ML17223B040

From kanterella
Jump to navigation Jump to search
Submits Comments on Draft Safety Evaluation on Station Blackout Rule (10CFR50.63),per NRC 901121 Request
ML17223B040
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 12/21/1990
From: Sager D
FLORIDA POWER & LIGHT CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
L-90-452, NUDOCS 9101030143
Download: ML17223B040 (19)


Text

ACCELERATED D TRIBUTION DEMONSTRATION SYSTEM REGULATORY INFORMATION DISTRXBUTION SYSTEM (RIDS)

ACCESSION NBR: 9101030143 DOC. DATE: 90/12/21 NOTARIZED: NO DOCKET FACIL:50-335 St. Lucie Plant, Unit 1, Florida Power & Light Co. 05000335 50-389 St. Lucie Plant, Unit, 2, Florida Power & Light Co. 05000389 AUTH. NAME AUTHOR AFFILIATION SAGER,D.A. Florida Power & Light Co.

RECXP.NAME RECIPIENT AFFILIATXON Document Control Branch (Document Control Desk)

SUBJECT:

Submits comments on draft safety evaluation on station blackout rule (10CFR50.63),per NRC 901121 request.

DISTRIBUTION CODE: A050D COPIES RECEIVED:LTR ENCL 0 .63,SIZE: A-22(0 TITLE: OR Submittal: Station Blackout (USI A-44 10CFR5 MPA NOTES:

RECIPIENT COPIES RECIPIENT. COPIES ID CODE/NAME LTTR ENCL XD CODE/NAME LTTR ENCL PD2-2 PD 1 1 NORRIS,J 1 1 XNTERNAL': ACRS 1 1 NRR PD1-4PM TAM 1 1 NRR/DET/ESGB 8D 2 2 NRR/DST/SELB 3 3 NRR/J39g+SPLB8 D1 3 3 NRR/DST/SRXB8E 1 1

~KEG FILE 01 1 1 EXTERNAL: NRC PDR NSIC 1 1 NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE iVASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOM P 1-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 16 ENCL 16

P.O. Box 128, Ft. Pierce, FL 34954-0128 December 21, 1990 L-90-452 10 CFR 50.63 U. S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D. C. 20555 Gentlemen:

Re: St. Lucie Units 1 and 2 Docket Nos. 50-335 and 50-389 Station Blackout Rule 10 CFR 50.63 By letter dated November 21, 1990 (J. A. Norris to J. H. Goldberg),

the NRC forwarded to Florida Power & Light Company (FPL), for comment, a draft Safety Evaluation on the Station Blackout (SBO) rule (10 CFR 50.63) for St. Lucie Unit 1. FPL strongly desires to resolve SBO for St. Lucie Units 1 and 2 in the same manner notwithstanding the exemption from the rule requirements granted for St. Lucie Unit 2. In this light, FPL provides the following comments.

FPL's approach to transient and emergency events at its nuclear power plants ensures the continued availability of Alternating Current (AC) electrical power. This approach has been an integral part of our nuclear plant operating strategy. The SBO rule permits licensees to implement this strategy in meeting the criteria and requirements of 10 CFR 50.63. FPL is committed to resolve SBO for St. Lucie Units 1 and 2 by use of an alternate AC (AAC) source.

FPL proposes to meet the requirements of the SBO rule by preventing a unit blackout or SBO; in that respect, the St. Lucie units will not cope with either event using Direct Current (DC) power, but, rather will recover from a Loss of Offsite Power (LOOP) with the assumed multiple EDG failures by means of a unit to unit AC electrical crosstie. The safety and non-safety related equipment FPL has proposed to load on the single operating Emergency Diesel Generator (EDG) is equipment which is necessary to place both units in safe shutdown (i.e., hot standby).

