IR 05000335/1998302

From kanterella
(Redirected from ML17229B052)
Jump to navigation Jump to search
NRC Operator Licensing Exam Repts 50-335/98-302 & 50-389/98-302 (Including Completed & Graded Tests) for Tests Administered on 981130,1204 & 14-18
ML17229B052
Person / Time
Site: Saint Lucie  
Issue date: 01/26/1999
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17229B050 List:
References
50-335-98-302, 50-389-98-302, NUDOCS 9903170390
Download: ML17229B052 (15)


Text

U. S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket Nos.:

50-335, 50-389 License Nos.: DRP-67, NPF-16 Report Nos.:

50-335/98-302, 50-389/98-302 Licensee:

Florida Power 8 Light Co.

Facility:

St. Lucie Nuclear Plant, Units 1 & 2 Location:

6351 South Ocean Drive Jensen Beach, Florida Dates:

November 30 - December 4 and December 14 - 18, 1998, Examiners:

Richard S. Baldwin, Chief License'Examiner Ronald F. Aiello, License Examiner Paul M. Steiner, License Examiner Approved by: Harold O. Christensen, Chief Operator Licensing and Human Performance Branch Division of Reactor Safety 9903i70390 9903i2 PDR ADOCK 05000335 U

PDR Enclosure

EXECUTIVESUMMARY St. Lucie Nuclear Plant, Units 1 8 2 NRC Examination Report No. 50-335/98-302 and 50-389/98-302 During the periods of November 30 - December 4 and December 14 - 18, 1998, NRC examiners conducted an announced operator licensing initial examination in accordance with the guidance of Examiner Standards (ES), NUREG-1021, Interim Revision 8. This examination implemented the operator licensing requirements of 10 CFR $55.41, f55.43, and f55.45.

Two Senior Reactor Operator (SRO) candidates and six Reactor Operator (RO) candidates received written examinations and operating tests.

One SRO candidate received a retake written examination.

All of the operating examinations were administered by NRC operator licensing examiners.

The written examination was administered by the licensee on December 18, 1998, and the operating tests were administered by the NRC the weeks of November 30 - December 4 and December 14 - 18, 1998.

~oeratinns During observed Control Room activities, the operators were found to be attentive and professional in their duties.

(Section 01.1)

The submitted written examination and operating tests met the requirements of NUREG-1021.

Minor problems were noted in the area of JPM follow-up questions.

The examinations had shown improvement in quality as compared to the 1997 and 1998 examination submittals. (Section 05.1)

Two of nine candidates passed the examination.

Overall performance on the operating test was considered marginal for the SROs and weaker for the ROs. Weaknesses were noted in the areas of developing clearances, identification of radiological posting requirements, manual control of Steam Generator level, and understanding a Component Cooling Water (CCW) system failure. (Section 05.1)

Candidate Pass/Fail Pass Fail SRO

RO Total Percent 22.3 77.7

~

The licensee was effective in conducting training and examinations in the requalification training program. (Section 05.2)

I Summa of Plant Status.

Re ort Details During the period of the examinations Unit 1 was at 100 percent power and Unit 2 was in an.

outage.

Conduct of Operations H

, 01.1 Control Room Observation During validation and administration of the examination, the examiners observed currently licensed operators conduct operations in the control room. The ROs'were attentive to the evolutions in progress.

The SROs limited personnel access for official business personnel only, which contributed to a quiet, professionally managed control room.

Operator Training and Qualifications 05.1 Initial Licensin 'xaminations a.

~Scc e

NRC examiners conducted regular, announced operator licensing initial examinations during the periods of November 30 - December 4, 1998 and December 14 - 18, 1998.

NRC examiners administered examinations developed by the licensee's training department, under the requirements of an NRC security agreement, in accordance with the guidelines of the ES, NUREG-1021, Interim Revision 8. Two SRO instant and six RO applicants received written examinations and operating tests.

One additional SRO instant was administered a retake of the written examination.

b.

Observations and Findin s The licensee developed the.SRO and RO written examinations, three Job Performance Measure (JPM) sets, and four dynamic simulator scenarios, with one spare scenario, for use during the examination.

