHED
c. IF Tavg within 6'F of Tref, THEN perform the following:
1) Ensure steam dump valves closed.

~

d.

Rod insertion limit alarms-EXTINGUISHED e.

NIS PR AI - WITHINi 5%

OF TARGET VALUE

2) Reset steam dump.
d. Borate as necessary and withdraw control rods to clear insertion limit alarms (refer to affected rod bank alarm response procedures if necessary).
e. Borate/dilute to restore AI to within limits.
f. Verify charging pump speed control in AUTO
f. Place charging pump speed control in AUTO if desired.
g. Verify Rod Control Selector Switch in AUTO
g. Place Rod Control Selector Switch in AUTO if desired.

Fa

EOP:

AP-RCC.3 DROPPED ROD RECOVERY REV:

0 PAGE 7 of 7 STEP ACTION/EXPECTED RESPONSE

RESPONSE

NOT OBTAINED NOTE:

Refer to 0-9.3, NRC IMMEDIATE NOTIFICATION, for reporting requirements.

10 Notify Higher Supervision 11 Return To Procedure Or Guidance In Effect

-END-