ML17215A137

From kanterella
Jump to navigation Jump to search
Restoration Project License Termination Plan Chapter 3, Revision 1 Identification of Remaining Site Dismantlement Activities.
ML17215A137
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 07/20/2017
From:
ZionSolutions
To:
Office of Nuclear Material Safety and Safeguards
Shared Package
ML17215A095 List:
References
ZS-2017-0084
Download: ML17215A137 (30)


Text

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN CHAPTER 3, REVISION 1 IDENTIFICATION OF REMAINING SITE DISMANTLEMENT ACTIVITIES

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 TABLE OF CONTENTS

3. IDENTIFICATION OF REMAINING SITE DISMANTLEMENT ACTIVITIES ............ 3-1 3.1. Introduction ..................................................................................................... 3-1 3.2. Completed and Ongoing Decommissioning Activities and Tasks .................. 3-2 3.2.1. Overview ......................................................................................................... 3-2 3.2.2. Spent Fuel Island and ISFSI Activities ........................................................... 3-3 3.2.3. Demolition and Dismantlement of Initial Structures ...................................... 3-3 3.2.4. Dismantlement of East Yard Tanks................................................................. 3-5 3.2.5. Demolition and Dismantlement of Crib House Structure ............................... 3-6 3.2.6. Additional Activities ....................................................................................... 3-7 3.3. Future Decommissioning Activities and Tasks ............................................... 3-7 3.3.1. Overview ......................................................................................................... 3-7 3.3.2. Turbine Building (Unit 1 and Unit 2) .............................................................. 3-8 3.3.3. Auxiliary Building ........................................................................................... 3-9 3.3.4. Unit 1 and Unit 2 Containments .................................................................... 3-10 3.3.5. Fuel Handling Building ................................................................................. 3-12 3.3.6. Waste Water Treatment Facility (WWTF) .................................................... 3-13 3.3.7. Miscellaneous Structures ............................................................................... 3-14 3.3.7.1. East and West Service Buildings ................................................................... 3-14 3.3.7.2. Forebay, Forebay Valve Houses and Intake and Outflow Structures located in Lake Michigan .............................................................................. 3-14 3.3.7.3. NGET, ENC, South Warehouse, North Security Access Gatehouse ............. 3-15 3.3.7.4. Laundry Building, North Security Restricted Area Gatehouse, South Security Restricted Area Access, Restricted Area Fence and Vehicle Barrier System ........................................................................... 3-16 3.3.7.5. Steam Tunnels and Waste Handling Area ..................................................... 3-16 3.3.7.6. Old Sewage Treatment Facility and Meteorological Tower .......................... 3-17 3.3.7.7. Storm Drain System, Manholes and Fire Protection Buried Piping .............. 3-17 3.3.7.8. Surface Soils, Subsurface Soil and Groundwater .......................................... 3-18 3.4. Radiological Impacts of Decommissioning Activities .................................. 3-18 3.4.1. Control Mechanisms to Mitigate the Recontamination of Remediated Areas.......................................................................................... 3-19 3.4.2. Occupational Exposure.................................................................................. 3-19 3.4.3. Exposure to the Public................................................................................... 3-19 3.4.4. Radioactive Waste Projections ...................................................................... 3-19 3.5. References ..................................................................................................... 3-20 3-i

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 LIST OF TABLES Table 3-1 Status of Major ZNPS Systems, Structures, and Components as of December 2014.............................................................................................. 3-21 Table 3-2 Radiation Exposure Projections for Decommissioning after 1/1/2015 ......... 3-23 Table 3-3 Projected Waste Quantities ........................................................................... 3-24 Table 3-4 General Project Milestones ........................................................................... 3-25 3-ii

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 LIST OF ACRONYMS AND ABBREVIATIONS ALARA As Low As Reasonably Achievable ACM Asbestos Containing Material CST Condensate Storage Tank DSAR Defueled Safety Analysis Report EPA Environmental Protection Agency FOT Fuel Oil Tank FSS Final Status Survey HVAC Heating Ventilation Air Conditioning ISFSI Independent Spent Fuel Storage Installation IRSF Interim Radioactive Waste Storage Facility LTP License Termination Plan MMTC Mechanical Maintenance Training Center NESHAP National Emissions Standards for Hazardous Air Pollutants NRC Nuclear Regulatory Commission ODCM Dose Calculation Manual PSDAR Post Shutdown Decommissioning Activity Report PWST Primary Water Storage Tanks RA Radiological Assessment RCRA Resource Conservation and Recovery Act RCS Reactor Coolant System RWP Radiation Work Permit SFP Spent Fuel Pool S/G Steam Generator TSCA Toxic Substances Control Act TSD Technical Support Document UFSAR Updated Final Safety Analysis Report ZNPS Zion Nuclear Power Station ZSRP Zion Station Restoration Project 3-iii

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 Page Intentionally Left Blank 3-iv

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1

3. IDENTIFICATION OF REMAINING SITE DISMANTLEMENT ACTIVITIES 3.1. Introduction In accordance with 10CFR50.82 (a)(9)(ii)(B), the License Termination Plan (LTP) must identify the remaining major dismantlement and decontamination activities for the decommissioning at the time of submittal. The information includes those areas and equipment that need further remediation and an assessment of the potential radiological conditions that may be encountered.

Estimates of the occupational radiation dose for completion of the scheduled task and the projected volumes of radioactive waste that will be generated are also included. These activities will be undertaken pursuant to the current 10 CFR 50 license, are consistent with the Zion Nuclear Station Post Shutdown Decommissioning Activity Report (PSDAR) (Reference 3-1),

and do not depend upon LTP approval to proceed.

ZionSolutions primary goals are to decommission the Zion Nuclear Power Station (ZNPS) safely and to maintain the continued safe storage of spent fuel. ZionSolutions will decontaminate and dismantle the ZNPS in accordance with the DECON alternative, as described in NUREG-0586 Generic Environmental Impact Statement on Decommissioning of Nuclear Facilities, Supplement 1, Volume 1 (Reference 3-2). Completion of the DECON option is contingent upon continued access to one or more low level waste disposal sites. Currently, ZionSolutions has access to low-level waste disposal facilities located in Barnwell, South Carolina, Andrews, Texas and in Clive, Utah.

ZionSolutions is currently conducting active decontamination and dismantlement activities at ZNPS in accordance with the PSDAR. Decommissioning activities are being coordinated with the applicable Federal and State regulatory agencies in accordance with plant administrative procedures. Applicable Federal agencies include the U.S. Nuclear Regulatory Commission (NRC) and the U.S. Environmental Protection Agency (EPA). Coordination with applicable State and local regulatory agencies are addressed in section 8.7.2 of Chapter 8. In order to minimize the impact of ongoing decommissioning activities, a Spent Fuel Pool (SFP) Island has been established to separate spent fuel storage functions from other plant functions and other decommissioning activities.

Decommissioning activities at the Zion Station Restoration Project (ZSRP) will be conducted in accordance with the Zion Station Defueled Safety Analysis Report (DSAR) (Reference 3-3),

the NRC Docket Number 50-295, Facility Operating License Number DPR-39 (for Unit One) (Reference 3-4), NRC Docket Number 50-304, Facility Operating License Number DPR-48 (for Unit Two) (Reference 3-5), all associated Technical Specifications and, the requirements of 10 CFR 50.82(a)(6) and (a)(7). At the time of LTP submittal, the remaining activities do not involve any un-reviewed safety questions or changes in the Technical Specifications for ZNPS. If an activity requires prior NRC approval under 10 CFR 50.59(c)(2),

or a change to the technical specifications or license, a submittal will be made to the NRC for review and approval before implementing the activity in question. Decommissioning activities are conducted under the scrutiny of the existing ZionSolutions Radiation Protection Program, Industrial Safety Program, and Waste Management Program. Such activities will be conducted in accordance with these programs, which are well established and frequently inspected by the 3-1

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 NRC. Activities conducted during decommissioning do not pose any greater radiological or safety risk than those conducted during operations, especially those during major maintenance and outage evolutions.

