ML17174B101

From kanterella
Jump to navigation Jump to search
Insp Repts 50-237/91-38 & 50-249/91-42 on 911202-06. Violations Noted.Major Areas Inspected:Routine & Announced Insp to Follow Up Previously Identified Electrical Distribution Safety Functional Insp Concerns
ML17174B101
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 12/20/1991
From: Darrin Butler, Gardner R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17174B098 List:
References
50-237-91-38, 50-249-91-42, NUDOCS 9201210106
Download: ML17174B101 (10)


See also: IR 05000237/1991038

Text

  • .

U .* S. NUCLEAR REGULATORY COMMISSION*

REGION III

Reports No. 50-237/91038 (DRS); No.

50-~49/91042 (DRS).

Docket Nos. 50-237; 50~249

Licenses No.

DPR~l9; No. DPR-25

Licensee:

Commonwealth Edison Company*

Opus West III

1400 Opus Place

Downers Grove, IL

60515

Facility Name:

_,

Dresden Nuclear Power Station

Units 2 and 3

In~pection At:

Morris, IL

60450

Inspection Conducted:

December 2-*6, 19 91

Inspector:

Appr9ved By:

.~i\\./~ryi~k

D. s. Butler

~I/\\.~~~

R~ N. Gardner, Chief

Plant Systems S~ction

Inspection summary

Id-/;;..n /'f /

Date

Date

Inspection 6n December 2-6, 1991 (Reports No. 50-237/9lb38(DRS);

No. 50-249/91042CDRS))

Areas Inspected:

Routine, announced inspection to follow up

previously id,ntif ied Electrical Distribution Safety Functional

Inspection (EDSFI) concerns (Temporary Instruction 25111).

Results:

In the area that ~as* reviewed~ the following items were

identified:

one violation for failure to include appropriate

acceptance ciiteria in post modification test procedures

.(Paragraph 2. i.); one deviation* from FSAR commitments (Paragraph

2.a.); four unresolved ite~s (Paragraphs 2.b., 2.c~, 2.e., and

2.f.); and three open items (Par~graphs 2.b., 2.g., and 3.0.).

DETAILS

1.

Persons contacted

2.

Commonwealth Edison Company CCECo)

  • C. Schroeder, ~tation Manager .
  • L. Gerner,- Superintendent, Technical Services
  • J. Kotowski, Superintendent, Production
  • G~ smith, Assistant Superintend~nt, Operations
  • D. VanPelt, Assistant Superintendent, Maintenance
  • K. Peterman, Supervisor, Regulatory Assurance

B *. Viehl, Supervisor, NED

J. Harrington; Nuclear Quality Programs (NQP)

  • J. Gates, Assistant Supervisor, Technical Staff
  • R. Stachniak, Performance Improvement (PI)
  • K. Deck, Orisite N~clear Safety

w. Morgan, Nuclear Operations

  • D. Karsala, PI
  • T. Gallaher, NQP
  • . *R. R~lph, Technicai Staff
  • B. Adams, Regulatory'Assurance (RA)
  • D. Lowenstein, RA

R. Falb(), RA

Illinois Department of Nuclear Safety CIDNS)

U.

s~ Nuclear Regulatory Commission CNRC)

  • R.

G~rdrier, Chief, Plant systems Section

  • *W~ Rogers, Senior Resident Inspector
  • M. Peck, Resident Inspector
  • D. Liao, Reactor Engineer

The NRC inspector also contacted and inter-Viewed other*

licensee personnel.

  • Denotes those present at the exit interview on* December*6,

1991.

Licensee Action on Previous Inspection Findings

The purpose of this inspection was to follow up deficiencies

previously identified in Electrical Distribution System

Functional Inspection (EDSFI) Reports No.* 50-237/91201 and

_No. 50-249/91201.

A numb~r of the EDSFI concerns will be

closed in this report based on additional inspections

conducted and a review of licensee commitments documented in

the licensee's November 4, 1991, response to the EDSFI

2

. - ----- --- ---~--*-** -

report.

The remaining concerns will be assigned a tracki~g

number associated with this report *. The attached appendix

contains the complete list of items discussed in this report

and their status.

.

.

.

a.

