ML17193A442

From kanterella
Jump to navigation Jump to search
IE Health Physics Appraisal Repts 50-237/80-13 & 50-249/80-17.Noncompliance Noted:Laundered Protective Clothing in Clean Laundry Storage Bins Read 22,000 Counts Per Minute
ML17193A442
Person / Time
Site: Dresden  
Issue date: 08/29/1980
From: Baltzo R, Fisher W, Murphy D, Oestmann M, Paul R, Schumacher M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17193A440 List:
References
50-237-80-13, 50-249-80-17, NUDOCS 8010220486
Download: ML17193A442 (46)


See also: IR 05000237/1980013

Text

U.S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION III

Report No. 50-237/80-13; 50-249/80-17

Docket No. 50-237; 50-249 *

License No. DPR-19; DPR-25

Licensee:

Commonwealth Edison Company

P. 0. Box .767

Chicago, IL

60690

Facility Name:

Dresden Nuclear Power Station~ Units 2 and 3

Inspection At:

Dresden Site, Morris, IL

Inspection Conducted:

June 18 - July 2, 1980

'-//(.~

Inspectors:

M. C. Schumacher

11/ *r-RJ -

~

tv, X~ .. ~~'V

l~R. A. Paul

Approved By:

11;,Jt(i~<.Al-~-

M. J. Oestmann

(l L;,-,,

' l.-**z-~

1n. w. Murp y

/'}

/7

J!'At f.6,

R. M. Baltzo

'11./r-1_~

W. L. Fislfur, Chief

Fuel Facility Projects and

Radiation Support Section

Inspection Summary

I

Health Physics Appraisal on June 18 to July 2, 1980 (Report No. 50-237/80-13;

50-249/80-17)

Areas Inspected:

Special, announced appraisal of health physics program,

including organization, management, training and qualification, exposure con-

trol, radiological controls, surveillance, instrumentation, facilities and

equipment, ALARA, and emergency response.

The inspection involved approxi-

mately 540 inspector-hours onsite by five NRC inspectors.

8010220

Results:

Significant weaknesses were identified in the health physics pro-

gram in the areas of organization and management (Section 2), training and

qualifications (Section 3), access control (Sections 5.4 and 5.6), contamina-

tion control (Sections 5.7, 6.2, 9.1, 9.2, and 9.4) surveillance (Section 6),

instruments (Section 7.5, 7.6, and 7.7), facilities (Section 9.1, 9.4, and

9.7), and emergency response (Sections 3.7, 6.6, 6.7, 9.7, 11.2, and 11.3).

Four apparent items of noncompliance (infractions) were identified:

failure

to follow procedures (Sectons 5.7 and 9.1); potential unrestricted area dose

exceeding two millirems in one hour (Section 5.7); inadequate control of

high radiation area access (Section 5.4); and an unposted radiation area

(Section 5.7).

- 2 -

1.

General

The Dresden health physics program was evaluated during a special

appraisal that began approximately 2:00 p.m. June 18 and ended July 2,

1980.

The Appraisal Team consisted of three inspectors from the NRC

Region III office and two DOE contractor health physicists.

Training required for unescorted access was obtained the first after-

noon and was followed by a meeting with senior plant management onsite.

Thereafter, the team had free access to the entire plant subject only

to the licensee's normal controls for posted and/or locked areas.

Throughout the appraisal, the team emphasized direct interaction with

workers and direct observation of ongoing work by licensee and contractor

personnel.

Considerable time was spent by the team in making direct radiation and

contamination surveys to independently ascertain plant radiological

status and to make comparisons with licensee measurements.

The appraisal

extended to evening, midnight, and weekend shifts, as well as normal

day shifts.

The appraisal was essentially limited to Units 2 and 3

since Unit 1 is undergoing an extensive decontamination program and is

empty of fuel.

Units 2 and 3 were at power during the period.

The Appraisal Team observed a health physics program that was somewhat

old fashioned and that was geared to routine conditions but uncertain

and incurious in the face of nonroutine conditions.

Program implementa-

tion was without significant influence of professional health physicists.

The situation results from a severe union-management dichotomy, and

management weakness in the face of it, together with abetting weaknesses

in Radiation Chemistry (R/C) personnel training and selection.

Significant

findings relating to these problems and othe.rs are addressed in Appendix A

of the letter covering this report.

Other findings of lesser significance

are mentioned throughout the report.

2.

Organization and Management

2.1 Organization

Dresden Station is organized along the same lines as other reactor

stations in the Commonwealth Edison Company (CECo) system.

The

Radiatfon Chemistry (R/C) Department Supervisor (equivalent to

ANSI N18.1 Radiation Protection Manager) reports through the

Assistant Superintendent for Administration and Technical Services,

who is not qualified in health physics.

Direct interaction with

the station superintendent appears limited to attendance at a daily

meeting where attention is directed at daily work plans.

It is not

a forum for discussion of matters of general health physics interests,

however.

It was apparent to the Appraisal Team that the superintendent

was not well informed about all aspects of the health physics program

- 3 -

at Dresden, and in particular about arbitrary limitations that have

limited the scope and quality of professional health physicists at

the station.

In matters relating to plant surveillance and health physics control

at the work site, Radiation Chemistry Technicians (RCT's) report to

and are assigned by R/C Foremen.

The Foremen, Lead Health Physicist

(LHP), Health Physicists (HP's), and Engineering Assistants (EA's)

all report directly to the R/C Supervisor.

The professionally trained

HP's are physically separated from the RCT's and foremen and in fact

have minimal contact.

The separation of RCT's from HP's and absence

of an experienced HP in the chain of command between the Foreman and

. the R/C Supervisor places an unreasonable burden on the Supervisor

and* denies the Foremen much needed technical support particularly as

it affects the quality of RCT work.

Observations related to this

problem are also reported in Section 6.0 (Surveillance).

A recent organization plan for the R/C Department is flawed in that

the Lead Chemist reports to the Technical Supervisor outside the

department instead of to the R/C Supervisor (result of a change made

in 1979) .. Responsibility for radiochemistry is ambiguous because

station administrative procedures continue to allo~ate responsibility

to both supervisors.

Where the Lead Chemist is responsible for routine

analysis of radwaste releases, under emergency conditions this responsi-

bility transfers to the R/C Supervisor, who has no routine concern for

this activity.

Daily laboratory analysis, counting, and related sample collection

is performed by a common pool of Radiation Chemistry Technicians

(RCT's).

RCT's report to the R/C Supervisor in matters relating to

surveillance and work control and to the Lead Chemist related to

laboratory centered functions.

This dual responsibility again de-

creases the effectiveness of superviso~y effort.

Corporate Health Physics has no line relationship with the station

R/C Department.

Corporate is responsible for formulation of CECo

health physics policies, for development of certain generally

applicable procedures, and for providing emergency support to stations.

2.2 Emergency Organization

Dresden GSEP and EPIP's cover emergency organization and respon-

sibility drawing upon plant, corporate, and contractor personnel.

Corporate Command Center, Station, Environs, and Division Groups

are assigned specific functional areas of responsibility.

In an emergency, the R/C Supervisor is designated the Rad/Chem

Director reporting to the Station Group Director.

He has respon-

sibility for onsite radiation protection and radiological controls,

laboratory and counting room operations under the plant chemist,

- 4.-

"

onsite assessment of effluent releases, and early offsite environs

monitoring~ The last activity is coordinated by the Rad/Chem

Director until the designated Environs Director reporting to the

Environmental Director of the Corporate Command Center Group

takes over this function.

2.3 Management and Control

Perhaps the most significant problem at Dresden is the absence of

significant professional health physics influence on the health

physics program.

The causes appear to be the strong union-management

antagonisms that exist within the station's R/C Department, lack

of adequate training for RCT's and newly assigned HP's (Section 3.5),

physical isolation of the HP's and RCT's, and, most importantly,

failure of management to define and support the role of the HP's at

the station.

Instead of a mutually beneficial cooperation between

plant-wise RCT's and professionally trained HP's to build a strong,

aggressive, and up-to-date program, there exists mutual antagonism

and lack of respect.

The result appears to be a health physics pro-

gram geared to stereotyped, routine operations but possibly lacking

the aggressiveness and imagination needed to cope with abnormal

conditions.

The R/C Supervisor is responsible for management of the health

physics program.

Foremen reporting to him direct the day-to-day

activities of the RCT's who implement the program.

HP's, also

reporting to the R/C Supervisor, are expected among other duties

to evaluate program implementation, suggest needed program changes,

and otherwise provide assistance to the R/C Supervisor.

Actually, the day-to-day program is run by the RCT's in virtual

autonomy.

The foremen provide little day-to-day supervision other

than making work assignments, and the HP's are largely prevented

from making meaningful evaluation of program implementation because

of locally interpreted work rules.

These rules, which appear more

stringently interpreted here than at other CECo stations, effectively

prevent use of portable survey and counting instruments by HP's ,in

making evaluations of program effectiveness or in gaining familiarity

with plant conditions.

Such instrument use was described as subject

to grievance or threat of grievance on the basis of management doing

work of the bargaining group.

Resolution was said to *occur usually

at an early stage without written record and to be accompanied by

implicit or explicit pressures from the Industrial Relations (IR)

representative to avoid grievances.

The scope of HP responsibility

and the character of the HP program appears to be defined in quasi-

litigation involving the union representative and second level station

management.

The Superintendent indicated his own understanding that HP's could,

in_ the course of their duties, use instruments without necessarily

infringing upon the legitimate concern of the union and that he knew

- 5 -

of no grievance resolutions or pressures to the contrary.

Whether

these pressures are real or only perceived as real, the effect is

the same.

Professional HP evaluation of routine program implementa-

tion and of RCT performance is weak and the program is weak because

of it.

Currently, two foremen are concerned with radiation protection; one

works the assignment desk while the other handles other duties in-

cluding in-plant observation and supervision.

The observation of

the Appraisal Team that the foremen spent little time in-plant was

reinforced in discussions.with a number of licensee employees who

indicated that in-plant presence of the foremen had substantially

diminished.

This necessary element of first line management should

be restored.

Management tools to encourage quality performance (adequate job

description, performance standards, performance review) by RCT's

and management are generally missing.

Supervisory training for

foremen and HP's was minimal.

2.4 Management Support

Management support for health physics is weak.

Most significant

is the absence of professional HP program evaluation and guidance

described in the previous section (2.3).

The lack of station and

corporate support was frequently cited for the significant loss of

HP's from the station and from the company,

Lack of encouragement

for professional development, low salary, and excessive overtime,

all expressions of weak management support have also been cited.

These appear to be CECo system problems not restricted to Dresden.

Other indications include a weak RCT training/retraining program,

ineffective preparation of HP's, lack of health physics involvement

in radiation work planning by other departments, and lack of a

formal ALARA program.

There appears to be a basic station management misunderstanding of

what constitutes a good health physics program.

The program seems

to be viewed as a set of rules administered by the R/C Department,

imposed and enforced by the NRC, which yields enforcement sanction

points if violations are discovered.

The number of sanction points

(not man-rem etc.) is tracked. as a measure of program success.

2.5

Communications

Information flow within the 9epartment and with other departments

was of mixed quality.

The aforementioned antagonism and the re-

sulting communication gap between RCT's and HP's is of principal

concern.

Review of the RCT log indicates that it 'is not effectively

- 6 -

used for communicating health physics concerns among RCT's or

between RCT's, HP's, and foremen.

These channels must work if an

effective program is to exist.

Another factor that affects RCT-HP communication is the physical

isolation that exists between them.

The HP group, housed in the

Administrative Center beyond the gatehouse, often is not conveniently

available for consultation.