All materials were submitted to the NRC on or before schedule.

NRC examiners reviewed, modified as necessary, and approved the examination prior to administration.

The NRC conducted an on-site preparation visit during the week of November 16, 1998, to validate examination materials and familiarize themselves with the details required for examination administration.

(1)

Written Examination The examination review was expedited due to the organization of the submitted examination materials.

Relevant portions of the reference materials were attached to each test item.

The licensee sent a representative to the Region II office a number of times to deliver and discuss the examination submittal. This fostered open dialogue leading to the mutual goal of developing a quality examinatio This was the licensee's third time at developing the examinations in accordance with a pilot NRC program whereby licensee's are authorized to write the examinations.

The NRC noted'that the quality of the licensee's submittal was-good and had shown improvement as compared to the 1997 and 1998 examination submittals.

Aside from minor editorial changes to clarify or improve the language of the questions, the number of technical errors noted were minimal. Most comments were to assure clarity in the question stem and to enhance the quality of the incorrect distractors.

The final examination was considered a good product, in that, it discriminated a competent from a less than competent candidate.

(2)

Operating Test Development The NRC reviewed three walkthrough examination sets submitted by the facility.

These were. comprised of JPMs and follow-up questions.

Only one walkthrough set was used due to the decrease in the number of candidates.

The examiners found that the JPMs were developed to the appropriate level as described in NUREG-1021. The NRC noted that the quality of some of the JPM follow-up questions were weak. Several JPM questions were considered direct look-up which lacked operational validity and some did not correctly elicit the answer provided. These questions were changed or the use of references were not

.

allowed to answer these questions.

The NRC reviewed four simulator scenarios (plus one spare) develope'd for the

'xamination.

Some changes and additions were made to the scenarios to

~

enhance the examiners opportunity to observe candidates perform all required competencies.

These were corrected during the examination preparation week.

Overall, the scenarios were found to be challenging and at the appropriate level of difficulty. The final scenarios were considered a good examination tool providing discrimination between satisfactory from less then satisfactory performance.

Only two of the scenarios were used due to the decrease in the number of candidates.

During the preparation and examination weeks the examiners found six procedures that were confusing or hard to use.

The facilityacted promptly to resolve these procedural weaknesses.

The facilityadministered the written on December 18, 1998, in accordance with NUREG-1021 and by direction of the examination assignment sheet.

The licensee during the course of the examination requested, by telephone, four, thirty minute extensions to the four hour time period of the examination.

The four extensions were granted by the acting Branch Chief, providing a total of six hours for the written examinatio Examination Results The facilitylicensee submitted post-examination comments for nine written examination questions, of which the NRC accepted four (see Enclosures 3 and 4). The acceptance of these comments did change the outcome of the grading for two of the SRO candidates.

The examiners reviewed the results of the written examination and found that two of nine candidates passed this examination.

Overall SRO candidate performance on the written examination was marginal while RO candidate performance on the written examination was weaker with all candidates failing the examination.

The licensee conducted a post-examination item analysis of the SRO and RO written examinations.

This analysis identified twelve questions where both SRO and RO candidates exhibited knowledge deficiencies.

The analysis also identified four other SRO specific knowledge weaknesses and eight other RO specific knowledge weaknesses.

The examiners concluded that no generic knowledge weaknesses existed where multiple questions on the same system'or topic were missed by a large number of candidates.

Examiners also identified several weaknesses in candidate performance during the operations portion of the examination.

Details of the weaknesses are described in each individual's examination report,, Form ES-303-1, "Operator Licensing Examination Report."

Copies of the evaluations have been forwarded under separate cover to the Training Manager in order to enable the licensee to evaluate the weaknesses and provide appropriate remedial training for those operators, as necessary.

In general, these weaknesses included the following: knowledge of radiological posting requirements, and during the performance of developing a clearance, candidates consistently did not maintain plant configuration control when restoring valves to their required locked position..

During scenario performance examiners noted:

In the area of identification of failed automatic actions, four of four crews identified that the "A"Main Steam Isolation Valve did not close on its closure signal. The candidates took appropriate action to close the valve prior to the SRO reading the Standard Post Trip Actions (SPTA).