The remaining decontamination and dismantlement activities that will be performed are described in section 3.3. The specific system considerations that will be taken into account are discussed in sections 3.3.2 through 3.3.7. These sections provide an overview and describe the major remaining components of contaminated plant systems and, as appropriate, a description of specific equipment remediation considerations. Table 3-1 contains a list of major systems and components that have been or are to be removed.

On January 25, 2008, Exelon and ZionSolutions submitted an Application for License Transfers and Conforming Administrative License Amendments (Reference 3-6) requesting that the NRC approve the transfer of Exelon Corporations Facility Operating Licenses for ZNPS to ZionSolutions. On September 1, 2010, the licenses were transferred from Exelon to ZionSolutions (Issuance of Conforming Amendments Relating to Transfer of Licenses for Zion Nuclear Power Station, Units 1 and 2 [Reference 3-7]). Integral to the transfer of the licenses, ZionSolutions entered into an agreement with Exelon Corporation titled Zion Nuclear Power Station, Units 1 and 2 Asset Sale Agreement (Reference 3-8). This document presents the terms and conditions under which ZionSolutions would decommission ZNPS, construct an Independent Spent Fuel Storage Installation (ISFSI), place the spent nuclear fuel in dry cask storage and transfer the loaded fuel casks to the ISFSI, and remediate the site to the unrestricted release criteria as specified in 10 CFR 20.1402. Once the balance of the site is remediated and the as-left radiological conditions are demonstrated to be below the unrestricted release criteria, the 10 CFR Part 50 license will be reduced to the area around the ISFSI and the site will be transferred back to Exelon under the 10 CFR Part 50 license. ZionSolutions commenced the active decommissioning of ZNPS on October 13, 2010. Spent fuel and decommissioning activities completed to date are provided in section 3.2.

3.2. Completed and Ongoing Decommissioning Activities and Tasks 3.2.1. Overview ZionSolutions and its subcontractor, Siempelkamp, have completed the segmentation of the reactor vessel internals in both units, which will be followed by the segmentation of both reactor vessels.

Other completed Decommissioning activities include:

  • Creation of large openings in each Containment Building (approximately 31 feet x 36 feet) and installation of a Heavy Lift Rail system to enable transport of components and wastes out of each Containment.
  • Abatement, packaging and disposal of known and readily accessible lead and/or lead containing material.
  • Abatement, packaging and disposal of known and readily accessible Asbestos Containing Material (ACM).

3-2

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1

  • Removal and shipment of the Unit 2 Reactor Coolant Pump Motors (4 of 4) and various RCS piping.
  • Installation of new temporary power feeds to each containment which will allow for a safer commodity removal effort.
  • Disconnection and termination of various plant systems.

3.2.2. Spent Fuel Island and ISFSI Activities A priority task for ZionSolutions has been the construction of the ISFSI and the necessary licensing, training and infrastructure modifications required to transfer spent fuel from the SFP to the ISFSI. As part of this process, the Fuel Handling Building was upgraded with a new single-failure-proof crane. The ISFSI was constructed and became operational in late 2013. To date, fifty (50) of the required sixty-one (61) dry cask storage canisters (1850 spent fuel assemblies) have been successfully moved to the ISFSI. The completion of the movement of spent fuel into dry cask storage and transfer to the ISFSI is scheduled for completion in early 2015.

3.2.3. Demolition and Dismantlement of Initial Structures To date, the Interim Radioactive Waste Storage Facility (IRSF), the Mechanical Maintenance Training Center (MMTC) & Warehouse and the Fire Maze complex have been demolished and properly dispositioned as radiologically-clean waste or potential clean hard fill. The IRSF was built to temporarily store ZNPS generated radioactive waste in the mid-1980s but was never utilized for that purpose. It was a reinforced concrete structure that measured 134.5 feet long, 66 feet wide and 49 feet tall. The MMTC was a single story, steel framed, sheet metal structure that measured approximately 40 feet by 77 feet. The structures in the Fire Maze complex consisted of the Fire Maze, which was a single story steel framed building with sheet metal siding that measured approximately 20 feet by 30 feet, the Fire Training Center, which was a three story, steel framed building with sheet metal siding that measured approximately 25 feet by 25 feet, the Fire Pit, which was a single story, steel framed building with sheet metal siding that measured approximately 14 feet x 25 feet and the Temporary Radioactive Waste Liner Building, which was a single story concrete building that measured approximately 36 feet by 39 feet.

These structures were selected as initial test cases to demonstrate that the plans, programs and procedures put in place by ZionSolutions for the demolition of buildings and structures on the site were ready for implementation. ZionSolutions instituted a Cold, Dark and Dry methodology that consisted of the following basic activities:

  • Identification of any operable systems that may have to be replaced or relocated. For these initial structures, none were identified.

3-3

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1

  • Isolation of all electrical and mechanical systems servicing the structures.
  • Issuance of a contract to a subcontractor designated as the Demolition Contractor to complete demolition activities.

For the test case buildings and structures, contracted demolition activities included the installation of any required environmental controls and the demolition and removal of all above grade structures, systems and components. All foundations were either completely removed or demolished and removed to a depth of 3 feet below grade. None of the initial test case structures had sub-grade basements. All buried piping (service air, service water and sewer lines) were removed with the structures. Electrical services (conduits and cables) were removed to a depth of 3 feet below grade. The remaining excavation void was radiologically surveyed and then backfilled using clean fill to the existing grade.

  • Inspection of each structure for all universal, Resource Conservation and Recovery Act (RCRA) or Toxic Substances Control Act (TSCA) wastes that would require removal prior to demolition. These materials included mercury switches, light lamps, electrical ballasts and ACM. For the initial test case structures, most of the wastes were directly removed and dispositioned by ZionSolutions. The exceptions were mineral oil in a de-energized transformer and the oil and brake shoes in the overhead crane in the IRSF. These wastes were identified to the selected Demolition Contractor and subsequently abated as part of the contracted work scope. ZionSolutions may elect to include any required waste abatement activities as part of the Demolition Contractor work scope for future structural demolition.
  • Completion of unconditional release surveys of each structure to ensure the structures can be demolished and free-released. Surveys were performed in accordance with the site procedure for the unconditional release of materials to verify that the material was free of plant-derived radioactive material. Materials released for unconditional use were recycled or released for disposal at a non-radiological landfill. No recycled materials remained on site.
  • Surveyed and verified concrete debris resulting from the building demolition that was designated for reuse as clean hard fill as radiologically clean. This concrete debris was then processed to remove all exposed rebar and to ensure that individual debris pieces were smaller than 10 inches in diameter. The processed concrete debris was then transported to a designated storage area where it was stockpiled for use as potential backfill material. These stockpile areas are isolated and controlled to prevent the inadvertent introduction of potentially contaminated materials and periodic surveillances are performed.
  • All other construction demolition debris that was not stockpiled as potential backfill material was packaged and transported to an appropriate landfill for disposal or, to an off-site recycling center.

At the ZSRP, all bulk material, regardless of destination, passes through a radiological truck monitor.

3-4

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 3.2.4. Dismantlement of East Yard Tanks The next structures to be demolished were the set of tanks located in the east yard of the Security-Restricted Area. These tanks included the Primary Water Storage Tanks (PWST) and the Condensate Storage Tanks (CST) for both units, the Fuel Oil Tank (FOT), the De-Chlorination and Chlorination tanks for both units and concrete pads and shacks constructed to service and house tanks, systems and components.