FPL's comments presented in the attachment to this letter address the following aspects of the NRC's draft Safety Evaluation:

1) The resolution of SBO for St. Lucie Units 1 and 2 using the AAC source approach increases safety margins from that of a Direct Current (DC) coping approach.
2) Electrical loading of the operating EDG for this event 9i01030143 90i22i PDR P

ADOCK 05000335

( PDR A $ ~.non FPL Group company

'tg, 4

4 l l~

l 1

includes the AC loads necessary to cope with a LOOP and failure of three EDGs for both units, excluding the following loads, as allowed by criteria embodied in 10 CFR 50.63:

a) Shutdown Cooling (SDC) pumps b) AC driven Auxiliary Feedwater (AFW) pumps

3) Reactor coolant depletion via seal leakage at the rate assumed in the NRC's Safety Evaluation is not a consideration for either unit.
4) Management of the site operations dictates standardized procedures, training, Technical Specifications, and licensing and design bases for both units on the site.

Since the St. Lucie plant operators are licensed to operate both St. Lucie units,'ifferent licensing bases, Technical Specifications, and emergency operating procedures for recovering from SBO on either unit will present unnecessary human factors concerns.

Attached are our detailed comments on the above issues as well as other aspects of the staff's draft Safety Evaluation. We appreciate the opportunity to review and comment on this Safety Evaluation.

Very truly yours, D. A. a er Vice ident St. Lucie Plant DAS/EJW/lef DAS/PSL 75312 cc: Stewart D. Ebneter, Regional Administrator, USNRC, Region Senior Resident Inspector, USNRC, St. Lucie Plant II

J

~ 'I t

,1

+%A,ph~Q~'

ATTACHMENT FPL comments on NRC draft Safety Evaluation Station Blackout Rule St. Lucie Units 1 and 2.

FPL strongly desires to resolve 10 CFR 50.63 for both St. Lucie Units 1 and 2 in the same manner (i.e., by means of an alternate AC (AAC) source). FPL has identified several licensing and design concerns with the resolution of 10 CFR 50.63 in the staff's draft Safety Evaluation (SE), as detailed below.

Introduction FPL's compliance with 10 CFR 50.63, "Loss of all alternating current power", and the guidance provided by Regulatory Guide 1.155 and NUMARC 87-00 are aimed at meeting 10~ per reactor year as an acceptable frequency for core damage contribution from sequences initiated by a station loss of offsite power (LOOP)'s established by the NRC. Resolution of Station Blackout (SBO) for St. Lucie Units 1 and 2 consists of plant enhancements and modifications which will result in reduced frequency of core damage from a unit or station blackout event to less than 105 per reactor year.

The Advisory Committee on Reactor Safeguards (ACRS), Committee to Review Generic Requirements (CRGR) and NRC staff recognized that some licensees could provide, or may actually have in place, additional diesels, gas turbines or cross-connect options at two-unit sites that could serve as a one-of-four emergency diesel generator (EDG) configuration rather than one-of-two EDG configurations for unit blackout considerations'. This recognition led to the "10-minute" alternate AC (AAC) source at multi-unit sites. In fact, the statements of consideration for the rule identified this approach as a "preferred option" to resolve 10 CFR 50.63.

In letters dated April 17, 1989 and March 7, 1990 (L-89-145 and L-90-58, respectively), FPL proposed to add a remote manual electrical intertie to cross-connect electrical buses between St. Lucie Units 1 and 2 such that the reliability of the emergency AC power system configuration after a LOOP is significantly improved. This configuration permits any one of four EDGs to mitigate the effects of a unit blackout at the

'NRC staff responses to questions from Commissioners Asselstine, Bernthal, Roberts and Zech during final rule making decision on "Station Blackout" regulation date November 10, 1985.

site. FPL has shown that one EDG is sufficient to provide all the necessary loads associated with placing both units in hot standby from 1004 power for the required blackout duration.

Additionally, FPL has performed a preliminary risk assessment which reflects the significant risk reduction gained by the modifications for a postulated SBO event.

2) Increased Safety Margins for AAC Approach.

