Notice of Violation from Insp on 911202-06.Violation Noted: Licensee Post Mod Test Procedure for Mod M-12-2-88-05 Failed to Include Appropriate Acceptance Criteria,Per Procedure DAP 5-1, Plant Design Change Program
ML17174B099
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 12/20/1991
From: Ring M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17174B098 List:
References
50-237-91-38, 50-249-91-42, NUDOCS 9201210082
Download: ML17174B099 (1)


Text

NOTICE OF VIOLATION Conimonwealth Edison Company Dresden Power station

units *2. an_d 3

- Docket Nos.~ 50-237; 50-249 Licehse Nos~: -DPR-19; DPR~25 During an NRC inspection _conducted.December 2 through 6 1 1991, a violation of NRC requirements was identified.

In accordance with.

the "General Statement of Policy and Procedure for*. NRC Enforcement Actions," 10 CFR Part 2, Appendix c (1991),-the violation is listed below:

10 CFR 50, Appendix B, Criterion V,requires that activities affecting quality be accomplished.in accordance with ins_tructions that. include appropriate quantitative or qualitative acceptance criteria-for determining that important activities have been satisfactorily accomplished.

Contrary to the above, prior to December 6, 1991, the licen.see's post modification test procedure ~or modification No. M-12-2-88-_

05 failed to include appropriate acceptance criteria required by procedure OAP 1,

  • 1ip1ant Design Change Program."

This is a*

  • Severity Level IV vioJation (Supplement I)~

Pursua!1t to the provisions of 10 CF'.R 2.201, Co~monwealth Edison Company is hereby required to submit-* a written statement or explanation to the U. S. Regulatory Commission, ATTN: Document Control Desk, Washington, D.C. 20555, with a copy to the U. ~.

Nuclear Regulatory Commission, Region III, *799 Roosevelt Road, Glen Ellyn, Illinois, 60137, anc:i a copy 'to the NRC Resident Inspector at the facility that is the subject of this Notice, within 30 days of ~the date.ofthe letter transmitting this Notice of Violation (Notice).

This reply should be clearly marked as a_

"Reply to a Notice of Violatioh" and should include for each violation: * (1) -the reason for the violation, or, if contested, the basis for di~puting the violation, (2) the corrective steps that have been taken and the results achieved, (3) the corrective steps that will be taken to avoid further violations, and (4) the date when full compliance will be achieved.

If an adequate reply

  • is not received ~ithin the time specified in this Notice, *an order may be issued to show-cause why the.license should not be modified, suspended, or revoked, or why such other action as may be proper should riot be taken.

Where good cause is shown, consideration will be giveri to extehding -the response time.

Da~ed ~t Clen Ellyn, Illinois

.this_

  • 1--<..'

day of 1(-e,c,.

, 19 91-Ma 'k A-._ Rin, Chief_

Engineering Branch