MONTHYEARML17241A5001999-10-21021 October 1999 Forwards Rev 3 to Emergency Response Data Sys (ERDS) Data Point Library for St Lucie Unit 1.Rev Provides Replacement Pages & Follows Format Recommended by NUREG 1394, ERDS Implementation, Rev 1,App C ML17309A9981999-10-19019 October 1999 Forwards Revised Epips,Including Rev 3 to EPIP-10 & Rev 25 to HP-202.EPIP-10 Added Onsite Monitoring Points,Made Administrative Changes & Incorporated New Attachments & HP-202 Added Red Team Survey Points ML20217F6171999-10-0808 October 1999 Forwards Insp Repts 50-335/99-11 & 50-389/99-11 on 990827 & 990907-09.No Violations Identified.Matl Encl Contained Safeguards Info as Defined by 10CFR73.21 & Disclosed to Unauthorized Individuals Prohibited by Section 147 of AEA ML17241A4811999-10-0101 October 1999 Reports Number of Tubes Plugged During Unit 1 Refueling Outage SL1-16,per TS 4.4.5.5.a ML20212M1601999-09-28028 September 1999 Refers to 990908 Engineering Meeting Conducted at NRC Region II to Discuss Engineering Issues at Lucie & Turkey Point Facilities.List of Attendees & Copy of Presentation Handout Encl ML17241A4701999-09-25025 September 1999 Forwards Info Requested by NRC Staff During 990916 Telcon to Complete Staff Review of Request for risk-informed Extension of Action Completion/Aot Specified for Inoperable Train of LPSI Sys at Plant ML17241A4721999-09-24024 September 1999 Forwards Rev 1 to Plant Change/Mod (PCM) 99016 to St Lucie Unit 1,Cycle 16 COLR, IAW TS 6.9.1.11.d.Refueling Overhaul Activities Are Currently in Progress & Reactor Operations for Cycle 16 Are Scheduled to Commence in Oct 1999 ML17241A4681999-09-22022 September 1999 Requests Restriction Be Added to Senior Operator License SOP-21093 for TE Bolander.Nrc Forms 369,encl.Encl Withheld Per 10CFR2.790(a)(6) ML17241A4671999-09-20020 September 1999 Forwards Completed NRC Form 536, Operator Licensing Exam Data, for St Lucie Units 1 & 2,as Requested in Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams. ML17241A4581999-09-13013 September 1999 Forwards Info Requested by NRC Staff During 990630 & 0816 Telcons,To Complete Review of Proposed License Amend for Fuel Reload Process Improvement Program ML17241A4531999-08-31031 August 1999 Informs That No Candidates from St Lucie Plant Will Be Participating in PWR Gfes Being Administered on 991006 ML17241A4521999-08-31031 August 1999 Withdraws Relief Request 16 & Suppl Relief Request 15 with Info Requested During 990526 Telephone Conference Re ISI Insp Plan,Third 10-yr Interval ML17241A4501999-08-26026 August 1999 Informs That FPL Has Reviewed Reactor Vessel Integrity Database,Called RVID2,re Closure of GL 92-01,rev 1,suppl 1. Requested Corrections & Marked Up Pages from Rvid 2 Database Summary Repts That Correspond to Comments,Attached ML17241A4371999-08-13013 August 1999 Forwards fitness-for-duty Program Performance Data for six- Month Period Ending 990630,per 10CFR26.71(d) ML17241A4461999-08-11011 August 1999 Requests That W Rept Entitled, Evaluation of Turbine Missile Ejection Probability Resulting from Extending Test Interval of Interceptor & Reheat Stop Valves at St Lucie Units 1 & 2, Be Withheld from Public Disclosure L-99-171, Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3)1999-07-29029 July 1999 Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3) ML17309A9911999-07-26026 July 1999 Forwards Revised EPIPs & Revised Procedures That Implement Emergency Plan as Listed.Procedures Provides Instruction for Operational Support Ctr (OSC) Chemistry Supervisor to Establish Remote Labs at Locations Specified ML17241A4471999-07-22022 July 1999 Requests That Rev 1 to WCAP-14732 & Rev 1,Add 1 to WCAP-14732 Be Withheld from Public Disclosure