ML17199F929

From kanterella
Jump to navigation Jump to search
Forwards Safety Sys Outage Mods Insp Rept 50-249/86-12 on 860421-0507,0609-13 & 0707-16.List of Potential Enforcement Actions,Based on Deficiencies Identified During Installation & Testing Insp,Also Encl
ML17199F929
Person / Time
Site: Dresden 
Issue date: 10/17/1986
From: Partlow J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
To: Reed C
COMMONWEALTH EDISON CO.
Shared Package
ML17199F930 List:
References
NUDOCS 8610270253
Download: ML17199F929 (9)


See also: IR 05000249/1986012

Text

Docket No. 50-249

0

'

. u'NII~'bsTATES

  • .

NUCLEAR Rii!~~A'tORY COMMISSION

WASHINGTON, D. C. 20555

October 17, 1986

Commonwealth Edison Company

ATTN:

Mr. Cordell Reed

Vice President

P.O. Box 767

Chicago, IL

60690

Gentlemen:

SUBJECT:

DRESDEN UNIT 3 - SAFETY SYSTEM OUTAGE MODIFICATIONS

INSPECTION (INSTALLATION AND TEST) 50-249/86-012

This letter conveys the results and conclusions of the installation and test

portions of the Dresden Unit 3 Safety Systems Outage Modifications Inspection

(SSOMI) conducted by the NRC's Office of Inspection and Enforcement.

The

inspection team was composed of personnel from the NRC's Office of Inspection

and Enforcement and Region III, and consultants. This inspection, which took

place at the Dresden site, was part of a trial NRC program being implemented

to examine the adequacy of licensee management and contr.ol of modifications

performed during major plant* outages*.

  • . ..

,r

.

The purpose of the installation and test portions of the trial SSOMI program

was to examine, on a sampling basis, installation and testing of plant modifi-

cations accomplished during the October 1985 - July 1986 outage at the Dresden

Unit 3 plant. This portion of the trial program concludes the trial outage

inspection program at Dresden Unit 3. Reports forwarding .the results of the

design inspection and the vendor inspections have already been issued. The

applicable report numbers are provided in *se9tion 3 of this report.

Section 2 of the report is the detailed discussion of the installation and

testing inspection. The ~ffort was hardware and test oriented and centered

around modifications*accomplished during the outage. Particular attention was

directed toward adequacy of installation, conformance of the modifications to

requirements, adequacy of functional tests, and adequacy of safety-related

maintenance activities.

Section 1 of the report is a summary of the results of the inspection and the

conclusions reached by the team.

The most significant concerns identified

were in the areas of:

(1) inadequate design change control, (2) improper

installation of equipment, (3) inadequate procedures and instructions,

(4) inadequate QA/QC overview of modification activities, and (5) inadequate

control of testing.

i(

B61Q270253 8

Ill

p DR

ADocu

61 01'7' . . ::-\\

1

G

.

-~ 05000249 '. ,;~;~}

  • --- *-

-- --

. *

P DR

      • )

...:...--::-:- ::-.,.__-,._

'~ . .

~

L*-

~--.--,

'(

____ ** .. *.:_. --

  • -

,

,

'-

~.-

______ *,,..-,-.

/.

Commonwealth Edison Company

-2-

October 17, 1986

Our letter of May 16, 1986 to you discussed the results to that point in time

of the installation and testing inspection, informed you of the first four

areas of concern noted above, and listed exampl~s of deficiencies identified

in each of the four areas. Although no response to that letter was requested,

two subsequent management meetings (on May 21 and July 2, 1986) were held at

the Region III office to discuss the inspection team findings and the CECo

corrective actions.

Based on our review of the corrective actions which had

been accomplished by the end of the inspection, and of the more comprehensive

corrective actions which were planned for the future, this office found no

reason to delay restart of Dresden Unit 3 at the conclusion of the outage.

The

Dresden station management was so informed during the site exit meeting on

July 16, 1986.