The logic for the removal of the tanks as the next structures in the demolition sequence included;

  • The tanks were located within the Security-Restricted Area and were considered to be radiologically impacted. Removal of the tanks would allow for the initial use and assessment of the plans, procedures and processes for open-air demolition on radiologically contaminated structures and systems and allow the Demolition Contractor to become acclimated to working in a radiologically controlled environment.
  • The radiological contamination of the tanks required contamination mitigation and engineering controls to be implemented as part of the work scope.
  • The removal of the tanks provided needed space for the eventual planned demolition of the Crib House and the Turbine Building.

Prior to commencing the dismantlement and demolition of the yard tanks, the tanks and systems were prepared in accordance with the Cold, Dark and Dry approach implemented at ZSRP. In order to retire the CSTs as part of this process, it was necessary to design and install a new Demineralized Water Processing system.

The interior and exterior of both PWSTs and CSTs were radiologically surveyed prior to commencing physical dismantlement activities. The survey results indicated that the interiors of the tanks were radiologically contaminated. As a contamination control measure, a fixative was applied to the interior surfaces of the tanks. Following the application of the fixative, a survey was performed to verify that the radiological conditions of the structures met the criteria for open-air demolition as presented in Technical Support Document (TSD)10-002, Technical Basis for Radiological Limits for Structure/Building Open Air Demolition (Reference 3-9).

Compliance with this criterion minimized the implementation of additional contamination controls that would be required for open-air demolition and allows for the use of heavy equipment to perform the demolition. The intent is to perform this type of survey to verify the radiological conditions in all radiologically-impacted structures, components and systems prior to demolition.

The soils surrounding the tanks were radiologically surveyed as part of the site characterization.

No soils were identified during the characterization that would necessitate excavation and removal as radioactive waste. During the course of the tank dismantlement, additional surveys and soil samples were taken of the soil surrounding the tanks. No soil was identified with residual radioactivity in excess of the release criteria. The PWSTs and the CSTs for both units were dismantled, properly packaged and dispositioned as low-level radioactive waste. All 3-5

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 radioactive waste was loaded and transported under the direction of ZionSolutions Waste Department personnel to the licensed Energy Solutions radioactive waste disposal facility in Clive, Utah. Sampling of surface and subsurface soil and groundwater in this area has been performed. Preliminary results demonstrate that some soil will require remediation and disposal off site due to the presence of polynuclear aromatic hydrocarbons above the Illinois EPA limits.

3.2.5. Demolition and Dismantlement of Crib House Structure The next major structure demolition activity planned for 2014 involves the demolition of the Crib House. The Crib House contains the Circulating Water pumps, the Service Water Pumps and the Fire Protection pumps. In order to implement the Cold, Dark and Dry approach in the Crib House, a number of design modifications are required to replace the functioning systems in the Crib House that are required for the operation of necessary systems, such as component cooling and fire protection. These include:

  • The retirement of the station fire pumps and the integration of a modified fire water ring header that is connected to the city water system for the Town of Zion as a replacement.

This modification also resulted in changing the pressurized fire suppression system at ZNPS to a dry system that would be supplied from a new exterior connection for the Town of Zion Fire Department.

  • The retirement of the Service Water pumps required the installation of a new pump to supply circulating water to certain systems. This new pump was installed in the Forebay in a manner that would allow for the demolition of the Crib House to proceed. This pump system provides dilution flow for liquid waste releases into the Forebay and also serves as a source of emergency make up water to the SFP via a hose connection. The previous Heating Ventilation Air Conditioning (HVAC) functions performed by Service Water were replaced by temporary, local heating and cooling installations and the relocation of certain functions (Hot and Cold Laboratories and Counting Room) to other areas.

Once the system modifications are in place and the Crib House has been successfully made Cold and Dark, the Crib House will be surveyed for unconditional release. Surveys will be performed in accordance with the site procedure for the unconditional release of materials to verify that the material is free of plant-derived radioactive material. Materials released for unconditional use can be recycled or released for disposal at a non-radiological landfill. No recycled materials will remain on site. In addition, all electrical and mechanical systems will be isolated and removed as commodities. Once the structure has been successfully surveyed and system removal is complete, the above grade portions can then be readily demolished by the Demolition Contractor. In order to perform system removal and perform unrestricted release surveys of the deep pump well areas, stop logs and dewatering pumps must be installed to isolate the sub-grade areas from the Forebay and Lake Michigan. These measures will be implemented by the Demolition Contractor, who will also supply temporary power, lighting and all other support required for the survey performance. Due to the depth of the Circulating Water (centerline elevation 33 feet below grade) and Service Water (centerline elevation 12 feet below grade) headers, they will be sealed off at the west wall of the Crib House. These pipe headers 3-6

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 will also be surveyed for compliance with the unrestricted release criteria prior to being isolated, abandoned in place and filled with grout or fill as appropriate. All concrete structures will be removed to a depth of 3 feet below grade in accordance with the requirements of the Asset Sale Agreement. All remaining structures below 3 feet below grade will be surveyed to demonstrate compliance with the unrestricted release criteria as specified in 10 CFR 20.1402.

3.2.6. Additional Activities Additional activities that have been completed or are ongoing include, but are not limited to the following:

  • Continued assessment of the functional requirements for plant systems, structures, and components.
  • Identification of plant systems, structures, and components needed to support safe storage of the spent fuel, support SFP cooling, and facilitate ongoing plant activities.
  • Design, installation and operation of a new Liquid Radioactive Waste Processing system.
  • Detailed planning and project scheduling.
  • At the start of 2014, a management change by ZionSolutions at the ZSRP was instituted which resulted in a partial site stand down to allow for the completion of a comprehensive planning and scheduling effort. Upon completion, decommissioning activities resumed in accordance with the revised project schedule.

The Liquid Radioactive Waste system at ZNPS had become degraded since the shutdown of the units and was not capable of successfully processing liquid radwaste for effluent discharge.

Consequently, ZionSolutions elected to design and install a new Liquid Radioactive Waste Processing system. This system is used to process liquid radwaste at ZNPS and, process the water from each of the reactor cavities (approximately 500,000 gallons each) and the SFP (approximately 700,000 gallons including the transfer canal) once all spent fuel has been moved to the ISFSI. The Turbine Building and Auxiliary Building cannot be completely placed in a Cold, Dark and Dry status until this liquid waste processing is completed in 2015.

3.3. Future Decommissioning Activities and Tasks 3.3.1. Overview The priority task at ZSRP is the movement of the spent fuel into dry cask storage and transfer to the ISFSI facility. Spent fuel movement to the ISFSI is currently scheduled to be complete in early 2015. Once the movement of the spent fuel is complete, then other significant dismantlement and decommissioning tasks will take precedent. The removal of the spent fuel from the Fuel Handling Building will allow ZionSolutions to implement a license amendment to the 10 CFR 50 license for each unit to remove operational requirements and technical specifications specifically required for the maintenance of spent nuclear fuel in wet pool storage.

These license amendments will greatly enhance the ability to completely place the remaining structures into a Cold, Dark and Dry state, to complete the processing of the remaining liquid radioactive waste, to allow for the complete removal of all remaining commodities and to allow for the enhanced ability to more freely move material and personnel around the site. The 3-7

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 complete dismantlement and decommissioning of the Turbine and Auxiliary Building is contingent upon completion of these tasks. The plans for the decontamination, dismantlement and anticipated end-state condition(s) for the remaining site structures are presented in the following sections.