The morning meeting provides a vehicle for communication with other

department heads.

At this meeting, daily work plans are discussed,

work requests assigned priorities, and required signatures are ob-

tained for high priority work requests.

Not infrequently, the work

is already underway while the meeting is going on.

Too often,

workers show up "ready to go" except for radiation protection sur-

veillance.

Opportunity for effective ALARA review and effective

RCT scheduling is thus lost.

Total Job Management (TJM) adopted

by CECo is supposed to avoid such problems, but as yet has not been

very effective; the maintenance superintendent estimated the TJM

was about five percent implemented.

The inadequacy of the morning

meeting for communication between the R/C Supervisor and the Plant

Superintendent was already mentioned.

(Section 2.1).

2.6 Staffing

Total staffing of the R/C Department (Figure 2) of 44 (33 RCT's,

three foremen, three EA's, four HP's, and one R/C Supervisor) appears

generally adequate.

Contract technicians have not been used at the

plant since 1977.

Health physics group staffing is marginal owing to

a lack of plant experience (18 months average) of the professionally

trained HP's.

Turnovers continue to hurt this group as the HP with

Unit 1 decontamination project experience is leaving.

RCT staffing levels appear adequate for routine operations.

However, problems with qualifications of backshift RCT's were noted.

(Section 3.2)

Foremen staff (three) appears adequate but should be reviewed

because not enough in-plant observation and supervision occurs.

Outage staffing should also be considered because union agree-

ments apparently limit the number of RCT's who can work on the

backshifts without supervision.

The chemistry group of four chemists and one EA is experienced

and stable.

Four college trained chemists have Dresden experience

of one, two, seven, and eight years.

2.7 Audit Program

Audits and surveillances by onsite and offsite personnel in 1979

and 1980 were reviewed.

None of the licensee's audits provide or

- 7 -

are intended to provide an independent technical review of radio-

chemistry or radiation protection.

This finding applies to all

CECo nuclear stations.

The audits gave only limited attention to matters of radiation

protection or radiochemistry interest and the findings were gen-

erally unremarkable.

Surveillances tended to concentrate on solid

waste shipping.

Audit No. 80-11 of February 1980 examined qualifications of onsite

review participants.

Included in the audit information was a matrix

showing ten individuals as qualified (i.e., meeting ANSI Nl8.l-1971

requirements) in a lumped category of radiation protection/chemistry.

On the basis of knowledge immediately available to the inspectors,

two individuals were qualified in radiochemistry but not radiation

protection and two the other way around.

The remaining six

individuals were not evaluated but it is doubtful that all would

be qualified in both areas.

The Technical Supervisor, who selects

review participants, stated that a reviewer's qualifications are

matched to the topic being considered.

The Appraisal Team recommends

that licensee procedures ensure this consideration.

The offsite audit of May 20-22, 1980, was a rather comprehensive

QA audit of health physics activities.

Significant findings in~

eluded failure to follow procedural requirements for measurement

and investigation of internal dose and included inadequacy of the

RCT retraining program.

The auditor noted that the qualifications

of four RCT's were compared with and found to satisfy Section 4.6.2

"Staff Specialist" of ANSI Ni8.l-1971.

In the opinion of the Appraisal

Team, RCT's in responsible positions must meet Section 4.5.2 "Techni-

cians" of that standard.

(Section 3. 2)

2.8

Summary

Unusually strong union-management dichotomy and weak management

support for professional health physics activity have had a per-

vasive, deleterious effect on the Dresden radiation protection

program.

Mutual antagonism, disrespect, and lack of cooperation

between RCT's and HP's have helped shape a superficial, somewhat

outdated program which appears adequate for routine situations

but which may not be under anomalous conditions.

This is a

significant finding that should be corrected to ensure a fully

adequate health physics program.

3.

Selection, Qualifications, and Training

.-,, ..

3.1 Selection

CECo procedures by which RCT candidates are recruited or selected

were not observed directly.

However, by observation of job per-

- 8 -

DR.t.SD[N ORGANlZATfON

(Aee~ev1Arto)

SUP(P.\\NTt:NOCNT

--~~--~---,._..~--------~---.' r--~---'--~----~~-----__.--~--.j'---~---

ASST. 5UPt

,f

ASST. SUPT.

PrRSONNE:\\;..

ADMINISTRATOR

-i-Rl\\tNrN&

WPVR.

'

~ lNSTR.

~STAtF.

SH1J:T

tNGR~

t

ASST,. . SUP1':

UN\\\\ l

O?~ATIONS

. f\\DMIN.¢ SUPPORT

MAINT£NANl£

PU.OJECT MGR. 9,

~ Ov1A~~

COOROINATllR


.

-

STAfr. ACS~1 s

I

....

  • OPE:t<.

WA~1E'

tNGQs

S'f$T~M

£:Ntifl-

k

k

r r

I

.

I

.

~_5-R_ u__,,'£-/0*-.. l~n.'c,~, _TC_. <:._H ___ Sti_A_n__,:* ,_M_A __ $_T_£R- -M-A,.-$it,g,___. MAST~

STO~t"

rvt"'\\,

-V~t'5',

SUPVR...

ME.CJ;.\\.

tl((..

INS'fg_

K£EPt.:R

l

R.CTs

.

formance and the effectiveness of training, the Appraisal Team

was able to identify factors essential to selection which must be

considered at Dresden.

RCT's are required to operate and evaluate the readings of several

small, single function portable instruments as part of a daily

routine.

RCT's also operate and evaluate the output of complicated

laboratory instrument systems.

However, under conditions of job

rotation at Dresden, the assignments recur at 6 to 12-month intervals

with no opportunity for study or retraining in the interim.

Further, RCT's suited to meticulous and dedicated laboratory and

instrument work draw upon skills vastly different from those re-

quired to exercise occasional authority over operators, engineers,

maintenance workers, and contractors in a production oriented work

place.

At CECo nuclear stations, RCT's are required to be proficient

in both areas.

The RCT candidate who can do both satisfactorily is

clearly a rare individual.

Separation of the two tasks would a~

once simplify selection and the problem of loss of competence owing

to the rotation period.

3.2 Qualification

In order to determine that Radiation Chemistry (R/C) Department

personnel qualifications meet ANSI N 18. 1 1971 standards, it was

- necessary to refer to separate records maintained by the Training

Department, R/C Supervisor, and RCT foremen.

Training Department

files are orderly but incomplete in that about a quarter of the

records do not list date of entry to the R/C Department at Dresden

Station, and there is no record establishing when or whether RCT

training was completed.

It was necessary to obtain these data by

reference to the supervisor and foremen records.

Since 1977, basic employee training data have been more systematic;

however, Training Department records do not keep current on con-

tent and completion dates for newly generated qualifying courses

related to new laboratory instruments and procedures.

It was

therefore impossible to verify by reference to records complaints

by RCT's that they had never been trained to perform functions

which are now part of the regular weekly assignment schedule (i.e.,

use of atomic absorption spectrometer, whole body counter, GeLi

counter, etc.).

The deficiency of records is largely attributable

to the divided responsibility for training at Dresden Station.

In common with other CECo nuclear stations, Dresden RCT's are

promoted to full journeyman status immediately upon completion of

their RCT training course.

No distinctions such as A level or B

level or years of experience are observed when they are given R/C

job assignments on a rotating weekly basis.

However, in practice,

- 9 -

the Appraisal Team recognized clear differentiation in job perfor-

mance, particularly with respect to routine and special surveillance

skills and in laboratory procedures.

It is further evident from a number of complaints received by the

Appraisal Team that about 30% of RCT's have not received training

which would qualify them to perform all assigned tasks.

This

deficiency has led to the practice of trading job assignments.

In

practice, several RCT's have gone for two or more years without

personally performing certain work assignments.

In addition, 14

of 33 RCT's had less than the requisite two years experience (ANSI

0 18.1 Section 4.5.2 "technicians") and were thus not qualified by

ANSI standards.

(Table 3.1).

It is therefore evident that backshifts and weekends are frequently

manned by inexperienced and unqualified personnel.

In the event of

an emergency, qualification deficiencies are likely to significantly

reduce capacity for effective response.

Table 3.1 - RCT Experience Summary

(as of 6/1/80)

Less than

2 years

14

2 to 6

years

14

Over 6

years

5

The R/C Supervisor, Lead Health Physicist, Lead Chemist, Health

Physicists, and Chemists meet their respective academic and

experience levels prescribed by ANSI N18.1-1971.

The Appraisal Team noted that disaffection and the lure of better

salaries, and improved working conditions elsewhere may be making

more inroads on Dresden Station's trained and experienced RCT's

and HP's than the radiation protection program can bear.

3.3 Training - General

The Dresden Station Training Department is located in a new admin-

istration and technical support service building just outside the

security gate house.

Well equipped classrooms and instruction

offices occupy about one third of the ground level.

An auditorium

permits training up to 50 persons at a time, using video tapes,

slides, or movies.

The Training Supervisor reports to the Personnel Administrator.

The principle mission of the Training Department was identified

as training of operator personnel.

Operator instructors exchange

positions with Operator Foremen to maintain currency.

Of a staff

of 12 instructors, eight are assigned to operator training, three

- 10 -

to general employee radiation protection training (NGET) and re-

training (NGER), and one to coordination of maintenance training.

The lead NGET instructor began teaching in 1977 after eight years

as an RCT and as an operator before that.

He has trained five

additional persons as auxiliary NGET instructors to handle peak

workload periods such as outages.

The Training Department provides routin~ operator pre-license

training (one year) and post-license training by means of a fifth

shift rotated into training.

Lesson plans for operator personnel

are derived from NUS.

Operator lesson plans are based on Nuclear

Energy Training Module 5 with supplements (i.e., 7-8 days) but do

not include sufficient training in instrument use and evaluation

to qualify them as self-monitoring individuals.

The Training Department also coordinates a comprehensive maintenance

skill advancement program based largely at CECo's Shorewood training

establishment.

Additional special courses (i.e., Control Rod Drive

Mock Up, Recirculating Pump Seal, Overhead Crane 0. 0. S., First Aid

and Fire Protection) are given at the station.

Approximately six

percent of maintenance staff mechanics and electricians are away at

scheduled training events throughout the year.

The training schedule

is not interrupted by outages.

The Training Department is not involved in RCT training, except for

annual qualification (NGER), fire, and first aid courses.

RCT train-

ing and retraining is addressed further in Section 3.5.

3.4 Nuclear General Entry Training

All persons entering the Dresden Station are required to receive

NGET unless they are to be escorted.

Special versions of the NGET

lesson plan have been developed for persons with restricted interests

such as emergency firemen, ambulance drivers, phone repairmen, and

food machine servicemen.

The normal radiation worker version lasts

four hours with the first 30 minutes devoted to security and general

safety and about three hours devoted to radiation protection topics.

It is followed (after lunch) by mask fitting and step-off pad procedure

(video tape and walk through).

Everyone does not receive the respirator

fitting and training and this can lead to uncertainty later in identi-

fication of persons unqualified to wear respirators.

(Section 4.3)

In June 1980, a written test was introduced.

Seventy percent correct

answers are required for a passing score.

Three failures were allowed

to repeat the course and take a different test.

Fourteen hundred and

thirty-five persons were NGET trained in 1979.

An Appraisal Team member attended the complete NGET in order to

evaluate scope and effectiveness.

The lesson plan included a broad

- 11 -

'1

selection of topics relevant to radiation protection with one

important exception.

Topics dealing with low-level exposure,

latent effects, vulnerability to internally deposited emitters,

and the relationship of these topics to cancer were given short

shrift and relegated to the end of each session, thus conveying

the impression that they were unimportant or irrelevant.