ML17241A4221999-07-22022 July 1999 Forwards List of Proposed Licensing Actions for St Lucie Units 1 & 2,planned During Fys 2000 & 2001,in Response to Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates. ML17241A4151999-07-22022 July 1999 Forwards Revised Relief Request 25 for Second 10-yr ISI Interval for Unit 2 ML17241A4101999-07-16016 July 1999 Forwards FP&L Supplemental Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants ML17309A9881999-07-0707 July 1999 Forwards Rev 5 to EPIP-03, Emergency Response Organization Notification/Staff Augmentation. Rev 5 to EPIP-03 Was Revised to Transfer EP Responsibilities from Training Manager to Protection Svcs Manager ML20209F1541999-07-0606 July 1999 Informs That NRC in Process of Conducting Operational Safeguards Response Evaluations at Nuclear Power Reactors. Plant Chosen for Such Review Scheduled for Wk of 990823-26 ML17241A4011999-06-30030 June 1999 Forwards Info Copy of Florida Wastewater Permit (FL0002208) (Formerly NPDES Permit) Mod,Which Was Issued by Florida Dept of Environ Protection on 990604 ML17241A3971999-06-30030 June 1999 Forwards Suppl Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, as Requested in 990317 Ltr ML17355A3661999-06-30030 June 1999 Forwards Florida Power & Light Topical QA Rept, Dtd June 1999.Encl I Includes Summary of Changes Made to Topical QA Rept Since 1998 ML17241A3951999-06-29029 June 1999 Provides Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants.Gl 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants, Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl ML17241A3731999-06-17017 June 1999 Supplements Relief Requests 4,11 & 13 for Third ten-year ISI Interval with Info Requested During 990526 Telcon.Expedited Review Is Requested by 990730 to Avoid Negatively Impacting Upcoming St Lucie Unit 1 Refueling Outage (SL1-16) ML17241A3641999-06-14014 June 1999 Submits Supplement to Relief Request 24 with Info Requested by Nrc.In Addition Relief Request 24 Is Identical to St Lucie Unit 1 Relief Request 4 for Third ISI Interval Being Supplemented by FPL Ltr L-99-139 ML20195F3871999-06-11011 June 1999 Final Response to FOIA Request for Documents.App a Records Being Withheld in Entirety (Ref FOIA Exemption 5) IA-99-247, Final Response to FOIA Request for Documents.App a Records Being Withheld in Entirety (Ref FOIA Exemption 5)1999-06-11011 June 1999 Final Response to FOIA Request for Documents.App a Records Being Withheld in Entirety (Ref FOIA Exemption 5) L-99-129, Forwards Rev 55 to Physical Security Plan,Summary of Changes & Marked Up Copy of Revised Pages.With Directions for Incorporating Rev Into Plan & Copies of Replacement Pages.Rev Withheld,Per 10CFR2.790(a)(3)1999-06-0909 June 1999 Forwards Rev 55 to Physical Security Plan,Summary of Changes & Marked Up Copy of Revised Pages.With Directions for Incorporating Rev Into Plan & Copies of Replacement Pages.Rev Withheld,Per 10CFR2.790(a)(3) ML17241A3561999-06-0707 June 1999 Forwards Rept Containing Brief Description & Summary of SEs for Changes,Tests & Experiments Which Were Approved for Unit 3 During Period of 970526-981209 ML17241A3601999-06-0707 June 1999 Forwards Correction to Annual Radiological Environ Operating Rept for CY98.Util Has Identified Transcription Error on Last Page of Attachment C of Rept,Results from Interlaboratory Comparison Program 1998 ML20195F3941999-05-27027 May 1999 FOIA Request That Memo from J Calvo to Fl Lebdon Re TIA - St Lucie,Unit 1 Environ Qualification of Woodward Governor Controls Be Placed in PDR ML17241A3461999-05-24024 May 1999 Forwards Revised Relief Request 22 to Clarify Several Areas of Relief.Nrc Action Is Requested to Be Complete by Aug 1999 