During a leak on the CCW. system, with a failure of an isolation to close, four out of four crews failed to understand/recognize what was occurring with the N-header and the "A"and "B" CCW header isolation valves on low CCW. Two of the four crews reinitiated CCW flowfrom the "8" header (not faulted) to the faulted "A"header and therefore reinitiated the leak.

In an attempt to control feed water manually during a high failure of a steam generator steam flow transmitter, four,of four crews were unable to take manual control of the steam generator feed water regulating valve and prevent a reactor trip on high steam generator level. Candidates consistently followed the license'e's communications, briefing and annunciator response procedures in accordance with operations standards and expectation. Conclusions In general, the examiners found that the submitted written examination and operating test met the requirements of NUREG-1021.

Minor problems were noted in the area of JPM follow-up questions.

The examinations had shown improvement in quality as compared to the 1997 and 1998 examination submittals.

Two of nine candidates passed the examination.

Overall performance on the operating test was considered marginal for the SROs and ROs. Weaknesses were noted in the areas of developing clearances, identification of radiological posting requirements, manual control of steam generator level, and understanding a Component Cooling Water (CCW) system failure.

05.2 Licensed Operator Requalification (LOR) Program Evaluation and Training and Qualification Effectiveness a

Ins ection Sco e 41500 71001 The inspector reviewed portions of the licensee's initial and requalification program for initial candidates and currently licensed reactor and senior reactor operators to ensure that proper Emergency Operating Procedure (EOP-01) and Standard Post Trip Actions (SPTAs) training was being conducted.

The inspector reviewed Administrative Procedure AP-0010120, Conduct of Operations, Revisions 102 through 107, and 2-EOP-01, Revisions 16 and 17 to verify that the appropriate actions were being taken to isolate the Steam Generators (SG) following an excessive steam demand event. The inspector also conducted a record review and interviews to verify that the instructors were appropriately delivering information to the classes and that students were being appropriately trained as required by 10 CFR 50.120 and 55.59.

b.

Observations and Findin s The inspector conducted a review of 2-EOP-01, Revisions 16 and 17.

Paragraph 5,

step 7, Contingency Actions, of EOP-01, Revision 16 stated "IfContainment pressure is greater than 3.5 psig, then ensure Safety Injection Actuation Signal (SIAS) and Containment Isolation Actuation Signal (CIAS) have actuated."

Procedure EOP-01 had been revised (Revision 17) to include Main Steam Isolation System (MSIS) actuation verification if containment pressure was greater than or equal to 3.5 psig. This change required operators to ensure MSIS was actuated when required and that steam generators isolated following an excessive steam demand event.

Combustion Engineering EOP Users Guide, CEN-152, stated that the. SPTAs are designed to stabilize the plant, take the minimum actions necessary due to plant conditions to maintain safety functions and diagnose the event(s).

The inspector noted that AP-0010120 was revised twice (Revision 104 and 106) to clarify guidance in the area of operator actions permitted/expected prior to Assistant Plant Supervisor (ANPS)

concurrence and expected operator action while performing EOP-0 In AP-0010120 Revisions 105 and earlier, one licensed operator would perform the SPTAs from memory then the other would verify the previous operator's actions with the procedure.

Consequently two "sets of'eyes" would have reviewed the control boards.

Revisions 106 and 107 required the operators to perform a two minute board walkdown of each of their respective panels from memory. When this review was completed, the ANPS would read the procedure and the operators re-verified the actions they had performed.

The inspectors noted that this "reader/doer" method of executing SPTAs may not be as thorough as the previous method since only one individual was observing his/her respective panel.

There would be only one "set of eyes" per panel. The licensee was soliciting comments from operators on how to best implement the SPTAs. The licensee facilityplans to have this implementation standardized by early 1999.

Licensed operator candidates who were examined during the summer of 1998 received additional training that reiterated the revised expectations thus far. This item is identified as Inspector Followup Item (IFI) 50-335,389/98-302-01, EOP-01, Standard Post Trip Actions, Implementation.