As noted in Section 1 of the inspection report, your corrective

action program did not address a review of modifications performed during

previous outages to determine if similar deficiencies exist.

We believe it

would be prudent to perform such a review, even on a sampling basis, in order

to provide additional assurance that plant safety margins, from a system

functionality standpoint, have not been. inadvertently degraded during the

modification process.*

.

.

.

~

The Appendix to this letter contains a list of potential*enforcement actions

which are based on the deficiencies identified during the installation and *

testing inspection. These wi'l 1 be reviewed by the. Office of Inspection and

Enforcement and the NRC Region III office for appropriate action.* At the

completion of that review, the Region III offi~e will issue any enforcemeht

actions resulting from the installation and testing inspection, as well as

from the earlier design and vendor inspections.

In addition, Region III will

monitor your corrective actions relating to .those enforcement actions.

.

.

In accordance with 10 CFR 2.790(a), a copy of this letter .and the enclosures ,,

will be placed in the NRC Public Document Room.*c No reply to this letter is

required at this time.

You will be required to respond.J:o Region III* regarding

the specific enforcement findings after those findings are issued by the region.

In responding to Region III, we suggest that you consider our views on enhancing

your corrective.action program as discussed above.

.

.

Should you have any questions concerning this inspection, please contact me or

Mr .. James Konklin (301-492-9656) of this office.

Enclosures:

Sincer~{l **.

  • Jame~~. Partlow, Director *

Divi~i~n of Inspection Programs

Office of Inspection and Enforcement

1. Appendix, Potential Enforcement Actions

2.

Inspection Report 50-249/86-012

cc w/enclosures:

. :.,

See next. page

j

..... *r

I ,

':::/

Commonwealth Edison Company

cc w/enclosures:

Mr. Michael I. Miller

Isham, Lincoln & Beale

Three First National Plaza

Suite 5200

Chicago, IL * 60602

Mr. J. Eenigenburg

Plant Superintendent

. Dresden Nuclear Power Station

Rural Route #1

Morris, IL

60450

U.S. Nuclear Regulatory Commission

Resident Inspectors Office

Dresden Station

Rural Route #1

Morris, IL

60450

Mr. D. L. Farrar, Director

of Nuclear Licensing

Dresden Nuclear Power Station

Rural Route #1

Morris, IL

60450

Chairman

Board. of Supervisors of Grundy County

Grundy County Courthouse

Morris, IL 60450

Gary N. Wright, Manager

Nuclear Facility Safety

Illinois Department of Nuclear Safety

1035 Outer Park Drive, 5th Floor

Springfield, IL

62704

Ms. Phyllis Dunton, Attorney

General's Office, Environmental

Control Division

Northern Region

160 N. LaSalle Street

Suite 900

Chicago, IL

60601

-3-

October 17, 1986

.;.,.,

.,. *-

Commonwealth Edison Company

Distribution

DCS

NRC PDR

Local PDR

RCPB R/F

DI R/F

JTaylor

RStarostecki

JGPartlow

RLSpessard

JKonkl in

SStein

Rlloyd

BKGrimes

JAxelrad

ELJordan

Regional Administrators

Regional Division Directors

ACRS (10)

NMSS

RES

.OGC

AEOD

SSOMI Team Members

NSIC

NTIS

RBernero, NRR

JZwolinski, NRR

RGilbert, NRR

- 4 -

.,

~

APPENDIX

POTENTIAL ENFORCEMENT ACTIONS

As a result of the NRC Safety Systems Outage Modification Installation and Test

Inspections at Dresden Unit 3 during April 21-May 7, June 9-13 and July 7-16,

1986, the following items are being referred to Region III as Potential

Enforcement Actions.

Section references are to the detailed inspection report.

1.

10 CFR 50.59 requires that safety evaluations be accomplished for

temporary or permanent design changes to the facility to determine

whether an unreviewed safety question exists or whether a change to the

Technical Specifications is involved.