Deficiency No.* 91-2.01-01: *Inadequate Short Circuit

Capacity of 4kV Circuit Breakers

The EDSFI team deterinined that 350MVA and 250MVA

circuit breakers, including safety related breakers on

bus Nos. 23 and 24, in the 4kV system could experience

fault currents up to 114 percent (overduty) of their

maximum interrupting rating.

These conditions are*

. .

contrary to Final Safety Analysis Report (FSAR)

sect~oh

.

.

/. .

.

.

a.2.2.2 which states, "All protective circuit breakers

are sized according to* standard electrical industry

practiGe.where maximum interrupting capability of the

circuit b*reakers exceed the available 1 ine to 1 ine or 3

phase short circuit .current taking into accourit the

impedances of the generator, transformers and other

electrical system componerits.J*

The inspector*

considered the overduty condition relative to maximum

breaker in~erru~ting ratings to be.a deviation

(237/91038-0l(DRS); 249/91042-0i(DRS)) from the

commitment made in FSAR Section a. 2. 2 .* 2.

The licensee performed a safety evaiuation and

concluded, based on redundancy and availability of ,

emergency power sources; that operability of emergency

safety feature (ESF) loads could be maintained.

The

EDS FI team concur.red with the licensee Is determination ...

b.

Deficienc~ No. 91-201-02:

Inadequate Calculation to

Determine Deciraded Grid Relay Trip Setpoint

TheEDSFI team determined that the.degraded voltage

setpoint may be set too low to adeql.lately protect

.safety related motors*during a LOCA concurrent with a

degraded grid voltage that hovers above the degraded

voltage relay .setpoint.

The licensee committed in their November 4, 1991;

response to the Diesden EDSFl repoit to complete the

degraded voltage calculations for bbth units by

J<inuary 31, 1992.

The safety significance of this item

will be determined following NRC review of the

calculations.

This is considered an unresolved item

(231/91038-02(DRS); 249/91042-02(DRS)).

.

.

The licensee reported the degraded voltage deficiency

in Licensee Event Report (LER) No.91-021.

Until the

degraded voltage calculations are completed and a

3

-


~--:---------.~ -~ :

proper setpoint has _been established, the licensee has

implemented compensatory measures to take manual

actions to ehsure safety related e~uipment will start

and run.

This LER will remain open (237/91021-LL)

p~nding further NRC.review of de~raded voltage concerns

at Dresden.

c~

Deficiency No. 91-201-03:

Fiilure to Take.Prompt

Corrective Action.

The EDSFI team identified that the licensee was aware

of the potential for degraded voltage condi~ions on

safety related motor control centers (MCCs) Nos. 28-1,

28-3, and 29-2.

This was documented in Dresden Unit 2

. .

_,

.

.

"ELMS Running Voltage Summary," da_ted November 9, 1990.

However, the licensee was unable to identify to the

EDS FI team. a nonconformance report, *or documentation of

corrective actions that eyaluated this deficiency.

The

safety significance of ~this item ~ill be determined

following NRC review of the degraded voltage

calculations to be completed January 31, 1992.

This is

considered an unresolved item (237/91038~b3(DRS);

i49/9102~03(DRS)).

.

.

d.

Deficiency 91-201-04:

Inadequate Acceptance Criteria*

for Battery Surveillance

The EDSFI team was coricerned that t~e 250 Vdc and 125

Vdc battery performance test surveillance procedures

did not contain adequate acceptance criteria to

determine the.batteries were inoperable if their

capacity was below 100 percent.

The team noted that

the 250 Vdc and 125 Vdc battery sizing calculations

were performed with design margin factors of 1.0 and

1.01, respectively, and an aging factor of 1.0.

I~EE

485 recommends using a design margin of 1 .. 15 and 1. 25

for aging.

The 250 Vdc battery sizing calculation indicate~ a

total r.emaining margin of 16. 6 percent between* the

actual number of positi~e plates provided in the

battery (10 plates) and the required number of positive.

plates to meet the design requirement (8 plates').

This

translates (1/1.166) to a minimum acceptable battery

capacity of 86 perceht for the battery to remaih

operable.

The 125 Vdc batte~y sizing calculation

  • indicates a.total remaining margin of 47 percent~

This

translates (1/l.147) to a minimum acceptable battery

capacity of 68 percent.