to Support Planning for Spring 2000 Unit 2 Refueling Outage ML17241A3391999-05-20020 May 1999 Forwards Notification of Change to Small Break LOCA ECCS Evaluation Model Used for St Lucie Unit 1.Anomaly Was Discovered & Corrected That Resulted in Reducing Calculated PCT for Limiting SBLOCA by More than 50 F ML17241A3371999-05-20020 May 1999 Forwards Util Suppl to GL 95-07 Response Re pressure-locking & Thermal Binding of safety-related power-operated Gate Valves,In Response to NRC Second RAI Dtd 990225 ML20207C7531999-05-17017 May 1999 Discusses Issue Identified by FPL in Feb 1998 Involving Potential for Fire to Cause Breach of Rc Sys High/Low Pressure Interface Boundary & NRC Decision for Exercise of Enforcement Discretion ML17241A3301999-05-17017 May 1999 Forwards LER 99-004-00 Re as Found Cycle 10 Psv Setpoints Outside TS Limits,Which Occurred on 990415.Root Cause Determination Not Yet Complete.Suppl to Include Root Cause & Corrective Actions Will Be Submitted ML17309A9821999-05-10010 May 1999 Forwards Rev 36 to St Lucie Emergency Plan, Per 10CFR50.54(q).Executive Summary & Summary of Changes Incorporated by Rev,Encl IR 05000335/19980141999-04-29029 April 1999 Provides Confirmation of NRC Staff Conclusions Re Cited & non-cited Violations in Insp Rept 50-335/98-14 & 50-389/98-14.Utils Position Re Consideration of Multiple Spurious Actuations in Event of Fire,Reiterated ML17241A3221999-04-29029 April 1999 Provides Confirmation of NRC Staff Conclusions Re Cited & non-cited Violations in Insp Rept 50-335/98-14 & 50-389/98-14.Utils Position Re Consideration of Multiple Spurious Actuations in Event of Fire,Reiterated ML17229B1071999-04-28028 April 1999 Forwards 1998 Annual Environ Operating Rept for St Lucie Unit 2. Rept Includes Discussions of 5-inch Barrier Net Maint & Taprogge Condenser Tube Cleaning Sys Ball Loss,As Agreed at First Biennial Sea Turtle Meeting Held on 980120 ML17229B1051999-04-22022 April 1999 Requests That Listed Individuals Be Placed on Official Serve List for Nuclear Matl Safety & Safeguards Info Notices ML17229B1061999-04-21021 April 1999 Notifies NRC of Change in Medical Status of Licensed Operator Pf Farnsworth (Docket 55-21285,license SOP-21094). NRC Form 3996, Medical Exam Certification, Encl.Encl Withheld Per 10CFR2.790(a)(6) ML17309A9851999-04-15015 April 1999 Requests That NRC Review Denial of Appeal from Assessment of Fees Assessed in 981101 Invoice RS0062-99 & Assessment of Fees in Invoice RS0182-99 Which Was Also Denied in 990305 Ltr.Both Invoices Are for Fees Re Inspector GG Warnick ML20205M0431999-04-13013 April 1999 Eighth Partial Response to FOIA Request for Records.App Q & R Records Encl & Being Made Available in PDR ML17229B0951999-04-0808 April 1999 Requests Approval of Encl Revised Relief Request 6,in Response to 990322 Telcon with NRC & 10CFR55.55a(a)(3). Request States That Visual VT-3 Exams Will Be Conducted IAW IWA-2213 & Repairs Will Be IAW Util ASME Section IX Program ML17229B0821999-04-0707 April 1999 Requests Approval of Interim Relief Request 26 Re Repair Requirements for Class 2 ECCS Piping,Per 10CFR50.55a(a)(3) & 50.55a(g)(iii).Alternative Actions Apply Guidance of GLs 91-18 & 90-05 & ASME Code Case N-513.Evaluation,encl 1999-09-28