3.3.2. Turbine Building (Unit 1 and Unit 2)

Large component removal in the Turbine Building is scheduled to commence in early 2015. Initial component removal will include the dismantlement and removal of most of the large components in Unit 1, including the turbines, generator, moisture separator reheaters, feedwater heaters and coolers and, several feedwater heaters and coolers in Unit 2. In parallel with this effort, the ZionSolutions Characterization/License Termination personnel will perform surveys for the unconditional release of materials, equipment and structural surfaces throughout the building. In addition, inspections were completed to identify any remaining waste streams. Surveys were performed in accordance with the National Emissions Standards for Hazardous Air Pollutants (NESHAP) to identify any potential ACM and all accessible friable ACM was removed. Any remaining identified potential ACM that was not accessible at this time, including but not limited to gaskets in piping systems, caulking around windows, floor and wall barrier seals, will be appropriately handled and abated by the Demolition Contractor as part of the contracted work scope.

All systems and materials that are or will be identified by radiological survey as contaminated with detectable plant-derived radioactive material will be removed by ZionSolutions personnel and dispositioned and properly disposed of as radioactive waste. The remaining structure and materials in the Turbine Building will be demonstrated as meeting the unconditional release criteria. Surveys will be performed in accordance with the site procedure for the unconditional release of materials to verify that the material is free of plant-derived radioactive material.

Materials released for unconditional use can be recycled or released for disposal at a non-radiological landfill. No recycled materials will remain on site. The remaining structure will then be made Cold, Dark and Dry and turned over to a Demolition Contractor as a non-radiologcally controlled structure for demolition as a contracted work scope.

The selected Demolition Contractor will remove and disposition all remaining commodities and demolish the structure to a depth of 3 feet below grade in accordance with the requirements of the Asset Sale Agreement. All remaining structures below 3 feet below grade will undergo a survey to demonstrate compliance with the unrestricted release criteria as specified in 10 CFR 20.1402. All equipment and components will be removed from the structure with the exception of the underground circulating water headers, discharge tunnels and buried service water piping running between the Crib House location and the Auxiliary Building. All remaining buried and piping embedded in concrete will be surveyed for compliance with the unrestricted release criteria prior to being isolated, abandoned in place and filled with grout or fill as appropriate.

3-8

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 Concrete debris from the building demolition will be designated for beneficial reuse as clean hard fill. Only concrete that meets the non-radiological definition of clean concrete demolition debris and where Final Status Survey (FSS) demonstrates that the concrete is free of plant derived radionuclides above background will be used. This concrete debris will then be processed to remove all exposed rebar and to ensure that individual debris pieces were smaller than 10 inches in diameter. The processed concrete debris will then be transported to a designated on-site storage area where it will be stockpiled for use as potential backfill material.

All other construction demolition debris that is not appropriate for reuse as potential backfill material will be packaged and transported to an appropriate landfill for disposal or, to an off-site recycling center following final assessment for the presence of any residual radioactive contamination by passing through a radiological truck monitor.

Once the remaining concrete structure located below 3 feet below grade (588 foot elevation) has been satisfactorily surveyed and compliance with the unrestricted release criteria has been demonstrated and, contingent upon the completion of confirmatory surveys and regulatory approval, the Turbine Building void will be backfilled using concrete debris suitable for reuse as clean hard fill and/or clean fill to the original site grade and contours. The top 3 feet of fill will be soil only (i.e. concrete clean hard fill will only be utilized as fill up to the 588 foot elevation).

3.3.3. Auxiliary Building Component and system removal is currently ongoing in the Auxiliary Building. Radiological surveys performed to verify as-left contamination levels are below the criteria established as suitable for open-air demolition are also being performed as a parallel activity. Based upon the results of these surveys, the remaining systems, components and structural surfaces that will be required to be removed or decontaminated prior to permitting open air demolition in accordance with TSD 10-002 are being identified. Identified radiological commodities in excess of the open-air demolition limits are currently being removed, or will be removed prior to structural demolition. All radioactive waste will be loaded and transported under the direction of ZionSolutions Waste Department personnel to the licensed Energy Solutions radioactive waste disposal facility in Clive, Utah. All structural decontamination activities will be performed in accordance with an approved Radiation Work Permit (RWP) and under the oversight of ZionSolutions Radiation Protection personnel. The current Liquid Radioactive Waste system will remain in place until all liquid radioactive waste has been successfully processed and dispositioned. When this task is complete, the Liquid Radioactive Waste system will also be dismantled and properly disposed of as radioactive waste.

When commodity removal is complete and all structural surfaces have been decontaminated to the open-air demolition limits in accordance with TSD 10-002, the Auxiliary Building will be placed in a Cold, Dark and Dry configuration and it will be turned over to a subcontracted Decommissioning Contractor. The selected Decommissioning Contractor will demolish the structure to a depth of 3 feet below grade in accordance with the requirements of the Asset Sale Agreement. All below grade interior floors (560 and 579 foot elevations) and walls will be removed. Contamination control methods (vaccuming, wiping, etc) will be used to mitigate 3-9

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 loose surface contamination on the remaining exposed structural surfaces. All construction debris resultant from the demolition of the Auxiliary Building structure will be treated as low level radioactive waste and will be shipped to the licensed Energy Solutions radioactive waste disposal facility in Clive, Utah by gondola railcar. All remaining structures below 3 feet below grade will be surveyed to demonstrate compliance with the unrestricted release criteria as specified in 10 CFR 20.1402.

Five 24 inch diameter sleeves that are buried in soil between each of the two containments and the Auxiliary Building 542 foot elevation will be surveyed for compliance with the unrestricted release criteria prior to being isolated, abandoned in place and filled with grout or fill as appropriate. Two of the five sleeves have been capped and were never used. The remaining three sleeves housed 20 inch diameter Recirculating Sump Suction lines which will be removed prior to surveying and abandoning the sleeves in place.

Several other sections of piping systems associated with the Auxiliary Building may also remain.

The list of buried piping, penetrations and embedded piping to remain is provided in ZionSolutions Technical Support Document (TSD)14-016, Description of Embedded Pipe, Penetrations, and Buried Pipe to Remain in Zion End State (Reference 3-10). The decision to remove or abandon in place will be made based on the results of a cost-benefit analysis that will be performed once access to the pipe sections become possible. In all cases, any buried or embedded piping that will remain will be surveyed for compliance with the unrestricted release criteria prior to being isolated, abandoned in place and filled with grout or fill as appropriate.

Once the remaining concrete structure located 3 feet below grade (extending between the 542 foot and 588 foot elevation) has been satisfactorily surveyed and compliance with the unrestricted release criteria has been demonstrated and, contingent upon the completion of confirmatory surveys and regulatory approval, the Auxiliary Building void will be backfilled using concrete debris suitable for reuse as clean hard fill and/or clean fill to the original site grade and contours. The top 3 feet of fill will be soil only (i.e. concrete clean hard fill will only be utilized as fill up to 588 foot elevation).

3.3.4. Unit 1 and Unit 2 Containments Component and system removal is currently ongoing in both Unit 1 and Unit 2 Containment Buildings. Surveys to verify as-left contamination levels are below the criteria established for open-air demolition are also being performed as a parallel activity. Based upon the results of these surveys, the remaining systems, components and structural surfaces that will be required to be removed or decontaminated prior to permitting open air demolition in accordance with TSD 10-002 are being identified.

Identified radiological commodities are currently being removed, or will be removed prior to structural demolition. All radioactive waste will be loaded and transported under the direction of ZionSolutions Waste Department personnel to the licensed Energy Solutions radioactive waste disposal facility in Clive, Utah. All structural decontamination activities will be performed in accordance with an approved RWP(s) and under the oversight of ZionSolutions Radiation Protection personnel.