The . inspector rev'.:i..ewed surveillance test procedure Nos~

DEP 8 3 00-2.0 (August 1989) , "2 50 Volt Station Battery

4

Performance Test," and DEP 8300-19*. (August 1989), "125

Volt Station Battery Performance Test" and determined

the procedures did contain adequate acceptance

criteria.

The 250 Vdc battery was to be declared

itioperable if its capacity was found to be less than 90

percent and the 125 Vdc battery inoperable if les*s than

80 percent.

Based on the above, this item is

considered closed.

e.

Deficiency 91-201-05:

Lack of 480 Vac Coordination

The EDSFI team determined that report No.

SL-4500~

dated March 24, 1989, did not demonstrate ~hat proper

electrical coordination existed between 480 Vac

components.

The following concerns were identified:

{l)

The report was not a controlled design document

and did not contain coordination curve.plots for

all devices.requiring coordination.

For example,

as-built_ plots were not provided for load breakers

at MCC Nos~ 29-3, 29-5, and 29~6.

.

.

(2)

Important information necessary to show adequate

coordination with equipment characteristics was

omitted.from the coordination curve pfots

including motor damage curves, maximum inrush

current; full lo.ad currents; locked rotor current

and cable thermal limits.

(3)

The maximum fault current shown on coordination

plots was 15,500A. * This value is bel6w the fault

currents determined in* calculation 6558-EAD-3 of

16,329A for bus No. 28 and. 16,0j8A for bus No. 29.

In addition, this value does not include motor

contributions from the 480V buses, which may

affect coordination for bus tie breakers and MCC

loa.d breakers.

(4)

Larik of coordination was noted between switchgear

Nos. 2~ and 29 feed break~rs and ~he bus tie

breakers.

(5)

Lack of coordination was noted between several MCC

feed and MCC load circuit breakers.

The EDSFI team noted that modifications were in

progress to resolve coordination problems.

The

licensee was replacing older electro-mecbani6al trip

current sensing devices with new solid state models

(RMS 9) .

.The replacement* schedule appeared to be based

on breaker preventive maintenance schedules that extend

into late 1995.

5

-

-~ ----.----------~-*---~~---~

The safety related buses at Dresden also supply power

to nonsafety lo.ads.

The NRC is also concerned that a

faulted, miscoordinated nonsafety 1oad eould cause the

loss of safety relat.ed equipment. * At the time of . this

inspection, the proposed modifications to improve

coordination had not been completed.

This item is

cpnsidered* an unresolved item (237/91038-04(DRS);

249/91042-04 (DRS)) pending NRC review of the lic.ensee' s

corrective actions.

f.

Unresolved Itein 91-201*-06:

Adequacy of Cable Ampacity

was not Established

The licensee was .unable to prov~de documentation to

establish that cables were properly sized.

The Sargent

and Lundy Interactive Cable Engineering (SLICE) program

was* run.to determine if currently *installed power*

cables*. were adequately sized to carry their. load

current.

Approximately 120 routing points were

identified as potentially thermally overloaded*.

Analysis of each routing point is currently ~n

progress.* In addition, the licensee committed to

perform a *pilot study to randomly verify the SLICE

routing information.

This is considered an unresolved

item (237/91038-0S(DRS): 249/91042-0S(DRS}) pending NRC

.review of the routing point*overload analysis and the*

pilot program re~u1ts .

. g.

Unresolved Item 91~201~01:

High Uhit 2/3 EDG Room

Temperature

The EDSFI team found the Unit 2/3 EOG room to be

excessively hot.

The diesel room was not provided with

any forced ventilation when in standby mode.

The Unit

2.and Unit 3 diesel rooms each r~ceive *1,000 cfm of air.

flow when in standby.

The electrical relays for the

EOG generator and exciter are rated for a maximum

temperature of 122°F.

The licensee committed to.

monitor the 2/3 EOG room temperature each shift.

If

the temperature exceeded 118.4°F, the operator was

instructed to start the vent fan for a period of time

to reduce the temperature below 114.B"F~

The licensee

plans to trend the 2/3 EOG.room temperatures during the

summer of 1992 and to assess the need for permanent

forced ventilation at that time *. This is considered an

open item (237/9103~-0G(DRS)) pending NRC review of the

licensee's assessment.