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML17241A5001999-10-21021 October 1999 Forwards Rev 3 to Emergency Response Data Sys (ERDS) Data Point Library for St Lucie Unit 1.Rev Provides Replacement Pages & Follows Format Recommended by NUREG 1394, ERDS Implementation, Rev 1,App C ML17309A9981999-10-19019 October 1999 Forwards Revised Epips,Including Rev 3 to EPIP-10 & Rev 25 to HP-202.EPIP-10 Added Onsite Monitoring Points,Made Administrative Changes & Incorporated New Attachments & HP-202 Added Red Team Survey Points ML17241A4811999-10-0101 October 1999 Reports Number of Tubes Plugged During Unit 1 Refueling Outage SL1-16,per TS 4.4.5.5.a ML17241A4701999-09-25025 September 1999 Forwards Info Requested by NRC Staff During 990916 Telcon to Complete Staff Review of Request for risk-informed Extension of Action Completion/Aot Specified for Inoperable Train of LPSI Sys at Plant ML17241A4721999-09-24024 September 1999 Forwards Rev 1 to Plant Change/Mod (PCM) 99016 to St Lucie Unit 1,Cycle 16 COLR, IAW TS 6.9.1.11.d.Refueling Overhaul Activities Are Currently in Progress & Reactor Operations for Cycle 16 Are Scheduled to Commence in Oct 1999 ML17241A4681999-09-22022 September 1999 Requests Restriction Be Added to Senior Operator License SOP-21093 for TE Bolander.Nrc Forms 369,encl.Encl Withheld Per 10CFR2.790(a)(6) ML17241A4671999-09-20020 September 1999 Forwards Completed NRC Form 536, Operator Licensing Exam Data, for St Lucie Units 1 & 2,as Requested in Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Exams. ML17241A4581999-09-13013 September 1999 Forwards Info Requested by NRC Staff During 990630 & 0816 Telcons,To Complete Review of Proposed License Amend for Fuel Reload Process Improvement Program ML17241A4531999-08-31031 August 1999 Informs That No Candidates from St Lucie Plant Will Be Participating in PWR Gfes Being Administered on 991006 ML17241A4521999-08-31031 August 1999 Withdraws Relief Request 16 & Suppl Relief Request 15 with Info Requested During 990526 Telephone Conference Re ISI Insp Plan,Third 10-yr Interval ML17241A4501999-08-26026 August 1999 Informs That FPL Has Reviewed Reactor Vessel Integrity Database,Called RVID2,re Closure of GL 92-01,rev 1,suppl 1. Requested Corrections & Marked Up Pages from Rvid 2 Database Summary Repts That Correspond to Comments,Attached ML17241A4371999-08-13013 August 1999 Forwards fitness-for-duty Program Performance Data for six- Month Period Ending 990630,per 10CFR26.71(d) ML17241A4461999-08-11011 August 1999 Requests That W Rept Entitled, Evaluation of Turbine Missile Ejection Probability Resulting from Extending Test Interval of Interceptor & Reheat Stop Valves at St Lucie Units 1 & 2, Be Withheld from Public Disclosure L-99-171, Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3)1999-07-29029 July 1999 Forwards Rev 56 to Physical Security Plan.Summary of Changes & Marked Up Copy of Revised Pages Also Encl.Encls Withheld from Public Disclosure Per 10CFR2.790(a)(3) ML17309A9911999-07-26026 July 1999 Forwards Revised EPIPs & Revised Procedures That Implement Emergency Plan as Listed.Procedures Provides Instruction for Operational Support Ctr (OSC) Chemistry Supervisor to Establish Remote Labs at Locations Specified ML17241A4221999-07-22022 July 1999 Forwards List of Proposed Licensing Actions for St Lucie Units 1 & 2,planned During Fys 2000 & 2001,in Response to Administrative Ltr 99-02, Operating Reactor Licensing Action Estimates. ML17241A4471999-07-22022 July 1999 Requests That Rev 1 to WCAP-14732 & Rev 1,Add 1 to WCAP-14732 Be Withheld from Public Disclosure ML17241A4151999-07-22022 July 1999 Forwards Revised Relief Request 25 for Second 10-yr ISI Interval for Unit 2 ML17241A4101999-07-16016 July 1999 Forwards FP&L Supplemental Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants ML17309A9881999-07-0707 July 1999 Forwards Rev 5 to EPIP-03, Emergency Response Organization Notification/Staff Augmentation. Rev 5 to EPIP-03 Was Revised to Transfer EP Responsibilities from Training Manager to Protection Svcs Manager ML17241A4011999-06-30030 June 1999 Forwards Info Copy of Florida Wastewater Permit (FL0002208) (Formerly