The inspector conducted a record review and interviews to verify that the instructors were appropriately delivering information during requalification training and the operators were being appropriately trained. The inspector identified that the 1998 operator training schedule, class content, and simulator training was planned, developed and scheduled at the beginning of the class year. Regular simulator demonstrations were added to the training classes of each cycle. The Training Department Manager (TM) and the Training Supervisors periodically observed training classes.

The purpose was to evaluate and critique the instructors. The TM and Supervisors monitored Instructor presentations to ensure instructors were not "purposefully" divulging test material to the operators..Class participants were provided Enabling Objectives (EOs)

at the start of each class cycle. Material and demonstrations relative to the EOs were intended and expected to be discussed or used in class instruction. Supervisors and instructors who were interviewed stated that simulator demonstrations were beneficial.

They also believed the degree of difficultyin training department's program has remained consistent and unchanged.

The inspector reviewed several cycles of the 1998 requalification program to determine the pass/fail rate for each class.

No unusual circumstances were identified.

Conclusions The inspector reviewed AP-0010120, Conduct of Operations, Revision 102 - 107; and EOP-01, Revision 16 and 17. The new revisions to these procedures adequately addressed all of the inspectors safety concerns.

Additional training was provided to licensed operators to reiterate revised expectations of these procedures.

However, the facility's EOP-01, SPTAs, implementation was not finalized due to unresolved implementation concerns.

The facilityexpected to have these concerns addressed early in 1999.

The inspector determined through record review and interviews that the licensee was effective in conducting training and examinations to ensure operator mastery of the requalification training program objectives.

The pass/fail rates were consistent over past cycles.

The inspector identified no negative trends in LOR training and examination e

08.0 Miscellaneous Operations Issues 08.1 (Closed) Violation 50-335,389/97-11-02:

Maintenance worker qualification not in accordance with a systems approach to training. The inspector verified corrective actions outlined in the licensee's response letter L-97-319, dated December 19, 1997, to be completed.

The inspector verified that the administrative procedures ADM08.02,

"Conduct of Maintenance", and ADM22.01, "Verification of Training/Certification for Temporarily Employed Personnel", have incorporated additional guidance to prevent supervisors from inadvertently assigning unqualified workers tasks which require qualifications.

Neither the licensee or the NRC identified any actual occurrences of non-qualified workers being assigned tasks which require qualification.

Mana ement Meetin s X1.

Exit Meeting Summary At the conclusion of the site visit, December 18, 1998, the examiners met with representatives of the plant staff listed on the following page to discuss the results of the examinations and other issues.

No proprietary material provided was provide PARTIALLIST OF PERSONS CONTACTED Licensee T. Bolander, Operations Training Instructor M. Allen, Operations Manager.

D. Brown, Initial Operations Training Supervisor D. Fadden, Training Manager C. Ladd, Operation Supervisor G. Loree, Simulator Engineering Group L. Rich, Operations Training Supervisor E. Weinkam, Licensing Manager R. West, Plant General Manager NRC T. Ross, Senior Resident Inspector R. Aiello, Examiner, Rll P. Steiner, Examiner, Rll ITEMS OPENED, CLOSED, AND DISCUSSED

~Oened:

50-335, 339/98-302-01 IFI Review licensee implementation of SPTAs (Section 05.2)

Closed:

50-335, 389/97-11-02 VIO Maintenance worker qualification not in accordance with system approach to training (Section 08.1)

I

SIMULATIONFACILITYREPORT.

Facility Licensee: Florida Power and Light Company - St. Lucie Nuclear Plant, Units 1 8 2 Facility Docket Nos.: 50-335 and 50-389 Operating Tests Administered on:

November 30 - December 4, and December 14 - 18, 1998, This form is to be used only to report observations.

These observations do not constitute audit or inspection findings and are not, without further verification and review, indicative of noncompliance with 10 CFR 55.45(b). These observations do not affect NRC certification or approval of the simulation facilityother than to provide information that may be used in future evaluations.

No licensee action is required in response to these observations.

While conducting the simulator portion of the operating tests, no configuration or fidelityitems were observed.

Enclosure 2

. FACILITYPOST-EXAMINATIONCOMMENTS Enclosure 3