3-10

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 When commodity removal is complete and all structural surfaces have been decontaminated to the open-air demolition limits in accordance with TSD 10-002, the Containment Buildings will be placed in a Cold, Dark and Dry configuration and they will be turned over to a Decommissioning Contractor. In both Containment basements, all concrete will be removed from the interior side of the steel liner above the 565 foot elevation, leaving only the remaining exposed liner below the 588 foot elevation, the concrete in the In-core Instrument Shaft leading to and including the area under vessel (or Under-Vessel area), and the structural concrete outside of the liner. Contamination control methods (vaccuming, wiping, etc) will be used to mitigate loose surface contamination on the remaining exposed structural surfaces. All construction debris resultant from the demolition of each of the Containment Building structures will be treated as low level radioactive waste and will be shipped to the licensed EnergySolutions radioactive waste disposal facility in Clive, Utah by gondola railcar. Once all commodities and interior concrete have been removed from the Containment shells, the exposed steel liner below the 588 foot elevation and Under-Vessel concrete will be surveyed for compliance with the unrestricted release criteria as specified in 10 CFR 20.1402. In addition, at this point, any confirmatory surveys required by the regulator will also be accomplished. Once the Containment structural surfaces located 3 feet below grade (588 foot elevation) have been satisfactorily surveyed and compliance with the unrestricted release criteria has been demonstrated and, contingent upon the completion of confirmatory surveys and regulatory approval, the Containment Building basements will be filled to above the 588 foot elevation using clean fill or concrete debris suitable for reuse as clean hard fill. The top 3 feet of fill will be soil only. An additional one foot of clean soil may be placed as sacrificial soil to minimize the potential for contaminating the clean fill.

After packing each Containment basement with clean fill, both Containment shells will be demolished to a depth of 3 feet below grade in accordance with the requirements of the Asset Sale Agreement. Demolition will include the removal of the pre-stressing tendons and the gradual demolition of the containment shells from grade, using ram-hoes to chip away the concrete along the bottom circumference of the shell and allowing the weight of the remaining structure to slowly demolish the structure to grade. This is the same or similar approach that was used to demolish the Containment structure during the decommissioning of the Connecticut Yankee Atomic Power Companys Haddam Neck Nuclear Power Plant. The process will also allow for the removal of all exposed rebar and to ensure that individual debris pieces are smaller than 10 inches in diameter. Concrete debris resulting from the building demolition may be designated for beneficial reuse as clean hard fill. Only concrete that meets the non-radiological definition of clean concrete demolition debris and where FSS demonstrates that the concrete is free of plant derived radionuclides above background will be used. The processed concrete debris will then be transported to a designated storage area where it will be stockpiled for use as potential backfill material. If the material is not used as clean hard fill, then it will be packaged and transported to an appropriate landfill for disposal or, to an off-site recycling center following final assessment for the presence of any residual radioactive contamination by passing through a radiological truck monitor.

3-11

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 3.3.5. Fuel Handling Building The dismantlement and decommissioning of the Fuel Handling Building is contingent upon the placement of the spent nuclear fuel located in the SFP into dry cask storage and transfer of the packaged fuel to the ISFSI facility. After all the fuel has been removed from the pool, the processing and discharge of the SFP water will commence. Initially, approximately 350,000 gallons or half of the water volume in the pool will be processed by the Liquid Radioactive Waste system, sampled and, once the radioactive concentration in the water meets the criteria for effluent release, discharged through the normal effluent release pathway into Lake Michigan. The decontamination of the upper portions of the steel pool liner will occur in parallel with the initial processing and discharge of the pool water.

With the water level lowered, the 23 empty spent fuel storage racks will be removed from the pool. A cost benefit analysis will determine if the fuel racks are processed for volume reduction on-site or off-site. The fuel racks will be properly packaged and shipped for eventual disposal as radioactive waste. Once the fuel racks have been removed, the remaining approximately 350,000 gallons of pool water will then be processed by the Liquid Radioactive Waste system, sampled and, once the radioactive concentration in the water meets the criteria for effluent release, discharged through the normal effluent release pathway into Lake Michigan. The lower sections and bottom of the steel pool liner will also be decontaminated as necessary while still wet.

When the pool is completely empty and dry, all known radioactively contaminated systems and components will be removed by either ZionSolutions personnel or a subcontracted Demolition Contractor and properly disposed of as radioactive waste. This will include the steel liner of the SFP. In parallel, ZionSolutions Radiation Protection personnel will perform surveys to verify as-left contamination levels are below those established for open-air demolition of the interior surfaces and remaining commodities in the Fuel Handling Building, including the exposed concrete of the SFP foundation once the liner is removed. Based upon the results of these surveys, the remaining systems, components and structural surfaces that will be required to be removed or decontaminated prior to permitting open air demolition in accordance with TSD 10-002. All radioactive waste will be loaded and transported under the direction of ZionSolutions Waste Department personnel to the licensed EnergySolutions radioactive waste disposal facility in Clive, Utah. All structural decontamination activities will be performed in accordance with an approved RWP(s) and under the oversight of ZionSolutions Radiation Protection personnel.

When the commodity removal by ZionSolutions personnel is complete and all structural surfaces and remaining commodities have been decontaminated to the open-air demolition limits in accordance with TSD 10-002, the Fuel Handling Building will be turned over to a subcontracted Decommissioning Contractor. Due to its strategic location adjacent to the Containment Buildings, the Auxiliary Building and the existing rail line, the shell of the Fuel Handling Building may be left standing for some period of time to aid in the removal of low level waste from the adjacent structures. When conditions become favorable, the Decommissioning Contractor will demolish all of the remaining interior systems, structures, components and concrete down to a depth of 3 feet below grade in accordance with the requirements of the Asset 3-12

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 Sale Agreement. All construction debris resultant from the demolition of the Fuel Handling Building will be treated as low level radioactive waste and will be shipped to the licensed Energy Solutions radioactive waste disposal facility in Clive, Utah by gondola railcar.

Once any remaining concrete structures, which could include the concrete sub-slab for the SFP, located below 3 feet below grade has been satisfactorily surveyed and demonstrated to be in compliance with the unrestricted release criteria as specified in 10 CFR 20.1402 and, contingent upon the completion of confirmatory surveys and regulatory approval, the void where the Fuel Handling Building once stood will be backfilled using concrete debris suitable for reuse as clean hard fill and/or clean fill to the original site grade and contours. The top 3 feet of fill will be soil only (i.e. concrete clean hard fill will only be utilized as fill up to 588 foot elevation).

3.3.6. Waste Water Treatment Facility (WWTF)

The Wastewater Treatment Facility (WWTF) was designed to treat non-radioactive and low-level radioactive liquid from ZNPS sources including building roof run-off and the Turbine Building Fire Sump, which received liquid waste from the Turbine Building Equipment and Floor Drains, and the Fuel Pool Cooling Tower Blowdown. The WWTF was designed to remove suspended solids and oil to ensure compliance with the facility National Pollutant Discharge Elimination System (NPDES) permit. Since the wastewater discharge rates were variable, an equalization tank was installed. The WWTF also includes other equipment such as mixing tanks, mixers, oil skimmers, flocculators, oil coalescers, clarifiers, sludge drying beds and filters. Discharge from the WWTF was by gravity to the Forebay. During ZNPS operations, liquid waste with detectable low-level radioactive contamination was processed by the WWTF.

Consequently, the internal surfaces of the WWTF systems are considered as potentially contaminated.

All systems, component and materials associated with the WWTF that are or will be identified by radiological survey as contaminated with detectable plant-derived radioactive material will be removed by ZionSolutions personnel and dispositioned and properly disposed of as radioactive waste. The remaining structure will then be made Cold, Dark and Dry. Once this is complete, all remaining commodities and all structural surfaces will be demolished to a depth of 3 feet below grade in accordance with the requirements of the Asset Sale Agreement. All remaining structural surfaces from the WWTF below 3 feet below grade will undergo a survey to demonstrate compliance with the unrestricted release criteria as specified in 10 CFR 20.1402.