NPDES Permit) Mod,Which Was Issued by Florida Dept of Environ Protection on 990604 ML17241A3971999-06-30030 June 1999 Forwards Suppl Response to GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs, as Requested in 990317 Ltr ML17355A3661999-06-30030 June 1999 Forwards Florida Power & Light Topical QA Rept, Dtd June 1999.Encl I Includes Summary of Changes Made to Topical QA Rept Since 1998 ML17241A3951999-06-29029 June 1999 Provides Response to NRC Request for Info Re Y2K Readiness at Nuclear Power Plants.Gl 98-01, Y2K Readiness of Computer Sys at Nuclear Power Plants, Requested Response on Status of Facility Y2K Readiness by 990701.Disclosure Encl ML17241A3731999-06-17017 June 1999 Supplements Relief Requests 4,11 & 13 for Third ten-year ISI Interval with Info Requested During 990526 Telcon.Expedited Review Is Requested by 990730 to Avoid Negatively Impacting Upcoming St Lucie Unit 1 Refueling Outage (SL1-16) ML17241A3641999-06-14014 June 1999 Submits Supplement to Relief Request 24 with Info Requested by Nrc.In Addition Relief Request 24 Is Identical to St Lucie Unit 1 Relief Request 4 for Third ISI Interval Being Supplemented by FPL Ltr L-99-139 L-99-129, Forwards Rev 55 to Physical Security Plan,Summary of Changes & Marked Up Copy of Revised Pages.With Directions for Incorporating Rev Into Plan & Copies of Replacement Pages.Rev Withheld,Per 10CFR2.790(a)(3)1999-06-0909 June 1999 Forwards Rev 55 to Physical Security Plan,Summary of Changes & Marked Up Copy of Revised Pages.With Directions for Incorporating Rev Into Plan & Copies of Replacement Pages.Rev Withheld,Per 10CFR2.790(a)(3) ML17241A3601999-06-0707 June 1999 Forwards Correction to Annual Radiological Environ Operating Rept for CY98.Util Has Identified Transcription Error on Last Page of Attachment C of Rept,Results from Interlaboratory Comparison Program 1998 ML17241A3561999-06-0707 June 1999 Forwards Rept Containing Brief Description & Summary of SEs for Changes,Tests & Experiments Which Were Approved for Unit 3 During Period of 970526-981209 ML20195F3941999-05-27027 May 1999 FOIA Request That Memo from J Calvo to Fl Lebdon Re TIA - St Lucie,Unit 1 Environ Qualification of Woodward Governor Controls Be Placed in PDR ML17241A3461999-05-24024 May 1999 Forwards Revised Relief Request 22 to Clarify Several Areas of Relief.Nrc Action Is Requested to Be Complete by Aug 1999 to Support Planning for Spring 2000 Unit 2 Refueling Outage ML17241A3371999-05-20020 May 1999 Forwards Util Suppl to GL 95-07 Response Re pressure-locking & Thermal Binding of safety-related power-operated Gate Valves,In Response to NRC Second RAI Dtd 990225 ML17241A3391999-05-20020 May 1999 Forwards Notification of Change to Small Break LOCA ECCS Evaluation Model Used for St Lucie Unit 1.Anomaly Was Discovered & Corrected That Resulted in Reducing Calculated PCT for Limiting SBLOCA by More than 50 F ML17241A3301999-05-17017 May 1999 Forwards LER 99-004-00 Re as Found Cycle 10 Psv Setpoints Outside TS Limits,Which Occurred on 990415.Root Cause Determination Not Yet Complete.Suppl to Include Root Cause & Corrective Actions Will Be Submitted ML17309A9821999-05-10010 May 1999 Forwards Rev 36 to St Lucie Emergency Plan, Per 10CFR50.54(q).Executive Summary & Summary of Changes Incorporated by Rev,Encl ML17241A3221999-04-29029 April 1999 Provides Confirmation of NRC Staff Conclusions Re Cited & non-cited Violations in Insp Rept 50-335/98-14 & 50-389/98-14.Utils Position Re Consideration of Multiple Spurious Actuations in Event of Fire,Reiterated IR 05000335/19980141999-04-29029 April 1999 Provides Confirmation of NRC Staff Conclusions Re Cited & non-cited Violations in Insp Rept 50-335/98-14 & 50-389/98-14.Utils