FPL's preliminary evaluation of risk reduction as a result of the AAC approach demonstrates that the core melt risk from SBO after a LOOP event has been reduced from approximately 7.6x104 to 2.9x10~ per reactor year. This is directly attributable to the proposed unit-to-unit cross-tie capability of the electrical system resulting in the added availability of two EDGs. The evaluation results in a risk reduction factor in excess of 200. By comparison, in NUREG-1032, "Evaluation of Station Blackout Accidents of Nuclear Power Plants" and in NUREG-1109, "Regulatory Analysis for the Resolution of Unresolved Safety Issue A-44, Station Blackout", the NRC staff reports a risk reduction factor of approximately 2.5 (i.e.

2.1x10 to 0.8x10~ per reactor year) as the basis for issuance of the SBO rule for units with a 4 hour4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> DC coping capability and one-out-of-two EDG configuration~.

3) Alternate AC (AAC) Loading FPL has re-analyzed the emergency diesel generator (EDG) loading for the proposed bus intertie for St. Lucie Units 1 and 2 to meet SBO criteria. This re-analysis results in revised load profiles from those provided to the NRC staff during the October 1989 SBO audit. The proposed electrical loadings for the EDGs to accommodate the SBO event are provided in attached Table 1 for St. Lucie Unit 1 and Table 2 for St. Lucie Unit 2. These loadings are essentially the major LOOP loads listed in the Updated Final Safety Analysis Report (UFSAR) with the following exceptions to account for the requirements of 10 CFR 50.63:

a) The SBO and non-blacked out (NBO) units'oadings do not include the motor driven Auxiliary Feedwater (AFW) pumps.

The NBO unit assumes failure of a redundant EDG (i.e.,

failure of three EDGs after LOOP event at the site) to qualify the fourth EDG as an AAC source. An assumed failure of the turbine driven AFW pump on either the SBO Rulemaking Issue Affirmation, SECY-88-22, January 21, 1988.

~ ~

P egg $

vk, t

or NBO unit for this event goes beyond the assumptions required by the regulations; FPL believes that this assumption is new criterion which was not considered in the regulatory analysis for 10 CFR 50.63 nor is included in Regulatory Guide 1.155.

it The regulatory analysis for 10 CFR 50.63 is based on a safety goal limiting the average contribution to core damage from a SBO to about 10'er reactor year. As a comparison, the NRC staff, in NUREG/CR-4710, "Shutdown Decay Heat Removal Analysis of a. Combustion Engineering 2-LOOP PWR" has analyzed a number of failure probabilities for the St. Lucie Plant. The NUREG reports that failure of a turbine driven AFW pump coupled with a common mode failure of 2 EDGs after a LOOP event results in a frequency of occurrence of 8.2x10~ per reactor year. For the postulated SBO event an additional EDG failure must be assumed. This additional failure will further reduce the core damage contribution by a factor of 5x10~. FPL believes that this is inconsistent with the analyses used to support 10 CFR 50.63 and is therefore, a new regulatory criterion beyond 10 CFR 50.63.

The NRC approved guidelines from "Combustion Engineering Emergency Procedures Guidelines" CEN-152, Rev. 03, address operator actions for LOOP and SBO events. These guidelines and FPL's procedures generated using these guidelines call for limiting flow to any one steam generator during these events to 150 gpm to minimize the probability of other postulated over-cooling events. The turbine driven AFW pump has greater capacity than the motor driven pumps and is capable of supplying sufficient AFW flow to both steam generators for decay heat removal. FPL's emergency operating procedures, which were developed using the guidance of CEN-152, require the operators to restrict AFW flow by placing the motor driven pump in the recirculation mode for the postulated case where a LOOP event has occurred and three of the four EDGs do not start. Procedures will instruct the operator to:

i) verify flow from the turbine driven AFW pump, ii) accordance secure flow from the NBO unit's motor driven pump (in with CEN-152 guidance), and iii) proceed with the 10-minute bus intertie to power the blacked out unit.