Moreover,

the relationship of these potential effects to the nuclear station

radiation protection program (i.e., access controls, work permits,

surveillance, whole body counts, and exposure records) was never

explained or referred to.

In the absence of such explanations,

production oriented workers in Operations and Maintenance may

develop negative attitudes toward R/C Department functions and

eventually come to disregard protective procedures.

The lack of

cooperation by some personnel that is evident at Dresden now may,

in part, be attributable to this missed opportunity for promoting

the role and function of the R/C Department during NGET and NGER.

Conversely, some topics in radiation science are important to the

further development of radiation protection for operators and RCT's

but are not directly relevant to general entry training.

Redistribution of the time involved may assist in keeping the course

within its four hour time frame.

3.5

RCT Training

Training new RCT candidates in radiation protection (background

and skills) is carried out completely within the R/C Department.

A health physicist or chemist is assigned to prepare, organize,

and deliver the course to each class of six or seven candidates.

While he develops his lesson plan with reference to earlier courses

and is free to add in fresh material, this method suffers a disad-

vantage in that each health physicist usually enters the classroom

without previous classroom teaching experience.

Unlike many tradi-

tional graduate departments, health physics degree candidates are

not always provided an opportunity to teach undergraduate classes

and it can not be assumed that they have the necessary skills.

As a result, the novice instructor may tend t6 talk over the head

of his class.

Since no RCT class was in process, training pro-

ficiency could not be directly observed.

The Appraisal Team could

only note that RCT's complained that chemists and health physicists

regularly appeared to present their course work at a level above the

student's comprehension and this contributed to a general feeling of

antagonism and mutual distrust.

Use of health physicists and chemists as the primary RCT instruction

source introduces a second element of discord in that the instructor

is normally new to Dresden and to a working environment.

Given the

rigid restrictions on what activities health physicists are eligible

- 12 -

to do in the bargaining unit's domain, limited opportunity is

available to temper their academic knowledge with reactor ex-

perience.

On the other hand, RCT students have one or two years

experience and are already plant-wise and share worker developed

attitudes toward many of the topics being discussed.

In the absence

of practical experience, the instructor is put at a severe disadvant-

age and classroom rapport, which is essential to effective training,

is undermined.

The existing RCT training organization is ~ major source of dis-

cord and antagonism within the Rad/Chem Department.

The normal

working relationship between RCT's and health physicists, already

strained by rigidly enforced definitions of bargaining unit pre-

rogatives, is undermined at the beginning of their career at Dresden.

The Appraisal Team's observations of RCT and HP performance indicate

that the RCT training responsibility needs thorough review and recon-

sideration.

The most recent RCT initial. training class was offered March through

June 1979.

It consisted of:

three weeks classroom training related

to general math, radiation science, and radiation protection; three

weeks devoted to chemistry and laboratory procedures:

and eight

weeks of on-the-job training.

Lesson plans examined were informal

collections of outlines and data which do not provide an indication

of when the material was ~dopted or approved.

In general, the

selection of topics appeared to follow outlines familiar in on-station

power reactor training elsewhere.

There was no opportunity for the appraisal team to directly observe

RCT training.

However, suspected deficiencies in training ~ere

confirmed by observation of RCT job performance and by subsequent

interviews with RCT's and other R/C personnel.

Among the significant

weaknesses observed were:

failure to recognize the need in good

radiation protection work to deviate from routine duties to pursue

and evaluate anomalous conditions; failure to recognize certain

conditions (particularly contamination incidents) as anomalies to

be pursued beyond the point of establishing control boundaries;

absence of system training relevant to radiation protection needs;

and inaccurate timekeeping.

3.6

RCT Retraining

In addition to weaknesses in subject matter and delivery enumerated

above, the ambitious retraining effort which began in 1976-1977 has

virtually been abandoned in 1979 and 1980.

Since 1977 (the apex of

Dresden support), training schedules have regularly been interrupted

in each instance where a need for RCT services develops and preempts

their attendance.

This practical coRsideration has not been allowed

to interfere with maintenance or operations instruction schedules.

- 13 -

In 1977 and early 1978 the RCT retraining program identified*

approximately 35 classroom and laboratory courses ranging from

one hour to one day.

Topics for retraining included plant wide

requirements for fire fighting, first aid, and NGER.

Additional

courses relevant to RCT interest covered whole body counting,

mask fitting, rad waste, CPR, gas samplers, and many other areas

representative of a dynamic and developing field.

In 1977, only

18 of 2~ RCT's fully participated.

Since that time, participation

.has decreased and, currently, many recent RCT's have never received

special retraining topics which may not have been included in their

initial training.

(Section 3.5).

There is no evidence that the retraining concept at Dresden re-

cognizes a need to review and update RCT performance .in those

topics covered in their initial training course.

This deficiency

is all the more conspicuous in view of the lack of regard for

presentation and effectiveness of the initial RCT training.

The

RCT training program at Dresden station is weak and the retraining

pro~ram is currently nonexistent.

This results in observably weak

RCT performance (Section 6) in several areas, particularly those

that contribute to effective handling of nonroutine or unplanned

events.

It is likewise evident that Dresden commitments to RCT excellence

through retraining falls short of the effort expended for other

personnel.

On the basis of station records, the appraiser estimated

RCT retraining at about one to two percent full time equivalent com-

pared with about 18 percent for operators, 8 percent for maintenance

personnel, and 11 percent for station men.

3.7

Emergency Training

Dresden Station training provides for a limited discussion of the

Emergency Plan (GSEP), of the emergency plan implementing proce-

dures (EPIP's), and of the individual's role in an emergency during

the initial orientation (NGET) for employees and contractors.

Basi-

cally, personnel are informed about emergency signals and assembly

areas.

The annual retraining (NGER) required for renewal of the

security badge includes repetition of this same material.

The licensee uses quarterly drills for training.

However, they

usually provide only minimal training to RCT's.

The annual medical

drill has limited involvement of the RCT's, as it is principally

directed toward ambulance and medical personnel.

Drills are seldom

held on weekends or on backshifts to test how rapidly offsite per-

sonnel could respond.

Critiques are held after each drill but

individual performance of specific emergency duties as demonstrated

in the drills is not routinely evaluated.

- 14 -

The drill conducted on June 19, 1980, (Section 11.3) was the first

in which RCT's were heavily involved in emergency response teams to

collect simulated highly radioactive samples and to provide radiation

assessments.

It also included use of environs teams to verify communi-

cations and to simulate plume tracking.

The licensee plans to conduct

more such drills in the future.

With the development of a new emergency plan and new implementing

procedures, the licensee's productions training department prepared

a detailed lesson plan for emergencies.

The lesson plan appeared to

be adequate.

However, the instructor teaching the program at the

--station has had limited experience in the subject and should receive

specialized training in this area.

Training was given to station personnel with GSEP responsibilities.

Approximately one-half of the RCT's received a review of the emergency

procedures (EPIP's 300-8, 300-9, 300-10, and 300-11) for post-accident

sampling of containment atmosphere, reactor coolant, and release rate

determination before the June 19, 1980, drill.

Discussion with in-

dividual RCT's indicated, in some cases, an unclear understanding of

their roles except for mustering at the Operational Support Center (OSC)

for further instructions.

Appraisal Team observations of this drill

identified sample handling and other practices that could be hazardous

during an actual emergency.

(Sections 9.7 and 11.2)

3.8

Summary

Based on the appraisal findings, significant improvements are needed

with regard to RCT qualification and training to achieve a fully

acceptable program.

Appraisal team observations indicated weaknesses

in basic health physics fundamentals, weakness in the identification

and evaluation of anomalous conditions, incomplete emergency training,

neglect of retraining, decline in competence resulting from the long

period rotation schedule, and failure to recognize RCT qualification

status in the rotation schedule.

4.

Exposure Control

4.1 External Dosimetry Program

The external exposure measurement.during routine operation consists

of timekeeping, paired indirect reading pocket chambers (pencils),

and Landauer film badge services.

The biweekly film badge results

are maintained as the official record for personal exposure data.

The timekeeping and pencil results used for daily updating of per-

sonal exposures are entered into the official exposure records only

when film badge results are not available (i.e., lost or damaged

f_ilm badge) .

- 15 -

,.

Weaknesses in the computerized official1,xposure records system

were observed during the Zion appraisal- .

The principal problem

was that performance standards and procedures for the control and

traceability of changes to the official exposure records had not

  • been established.

In addition, the potential of the system for

retrieving selected dose data and for computer auditing of redun-

dant exposure files had not been exploited.

The same system weak-

nesses were also observed at Dresden.

However, Dresden station

practices resulted in satisfactory documentation of exposure record

changes.

The various records (film badge, pencil sheets, lost/damaged

badge reports, etc.) are maintained in easily accessible biweekly

report*files.

However, retention time* had not been defined for these

supporting dosimetry records.

Generally, the* exposure program suffers from lack of good review

and built-in quality assurance.

Various people have responsibility

for different parts of the program, but no one person provides

continuity through an overview of the entire program.

Little pr

no interaction is maintained between the RCT's who imple~ent the

program in-plant and the health physics professionals responsible

for the overall program.

The pencil dosimeters are not quality assurance tested as suggested

by ANSI 13.5 "Performance Specification for Direct Reading and

Indirect Reading Pocket Dosimeters of X and Gamma Radiation."

New

pencils are placed in service after leak testing.

When a discharged

pencil is encountered during the daily pencil reading, the dosimeter

is taken out of routine use and "quality controlled" according to

DRP-1250-3.

The procedure includes leak testing and 45 mR and 145

mR source exposure checks.

If the pocket chamber performs satis-

factorily, it is returned to routine use.

The approximately 1700

self-reading pocket dosimeters, which are available for routine use

and for timekeeping purposes, are subject to the same program.

Film badges spiked over a range of about 100 to 3000 millirems

are routinely submitted to the vendor for evaluation.

The data

reviewed.by the appraisal team indicated that at the lower end of

the scale. the vendor consistently reports a dose higher than

supposed by the licensee.

The licensee looks at but does not

evaluate these data so that it is not known whether the bias

exists in the spiking or in the vendor's analysis.

The licensee

should also review neutron dose accounting because the track etch

dosimeter used very likely underresponds to the moderated neutron

fields seen at the station.

The station relies upon the use of timekeeping in high radiation

areas to control daily dose limits.

Available self-reading pocket

chambers are seldom used with .. timekeeping, and indirect reading

!/ RIII Inspection Report 50-295/80-05

- 16 -

pocket chambers are usually immediately read only at the request

of the employee or a supervisor.

A review of the timekeeping/

pencil sheets and the film badge results indicated that the

timekeeping results were routinely much higher than the associated

film or pencil results.

In some cas~s, the timekeeping results

were a factor of ten higher.

Timekeeping is a historical method of dose control.

When done

well, it is an impressive demonstration of job control from a

radiation safety standpoint.

In many cases, dose estimates will

not vary from other dose measurements by more than 20 percent.

However, it is a difficult skill to master, and the technique is

subject to errors from such factors as radiation field complexity,

size and scatter of crew(s) monitored, and the ability and diligence

of the RCT involved.

The discrepancies noted here would indicate

the *skill is not well mastered by the relatively inexperienced group

of RCT's at the station.

Discrepancies are usually inconsequential since the film badge

results are used to generate the official individual dose records.

However, when the film badge is lost or damaged, timekeeping re-

sults (plus the pencil results) are used to assign the individual's

dose, which, in most cases, means assigning a dose significantly

higher than probably received.