6

h.

Unresolved Item 91-201~08: Insufficient Fuel in EOG

Day Tanks

The EDSFI team was concerned that -insufficient fuel was

being maintained in the day tanks.to provide EOG

operation for four hours at rated load.

The FSAR fuel

consumption rate wa~ 192 gallons per hour.

Therefore,

768 gallons of fuel was required in the day tank.

The

fuel transfer pump automatic stop was set at 743

gallons (185.75 gallons per hour).

The licensee

provided the inspector fuel consumption tests that.were

performed prior to the EDSFI.

The following fuel

consumptions were determined:

  • unit 2
      • unit.3

- *units 2/3

_,

184.43 gallons per hour

171.67 gallons per hour

183.74 gallons per hour

In each case, sUffici~nt fuel was maintained in the

days tanks.

The licensee plans to evaluate EDG fuel oil day tarik

level instrumentation design changes as a long term

actibn tb assure four hours* of fuel will be

automatically.maintained in the day tanks:* In

addition, the "licensee coiilmitted_ to perfo:i;-m semiannual

£uel consumption ~est~ for all EDGs.

Based on the

above, this item is considered cl9sed.

i.

Deficiency 91-201-09:

Inadequate Post Modification

Testing

The EDSFI_ team determined that contact Tl/Ml of control

relay 2871/a had not been tested during post-

modification testing of Modification No. Ml2-2-88-05,

"Replace Feed Breakers on MCC 28/29-7." -Procedure OAP

5-1, "Plant Design Change Program," required-a_test be

performed to written instructions including acceptance

criteria that demonstrated the modified component

funcitioned properly and did not affect the

interrelationship with other components.

Special test-

procedU:re No.

SP-89-1~4, Revision o, "LPCI Swing Bus,"

did not include acceptance criteria that verified

contacit Tl/~l would trip breaker No. 2971.

In

addition, construction testing did not contain

-documented evidence that specific circuit checkout

- criteria had been met.

Failure of the licensee's post modification test

procedure to include appropriate acceptance criteria is

a violation (237/91038-07(0~8); 249/91042-07(0RS)) of

10 CFR 50, Appendix.B, Criterion v. _

7-

The licensee plans to retest the affected circuits

described above in accordance wi~h Dre~den's Safety

Related Contact Testing Adequacy Program.

3.

250 Volt Battery Testing

On October 14,

1991~ CECo removed the Dresden Unit 3 250 Vdc

battery from.service in preparation for a service test.

Prior to this date, the licensing basi~ for Dresden only

required a rated load discnarge*test (performance test) each

refueling outage to demonstrate battery operability.

The

service test was performed utilizing the original battery

sizing profile.

During .the first minute of the test, when

. subjected to a load of 1017 amperes, the battery voltage

decreased to 209.1 volts (acceptance/criteri~ was 210

v.ol ts) ...

On October 18, 1991, following a recharge of the .batter~, a

performance test was performed to determine whether the

service test failure was due to battery degradation.

The

test demonstrated that battery capacity was 96%.

This valtie

was within 10% of the previous.test which satisfied the

acceptance criteria specified in IEEE 450.

On October 20, 1991, the licensee developed a new worst case

load profile based on a large break LOCA an.d HPCI in

standby.

The NRC's review of this.profile questioned the

li~ensee's methodology for addressing the potential

coincidence of random.loads.

The NRC also questioned the

licensee's decision not to address the potential effects of

~HPCI being in test~

The prbfile indicated the main turbine

emergency bearing oil pump (EBOP) would start at 57 seconds

into the event.and a cycling of the HPCI valves due to

reactor high water level could occur at 62 seconds into the

event.

Since plant.operators had been trained to manually

start the *EBOP pump on a turbine trip ~nd since the cycling

of theHPCI valves, depending on break size, could occur

simultaneously with th~ start of the EBOP pufup, these loads

were considered to be random~

The controlling profile

segme_nt was the one to two minute period.

Adding the

purrent resulting from the cycling HPCI valves and the EBOP

    • pump starting current would cause t.he profile peak to be.

.

greater than 1200 amperes, which exceeds the battery sizing

cal6ulation first minute current (1017 ~mperes).