Similar actions will take place on the SBO unit. Based on the above, the SBO load evaluation does not require including the motor driven AFW pump.

/

Q 'a l

b) Title 10 CFR 50.63 and NUMARC 87-00 define safe shutdown as hot standby or hot shutdown, as appropriate. For EDG evaluation purposes, FPL intends to maintain both units at hot standby for the eight hour LOOP/SBO duration. For units in hot standby, operating pressures and temperatures prohibit the use and operation of the Shutdown Cooling (SDC) system (i.e., the Low Pressure Safety Injection pumps which are used in non-accident conditions for shutdown decay heat removal).

Pursuant to the design bases of the St. Lucie Units 1 and 2, the SDC system is manually placed into service when the Reactor Coolant System (RCS) pressure is approximately 275 psig, and temperature is less than 325 degrees F. The St. Lucie Units 1 and 2 SBO EDG loading evaluations will not consider mode changes (i.e., to cold shutdown) during the eight hour AAC coping period; therefore, the SDC system will not be used during this time. Based on the above, FPL has not included the SDC pump loads in the EDG load evaluation for SBO.

4) Reactor Coolant Inventory St. Lucie Units 1 and 2 use AAC for safe shutdown during the postulated SBO event. FPL believes the generic Reactor Coolant Pump (RCP) leakage criterion of 25 gpm per pump (for plants with DC coping), was intended to address units that do not provide cooling to the RCP seals. As AAC plants, St.

Lucie Units 1 and 2 will provide cooling water to the RCP seals on the SBO unit shortly after energizing the intertie (i.e., in approximately 10 minutes). As a result, no seal damage is postulated and only normal seal leakoff need be assumed for the RCPs.

With respect to the integrity of St. Lucie Unit .1 and 2 RCP seals following a loss of component cooling, it should be noted that the integrity of the RCP seals of the type used in the St. Lucie Unit 1 and 2 reactor coolant pumps was verified in a qualification test conducted at the pump manufacturer's test facility. This full-scale test simulated all the conditions of temperature, pressure and fluid flow that would be experienced in a LOOP event when seal cooling is interrupted and the pump, shaft stopped. It was the goal of the test to identify the effects of loss of cooling to the seals over a four hour period which would represent an extended loss of AC power. After four hours without any cooling water flow, there was no observed increase in seal leakage although the seal temperatures had risen to over 400'F while the system pressure was maintained at 2500 psi. The test was continued for over 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> and at no time did seal

Y

.1 i f%

leakage exceed 16.1 gallons per hour. This test demonstrated that the RCP seals will maintain their integrity through an extended LOOP event. This test was performed to provide information to resolve the St. Lucie Unit 2 loss of AC power Operating Licensing review and the information is directly applicable to St. Lucie Unit 1 which utilizes identical RCP seals. The test reaffirmed that the RCP seals used in St.

Lucie Unit 1 and 2 will withstand the environment associated with a sustained loss of AC power and will not degrade the reactor coolant pressure boundary.

5) Other Comments a) Station Blackout Duration (Section 2.1)

With respect to the coping assessment, St. Lucie Units 1 and 2 should be evaluated as AAC plants with power available to the shutdown buses within 10 minutes of the onset of an SBO event. Therefore, a coping assessment does not need to be addressed.

b) Alternate AC AAC Source (Section 2.2)

The strategy for recovering from an SBO event on both St.

Lucie units will involve electric load management (i.e.,

manual actions outside the Control Room). Trained operators are an important and necessary part of the plant's.response to any LOOP and concurrent unit blackout recovery plan. FPL maintains that operators can and will perform load management actions required to maintain the necessary loads for safe shutdown while ensuring the EDG remains within its load rating.