Position Re Consideration of Multiple Spurious Actuations in Event of Fire,Reiterated ML17229B1071999-04-28028 April 1999 Forwards 1998 Annual Environ Operating Rept for St Lucie Unit 2. Rept Includes Discussions of 5-inch Barrier Net Maint & Taprogge Condenser Tube Cleaning Sys Ball Loss,As Agreed at First Biennial Sea Turtle Meeting Held on 980120 ML17229B1051999-04-22022 April 1999 Requests That Listed Individuals Be Placed on Official Serve List for Nuclear Matl Safety & Safeguards Info Notices ML17229B1061999-04-21021 April 1999 Notifies NRC of Change in Medical Status of Licensed Operator Pf Farnsworth (Docket 55-21285,license SOP-21094). NRC Form 3996, Medical Exam Certification, Encl.Encl Withheld Per 10CFR2.790(a)(6) ML17309A9851999-04-15015 April 1999 Requests That NRC Review Denial of Appeal from Assessment of Fees Assessed in 981101 Invoice RS0062-99 & Assessment of Fees in Invoice RS0182-99 Which Was Also Denied in 990305 Ltr.Both Invoices Are for Fees Re Inspector GG Warnick ML17229B0951999-04-0808 April 1999 Requests Approval of Encl Revised Relief Request 6,in Response to 990322 Telcon with NRC & 10CFR55.55a(a)(3). Request States That Visual VT-3 Exams Will Be Conducted IAW IWA-2213 & Repairs Will Be IAW Util ASME Section IX Program ML17229B0821999-04-0707 April 1999 Requests Approval of Interim Relief Request 26 Re Repair Requirements for Class 2 ECCS Piping,Per 10CFR50.55a(a)(3) & 50.55a(g)(iii).Alternative Actions Apply Guidance of GLs 91-18 & 90-05 & ASME Code Case N-513.Evaluation,encl ML17229B0851999-04-0505 April 1999 Requests Approval of Encl Relief Request 25 Which Proposes to Use Alternative Requirements of ASME Code Case N-613 in Lieu of Requirements of ASME Section XI Figures IWB-2500-7(a) & IWB-2500-7(b).Action Requested by Aug 1999 ML17309A9791999-03-31031 March 1999 Forwards Revised EPIPs Including Rev 2 to EPIP-00,rev 2 to EPIP-09,rev 2 to EPIP-10 & Rev 10 to HP-207.Summary of Revs Listed ML17309A9761999-03-23023 March 1999 Forwards Revised Epips,Including Rev 4 to EPIP-03, Er Organization Notification/Staff Augmentation, Rev 3 to EPIP-05, Activation & Operation of OSC & Rev 14 to HP-200, HP Emergency Organization. Changes to Epips,Discussed ML17229B0691999-03-19019 March 1999 Transmits TS Pages Requested by NRC for Use in Issuance of Proposed License Amend Re SFP Storage Capacity,Per Soluble Boron Credit ML17229B0721999-03-16016 March 1999 Requests Approval of Enclosed Relief Requests 23 & 24 Re ISI Plan for Second ten-year Interval.Nrc Action Is Requested to Be Complete by Aug 1999 to Support Planning for Spring 2000 Unit 2 Refueling Outage ML17355A2631999-03-12012 March 1999 Forwards FPL Decommissioning Fund Status Repts for St Lucie, Units 1 & 2 & Turkey Point,Units 3 & 4.Rept for St Lucie, Unit 2 Provides Status of Decommissioning Funds for All Three Owners of That Unit ML17229B0481999-03-10010 March 1999 Informs That Util Delivered Matls Requested in Encl 1 of NRC Ltr by Hand on 990308,as Requested by NRC Ltr Dtd 990218 1999-09-25
[Table view] |
Text
ACCELERATED DISTRIBUTION DEMONSTPA.TION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
ACCESSION NBR:9202270076 DOC.DATE: 92/02/19 NOTARIZED: NO DOCKET ACIL:50-335 St. Lucie Plant, Unit 1, Florida Power & Light Co. 05000335 50-389 St. Lucie Plant, Unit 2, Florida Power & Light Co. 05000389 AUTH. NAME'UTHOR AFFILIATION GOLDBERG,J.H. Florida Power & Light Co.
RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)
SUBJECT:
Responds to NRC 920219 ltr re violations noted in insp rept 50-335/91-22 & 50-389/91-22.Corrective actions:containment integrity was established & foreman crew were "counseled on need for strict adherence to procedures.