Contrary to the above, the NRC inspectors found that the licensee's

procedures for accomplishing engineering safety evaluations were either

not effectively implemented or were deficient in that:

a.

b.

c.

d.

e.

f.

g.

No safety evaluations had been accomplished for specific lead

shielding installations (Section 2.2.1).

No safety evaluation had been accomplished for an increase in the

hydrostatic test pressure for core spray system flow transmitters

(Section 2.2.3).

No safety evaluations had been accomplished for electrical jumpers

installed prior to December 24, 1985 (Section 2.2.6).

Inadequate safety evaluations were accomplished for Station

Procedure Temporary Change Requests written to functionally test

modifications (Section 2.2.7).

Changes were made in the design of reactor building penetrations

without a safety evaluation (Section 2.2.8).

Safety evaluations were not sufficiently detailed and were not

completed in a timely manner (Section 2.2.15).

Dual safety evaluations completed on the same modification resulted

in different conclusions (Section 2.4.4).

2.

10 CFR 50 Appendix B, Criterion III, as implemented by Commonwealth Edison

Company (CECo) Quality Assurance Manual (QAM) Section 3, requires that

measures be established to assure that appropriate quality standards are

specified and included in design documents and that deviations from such

standards are controlled.

Contrary to the above, the NRC inspectors found that the licensee's

programs were not effectively implemented in that:

(,

,,

J,

a.

HPCI pipe whip restraints were inadequately designed and installed

(Section 2.2.2).

b.

Design requirements were not controlled for modification package

M12-3-84-8 (Section 2.2.4).

c.

A design change to the installation packages for EQ motor terminal

leads was not reviewed (Section 2.2.5).

d.

Incorrect design requirements were included in the installation

procedures for modification package M12-3-85-50 (Section 2.2.10).

e.

Uncontrolled design changes were made to solenoid operated valves

(Section 2.2.12).

f.

Undocumented and unreviewed design changes were incorporated into

the installation of the torus to reactor building vacuum breaker

valves (Section 2.2.13).

g.

Unauthorized and unreviewed pen-and-ink design changes were made to

a reactor building penetration modification work package (Section

2.2.14).

3.

10 CFR 50, Appendix B, Criterion VI, as implemented by CECo QAM Section 6,

requires that measures be established to control issue and distribution

of procedures and drawings and that changes to these documents be reviewed

and approved by authorized personnel.

Contrary to the above, the NRC inspectors found that the licensee's

document control procedures were not adequately implemented in that:

a.

Modification package drawings were not controlled in that numerous

drawings were improperly changed or had inaccurate information

(Section 2.3.1).

b.

A drawing revision was not reviewed by an engineer to determine

whether the modification package also required related changes

(Section 2.3.2).

c.

The Master Temporary Change Request Log was inaccurate and not kept

current (Section 2.3.4).

d.

Drawings or other work package documents were in conflict with design

requirements (Section 2.3.5).

4.

10 CFR 50, Appendix B, Criterion V, as implemented by CECo QAM Section 5,

requires that activities affecting quality be prescribed by documented

instructions, procedures or drawings of a type appropriate to the circum-

stances, and that these instructions, procedures, and drawings include

appropriate acceptance criteria.

Contrary to the above, the NRC inspectors found that the licensee's

programs were not effectively implemented in that:

A-2

'(

a.

Work packages contained inadequate acceptance criteria for the

inspection and testing of modifications (Section 2.4.1).

b.

Modification packages were not maintained in accordance with Dresden

administrative procedures (Section 2.4.2).

c.

Test steps which were signed as completed contradicted required test

steps which were also signed as completed (Section 2.4.3).

d.

A Maintenance/Modification Procedure (MMP) was not revised to be in

accordance with Technical Specification requirements (Section 2.4.5).

e.

Work packages did not contain required QA/QC hold points (Section

2.4.6).

f.

Sub Station Construction Department approved procedures did not

contain adequate instructions for safety-related work activities

(Section 2.4.7).

g.

Operating procedure review periods are not in accordance with ANSI

N18.7 requirements (Section 2.4.8).

h.