Although the method used is con-

servative, the dose assessed should be based on the most reasonable

or realistic estimate.

Timekeeping data are also used as the basis for developing the li-

censee's REP program wherein exposures are retrospectively apportioned

to different job activities. Errors undermine timekeeping's

accuracy

and usefulness as an exposure predictor for recurring jobs.

More

importantly, ALARA is subtly undermined because the consistent time-

keeping overestimate results in unnecessary and wasteful (in terms

of dose) crew changes in order to stay within assigned daily dose

limits.

Based on the appraisal findings, this portion of the licensee's

program is acceptable.

However, the following should be considered

for improvement of the program: review of timekeeping* results, use

of self-reading dosimeters as a supplement to timekeeping, better

quality assurance for pocket chambers and film dosimeters, and

evaluation of neutron dose accountability.

4.2

Internal Dosimetry

Internal exposure measurement (whole body counting and urine

analysis) is supplied by RMC.

The whole body counter (WBC) is

dependent upon an associated computer for continued operation.

The ability to manually operate the WBC and interpret the results

onsite is nonexistent.

Urine sampling is the backup for the WBC;

however, the WBC is the primary means for internal measurement.

- 17 -

"

A baseline whole body count is required for badging of potential

.radiation workers and another is required upon termination.

A second counter was set up to help process contractors during

the last outage.

The quality assurance (QA) for internal measurement is vendor

supplied.

Check sources supplied are used in the same rolled up

fashion observed at other CECo stations.

NBS traceability of

these sources appeared to be five to ten years old.

The licensee

performs no QA with other standard sources nor are recounts used

for replication checks.

The offsite audit of May 20-22, 1980, noted that during the high

traffic period of the last outage, standard source and empty bed

counts were frequently not done at the end of the day as required

by licensee procedure DRP 1340-2.

On the advice of the vendor,

the requirements were changed to require these counts in the morning

and/or over lunch.

No problems in adherence to the revised procedure

were noted during the appraisal.

The WBC is located in an area that is subject to changing Back-

ground radiation levels.

The problems associated with the WBC

facility are addressed in Section 9.3.

The action level in percent of MPBB are posted and adequate.

The mechanism for investigation of possible internal depositions

(showering, recounts, etc.) is well established and has adequate

forms for documentation available (DRP 1340-2).

Two forms are.

used in evaluating a suspected deposition.

The first form contains

the essential information about the individual and the WBC results;

the second form contains the followup information.

The second

form contains no personal identification and when filed, the two

forms may not be attached to each other and thus may become

separated.

This practice is not consistent with the maintenance

of scientific or legal records or with the recommendations of

ANSI N13.6, "Practice of Occupational Exposure Records Systems."

Based on the appraisal findings, this portion of the licensee's

program is acceptable; however, the following matter should be

considered for improvement of the program:

better identific.ation

and filing of the investigation forms.

4.3 Respiratory Protection

The licensee has implemented a respiratory protection program that

includes procedures covering administrative and technical details

required by 10 CFR 20.103 and Regulatory Guide 8.15.

Basic

engineering control~ in use include fume hoods in hot laboratories

and sampling area, temporary ventilation systems, and directed air

flows.

- 18 -

Qualification of respirator wearers includes medical approvals,

training, and fitting.

However, licensee procedures do not ensure

that accurate, timely information regarding approved users is

available to an RCT at the mask issue room.

There, qualification

is often confirmed by questioning of the would be user.

Security badges giving unescorted access imply but apparently do

not guarantee that all qualifications for use have been met because

of individual variances permitted.

Security badges are sometimes

punched to indicate that an individual requires a special respirator.

NGET cards, which indicate respirator approval status have not been

issued to all station personnel and their use to identify qualified

users is not stressed.

Quantitative fitting results are entered on

an individual's NRC Form 5, but these are not sufficiently timely

for use in issuance and, furthermore, are kept in the Administrative

Center outside the gatehouse.

The program appears to lack the built-in controls and internal

audits necessary for management to ensure program reliability.

By

procedure, each respirator is cleaned, inspected, and packaged for

reissue.

However, no program exists to examine a sample of these

available masks.

Quantitative fit test results are apparently not

reviewed by cognizant management; nor, apparently, are issuance

records spot checked to ensure that qualifications are being met.

Based on the appraisal findings, ihis portion of the licensee's

program appears acceptable.

However, the mask issuance procedure

should be upgraded to ensure that qualified users can be readily

identified by the issuing RCT.

Built-in controls and/or audits

necessary to ensure proper program functioning should also be

considered.

4.4 Emergency Conditions

Provisions for dosimetry services for unusual or emergency situations

appear generally adequate.

Significant backup of dosimetry and

respirator supplies and bioassay capability exists at other CECo

stations and/or from licensee contractors.

Dresden's supply of

full-face filter respirators, self-contained breathing apperatus,

and spare air bottles appears adequate for short term emergencies.

Potassium iodide tablets for thyroid blocking are available onsite

and the licensee's medical director has provided instructions for

their use.

Based on the appraisal findings, this portion of the licensee's

program appears acceptable.

- 19 -

5.

Access and Contamination Control

5.1 Restricted Area Access

The Dresden restricted area is basically the same as the protected

area defined for security purposes.

All major buildings (Reactor,

Turbine, Radwaste) except the Administrative Center are within

this area.

Access through a guardhouse requires an identification

security badge or escort.

The security badges are color coded to

indicate levels of unescorted access permitted.

Based on the appraisal findings, this portion of the licensee's

program appears adequate.

5.2 Controlled Area Access

Unescorted access to controlled areas requires completion of

radiation protection training in addition to the basic security

orientation.

It also requires a baseline whole body count.

Persons entering the controlled area are required to wear a film

badge and pocket dosimeter, which are available from the R/C office

or from badge racks at access control.

There is presently no

mechanism to ensure that persons entering are wearing personal

dosimetry.

Security guards stationed to check that persons are

properly badged do not routinely check that dosimeters are worn.

Individual entries to controlled areas are not recorded and per-

sonnel accountability in an emergency will depend upon a comparison

of gatehouse and assembly area muster records.

The station is chang-

ing to a coded magnetic card system which will permit or deny access

to specific areas based on authorization status entered in a computer.

It will maintain a log of entries and exits wherever a magnetic card

is used.

The system, scheduled for implementation sometime in the

third quarter of 1980, should greatly speed up personnel accountability.

However, the appraisal team notes that precise accountability of

persons in the Reactor Building, a significant concern in a serious

emergency, will be jeopardized unless all in and out movements 'there

are recorded.

Based on the appraisel findings, this portion of the licensee's

program is acceptable.

However, the licensee should consider

implementing measures to ensure that personal dosimeters are worn

in the controlled area and to enhance accountability of persons in

the Reacto~ Building.

5.3 Radiation Area Access

The entire controlled area was designated as a radiation area and

was properly pogted.

Within that general designation, radiation

levels varied markedly.

"Hot Spot" signs are used to call atten-

tion to areas w9ere localized higher radiation levels exist.

Some

- 20 -

of these signs were old (two to four years) and carried radiation

level information that disagreed with more recent licensee surveys

or inspector surveys.

Radiation levels were sometimes significantly

changed although the radiation area status had not.

Based on the appraisal findings, this portion of the licensee's

program is acceptable.

However, local postings of radiation level

information should be maintained up-to-date.

5.4 High Radiation Area Access

Control of high radiation area (HRA) access is basically weak.

It relies on faithful adherence to administrative procedures for

key issuance and entry notification.

The procedure requires that

keys be logged out and returned after use and that the control

room be notified of each actual entry and that it be logged in a

HRA control Log.

Approximately 50 keys have been issued to the

various departments a'nd a master assignment log is kept by the

R/C Supervisor. It is unlikely that the control room personnel

can maintain continuing awareness of entries because of the large

number of keys potentially available and because of competing

demands for their attention.

Operator and foreman rounds are usually made alone and without

dose rate instruments.

Radiation levels are not posted at the

entrance to an HRA, partly to encourage contact with the R/C

Department regarding radiological conditions.

Even with this

information, such entries are vulnerable to abruptly changed

field conditions.

The licensee uses fences and gates of varying heights and locked

doors to bound HRA's.

Except for one described below, all were

locked and plainly posted;

Fences and/or gates ranged upward

from about three and a half feet and were adequate to prevent

inadvertent but not deliberate entry.

The areas noted were below

one rem per hour and under waivers to 10 CFR 20.203(c)(2) often

granted would not require locking.

However, the licensee makes

no apparent distinction between HRA's of varying severity.

More-

over, fence heights were said to be a matter of discretion of the

Maintenance Department, which installs them, rather than the R/C

Department.

Clear noncompliance with 10 CFR 20.203(c)(2) HRA control requirements

was identified on June 20, 1980, at the unit 2 west CRD accumulator

bank.

The fence (approximately five foot) barricade was unsecured

at one end leaving an opening for unobstructed access.

Exposure

rates ranged to about 130 mR per hour.

The R/C Supervisor had the

problem corrected the following day.

Based on the appraisal findings, HRA access controls should be

strengthened.

Of most concern are better dose rate information

  • - 21 -

for operators making rounds and better control room awareness of

all HRA entries, particularly in areas where fields above one R

per hour exist.

5.5 Airborne Radioactivity Area Access

By procedure, the licensee posts airborne areas when air samples

exceed 25% of MPC.

Also, areas where contamination greater than

5000 counts per minute per square foot exists in substantial ex-

tent are automatically posted as airborne.

The station makes a

practice of taking job specific air samples for work in these areas.

Entrance postings give neither measured airborne activity nor level

of contamination, although both aie available from survey sheets.

Entry to these areas requires use of respirators which are obtained

through the R/C Department.

Based on the appraisal findings, this portion of the licensee's

program is acceptable.

5.6

Contaminated Area

Contaminated area access control is marginal.

Dresden procedures

do not explicitly define contaminated areas, do not explain appropriate

behavior between step-off-pads (SOP's), and, until recently, did not

address specific protective clothing (PC) requirements.

Contaminated areas in the plant are generally well identified by

standard means such as barriers, posting, and SOP's.

However, two

interpretations of double SOP behavior are practiced.

One group,

largely operators who make rounds, regards the area between the

two pads as clean ~nd enters accordingly; it obviates the need for

protective footwear if one only wants to open a door and look inside.

The other view, espoused generally by the R/C Department and others,

regards the area as suspect requiring protective footwear (booties).

This discrepancy probably contributes to the frequent incidence of low

level shoe contamination seen at the station.

Protective clothing requirements are set from RCT surveys.

A recent

innovation has the surveys reviewed and requirements stamped on the

survey while still fresh in the mind of the surveyor.

The new pro-

cedure also recognizes a minimum clothing requirement for observers

and no-touch.workers.

Observations by the Appraisal Team of collec-.

tions of rubbers without the procedurally required booties, and of

entries between double SOP's indicate the need for improvement.

The

procedure can remain viable only if the conditions are truly followed

and if the question of SOP behavior is settled.*

The.Appraisal Team made extensive surveys to confirm postings and

generally check the licensee's contamination surveillance.

Removable

- 22 -

floor contamination was generally within the lice2see's "standard"

of 100 counts per minutes per square foot (cpm/ft ) when his field

method was used.

However, smear surveys of other horizontal2surfaces

appeared less diligent and levels in the range of 400 cpm/ft were

commonly found with isolated spots ranging to several thousand.

In discussion with RCT'~, it was learned that new protective clothing

(PC) or clothing indistinguishable from protective clothing is

sometimes worn by nonradiation workers.

Sometimes, new protective

clothing was put into service without the required identification

markings.