In accordance with the SBO rule, a test will be performed to verify that the AAC power source will be available to power the shutdown buses within 10 minutes of the onset of SBO.

c) Com ressed Air (Section 2.3.3)

The air compressors have the capability to be manually loaded on the EDGs. These air compressors are electrically driven, not diesel driven. In addition, the compressors will operate as required (not continuously) to maintain pressure. This equipment is not required to maintain hot standby but has been added as an operator a 3.d ~

r' Jt

d) Effects of Loss of Ventilation (Section 2.3.4)

All necessary ventilation equipment will be powered by the AAC Source during an SBO event. Therefore, additional ventilation studies are not required.

e) Sco e of Staff Review (Section 2.8)

As discussed in the comments on Section 2.3.4, "Effects of Loss of Ventilation", item f (heating and ventilation calculations) should be deleted.

f) St. Lucie Unit 2 SBO Withstand Ca abilit (Section 3.0)

As discussed above, the EDGs of either Unit 1 or Unit 2 are capable of supplying the SBO loads of both units.

Therefore, the EDGs from both Unit 1 and 2 have the capability and capacity to be AAC power sources.

g) Summar and Conclusions (Section 4.0)

Based on comments for the preceding sections, this section should be revised accordingly.

4 4'

~ ~ 4 Florida Power and Light Table 1 St. Lucie Unit 1 Electrical Loadings UNIT 1 DESIGNATIONS PDHD SH ~ FLA HP/KVA KW EMERGENCY LIGHTING MISC. LP'S 125.75 86.85 CLASS 1E POWER PANELS MISC. PP'S 149.08 109.14 CONTAINHENT FAH COOLERS (2) 1HVS 1A&B OR C&0 16 203 150 123.00 123.00 COHPOHENT COOLIHG WATER PUHPS 1A,18,1C 4,5 60 450 369.00 369.00 INTAKE COOLING WATER PUHPS 1A,18,1C 4,5 81 600 451.00 451 ~ 00 ICW BUILDING COOLING FANS CONTROL ROOM A/C ACC&HVA 3A,B,C 35,36,41 54.4/10.6 40/7.5 42.70 42.70 AUXILIARY BUILDING SUPPLY FANS 1HVS 4A,48 34,39 36,42 72 60 44 '0 37.83 44.20 ECCS AREA EXHAUST FANS 1HVE 9A,98 59,49 50,40 32.20 REACTOR CAVITY COOLING FANS 1HVS 2A,28 31,38 26 20 15.46 15.46 REACTOR SUPPORT COOLING FANS 1HVE 3A,38 31,39 49 40 21.57 21.57 EE ROOM SUPPLY FANS 1HVS 5A,58 33,39 38 22.1 13.48 13.48 EE ROOM EXHAUST FANS 1HVE 11,12 35,41 10 7.5 4.39 4.39 EE ROOM ROOF VENTS 1RV3,1RV4 32,41 2.5 1.5 1.40 1.40 BATTERY ROOH EXHAUST FANS 1RV1,1RV2 5C,53 4.2 .25 0.22 0.22 BATTERY CHARGERS 1A,18 32,39 90 68KVA 68.00 68.00 UPS INVERTERS INV. UPS. REC. 44 47.2 20KVA 20.00 20.00 PLANT SECURITY INVERTERS PL. SEC. INV. 44A 48.6 20KVA 20 F 00 20.00 PRESSURIZER HTRS. BACKUP BANK

  • 82 OR 85 19 387.50 186 186.00 186.00 INST'IR (IA) COMPRESSORS
  • 1A,18 35,43A 49 40 36.00 36.00 COOLING FOR IA COMPRESSORS AIR COMP MOTOR 62 11 7.5 6.70 6.70 EDG FUEL TRANSFER PUMPS
  • 1A,18 62 21 5 4.50 4.50 CHARGING PUHPS
  • 1A,18,1C 16 118 100 82 F 00 82.00
  • USED INTERHITTENTLY - ONLY PRESSURIZER HEATERS INCLUDED IN TOTAL 1693.08 1608.61 UNIT 1 EDG RATINGS REF. FLO 8770-305 CONTINUOUS DUTY -"3500 KW U1 MAXIMUM VALUE = 1693.08 KW 2000 HRS RATING = 3730 KW U2 MAXIHUH VALUE = 1800.11 KW 7 DAY RATING = 3790 KW COMBINED TOTAL = 3C93.19 KW 4 HRS RATING = 3860 KW COMBINED TOTAL = 100 K OF UNIT 1, CONT. RATING 30 HIN RATING -"3960 KW