DISTRIBUTION CODE: IEOlD COPIES RECEIVED:LTR t ENCL i SIZE:
TITLE: General (50 Dkt)-Insp Rept/Notice of Violation Response NOTES:
RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD2-2 PD 1 1 NORRISiJ 1 1 INTERNAL: ACRS 2 AEOD 1 1 AEOD/DEIIB 1 AEOD/DSP/TPAB 1 1 DEDRO 1 NRR HARBUCKgC. 1 1' NRR MORISSEAU,D 1 NRR/DLPQ/LHFBPT 1 NRR/DLPQ/LPEB10 1 NRR/DOEA/OEAB 1 1 NRR/DREP/PEPB9H 1 NRR/DST/DIR 8E2 1 '1 NRR/PMAS/I LRB 1 2 1 NUDOCS-ABSTRACT 1 1 OE D 1, OGC/HDS3 1 1 RE %PIKE -
02 1 RGN2 FILE 01 1 1 EXTERNAL EG&G/BRYCE i J H ~~ NRC PDR
'NSIC NOTE TO ALL "RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOM P 1-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!
TOTAL NUMBER OF COPIES REQUIRED: LTTR 24 ENCL 24
P.O. Box14000, Juno Beach, FL 33408-0420 FPL FEB 19 1992 L-92-36 10 CFR 2.201 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Gentlemen:
Re: St. Lucie Unit Nos. 1 and 2 Docket Nos. 50-335 & 50-389 Reply to Notice of Violation Ins ection Re ort 91-22 Florida Power and Light Company has reviewed the subject inspection report and pursuant to 10 CFR 2.201 the response is attached.
Very truly yours, J. H. Goldberg President Nuclear Division JHG/JWH/kw Attachment cc: Stewart D. Ebneter, Regional Administrator, USNRC Region Senior Resident Inspector, USNRC, St. Lucie Plant II DAS/PSL 8619-92 9202270076 920219
/(o PDR ADOCK 05000335 8 PDR an FPL Group compani
~f~ItQ,rip Q
~
<~ gJ /
L i ATTACHMENT REPLY TO NOTICE OF VIOLATION FINDING A Unit 1 Technical Specification (TS) 3.9.4.c requires that, during core alterations or movement of irradiated fuel within the containment, containment penetrations providing direct access from the containment atmosphere to the outside atmosphere shall be closed. The TS specifically addresses manual isolation valves on penetrations communicating with the containment.
Un'it 1 TS 6.8.1.a requires that written procedures shall be established, implemented and maintained covering the activities recommended in Appendix A of Regulatory Guide 1.'33, Revision 2, February 1978. Appendix A, paragraph 9.e, addresses general procedures for the control of maintenance, repair, replacement, etc. and that these procedures include the method for obtaining permission and clearance for operation personnel to work and for logging such work. These requirements are implemented on site, in part, by, Administrative Procedure (AP) 0010432, Revision 56, Nuclear Plant Work Orders, paragraphs 8.4.4 and 8.4.5, which require that Senior Reactor Operator (SRO) permission be obtained prior to starting work on installed plant. equipment.
Contrary to the above, on November 10, 1991, at approximately 4:00 p.m., while fuel movement was in progress, licensee personnel failed to implement (follow) AP 0010432 by, without SRO permission, removing relief valve SR 14-8B in containment by grinding it off a component cooling water (CCW) pipe and covering the one-inch hole with a non-airtight cover. The CCW pipe, which penetrated containment, had been drained in preparation for the valve removal, however, the pipe surface was being used to establish containment boundary integrity and workers did not have SRO permission to proceed. Removing valve SR 14-8B created a direct access between the containment atmosphere and the Reactor Auxiliary Building atmosphere via open one-,inch manual drain valve V14319. On November 11, at approximately 1:30 p.m., when, workers requested permission to proceed with the valve repair, the SRO discovered what had happened and immediately closed V14319, restoring containment boundary integrity. Seven fuel bundles had been moved without containment integrity.
RESPONSE A
- 1. The reason for the violation was procedural non-compliance personnel error.
~ '
- 2. a) Containment integrity was established by Operations on November 11, 1991 at 0210 by closing drain valve V-14139.
b) The foreman and crew were counseled on the need for strict adherence to procedures.
c) This event was also discussed with all maintenance crews stressing the importance of receiving proper authorization prior to beginning work on plant systems.
- 3. a) This event will be included as part of In-House Events training to be held in February of 1992.
b) A change to the clearance procedure will be made to include a check by the NPS/ANPS/NWE when authorizing clearances to evaluate their effects on containment boundaries. This change is scheduled for completion by April 20, 1992.
- 4. Full compliance was achieved on November 11, 1991.