Once the remaining concrete structure located below 3 feet below grade (588 foot elevation) has been satisfactorily surveyed and compliance with the unrestricted release criteria has been demonstrated and, contingent upon the completion of confirmatory surveys and regulatory approval, the WWTF void will be backfilled using concrete debris suitable for reuse as clean hard fill and/or clean fill to the original site grade and contours. The top 3 feet of fill will be soil only (i.e. concrete clean hard fill will only be utilized as fill up to the 588 foot elevation).

3-13

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 3.3.7. Miscellaneous Structures 3.3.7.1. East and West Service Buildings These two structures are located to the south of the Unit 1 Turbine Building and have been utilized primarily as office space and a machine shop. Both are steel framed structures that have no sub-grade basement. The remaining structure and materials in the East and West Service Buildings will be demonstrated as meeting the unconditional release criteria. Surveys will be performed in accordance with the site procedure for the unconditional release of materials to verify that the material is free of plant-derived radioactive material. Materials released for unconditional use can be recycled or released for disposal at a non-radiological landfill. No recycled materials will remain on site. The remaining structure will then be made Cold, Dark and Dry and turned over to a Demolition Contractor as a non-radiologically controlled structure for demolition as a contracted work scope. Both buildings are scheduled for demolition at essentially the same period as the Turbine Building. The concrete base slabs and edge beams will be removed to a depth of 3 feet below grade in accordance with the requirements of the Asset Sale Agreement and all associated buried piping systems associated with these buildings are targeted for complete removal and disposal as waste. Any void created by the demolition of these structures will be surveyed by the ZionSolutions Characterization/License Termination group and documented as a Radiological Assessment (RA). Upon completion of the RA and acceptance of the survey results, any voids will be backfilled to the original site grade and contours.

3.3.7.2. Forebay, Forebay Valve Houses and Intake and Outflow Structures located in Lake Michigan The Circulating Water Intake Piping and Discharge Tunnels located at the bottom of Lake Michigan will remain and be abandoned in place. These structures will be surveyed in place to demonstrate compliance with the unrestricted release criteria as specified in 10 CFR 20.1402.

The accessible Forebay surfaces above the 588 foot elevation and the Valve Houses will be radiologically surveyed to demonstrate that the structural surfaces and materials meet the unconditional release criteria. Surveys will be performed in accordance with the site procedure for the unconditional release of materials to verify that the material is free of plant-derived radioactive material. Materials released for unconditional use can be recycled or released for disposal at a non-radiological landfill.

No recycled materials will remain on site. The Valve Houses and the Forebay will then be made Cold, Dark and Dry and turned over to a Demolition Contractor as a non-radiologically controlled structure for demolition as a contracted work scope. The structural surfaces of the Forebay located below the 588 foot elevation will be surveyed to demonstrate compliance with the unrestricted release criteria as specified in 10 CFR 20.1402. As it is difficult to completely 3-14

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 isolate the Forebay from Lake Michigan, safety concerns will prevent personnel from physically entering the Forebay to perform this survey. Consequently, it is anticipated that this survey will be performed remotely using detectors deployed by extended booms or long-handled tools.

Once the compliance survey is complete, and contingent upon the completion of confirmatory surveys and regulatory approval, the selected Demolition Contractor will remove and disposition all remaining commodities and completely demolish the Valve Houses and demolish the Forebay structure to a depth of 3 feet below grade in accordance with the requirements of the Asset Sale Agreement. All other construction demolition debris that is not appropriate for beneficial reuse as potential backfill material will be packaged and transported to an appropriate landfill for disposal or, to an off-site recycling center following final assessment for the presence of any residual radioactive contamination by passing through a radiological truck monitor.

Once the remaining concrete structure located below 3 feet below grade (588 foot elevation) has been satisfactorily surveyed and demonstrated to be in compliance with the unrestricted release criteria as specified in 10 CFR 20.1402, the Forebay void will be backfilled using clean fill or concrete debris suitable for reuse as clean hard fill to the original site grade and contours. Large blocks of concrete will be placed in the Forebay at the mouth of the intake prior to the actual backfill to minimize any long term erosion concerns. The top 3 feet of fill will be soil only (i.e.

concrete clean hard fill will only be utilized as fill up to 588 foot elevation).

3.3.7.3. NGET, ENC, South Warehouse, North Security Access Gatehouse These structures are located in the Radiologically-Restricted Area and have been utilized primarily as office and storage space. All are steel framed structures that have no sub-grade basement. The structural surfaces and materials in each of these buildings will be demonstrated as meeting the unconditional release criteria. Surveys will be performed in accordance with the site procedure for the unconditional release of materials to verify that the material is free of plant-derived radioactive material. Materials released for unconditional use can be recycled or released for disposal at a non-radiological landfill. No recycled materials will remain on site.

The structures will then made Cold, Dark and Dry and turned over to a Demolition Contractor as non-radiologically controlled structures for demolition as a contracted work scope. The concrete base slabs and wall foundations will be removed to a depth of 3 feet below grade in accordance with the requirements of the Asset Sale Agreement and all associated buried piping systems associated with these buildings are targeted for complete removal and disposal as waste.

All electrical services will be de-energized and removed to a depth of 3 feet below grade. Any void created by the demolition of these structures will be surveyed by the ZionSolutions Characterization/License Termination group and documented as a RA. Upon completion of the RA and acceptance of the survey results, any voids will be backfilled to the original site grade and contours.

3-15

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 3.3.7.4. Laundry Building, North Security Restricted Area Gatehouse, South Security Restricted Area Access, Restricted Area Fence and Vehicle Barrier System These structures are located in the Security-Restricted Area and are primarily security structures that will no longer be required once all the spent nuclear fuel is moved to the ISFSI. The structures are a mix of steel frame, slab on grade and reinforced concrete construction. The structural surfaces and materials in each building and area will be demonstrated as meeting the unconditional release criteria. Surveys will be performed in accordance with the site procedure for the unconditional release of materials to verify that the material is free of plant-derived radioactive material. Materials released for unconditional use can be recycled or released for disposal at a non-radiological landfill. No recycled materials will remain on site. The structures will then made Cold, Dark and Dry and turned over to a Demolition Contractor as non-radiologically controlled structures for demolition as a contracted work scope. The concrete base slabs and wall foundations will be removed to a depth of 3 feet below grade in accordance with the requirements of the Asset Sale Agreement and all associated buried piping systems associated with these buildings are targeted for complete removal and disposal as waste. All electrical services will be de-energized and removed to a depth of 3 feet below grade. Any void created by the demolition of these structures will be surveyed by the ZionSolutions Characterization/License Termination group and documented as a RA. Upon completion of the RA and acceptance of the survey results, any voids will be backfilled to the original site grade and contours.

3.3.7.5. Steam Tunnels and Waste Handling Area The Steam Tunnels are buried structures that connect the Unit 1 and Unit 2 Containment Building with the Turbine Building at the 570 foot elevation. They are constructed of reinforced concrete. The Waste Handling Area is a steel frame building built on an on-grade concrete slab.

Both of these structures will undergo radiological surveys to verify that as-left contamination levels are below those established for open-air demolition prior to commencing decommissioning. Based upon the results of these surveys, the remaining systems, components and structural surfaces that will be required to be removed or decontaminated prior to permitting open air demolition in accordance with TSD 10-002 will be removed or successfully decontaminated prior to structural demolition. All radioactive waste will be loaded and transported under the direction of ZionSolutions Waste Department personnel to the licensed EnergySolutions radioactive waste disposal facility in Clive, Utah.