SWI

-Florida Power and Light Table 2 St. Lucie Unit 2 Electrical Loadings UNIT 2 DESI GNAT IONS PDMD SH. FLA HP/KVA KW EMERGENCY LIGHTING MISC. LP'S 84.92 69.43 CLASS 1E POWER PAHELS MISC. PP'S 65.84 54.87 CONTAINMENT FAN COOLERS (2) 2HVS 1A&B OR C&D 102 144 125 141.00 141.00 COMPONENT COOLING WATER PUMPS 2A,2B,2C 4,5 60 450 369.00 369.00 INTAKE COOLING WATER PUMPS 2A,28,2C 4,5 82.4 600 492.00 492.00 ICW BUILDING COOLING FANS 2HVE 41 A,B 34,39 9.4 7.5 6.70 6.70 CONTROL ROOM A/C 2HVA/ACC-3A,B,C 36,42 68.1,49 55,40 49.40 49.40 AUXILIARY BUILDING SUPPLY FANS 2HVS-4A,4B 111 165 150 112.97 112.97 ECCS AREA EXHAUST FANS 2HVE 9A,98 31,42 73,65 60 50.81 52.94 REACTOR CAVITY COOLING FANS 2HVS 2A,2B 37 24 '20 13.66 13.66 REACTOR SUPPORT COOLING FANS 2HVE'3A,3B 36,39 47 40 21.77 21.77 EE ROOM SUPPLY FANS 2HVS 5A,5B 33,39 115 100 77.17 77.17 EE ROOM EXHAUST FANS 2HVE 11,12 35,41 59 50 41.74 41.74 EE ROOM ROOF VENTS 2RV3,2RV4 32,41 6.59 5 4.46 4.46 BATTERY ROOM EXHAUST FANS 2RV1,2RV2 37A,438 1.42 0.75 0.67 0.67 BATTERY CHARGERS 2A,28 32,39 90 68KVA 68.00 68.00 UPS INVERTERS INV. UPS. REC. 44 18,40 20KVA 20 F 00 20.00 PLANT SECURITY INVERTERS VITAL A/C CAB. 44A 60 30KVA 30.00 30 F 00 PRESSURIZER HTRS ~ PROPS BANKS

  • P1 OR P2 19 312.5 150KW 150.00 150.00 INST. AIR (IA) COMPRESSORS
  • 2A,28 35,43 75 60 54.00 54.00 COOLING FOR IA COMPRESSORS " AIR COMP MOTOR 62 11 7.5 6.80 6.80 EDG FUEL TRANSFER PUMPS
  • 2A,2B 62 4 3 2.70 2.70 CHARGING PUMPS
  • 2A,28,2C 16 145 125 102.47 102.47
  • USED INTERMITTENTLY - ONLY PRESSURIZER HEATERS INCLUDED IH TOTAL 1800.11 1775.78 UNIT 2 EDG RATINGS REF. FLO 2998-305 CONTINUOUS DUl'Y = 3685 KW U1 MAXIMUM VALUE ~ 1693 ~ 08 KW 2000 HRS RATING "- 3935 KW U2 MAXIMUM VALUE = 1800 ~ 11 KW 7 DAY RATING = 3985 KW COMBINED TOTAL < 3493.19 KW 4 HRS RATING < 3985 KW COMBINED TOTAL > 95 X OF UNIT 2, CONT. RATING 30 MIH RATING -"3985 KW