In either case, confusion is introduced and the job of

contamination control made more difficult.

When more sensitive counting methods were used (e.g., low background,

laboratory proportional counters) floor contamination was still rea-

sonable but not always within the 100 counts per minute per square

'foot "standard." However, only approximate comparisons were possible

owing to the antiquated standard which was written for an unspecified

portable GM survey meter.

In effect, the "standard" is no standard

at all.

The 100 counts per minute per square foot "standard" is included

in the "Radiation Control Standards" package for all CECo stations

that is negotiated with the union and cannot, therefore, be changed

unilaterally.

The Appraisal Team understands that a change to suit-

able units is part of the package that has been under negotiation

for several years and is nearing agreement.

If true, it would be a

significant step toward defining a meaningful removable contamination

limit.

Based on the appraisal findings, the licensee needs to clearly define

and enforce the requirements for contaminated area access in order to

achieve an acceptable program.

The improvement should include meaning-

fully defined removable contamination lim~ts.

5.7

Contaminated Materials Control

The licensee, in response to IE Bulletin 80-22, identified two

onsite dumps that unexpectedly contained radioactive materials.

Both areas were some distance from any site boundary.

However,

the inspectors observed that the areas were accessible without

interdiction from road and river and were thus not in restricted

areas as defined in 10 CFR 20.3(a)(14).

The material consisted

mainly of metal objects such as buckets, drums, and tanks.

A resin tank in one area read 130 mR/hr at two inches and .IO mR/hr

at three feet thus giving noncompliance with 10 CFR 20.lOS(b)(l)

for a potential dose of two millirems in one hour.

Removal of the

radioactive material from a controlled area to an unrestricted area

violated Dresden's "Radiation Control Standards" and thus Technical

- 23 -

Specification 6.2.B which requires adherence to the stations radio-

logical procedures.

The licensee was in the process of removing the material from the

dump site at the time of the appraisal.

The inspectors were in-

formed by telephone that all the material had been removed to a

restricted area and that the dump site survey had been completed

by July 12, 1980.

This matter was discussed at the exit interview.

Some of the material was recognized as having come from pilot runs

with the new waste solification system but licensee employees ipter-

viewed were unable to explain the occurrence.

Licensee practices

observed with regard to normal trash appeared satisfactory.

Trash

bound for the dump is surveyed and placed in bins under the direction

of the R/C Department.

The bins are kept locked and the key is kept

by the R/C Department so that unsurveyed trash cannot be added.

During an appraisal team survey on June 21, 1980, a pair of con-

' taminated pliers was found in a storage cage on the 670' level at

the Unit 3 Reactor Building.

The unmarked tool read about 80,000

cpm (at contact, window open) and a smear of its entire surface

showed about 700,000 dpm.

The tool was removed after .the R/C

foreman was notified.

Based on the appraisal findings, control of contaminated materials

needs to be strengthened to achieve a fully acceptable program.

6.0 Surveillance

6.1

Routine

Daily surveys, sample collections, and other routinely assigned

RCT surveillance activities were observed by all members of the

team throughout the 12-day appraisal.

Observations included all

three shifts and weekends although the majority of routine survey

work is performed during days.

Minimum routine ~urvey frequencies

are determined on the basis of work load in the area and the

vulnerability to spreading contamination.

Additional surveys are

ordered by the foremen in response to new work requests in order

to keep current on a continuously variable situation.

The foremen expressed concern that frequently they are not pro-

vided advance warning of new work requests to ensure timely survey

coverage of the affected area.

Survey reports are maintained on over 100 survey charts of the

two reactor and turbine buildings and 40 additional clean support

areas.

For convenience in assignment and filing, routine survey

- 24 -

"

area charts have been reduced to 8" x 11" size.

A standard notation

system has been developed to enable the reviewer to distinguish bet-

ween direct exposure and wipe sample data.

The form also provides

for notation of the surveyors' initials and operating conditions

prevailing at the time of the survey; however, these items are fre-

quently not recorded.

In addition to the formally identified survey

areas (maps), a general survey form "Station Radiation Survey Report"

for documenting nonroutine surveys has been developed.

The file

contained a number of such records.

Co~pleted surveys are filed in

duplicate sets of loose leaf notebooks by location and date to

provide a ready reference for the foremen and *the RCT's.

Each

survey is numbered and a record that the survey was completed is

entered in the RCT operations and staffing log.

The Appraisal Team reviewed survey records covering six preceding

months.

Three hundred fifty-two surveys were conducted during

the 30 days immediately preceding the appraisal.

Number of surveys

per month appeared to be reasonably constant over the period.

How-

ever, in about half of the records reviewed the amount of survey

data appeared to be barely sufficient to support evaluation of area

control requirements.

This inference was corroborated by comparison

surveys conducted by an appraiser in several of these areas.

Routine survey coverage in main traffic and work areas was adequate

to locate control work areas and establish perimeters or provide

a basis for timekeeping.

However, Dresden records2do not indicate

the widespread low-level contamination (400 cpm/ft ) that exists

on horizontal surfaces in out-of-the-way locations in both reactor

buildings.

As a consequence, the source of contamination and

opportunties for control have not been evaluated.

This is significant

in view of the number of personal contamination events being encount-

ered at Dresden (see below).

The Appraisal Team concluded on this basis (and other supporting

observations) that in general RCT performance has adapted to satisfy

minimal norms for routine service and consistently lacks elements of

curiosity and concern essential to a high quality surveillance program.

This in turn appears to reflect RCT training deficiencies, lack of

direct supervision by their foremen, and a high degree of isolation

from professional health physicists, who normally pursue findings of

this kind.

6.2 Contamination

The Appraisal Team members observed five incidents where plant workers

arrived at the RCT office or decontamination station with contaminated

clothing or shoes.

Examination of a contamination log book at the

station showed that there have been nine skin contamination events in

the past year and 83 personal clothing and shoe contaminations in only

-six months.

Furthermore, plant workers have become proficient at

- 25 -

decontaminating themselves and frequently do not leave a record.

In

all, the Appraisal Team feels that an overly casual interest is

manifested by the R/C Department regarding the control of repeated

contamination and the cause and effect relationships which could

result in control.

Of further concern, the contamination logs identify persons, area

of the body or article of clothing, date, and contamination level

but do not specify* locations where the problem was encountered or

what activity was taking place.

Further inquiry indicated that

contamination records are not routinely reviewed to identify

patterns.

This appears to confirm that incidental low level con-

tamination is generally accepted at Dresden Station and is not

perceived as related to principal RCT functions, such as surveys,

timekeeping, and sample collecting.

6.3 Air Sampling

Air contamination in working areas is monitored by means of high

volume air samples assigned by the foreman in connection with

direct exposure and wipe sample surveys.

The sample taker/surveyor

is likewise responsible for counting and recording his results on

the survey record.

This association of duties makes for a more

complete area survey record and has resulted in excellent coverage

of the plant.

The only negative factor is that samples are not

always taken in the area of greatest concern if it is not located

within 10' (line cord distance) of the 110 volt line outlets.

Dresden Station uses both air sa2ple measurements and a removable

contamination limit (5000 cpm/ft ) as criteria for establishing

respiratory requirem~nts.

6.4 Nonroutine

Pursuant to findings relative to routine surveillance, the Appraisal

Team made a special effort to evaluate RCT response to several

unplanned situations which came to our attention.

These included

items of varying severity.

Two RCT's returning from a routine survey assignment failed to

respond to indications of a contaminated shoe counter that was

blocking traffic at the trackway 2 entry.

Not only did the

problem remain uncorrected until other RCT's took care of it, but

the group of operators and maintenance men whose work was*delayed

received an unmistakable message that R/C representatives are not

concerned with minor contamination.

On another occasion, an RCT was observed performing assigned

surveys in support of work in progress.

Direct exposure measure-

ments and timekeeping were conducted proficiently by the experienced

RCT who exercised effective control over personnel in this area.

-

26 -

Observations at the job site indicated that an air sample, not

specified by the foreman on the controlling work permit, should

have been taken.

The situation was pointed out to the RCT, who

agreed with the appraiser that air contamination there was a

possibility.

A third situation arose when on the evening of June 27, 1980,

jack hammer operators returning from a work assignment near the

unit 3 CRD area were. found to have extensive contamination.

The

first RCT they encountered told them to put their clothing in a

plastic bag and take a shower and returned to his routine assignment.

Following an inquiry made by the Appraisal Team, a second RCT surveyed

the clothing and then went to survey the work area.

His survey was

conducted along routine lines to establish a contaminated area peri-

meter, without ascertaining the source and circumstances by which

contamination was present at a point considered to be clean earlier

in the day.

The following morning RCT foremen had be.en advised of the Jack

hammer.incident and procedures were initiated to decontaminate

the area.

The foremen had established to their own satisfaction

that the source of cont

1amination at the work site was related to

work in the CRD work area 40' away.

This cause-effect relation-

ship was based on a long history of problems in the CRD cage, but

the appraiser saw no evidence that an attempt had ever been made

to employ RCT surveillance techniques to illuminate the.situation

and thus to lend support to their appeals for corrective action.

Measurements such as detailed distribution of contamination, and

isotopic makeup of contamination and supporting air samples, which

are but an extension of routine RCT procedures, were not made in

this case.

On further discussion of this observation with the

foreman and several RCT's, the Appraisal Team's observations were

confirmed as generally stated.

Apparently the RCT's at Dresden Station have accepted narrowly

defined roles related to routine work.

They may not be able to

recognize departures from the routine or the essential role they

are expected to play _in the face of nonroutine situations.

Ability

of RCT's to respond appropriately and proficiently to the challenge

of any accident is suspect.

6.5

Emergency Monitoring Onsite

The Radiation/Chemistry Department is responsible for onsite

emergency monitoring; other station personnel are generally un-

qualified to perform such duties.

The station chemist, who reports

to the R/C Director during an emergency, is responsible for the

necessary analysis of samples collected by the RCT's.

During off-

shifts, the two or three RCT's present will have to make needed

measurements both onsite and offsite until additional help arrives

(30 minutes to one hour).

- 27 -

,,

Containment sampling and analysis, reactor water sampling and

analysis, and estimation of airborne effluent releases are the

emergency tasks that may have to be performed immediately.

The

Appraisal Team believes that a minimum of two fully competent

RCT's would be needed to initiate these tasks within one hour on

whatever

response

rooms or

shift a response is required.

Moreover, timely emergency

depends on the availability of the laboratory and counting

convenient backup capabilities.

Appraisal Team members also discussed with control room personnel

their emergency duties and responsibilities as described in the

GSEP.

In general, these individuals appeared well acquainted with

their emergency duties.

6.6 Emergency Environmental Monitoring

The licensee's Environmental Director who has the overall responsi-

bility for the (routine and nonroutine) radiological environmental

monitoring program (REMP), manages contracts with the environmental

monitoring contractor (Eberline Instrument Corporation) and the

meteorological contractor (Murray and Trettle, Inc.).

During an

emergency, the Environmental Director provides, through the

Corporate Command Center, direction and guidance to the emergency

environs team at the station.

Initially, the professional health

physics staff is responsible for the emergency offsite .monitoring.

The licensee's environmental contractor will assume the job of

emergency environmental monitoring upon arrival at the site.

License procedure EPIP 300-12, "Initiation of Environmental Monitor-

ing Activities by the Rad/Chem Director," specifies team surveys to

confirm and/or identify.releases and specifies samples to be taken.

Beyond specifying minimal survey equipment, the procedure offers no

guidance on the use of portable instruments for plume monitoring.

Additional guidance is needed.