Modification work packages contained incorrect references to

Technical Specifications (Section 2.4.10).

i.

Dresden Administrative Procedure 15-1 "Work Requests," did not

adequately address revisions of work requests for work in progress.

(Section 2.4.11).

j.

Work was not performed or documented per procedural requirements

for removal and installation of interferences associated with

recirculation piping replacement (RPR) (Section 2.4.13).

k.

Inadequate cleanliness and foreign material exclusion practices were

identified during plant walkdowns and procedure reviews (Section

2.4.14).

5.

10 CFR 50, Appendix B, Criterion V, as implemented by CECo QAM Section 5,

requires that activities affecting quality be accomplished in accordance

with the appropriate instructions, procedures and drawings.

Contrary to the above, the NRC inspectors found that the licensee's work

activities were not accomplished in accordance with requirements in that:

a.

Wrong cable connections had been made in two motor control centers

(Section 2.5.1).

b.

Safety-related cables were bundled with nonsafety-related cables in

panels 2203-73A and 2203-738 (Section 2.5.1).

c.

An RPR electrical installation deficiency was not corrected in

accordance with instructions (Section 2.5.2).

A-3

a

,

'

.,

d.

e.

f.

g.

h.

i .

j.

k.

1.

m.

n.

Cable splices were not made in accordance with vendor requirements

(Section 2.5.4).

LPCI/CS relay wiring did not conform to their wiring diagrams

(Section 2.5.5.1).

All damaged LPCI room cooler motor leads were not repaired, in

addition to other installation deficiencies (Section 2.5.6).

EQ solenoid operated valves were not installed in accordance with

the work procedure (Section 2.5.8).

Uncontrolled and incorrect modifications were accomplished on the

torus to reactor building vacuum breaker valves (Section 2.5.9).

Installation of the Unit 2 CCSW modification was not in accordance

with as-built or design documentation (Section 2.5.11).

A diesel generator instrumentation modification was not installed in

accordance with the work procedure or the design requirements

(Section 2.5r12).

Reactor building penetrations were not fabricated or installed in

accordance with procedures (Section 2.5.13).

Work was accomplished which replaced CCSW piping which was outside

the scope bf the modification (Section 2.4.12).

Snubbers affected by RPR modifications were not properly installed

and inspected (Section 2.5.14).

The fitup of a main steam piping lug was not in accordance with

drawing requirements (Section 2.5.16).

6.

10 CFR 50, Appendix B, Criterion XI, as implemented by CECo QAM Section

11, requires that measures be established to assure that all testing

required to demonstrate that structures, systems and components will

perform satisfactorily in service is identified and performed in accord-

ance with written test procedures.

Contrary to the above, the NRC inspectors found that the licensee's test

programs were not effectively implemented in that:

a.

Test procedures contained a number of inaccuracies, errors and

omissions, even though the tests had been reviewed and approved

(Section 2.7.1).

b.

RPR special test procedures did not include steps to verify the

tests or to document equipment verifications (Section 2.7.2).

c.

Test control was inadequate in that there was a lack of requirements

for documentation of test completion, test acceptability, or

temporary changes to test requirements (Section 2.7.3).

A-4

(_

d.

Discrepancies were found between the FSAR, the Technical Specifica-

tions, and operational surveillance tests of containment isolation

valves (Section 2.7.9 and Table II).

e.

Valve cycling tests were inadequate in that they did not specify

verification of proper stroke times as required by ASME Section XI

(Section 2.7.10).

f.

Test failures or deviations were not properly documented (Sections

2.8.1, 2.8.4, 2.8.6, 2.8.8).

g.

Functional tests for motor operated valves did not provide for

specified acceptance criteria (Section 2.8.9).

h.

Undervoltage and ECCS integrated functional tests were inadequate

(Sections 2.8.10 and 2.8.11).

i.

A hydro test was performed without steps adequate to ensure that each

line was vented prior to the increase in pressure (Section 2.8.17) .

A-5