Once all identified radioactive systems have been removed and any structural surfaces that require remediation have been decontaminated, the structures will then be made Cold, Dark and Dry and turned over to a Decommissioning Contractor for demolition as a contracted work scope. The Waste Handling Building will be completely removed, including the concrete slab.

The roof of the Steam Tunnels will be exposed by excavation. The concrete roof slabs will be demolished and removed and all remaining materials in the Steam Tunnels will be removed through the created opening. Concrete debris resulting from the building demolition may be designated for beneficial reuse as clean hard fill. Only concrete that meets the non-radiological definition of clean concrete demolition debris and where FSS demonstrates that the concrete is 3-16

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 free of plant derived radionuclides above background will be used. All clean construction debris that is not appropriate for reuse as potential backfill material will be packaged and transported to an appropriate landfill for disposal or, to an off-site recycling center following final assessment for the presence of any residual radioactive contamination by passing through a radiological truck monitor.

The remaining structural surfaces of the Steam Tunnels located below the 588 foot elevation will be surveyed to demonstrate compliance with the unrestricted release criteria as specified in 10 CFR 20.1402. Once the compliance survey is complete, and contingent upon the completion of confirmatory surveys and regulatory approval, the selected Decommissioning Contractor shall demolish the Steam Tunnel structures to a depth of 3 feet below grade in accordance with the requirements of the Asset Sale Agreement.

Once the remaining concrete structure located below 3 feet below grade (588 foot elevation) has been satisfactorily surveyed and compliance with the unrestricted release criteria has been demonstrated, the Steam Tunnels voids will be backfilled using concrete debris suitable for reuse as clean hard fill and/or clean fill to the original site grade and contours. The top 3 feet of fill will be soil only (i.e. concrete clean hard fill will only be utilized as fill up to 588 foot elevation).

3.3.7.6. Old Sewage Treatment Facility and Meteorological Tower The Old Sewage Treatment Facility and the Meteorological Tower will be demonstrated as meeting the unconditional release criteria. Surveys will be performed in accordance with the site procedure for the unconditional release of materials to verify that the material is free of plant-derived radioactive material. Materials released for unconditional use can be recycled or released for disposal at a non-radiological landfill. No recycled materials will remain on site.

The structures will then be made Cold, Dark and Dry and turned over to a Decommissioning Contractor as non-radiologically controlled structures for demolition as a contracted work scope.

The structures, concrete slabs all associated buried piping systems associated with these buildings will be completely removed and disposed of as waste. All electrical services will be de-energized and removed to a depth of 3 feet below grade. Any void created by the demolition of these structures will be surveyed by the ZionSolutions Characterization/License Termination group and documented as a RA. Upon completion of the RA and acceptance of the survey results, any voids will be backfilled to the original site grade and contours.

3.3.7.7. Storm Drain System, Manholes and Fire Protection Buried Piping It is anticipated that once fire suppression is provided by temporary or local systems and physical conditions support the retirement of the on-site fire suppression system, the existing fire protection piping (including hydrants and valves) and the storm drain system (including the oil separators) will be removed and disposed of as clean waste. If a situation occurs where difficulty is encountered with ground water, some of the piping and/or catch basins located greater than a depth of 5 feet below grade may be abandoned in place. In these cases, any piping or catch basins that remain will be surveyed for compliance with the unrestricted release criteria as specified in 10 CFR 20.1402 prior to being isolated and abandoned in place. Any voids created by excavation to support the removal of these systems will be surveyed by the ZionSolutions 3-17

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 Characterization/License Termination group and documented as a RA. Upon completion of the RA and acceptance of the survey results, any voids will be backfilled to the original site grade and contours.

3.3.7.8. Surface Soils, Subsurface Soil and Groundwater Characterization survey results and historical survey data indicate that there is minimal residual radioactivity in soil and no groundwater contamination identified to date. As needed, additional investigations will be performed to ensure that any changing soil radiological contamination profile during decommissioning is adequately identified and addressed. Chapter 5 discusses soil sampling and survey methods.

The release criteria that will be used to demonstrate compliance with the 25 mrem/yr dose criterion are provided in Tables 5-4 and 5-5 of Chapter 5. Throughout the course of the decommissioning and through site closure, ZSRP will continue to survey and characterize soils as they are exposed by excavation during building demolition or made accessible by the removal of structures or components. If residual radioactivity is discovered in surface or subsurface soils, ZSRP will excavate, package and dispose of any soil contaminated with residual radioactivity at concentrations greater that the unrestricted release criteria.

3.4. Radiological Impacts of Decommissioning Activities The decommissioning activities described are and will be conducted under the provisions of the ZionSolutions Radiation Protection Program and Radioactive Waste Management Program.

These programs are and will continue to be implemented as described in the DSAR. The ZionSolutions Radiation Protection Program and written site procedures are intended to provide sufficient information to demonstrate that decommissioning activities will be performed in accordance with 10 CFR 19, Notices, Instructions And Reports To Workers, 10 CFR 20, Standards For Protection Against Radiation and to maintain radiation exposures As Low As Reasonably Achievable (ALARA). The ZionSolutions Radioactive Waste Management Program controls the generation, characterization, processing, handling, shipping, and disposal of radioactive waste in accordance with the approved ZionSolutions Radiation Protection Program, Process Control Program, and written plant procedures.

The current Radiation Protection Program, Waste Management Program, and Radiological Effluent Monitoring and Offsite Dose Calculation Manual (ODCM) (Reference 3-11) will be used to protect the workers and the public during the various decontamination and decommissioning activities. These well-established programs are routinely inspected by the NRC to ensure that workers, the public, and the environment are protected during facility decommissioning activities. It is also important to note that decommissioning activities involve the same radiation protection and waste management considerations as those encountered during plant operations, maintenance and outages. As described in the PSDAR, the decommissioning will be accomplished with no significant adverse environmental impacts in that:

  • No site-specific factors pertaining to the decommissioning of the ZNPS would alter the conclusions presented in NUREG-0586 (see LTP Chapter 8).
  • Radiation dose to the public will be minimal.

3-18

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1

  • Decommissioning is not an imminent health or safety concern and will generally have a positive environmental impact.

Continued application of the current and future Radiation Protection and Radiological Effluent Monitoring Programs at ZNPS ensures public protection in accordance with 10 CFR 20 and 10 CFR 50, Appendix I. ODCM reports for ZNPS to date conclude that the public exposure as a result of decommissioning activities is bounded by the evaluation in NUREG-0586, which concludes the impact is minimal.

3.4.1. Control Mechanisms to Mitigate the Recontamination of Remediated Areas Due to the large scope of remaining structures and systems that will be decontaminated and dismantled, FSS of areas may be performed in parallel with decommissioning activities.

Consequently, a systematic approach will be employed to ensure that areas are adequately remediated prior to performing FSS and ongoing decommissioning activities do not impact the radiological condition of areas where compliance with the unrestricted release criteria as specified in 10 CFR 20.1402 has been demonstrated. These measures and mechanisms are described in Chapter 5, sections 5.6.3 and 5.12.

3.4.2. Occupational Exposure Table 3-2 provides the cumulative site dose and estimates for the decommissioning of ZNPS.

These estimates were developed to provide site management ALARA goals. The goals are verified by summation of actual site dose, as determined by appropriate dosimetry. ALARA estimates are a compilation of RWP estimates for the period. This information is in addition to information gathered for reporting of yearly site dose. The annual report of occupational dose meets the guidance of NRC Regulatory Guide 1.16, Reporting of Operating Information, Appendix A, Technical Specifications (Reference 3-12). The total radiation exposure impact for decommissioning and spent fuel management is estimated to be approximately 935 person-rem.

3.4.3. Exposure to the Public Continued application of ZionSolutions Radiation Protection, Radioactive Waste, Radiological Effluent Technical Specification and Radiological Environmental Monitoring Programs assures public protection in accordance with 10 CFR 20 and 10 CFR 50, Appendix I.