Several minor sampling difficulties observed during the June 19,

1980, drill included a small-scale sample recording map, and un-

weighted and difficult~to-sink water sample collectors.

Possibly

more significant was the use of a four foot long section of copper

pipe ahead of the charcoal adsorber in the three onsite monitoring

stations.

The effect on iodine collection efficiency had not been

evaluated.

The meteorological tower and associated recorders at the tower base

and in the control room were operable and properly calibrated.

This

is the responsibility of the licensee's meteorological contractor.

6.7

Summary

Based on the appraisal findings, surveillance,. especially for

nonroutine conditions, needs improvement to achieve a fully

.- 28 -

..

.,:

acceptable program.

Such occurrences as unexpected spread of

floor contamination and low level personnel contamination 'need

more aggressive followup and evaluation.

Emergency procedures

should contain additional guidance on the use of portable instru-

ments for plume monitoring.

Routine surveillance is generally

acceptable but stereotyped and oriented more to definition of control

boundaries than to source identification and control.

RCT performance

shortcomings and management's acceptance of them appear to reflect

management and training weaknesses described elsewhere (Sections

2 and 3).

7.0

Instrumentation

7.1

Portable Instruments

An adequate supply of dose rate instruments is available for routine

use.

Of the approximately 50 Cutie Pie (CP) type instruments at the

station, 37 were in service during the appraisal, with 11 to 15 of

the instruments readily available at any given time.

Enough additional

CP's are on order such that each Rad/Chem Technician (RCT) will even-

tually have an assigned instrument.

Instrument calibration records were reviewed and found to be

adequate.

Throughout the records lapses in calibration frequency

were observed; however, investigations into the discrepancies showed

the instruments were usually in the instrument maintenance shop for

checking or repair.

Better documentation in the calibration records

should be used to explain the apparent voids.

An instrument maintenance program exists with the Instrument

Maintenance Shop.

The program has a full-time instrument mechanic

dedicated to the maintenance, repair, and electronic calibration

of the H.P. instruments.

A log is maintained on all instruments

repaired.

At pre~ent~ a problem has been encounte~ed in getting

the necessary parts to repair Eberline instruments; therefore,

s~veral instruments are out of service.

The gamma calibration sources have not been calibrated to NBS

traceable standards.

However, a new facility calibration procedure

is being developed to utilize the recently purchased MDH X-ray

monitor, which presently has NBS traceability.

Also, the maximum

exposure rate currently achievable is only 30 R/hr, which is

inadequate for calibration of the high range instruments.

The

Xetex high range instruments (up to 1000 R/hr) are sent to the

vendor for high range calibration yearly.

A U-238 slab is used

to develop a single point beta calibration curve for the CP's.

- 29 -

Neutron calibrations are performed at the Zion plant; problems

with neutron calibrations were identified during the appraisal of

the Zion facilities.

However, a neutron startup source is used

as a source check for the neutron instruments.

GM instruments

are electronically calibrated and then must pass a source check

across all ranges before being put into use.

Based on the above findings, this portion of the licensee's program

appears acceptable.

However, a better neutron calibration system

should be considered.

7.2

Emergency Instruments

The portable instruments available in the plant for use during an

emergency are generally adequate except for the high range instru-

ments. *At present two Xetex high range instruments are available

at the station; however, three additional high range (up to 1000

R/hr) are on order.

Experience from TMI and the performance

criteria stated in ANSI 323 suggest that instrumentation should

exist for measurements up to 10,000 R/hr .

. The licensee maintains a limited number qf emergency survey instru-

ments.

These were found to be in accordance with the inventory list

for the GSEP trailer and to be maintained operable with current cali-

bration tags.

GM survey instruments are calibrated yearly and checked

quarterly.

CP's and high range CP's, alpha survey meters, neutron

survey meters, and high volume air samplers are calibrated on a six-

month schedule.

This schedule is inconsistent with that used to

calibrate the portable instrumentation used routinely but is considered

adequate.

The licensee recently obtained two survey instruments SAM

II with scintillation probes for emergency radioiodine monitoring.

Based on the appraisal findings, this portion of the licensee's pro-

gram is acceptable.

However, suitable high range portable instruments

should be added when available.

7.3 Air Monitors

The H.P. program relies primarily upon portable air sampling equipment.

Air samplers are calibrated quarterly and are well maintained.

The

station has a continuous air monitor for use in the Techncial Support

Center.

Three more are on order to monitor the assembly areas (2),

and the control room (1) atmospheres during emergency conditions.

Problems have been encountered in the performance testing and calibra-

tion of the instrument on hand and it is not yet being utilized.

An

adequate supply of air monitors appear.s to be available for routine use.

Based on the appraisal findings, this portion of the licensee's

program appears adequate.

However, the new constant air monitors

should be placed into service promptly.

- 30 -

7.4 Contamination Control Monitors

An adequate supply of contamination control monitors is available.

The hand and shoe counters and friskers are electronically calibrated

quarterly and source checked in a low background area.

Alarm points

are checked daily using a low-level check source.

Throughout the

plant friskers were commonly found set on the IOX scale and, in one

instance, the lOOX scale; thus the possibility of detecting low-level

contamination requires that the user be well trained in the proper

interpretation of the instruments' response.

In these high background

areas, the use of a shielded area (such as the one built for the hand

and shoe counter on the main turbine floor exit) would be beneficial.

The sensitivity of the hand and shoe counters appeared to be excellent.

This can be seen in the number of contamination reports that have

been filed and in the frequency of use of the shoe decontamination

area.

It was also confirmed in checks made by the appraisal team.

Based on the appraisal findings, this portion of the licensee's

program appears acceptable.

7.5 Fixed Area Monitors

An adequate supply of fixed area monitors is in place for routine

use throughout the station.

Maintenance and calibration programs

exist to maintain the monitors.

The range of the monitors is

insufficient for accident conditions and do not meet the guidance

of ANSI 320.

A generic problem in the use of the multiple point recorder exists

at the station.

Approximately 30 points are printed on the area

monitor charts for each unit.

Identifying trends is nearly impossible.

Not only is the chart cluttered, but the number printouts are illegible.

Based on the appraisal findings, monitor recording should be improved

to ensure a fully acceptable program.

7.6 Process and Effluent Monitors

An adequate supply of process and effluent monitors is available for

routine purposes.

A program is available for adequate maintenance

and calibration of the instruments.

Sample lines from the main

chimney sampler and the reactor building vents appear to be well

placed and designed.

The range of the monitors is inadequate to

meet the emergency performance standards stated in ANSI 320 or the

criteria from THI Lessons Learned.

New sampling and monitoring

capabilities are being developed to .meet the requirements of

NUREG-0578 (Section 11.2).

- 31 -

All recorders are checked at least daily with the date and time of

the check noted on the chart.

No personnel identification is noted

on the chart.

During the appraisal period (June 27, 1980), the

Reactor Building Vent Exhaust Monitor recorder was not printing.

The chart was last checked at 2300 hours0.0266 days <br />0.639 hours <br />0.0038 weeks <br />8.7515e-4 months <br /> on June 26, 1980', and

ink flow subsided at approximately 2315 hours0.0268 days <br />0.643 hours <br />0.00383 weeks <br />8.808575e-4 months <br />.

While reviewing

the radiation monitor readout in the control room, one of the

Appraisal Team members found the nonrecording chart at 1115 hours0.0129 days <br />0.31 hours <br />0.00184 weeks <br />4.242575e-4 months <br />

on June 27, 1980.

This problem should have been noticed before 12

hours had elapsed.

Based on the appraisal findings, better review of monitor recording

is needed to achieve a fully acceptable program.

7.7 Analytical Instruments

Analytical capabilities for routine counting of gross beta and

alpha activities appear to be outmoded.

In addition, the instru-

ment records for standardizing and calibrating of these counters

were over ten years old.

The station is to upgrade the counting

equipment with new alpha/beta counters when the new counting room

becomes available.

These new counters will have to be calibrated

before use and new records of calibrations must be available at

the station.

The two GeLi detectors and associated equipment are

several years old and are also scheduled for replacement.

Quality control in the laboratory and counting room is weak.

Laboratory quality control does not include the use of spikes or

blind samples.

No control charts of reference source counts or

background measurements were available.

Although the licensee has QC procedures for setting up the Hewlett-

Packard Multichannel Ana,lyzer, data on performance checks were not

available.

Chemical procedures and check sheets for laboratory

results do not contain acceptance criteria.

A management member

reviews counting data daily and is responsible for verbally notifying

management if results are out of specification.

Such notifications

of variant results are not documented.

The licensee is training

the RCT's to use the multichannel analyzer.

Following the one week

training period (as part of the normal work schedule), a RCT may

not operate the equipment for 30 or more weeks.

Due to this rota-

tion schedule, some RCT's on off~shifts do not feel confident to

run analyses without assistance.

A similar problem exists with

respect to other sophisticated procedures.

Several alternatives could possibly be adopted to alleviate this

problem, such as the use of dedicated specialists, reorientation

of RCT's at time of rotation, or creation of separate technician

pools for chemistry and radiation protection activities.

- 32 -

Based on the appraisal findings laboratory quality control

should be improved to achieve a fully acceptable program.

8.

Radwaste.Management

8.1 Solid Radwaste

Solid wastes prepared for shipment at Dresden include compacted

materials (paper, plastics, etc.) in drums, noncompactible solids

(e.g., construction materials) in metal bins, and solidified wastes

(spent resins, filter sludges, and evaporator bottoms) in drums.

Operators solidify radwaste under the direction of a Radwaste Foreman.

Other solid wastes are handled by the Stationmen under the direction

of their foremen.

Technical guidance is provided by the Waste Systems

Engineer.

Solidified waste volume has been significantly reduced (Table 8.1)

with the startup in late 1979 of a new waste solidification system.

The savings (a factor of two to four) result from more efficient

mixing allowing a higher waste-to-cement ratio.

Volume reduction

has also resulted from more effective regeneration and cleaning of

  • condensate demineralizers and by permutation of resin beds to extend

useful life.

An effort is also being made to reduce other solid

waste volume by such measures as better identification and segrega-

tion of trash and removal of items from packaging before entry into

controlled areas.

TABLE 8.1

Volume of Solidified Wastes by Year

Total Sol~d

Year

Waste (ft )

% DAW

CY 1977

79447

64

CY 1978

62604

41

CY 1979

36687

44

  • 5288 ft3 during July-December 1979

Total Sol~dified

Waste (ft )

28601

36936

20543*

The new solidification system with both drumming stations operating

would allow a throughput of about six drums per hour.

The system

does have some problems arid generally one drumming station is operable

at any given time. Still the new system is a significant improvement

over the old and, according to licensee estimates, has resulted in

reduction of associated man-rem by about 75%.

- 33 -

Solid waste drum storage capacity is about 2400 drums, including

1500 drum storage* capacity added with the new solidification system.

At the end of June 1980, approximately 750 drums were onhand await-

ing shipment.

Based on the appraisal findings, this portion of the licensee's

program appears to be acceptable.

8.2 Liquid Radwaste

Operators under the direction of radwaste foremen run the liquid

waste treatment system.

Te~hnical guidance is provided by the

Waste Systems Engineer.

RCT's working for the Station Chemist

sample and quantify releases to ensure that regulatory requirements

are met.

Liquid wastes are treated within the plant by evaporation and/or

demineralization.

About 99 percent of the water is recycled within

the plant.

The remainder is released to the Illinois River via the

unit 1 or unit 2/3 discharge canals into a dilution flow ranging

from 25,000 to 500,000 gallons per minute {gpm).

Approximately 0.26

Ci were released in liquids during 1979.