FINDING B Units 1 and 2 TS 4.8.1.1.2.d require that, at least once every 31 days, emergency diesel generator (EDG) fuel oil storage tank total particulate concentration be verified to be below 10 .
milligrams/liter (mg/1) when checked in accordance with ASTM standard D2276-83, Method A, or Annex A-2. The ASTM test methodology was implemented by site test procedure C-121, Revision 0, Determination of Particulate Contamination ... Diesel g2 Fuel Oil.
Contrary to the above, although the emergency diesel generator fuel oil storage tanks had been sampled appropriately and tested at the proper times, the test methodology was not transcribed correctly from the ASTM standard to the test procedure in that an incorrect reagent was specified. When used, the incorrect reagent (isopropyl alcohol instead of either petroleum ether or trichlorotrifluoroethane) washed away a portion of the total particulate content such that the site's analysis result was consistently less than the actual value.
Incorrect licensee analysis contributed to three of the four onsite EDGs being inoperable. Analysis of October 1991, samples by an offsite test laboratory that were reported 23,on November 4, 1991, showed particulate concentrations exceeding TS limits in three of four fuel oil storage tanks (12.9, 16.4, and 16.6 mg/1 for tanks 1A, 1B, and 2B respectively). Comparable licensee analysis results of November 4, 1991, samples showed 2.3 and 6.1 milligrams per liter in the 1B and 2B fuel oil storage tanks, respectively.
RESPONSE B 0
- 1. The reason for the violation was personnel error in transposing a pertinent step from the ASTM to the plant procedure.
- 2. The affected procedure, "C-121 Determination of Particulate Contamination; and Check for Clear and Bright Appearance with Proper Color Diesel g2 Fuel Oil," was revised on November 5, 1991 to include the correct reagent, making the analytical method correct.
- 3. The revised procedure C-121 and all other diesel analytical procedures were evaluated by an outside contractor, knowledgeable in fuel oil testing and ASTM methods. The result of this evaluation showed that the other analytical methods are technically correct.
- 4. Full compliance was achieved on November 5, 1991.
Unit 1 TS 6.8.1.a requires that written procedures shall be established, implemented and maintained covering the activities recommended in Appendix A of Regulatory Guide 1.33, Revision 2, February 1978. Appendix A, paragraph 10, addresses procedures for maintaining water quality within prescribed limits.
Unit 1 TS 3.4.7 requires Reactor Coolant System (RCS) chloride steady state concentration be maintained less than or equal to 0.15 part per million (ppm) and requires certain actions if this limit is exceeded for 24 hours.
These requirements, as well as various commitments under the approved quality assurance program, were implemented on site by procedure QI 13-PR/PSL-2, Revision 14, Cleanliness Control Methods.
Sections 5.1, 5.3, and 5.7 of this procedure allowed cleaning RCS components only with approved solvents or water with less than 0.15 ppm chloride concentration.
'1 Contrary to the above, on November 25, 1991, licensee personnel failed to implement procedure QI 13-PR/PSL-2 during high pressure water jet cleaning of the reactor vessel head seating area, which was submerged in water in the reactor cavity. No procedure controlled the high pressure water jet cleaning activity. The water supply hose was connected to an .improper source and approximately 1000 gallons of chlorinated potable water from the city water main was introduced into the RCS. This contamination resulted in RCS chloride levels of 226 ppb (0.226 ppm) which exceeded the TS steady state limit. This condition was mitigated by the chloride contamination being reduced to acceptable limits within forty hours. The TS 3.4.7 required evaluation was performed and indicated that no damage had occurred to the fuel or RCS subcomponents.-
RESPON8E C
- 1. The reason for the violation was inadequate procedural guidance.
- 2. a) Operations personnel performed a feed and bleed of the RCS until acceptable chloride levels of less than or equal to .15 ppm were attained.
b) Engineering performed an evaluation of the consequences of the chlorides -in contact with the fuel assemblies and the RCS piping which concluded that operation could continue in any operational mode.
- 3. a) A specific hydrolazing procedure is being developed to control the use of supply water for these types of evolutions.
This procedure will be completed by April 20, 1992.
b) The Unit 1 and 2 Reactor Vessel Maintenance procedures are being revised to reference the hydrolazing procedure. This procedure will be revised by April 20, 1992.
- 4. Full compliance will be achieved on April 20, 1992.