3.4.4. Radioactive Waste Projections The Radioactive Waste Management Program is used to control the characterization, generation, processing, handling, shipping, and disposal of radioactive waste during decommissioning.

Activated and contaminated systems, structures, and components represent the largest volume of low level radioactive waste expected to be generated during decommissioning. Other forms of waste generated during decommissioning include:

  • Contaminated water;
  • Used disposable protective clothing;
  • Expended abrasive and absorbent materials; 3-19

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1

  • Expended resins and filters;
  • Contamination control materials (e.g., strippable coatings, plastic enclosures); and
  • Contaminated equipment used in the decommissioning process.

Table 3-3 provides projections of waste classifications and quantities that will be generated by the decommissioning of ZNPS. These waste quantities are consistent with the waste quantities projected in the PSDAR. As ZionSolutions has elected to institute an approach commonly referred to as rip & ship verses performing significant on-site decontamination activities, the total volume of low-level radioactive waste for disposal has been estimated at approximately 6,000,000 cubic feet. Actual waste volumes and classifications may vary. The vast majority of this waste will be shipped to the licensed EnergySolutions radioactive waste disposal facility in Clive, Utah by gondola railcar.

3.5. References 3-1 Zion Nuclear Power Station, Post Shutdown Decommissioning Activity Report (PSDAR), - March 2008 3-2 U.S. Nuclear Regulatory Commission NUREG-0586 Generic Environmental Impact Statement on Decommissioning of Nuclear Facilities, Supplement 1, Volume 1 -

November 2002 3-3 Zion Station, Defueled Safety Analysis Report (DSAR) - September 2014 3-4 U.S. Nuclear Regulatory Commission Docket Number 50-295, Facility Operating License Number DPR-39 (for Unit One) 3-5 U.S. Nuclear Regulatory Commission Docket Number 50-304, Facility Operating License Number DPR-48 (for Unit Two) 3-6 Letter from ZionSolutions to the U.S. Nuclear Regulatory Commission, Notification of Amended Post-Shutdown Decommissioning Activities Report (PSDAR) for Zion Nuclear Power Station, Units 1 and 2 - March 18, 2008.

3-7 Letter from J.B. Hickman (U.S. Nuclear Regulatory Commission) to J. Christian (ZionSolutions), Issuance of Conforming Amendments Relating to Transfer of Licenses for Zion Nuclear Power Station, Units 1 and 2 - September 2010 3-8 Zion Nuclear Power Station, Units 1 and 2 Asset Sale Agreement - December 2007 3-9 ZionSolutions Technical Support Document 10-002, Technical Basis for Radiological Limits for Structure/Building Open Air Demolition 3-10 ZionSolutions Technical Support Document 14-016, Description of Embedded Pipe, Penetrations, and Buried Pipe to Remain in Zion End State 3-11 Exelon Nuclear Radiological Effluent Monitoring and Offsite Dose Calculation Manual (ODCM) - January 2001 3-12 U.S. Nuclear Regulatory Commission Regulatory Guide 1.16, Reporting of Operating Information, Appendix A, Technical Specifications - August 1975 3-20

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 Table 3-1 Status of Major ZNPS Systems, Structures, and Components as of December 2014 Required for System or Component Status SFP Reactor Coolant System No Partially Removed Reactor Vessel Internals No Segmentation completed Reactor Vessels No Segmentation underway Steam Generators No Removal preparations underway Reactor Coolant Pumps No Removed from site Pressurizer No Removal preparations underway Chemical & Volume Control System No Partially removed Safety Injection System No Partially removed Residual Heat Removal System No Partially removed Containment Spray System No Partially removed Component Cooling Water System No Partially removed Service Water System No Partially removed.

Spent Fuel Pool Yes In place Fuel Handling Equipment No In place Spent Fuel Pool Cooling and Yes In place Demineralizer System (SFPI systems)

Condensate System No Partially removed Feedwater System No Partially removed Steam Generator Blowdown System No Partially removed Primary Makeup Water System No Partially removed Refueling Water Storage Tank No In place Plant Effluent Monitoring System No In place Containment Ventilation System No In place Fuel Building Ventilation System Yes In place Aux Building Ventilation System No In place Auxiliary Boiler No In place 3-21

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 Table 3-1 (continued)

Required for System or Component Status SFP Instrument and Service Air System No Partially removed Gaseous Radioactive Waste System No Partially removed Solid Radioactive Waste System No Partially removed Partially removed; New system Liquid Radioactive Waste System No operational.

Makeup Water Systems Yes In place Radioactive Monitoring System Yes In place Process Sampling System No Partially removed Fire Protection System Yes Partially removed Electrical Systems Yes Partially removed Some equipment removed.

Containment Building No Decontamination activities are in progress.

Some equipment removed. Interior Auxiliary Building No dismantlement and decontamination activities are in progress.

Fuel Handling Building Yes In place Turbine Building No Some equipment removed.

Service Buildings No Some equipment removed.

3-22

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 Table 3-2 Radiation Exposure Projections for Decommissioning after 1/1/2015 Activity Exposure (person-rem)

Dismantlement Activities Asbestos Abatement (includes scaffolding) 2 Steam Generators and Pressurizer 31 Reactor Coolant System 32 Plant Systems 180 Structures 50 Miscellaneous 136 Subtotal Dismantlement Activities 431 Transportation and Waste Processing/Packaging 41 Total for Decommissioning 472 3-23

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 Table 3-3 Projected Waste Quantities WASTE PACKING WASTE WASTE WASTE TYPE WEIGHT DENSITY VOLUME CLASS (lbs) (lbs/cubic feet) (cubic feet)

Bulk Concrete A 223,263,000 66 3,370,000 Soils A 4,500,900 100 45,009 Metal Debris A 66,890,000 25 - 47 2,590,000 Large Components A 18,200,000 68 - 388 69,700 HazMat A 1,450,000 59 24,700 (containerized)

Highly Radioactive B or C 305,000 80 3,800 Very Highly

>C 71,600 112 640 Radioactive Clean Concrete (on-

- 345,900,000 71 4,870,000 site fill)

Clean Asbestos - 1,008,000 8.3 121,400 Clean Debris (local

- 28,000,000 100 280,000 landfill)

Clean Scrap Metal

- 44,570,000 129 346,000 (recycler)

Totals - 734,159,000 11,721,200 3-24

ZION STATION RESTORATION PROJECT LICENSE TERMINATION PLAN REVISION 1 Table 3-4 General Project Milestones Date Milestone Q3/2014 Unit 2 Reactor Internals Segmentation Complete Q4/2014 Unit 1 Reactor Internals Segmentation Complete Q4/2014 License Termination Plan Submittal to NRC Q1/2015 Complete Transfer of Spent Nuclear Fuel to ISFSI Q1/2015 Cold and Dark Complete (Electrical)

Q2/2015 Complete Demolition of Crib House Q2/2015 Unit 2 Reactor Vessel Segmentation Complete Q3/2015 Complete Demolition of Service Building (East/West)

Q4/2015 Complete Demolition of Turbine Building Q4/2015 Unit 1 Reactor Vessel Segmentation Complete Q4/2016 Complete Interior Dismantlement of Auxiliary Building Q1/2017 Complete Interior Dismantlement of Unit 2 Containment Q4/2017 Complete Interior Dismantlement of Unit 1 Containment Q4/2018 Complete All Major Demolition Q4/2018 Complete FSS and Site Restoration Q4/2018 Complete Zion Station Restoration Project Note; Circumstances can change during decommissioning. If ZionSolutions determines that the decommissioning cannot be completed as outlined in this schedule, ZionSolutions will provide an updated schedule to the NRC.

3-25