Approximately 0.3 Ci were

released during the first six months of 1980.

A review of selected

records since 1977 indicated releases were below five percent of the

.technical specification limits.

Since 1978, radioactive effluents

have decreased owing to replacement of the laundry system by a dry

cleaning facility.

Based on the apprasial findings, this portion of the licensee's

program appears to be adequate.

8.3

Gaseous Radwaste

Gaseous radioactive effluent is released via the unit 2/3 reactor

building vent (RBV) and via the 300-foot-high unit 2/3 chimney.

The RBV discharge is*monitored and activity above the set point

causes shutdown of the pathway and startup of the Standby Gas

Treatment System (SBGTS), which discharges to the chimney.

The

bulk of the chimney airflow is from turbine building ventilation

air. Activity comes from the treated offgas, turbine gland seal

exhaust, and the radwaste building ventilation.

The off-gas is

treated by passage t~rough a recombiner, charcoal beds, and HEPA

filters before discharge.

Both release paths are monitored for noble gas release and con-

tinuously sampled for iodines and particulates.

Both monitors

read out in the control room and are recorded on a six-cycle strip

recorder. \\Calibration charts relating monitor reading to release

rate (uCi/second) are posted beside the recorders.

Chimney monitor

data are also available in printed format from the control room

computer.

- 34 -

At the time of this review, the combined chimney release rate was

about 3500 uCi/sec (110 counts per second) with units 2 and 3

operating at 605 and 815 MW (electrical), respectively.

The alarm

set point was 105,000 uCi/second.

The unit 2 and 3 vents were

releasing in the ranges of 43 to 52 and 60 to 100 uCi/second,

respectively.

This condition represented less than one percent

of the instantaneous noble gas release rate limit.

Isotopic distribution of noble gas discharge is obtained from

GeLi analysis of grab samples taken from the chimney (monthly)

and RBV (weekly).

The distribution is applied to measurements of

gross activity released to determine releases by isotope.

Conver-

sion factors relating monitor readings and discharged activity

are based on comparing monitor readings with isotopic analyses of

grab samples following each quarterly electronic calibration by

instrument maintenance.

Continuo~sly collected filters are periodically removed and counted

to determine particulate and iodine releases.

Additionally, a

monthly particulate filter is forwarded to a licensee contractor

(Eberline) for analysis and confirmation.

The contractor also

performs tritium analyses; a new scintillation counter ordered

for 1981 will give onsite tritium capability.

Selected release records for 1979 and 1980 reviewed indicated no

releases exceeding regulatory limits.

However, recurring inter-*

ference is seen from time to time in the iodine region of the

station whole body counter located south of unit 3 reactor build-

ing.

(Section 9.3).

The licensee presumes but so far has not

established a relationship to station releases.

This needs to be

explored.

The chimney monitor/sampler is located in the rear of the radwaste

building 40 feet from the base of the chimney.

Lead shielding and

the distance from the chimney and from underground treatment system

components protect the sampling point from elevated backgrounds

which might interfere with measurements during an accident.

Examina-

tion of the design and components of the sample line reflect satis-

factory consid~ration for principles of isokinetic sampling and

delivery of a representative sample at the point of measurement.

Dresden chemists also perform weekly analysis of air ejector,

filter building, and recombiner grab samples.

These measurements

are routine in-house surveillance of fuel condition independent

of discharge monitoring but with considerable predictive value

and thus relevant to overall control.

Based on the appraisal findings, the gaseous radwaste management

program appears acceptable.

However, investigation should be made

to determine if interferences seen on the whole body counter are

related to station releases.

(Section 9.3)

- 35 -

>

9.0 Facilities

=

9.1

Laundry

The Dresden decontamination laund~y occupies two sites.

The

original facility at unit one was not examined.

The unit 2 and 3

facility is located in a 40-foot mobile unit in the unit 3 track-

way.

Available space for the three dry cleaning units and one

dryer is augmented by enclosure of a 12' x 20' area of trackway

by a 4' chain fence.

The facility is operated by two to four stationmen.

The station-

man foremen, who also have other concerns, are responsible for

overseeing the facility's operation.

At the time of the appraisal, with only a modest workload, each

day's input was folded and ready by mid-afternoon.

Even so,

exposure measurements in the vicinity of "clean" materials were

2-3 mR/hr and levels up to 110 mR/hr were encountered in the

soiled clothing area inside the fenced enclosure.

One of the

friskers and the ion chamber survey meter assigned to the laundry

were found to be inoperable.

Additional exposure measurements

(with an R0-3A) at the Unit I trackway SWP clothing supply area

were 2-3 mR/hr as a result of several hundred folded, clean

coveralls on the shelves.

Clothing contamination exceeded station

limits (3000 cpm) in 20 of 23 samples tes~ed with levels ranging

from 4000 to 22,000 cpm.

This suggests little cognizance of the

radiation protection role at the laundry and the absence of a

quality control program.

It was reported that, during the last outage, incoming soiled

laundry at the unit 3 track way was stacked higher than the roof

of the mobile unit and that individual contaminated garments were

contaminated up to 500 mR/hr.

This combination of reports and

observations suggests that exposure levels at the laundry have

been much higher than those observed during the appraisal.

Also,

no use is made of shielded clothes bins or.ventilated hood sorting

facilities to control this reducible exposure to laundry operators.

Operation of the clean laundry monitor instrument was observed and

discussed with the assigned stationmen and foremen.

The monitor,

improvised from the foot counter components of a hand and foot

counter, is surrounded by lead bricks.

If used properly, this

improvised unit can perform better than counters routinely encount-

ered at other nuclear station laundries.

With insights provided by

the foreman, and assistance of a health physicist and instrument

mechanic, the advantageous features of the counter could be developed

as an advancement in the industry and a significant ALARA contribution.

- 36 -

Judging from measurements made during this appraisal (and experience

elsewhere), heavily contaminated "clean" garments may contribute

five to ten millirems per hour to the wearer.

In some cases, beta

dose contribution (unrecorded by dosimetry) could be much higher.

Based on the appraisal findings, significant improvements in the

control of contamination levels on reusable laundry are needed to

achieve a fully acceptable program.

As part of this improvement,

an evaluation should be made of the contribution to dose from

laundry in order to determine the acceptability of current laundry

limits.

Acceptance criteria should be defined in terms of the

monitors used for laundry surveillance.

A quality assurance

program for laundered protective clothing should be established.

9.2 Equipment Decontamination Areas

A limited number (6) of decontamination shops (decon pads) are

provided throughout the plant.

The principal one is ~t one end

of the Unit 1 machine shop.

The shop is reasonably confined by a

12-foot concrete block wall' on the machine shop side and totally

enclosed around the others.

Ventilation appears to be adequately

controlled.

A wipe sample survey conducted by the Appraisal Team

showed that the area was in good order and controlled.

It was, however, noted that hot tool boxes stored in the area are

not uniformly identified by radiation labels in accordance with

Dresden procedure.

No evidence of excessive radiation exposure

or smearable contamination was seen.

The in-plant decon pads

were observed from time to time in passing.

In each case, the

activities within were indicative of proper regard for personal

exposure control and Dresden procedures.

However, the number of

incidents (reported under nonroutine surveillance) involving re-

peated recontamination of floor areas outside the Unit 3 Control

Rod Drive (CRD) pad (570 foot level) elicited more detailed

investigation.

The particular concern is that the CRD maintenance facility itself

has been a source of contamination to the surrounding areas.

The

temporary facility consists of a plastic covered wire fence perimeter

and a CRD disassembly area with an improvised airborne contamination

control system (a homemade hood of plastic sheeting, an exhaust duct

and a HEPA filter).

R/C Department requests to have more effective

contamination controls installed or to have the work moved to the

permanent Unit 2 CRD maintenance area have apparently been ignored.

An additional concern is the attitude that the contamination of sur-

rounding areas is not the responsibility of the offending department

but is the responsibility of the stationmen.

This attitude violates

a longstanding and successful tenet of radiation protection that

those who make the mess should be responsible for cleaning it up.

- 37 -

A similar situation exists with the continual recontamination of

the Unit 2 accumulator gallery as a result of work activity in the

Traveling In-Core Probe (TIP) room.

Based on the appraisal findings, this portion of the licensee's

program is acceptable; however, improvement or the relocation of

the temporary CRD repair area should be investigated.

9.3 Whole Body Counter

The present location of the whole body counter facility is adequate

0 to provide the necessary measurements for the internal dosimetry

program.

However, improvement is needed.

The facility is subject

to rapid changes in background radiation levels.

A common problem

is the unexplained appearance of I-131 during counting.

During the

Appraisal Team's visit, extraneous I-131 was seen in two whole body

counts.

This recurrent phenomenon is thought to be due to normal

station releases being held in an inversion layer or by some other

meteorologic condition.

However, no investigation has been made of

the relationship between this interference and plant releases or

meteorological conditions.

When the problem appears, either the

person is recounted at a later time or a new background is taken

before recounting.

The facility is also affected by radwaste ship-

ments which must pass nearby.

Additionally, the background radiation

levels are apparently dependent upon the status of the three plants.

The RMC report of 1/9/78 referred to significantly fluctuating back-

ground.

Since then, a standardized reference paragraph has been

included in each RMC report which alludes to the fluctuating back-

ground and erroneous I-131 results.

The present whole body counting facility lacks an easily accessible

shower and/or personal decontamination area.

In order to determine

if positive whole body count results are due to external contamination,

the person involved must dress, return to the Access Building personal

decontamination area, shower, and then return to the whole body count-

ing facility.

The licensee has developed plans to relocate the whole body counter

in the Access Building.

The new area, though somewhat small, is

well shielded and will have access to the nearby personal decontam-

ination area and shower.

The new location should eliminate the

problems associated with the present facility.

Based on the above findings, this portion of the licensee's program

appears acceptable.

However, as indicated in Section 8.3, the inter-

ferences observed in the iodine channel of the whole body counter

should be investigated.

- 38 -

9.4 *

Personal Decontamination

With only one shower stall, the personal decontamination area is

adequate for one or two persons.

The facility would be unable to

accommodate a larger group and the necessary R/C personnel.

In

an emergency, when a greater incidence of personal contamination

might be expected, the facility would be inadequate and no auxiliary

personal decontamination areas have been established.

The personal decontamination area also serves as the medical/medical

decon area.

The ability to work on an injured person who required

a stretcher would be severely hampered.

Remodeling plans have been

made to establish a dedicated medical decontamination area in the

Access Control Building.

A dedicated shoe decontamination area has been established.

This

area lacks so~e of the necessities for the proper decontamination

of footwear.

No running water is available; no contaminated waste

cans are available for proper disposal of paper towels.

Also, no

procedure or guidance on proper techniques for decontamination of

shoes is available to the individual.

The housekeeping in the shoe

decontamination facility and the surrounding area is poor.

Based on the appraisal findings, facilities for personnel and shoe

decontamination should be improved to achieve a fully acceptable

program.

9.5

Instrument Storage

The instrument storage facility, which consists of several shelves

and three lockable wall cabinets, is excellent.

The room is segre-

gated from the general work areas and from traffic flow.

However,

as the instrument inventory increases the area may become too small.

Based on the above findings, this portion of the licensee's program

appears acceptable.

9.6 Emergency Facilities and Supplies

The licensee provides emergency supplies and kits at the GSEP trailer

onsite, the medical decontamination area in the station, and the St.

Joseph Hospital emergency room for contaminated injured personnel.

Although stretchers, respiratory equipment, and first aid kits are

distributed throughout the station, emergency supplies and instruments

are not located in the station control room.