The licensee develop*ed another .load profile which had a

first ~inute peak current of 910 ~mperes. This profile was

based on a large break LOCA'with HPCI in test.

To meet this

profile, the licensee modified the HPCI system adding

interposing relays in the HPCI valve circuits to prevent

coincident operation of the HPCI valves.

In addition, plant

procedures were modified to delete the instructions to plant

8

operators to manually start the EBOP pump.

On November l,*

1991, a service test was performed utilizing the revised

load profile.

The battery m_aintained a voltage of 211. 76

volts during the first minute and maintained a voltage of

greater* than 210 volts fo~ the remainder of the four hour

test.

Subsequently, the licensee identified a small.break

LOCA profile with HPCI in. standby that had the potential to

produce a 953 ampere current peak 6 minutes into the *

profile.

This peak exceeds th.e large break LOCA first

minute current of 910* amperes.*

The licensee *considered *this

momentary current peak to be of such short duration (60

milliseconds or less) that equipment would not be adversely

affected.

In addition, the licensee also considered the

pro:file to be conservativ~, based on momentary loads having

to be considered for a full minute in the tes.t profile.

In addition to the HPCI modifications and the plant

procedure modifications described above,*the licensee's

corrective actions include increasing the existing battery

size from116 cells to 120 cells, and a commitment to

install a new nonsafety related 250 Vdc battery to supply

the EBOP pump.

The licensee reported this item in LER No.91-013.

This LER will remai_n open (249/91013-LL) pending

NRC review of the licensee's corrective actions.

4 .

  • Open Items

Open items are matters which have been discussed with the

licensee, which will be reviewed further by the NRC, and

which involve some action on the part of the NRC or licensee

6r both.

Open items discussed during this inspection are

discusse~ in Paragraphs 2.b., 2.g., *and 3.

5.

Unresolved Items

  • Unresolved items are matters about which more information is

required.in order to ascertain whether they are acceptable.

items, violations, or deviations.

Unresolved *items

disclosed_during this*inspection are discussed in Paragraphs

2 . b . ; 2 . c . *, . 2 * e ~ , and 2 . f.

6.

Exit Interview

The inspectdr met with licensee representatives (denoted in

Paragraph 1) following the inspection on December 6, 1991,

to discuss the scope and findings of the inspection.

The

  • . inspector** also discussed the likely. informat:ional content of

the inspection report with regard to documents or processes *

reviewed-by the inspector during the inspection.

Licensee

repre~entatives did not id~ntify any sueh documents or

processes as proprietary.

9

. --

-~ -..--~-~--- ------ _______ __... ____ -.-*.

  • ~:
  • APPENDIX A

Concern Number

Title

Status

a. Deficiency 91-201..:.01

Inadequate Short

237/91038-01

Circtiit Capability

249/91042-01

of 4kV Circuit Breakers .*

b. Deficiency 91-201-02

Inadequate Calculation

237/91038-02

to Determine Degraded

  • 249/91042-02

Grid Relay Trip Setpoint

-c~ peficiency 91-201-03 ..

Failure to.Take

237/91038-03

  • .Prompt Correctfve Action 249/91042-03

d. Deficiency 91-201-04

e. Deficiency.91-201-05

f. Unresolved Item

91-201-06

g. Unresolved Item

.

.

91-201-07

ll * Unresolved Item

91-201-08"

i. Deficiency 91.,..201-09

Licensee Event Report

a. 91.,..013-0

b. 91-021-0

---* -~----------~- -~--~----.- --

Inadequate Acceptance**

Criteria for Battery

Surve~llances

Lack of 480 Volt

Coordination

Adequacy of Cable

Ampacity was not

Es.tablished *

High Unit 2/3 EDG

Room Temperature

Insufficient Fuel in

EDG Tanks

Inadequate Post*

Modification-Testing

Closed

237/91038-04

249/91042~04

237/91038-05-

249/91042-05

237/91038-06

  • closed

237/91038-07

249/91042-07

Title

Status

250 Volt DC Battery

249/91013-LL

Discharge Voltage

Decreased Below Design .

Basis Limit*

Imprope~ Setpoint of

237/91021-LL

Second Level Undervoltage

Relays Due to Management

Deficiency