The GSEP trailer was found to be maintained in good order with each

drawer labeled with the supplies present.

During the June 19, 1980,

drill, some supplies were brought into the station the day before for

use in the emergency drill.

Licensee representatives recommended

- 39 -

that some of the emergency supplies be located in the station

near the trucks that would be used by the environs teams.

The

Appraisal Team agrees that the licensee should provide a location

for placing certain emergency supplies in the station nearer to

where they will be used.

Emergency supplies and survey instrumentation were found present

at the above mentioned locations in accordance with licensee's

procedures DRP 1470-2 and 1740-2, both dated September 1979,

except for the keys for the environs stations.

The keys, which

had been used in the June 19, 1980, drill, were later found in a

van used by an environs team in the drill.

Based on the appraisal findings, this portion of the licensee's

program appears acceptable.

9.7 Analytical Laboratory and Counting Room

Analytical laboratory facilities (cold laboratory, hot laboratory,

sample preparation room, counting room, and gamma spectrometry

room) are generally overcrowded, poorly organized, .and subject to

poor housekeeping.

The licensee was in the process of converting

recently vacated radiation protection office space to an expanded

counting facility, which will also house the whole body counter

when it is moved (Section 9.3).

Analytical equipment in the cold and hot laboratories appeared

adequate.

Some of the counting room equipment is outmoded and

scheduled for replacement (Section 7.7).

The cold and hot laboratories and the sample preparation rooms

are adequately equipped with fume hoods and sinks with drains

routed to holding tanks.

A lead cave was in the corner of the

hot laboratory, but there was no shielding within a hood for the

handling of very hot samples that might be collected during an

accident.

Lead bricks were said to be available from the store-

room.

The appraisal Team observed poor sample handling procedures in

the hot laboratory, such as ungloved handling of samples, trans-

port of samples from the hot laboratory without monitoring, and

personnel leaving the hot laboratory without hand and foot moni-

toring.

Such practices are fundamental to a well run radiochemistry

laboratory.

The licensee has recently appointed a foreman as laboratory co-

ordinator.

This should result in an improvement of laboratory

operations.

However, the foreman still needs some training to

become fully conversant with his duties.

- 40 -

..

The licensee lacks a portable GeLi system in the event that the

counting room becomes uninhabitable during an accident.

The

licensee plans to use counting facilities at the other licensee

plants as backup facilities, as well as the licensee's contractor,

Radiation Management Corporation, and the nearby GE Horris Plant.

Based on the appraisal findings, sample handling practices in the

hot laboratory should be improved and ventilated shielding for hot

sample handling should be provided.

9 .. 8 R/C Department Office Space

Space dedicated for non-laboratory work.of the R/C Department has

recently been enlarged and upgraded.

The R/C Supervisor and the

HP group have recently been moved into the Administrative Center

outside the main gate.

The space is adequate, but the move greatly

increases the physical isolation of the HP's from the foremen and

RCT's.

In addition, the exposure records system, including the

computer terminal giving access to the records, is not convenient

to access control, a disadvantage particularly when large numbers

of people are being processed.

The former lunchroom has been converted into a service area for

transacting business with R/C personnel, a foremen's office, an

RCT work area, and an instrument storage room.

The facility is

conveniently located at the junction of access corridors to all

units.

A disadvantage of the arrangement is the increased isola-

tion of the foremen from the service counter and thus from a main

point of interaction between the department and outsiders.

Based on the appraisal findings, the facilities appear to be

acceptable.

However, the licensee should consider installing a

window with pass-through between the foremen's office and the

service counter and providing of HP office space near access control.

10.

A1ARA

No formal A1ARA program exists at Dresden.

Man-rem goals are not

established for the station, for the departments, or for specific jobs.

Job planning does not routinely involve the R/C Department and work

requests are not routed through it for an A1ARA assessment.

The station does participate in a Radiation Evaluation Program (REP)

established by the corporate office.

REP provides exposure data by

work task and, if used properly, could be useful in identifying work

requests where A1ARA review might be beneficial.

At present, REP is

strictly an after-the-fact record.

Moreover; REP is flawed because of

inaccuracies in the data base (Section 4.1) and is therefore of question-

able use at this time.

An effective ALARA program must involve the

entire station and not just the R/C Department or health physics group.

- 41 -

. .. * ...

~ *-~~

. -*-;*** .

...

ALARA principles have been applied in singular cases at the station.

A noteworthy example was the use of hydrolazing to decrease dose

associated with NRC mandated work in the torus areas.

Another signi-

ficant ALARA benefit was realized when the new solid waste handling

system was installed (Section 8.1).

Yet another occurred with the use

of a shielded platform during work done in the reactor vessels.

The

dose saving in each of these cases was significant and probably necessary

to avoid an intolerable burden on the station.

The need for a formal

ALARA program increases with plant age.

Two areas currently ripe for

review are routine maintenance and wearing of laundered protective

clothing (Section 9.1).

Based on the appraisal findings, this portion of the licensee's program

appears acceptable.

However, the licensee should consider implementation

of a formal ALARA program with a dedicated ALARA engineer or health

physicist.

11.

Accident/Reentry

11.1 Leakage Outside Containment

In response to item 2.1.6.a of the TMI-2 Lessons Learned Task

Force Report (NUREG-0578), the licensee has implemented a leakage

control program for systems outside containment.

Included in the

consideration were the high pressure coolant injection system (HPCI),

isolation condenser, low pressure coolant injection system (LPCI),

core spray, shutdown cooling system, reactor cleanup system, primary

system instrumentation, reactor water sample system, primary system

isolation valves, and the standby gas treatment system (SBGTS).

The program, as defined in administrative procedure DAP 14-2,

"Leakage Reduction Program," and in technical procedure DTP-9,

"Leakage Detection and R~duction Program," consists of baseline

leakage measurements, periodic visual inspections for leakage by

the operating department, once per refueling cycle measurement *Of

.leakage by the technical staff, and priority processing of leakage

related work requests.

A technical staff engineer was assigned

to work in the area of leak reduction.

Baseline measurements made

in December 1979 showed approximately 15 and 30 gallons per hour

on units 2 and 3, respectively.

The Appraisal Team did not review this program in detail.

However,

inspector observations, including those made during rounds with

operators, indicated no significant leakage.

11.2 Post Accident Sampling and Monitoring

The results of a shielding study by a licensee contractor indicates

that access to the reactor building for reactor coolant and containment

- 42 .,.

sampling would probably be impossible under worst case accident

conditions.

The licensee is now constructing sampling buildings

outside of each reactor building that will permit sample collec-

tion and dilution under such conditions.

The facilities, which

will also be used for routine sampling, are scheduled for January

1981 completion.

Interim emergency sampling procedures (EPIP's 300-8, 300-9, 300-10)

for less than worst case conditions are inplace but are weak owing

to the lack of local shielding at the sampling stations in the reactor

building or in the hot laboratory (Section 9.7).

In addition, the

procedure (EPIP 300-9) for taking the reactor coolant sample does not

address purging .of the sample lines.

The procedures do specify the

use of cart mounted lead shields for transporting the samples to the

hot laboratory and counting rooms for analysis.

These were observed

along with tongs provided for remote sample handling.

However, the

facility with which 15 cc gas sample vials could be handled with tongs

appeared not to have been determined.

The current systems for monitoring the chimney and the reactor.

building vents do not meet the dynamic range recommended in the

TMI-2 Lessons Learned Task Force Report (NUREG-0578) item 2.1.8.b.

A modification to provide instruments with the required ranges

for these release paths is underway and scheduled for January 1981

completion.

An interim procedure (EPIP 300-11) has been written for estimating

accident noble gas releases by means of direct readings on the unit

2/3 chimney sample line with a portable survey instrument.

The

inadequacy of this procedure was revealed to the licensee when an

attempt was made to use it during the June 19, 1980, emergency drill.

The failure resulted because of an illegible graph legend and because

the procedure was not well understood.

Based on the appraisal findings, the licensee needs to strengthen

his capability for emergency sampling and monitoring in order to

achieve a fully acceptable program.

Improvements should include

thorough rereview with actual walk-through of pertinent procedures,

upgraded shielding at the current sampling stations, and thorough

training in the procedures for all RCT's, chemists, and HP's

(Section 3.7).

-

43 -

11.3 Emergency Drill of June 19, 1980

The licensee conducted an exercise to demonstrate integrated

emergency response capability. It was generally successful in

this, and moreover provided a significant training experience for

the station, including R/C Department personnel who were heavily

involved (all but three of 23 RCT respondents were used).

It

also provided a valuable diagnostic for the observing Appraisal

Team members who were present in the Technical Support Center

(TSC)and Operations Support Center (OSC), and who accompanied

sampling and survey teams and observed laboratory analyses.

The licensee's organizational response, including that of the R/C

Department, was generally adequate.

R/C foremen displayed evident

awareness that only 17 of 23 responding RCT's had been emergency

trained and made team assignments accordingly.

The exercise

demonstrated weaknesses in emergency sampling procedures (Section

11.2), in shielding provisions made for sampling stations and hot

laboratory (Sections 9.7 and 11.2), and in basic hot laboratory

sample handling practices (Section 9.7).

The poor sample handling

techniques observed during the drill (ungloved sample handling,

absence of finger dosimeters, sample transfer within the counting

room, and unshielded syringes) were basically not different from

those practiced with low-level routine samples.

One can speculate

that practices would have been much better given truly "hot"-samples

but the need for review of basic principles as discussed in Section

3.6 was clear.

The drill scenario was flawed in that simulated high

radiation levels were not assigned to samples and key locations so

that such matters could be better gauged.

The Appraisal Team also noted that the noise level in the OSC

interfered wi~h radio and telephone communications, that there

was no procedure for systematically debriefing returning survey/

sampling teams to obtain pertinent survey information, and that

there was no means for recording and displaying such information

in the OSC.

Based on the Appraisal Team's observation, the licensee conducted

a satisfactory drill.

However, the lessons learned from this drill

should be incorporated into emergency procedures and training and

should be applied in future drills.

12.

Exit Interview

.*. ,,., .*

The results of the appraisal were discussed with representatives of

licensee corporate and station management (Section 13) at the close of

the appraisal on July 2, 1980.

Significant findings in the areas of

Organization and Management (Section 2), Qualifications and Training

(Section 3), Access Controls (Section 5), Contaminatio~ Controls (Sections

5, 6 and 9)'; Surveillance (Section 6), Instrumentation (Section 7) and

      • ...

- 44 -

..

I

-If

W. Hildy, Master Instrument Mechanic

H. Waclaw, Engineering Assistant

M. Stanish, Quality Assurance Coordinator

T. Walsh, Engineering Assistant

B. Coen, Technical Staff Engineer

B. Dunbar, Technical Staff Engineer

B. Saunders, Security Supervisor

L. Dimmock, Shift Foreman

D. Reece, Shift Engineer

CECo Offsite

  • C. Reed, Vice President
  • F. Palmer, Manager, Nuclear Generation
  • J. Bitel, Manager, Technical Services Nuclear
  • G. Abrell, Quality Assurance
  • J. Smith, Staff Assistant
  • H. Dellsy, Staff Assistant

W. Nestel, Station Nuclear Engineering

  • E. Pierard, Industrial Relations

Non CECo

  • J. Barker, Resident Inspector USNRC
  • T. Tongue, Resident Inspector USNRC
  • A. Davis, Region III USNRC
  • W. Fisher, Region III USNRC
  • Denotes those present at the exit interview of July 2, 1980.

The Appraisal Team also interviewed other licensee and contractor

personnel during the appraisal.

- 46 -