ML17059C203

From kanterella
Jump to navigation Jump to search
Insp Repts 50-220/98-13 & 50-410/98-13 on 980720-24.No Violations Noted.Major Areas Inspected:Operations
ML17059C203
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 08/11/1998
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17059C202 List:
References
50-220-98-13, 50-410-98-13, NUDOCS 9808180007
Download: ML17059C203 (36)


See also: IR 05000220/1998013

Text

i

U.S. NUCLEAR REGULATORYCOMMISSION

REGION I

Docket/Report Nos.:

50-220/98-1 3

50-410/98-1 3

License Nos.:

DPR-63

NPF-69

Licensee:

Niagara Mohawk Power Corporation

P. O. Box 63

Lycoming, NY 13093

Facility:

Nine Mile Point, Units 1 and 2

Location:

Scriba, New York

Dates:

July 20-24, 1998

Inspectors:

J. Trapp, Group Leader

S.

Dennis, Operations Engineer

C. Osterholtz, Resident Inspector - Ginna

Approved by:

Richard J.

Conte, Chief

Operator Licensing and Human Performance

Branch

Division of Reactor Safety

9808180007

9808 L.i

PDR

ADQCK 05000220

G

PDR

0

EXECUTIVE SUMMARY

Nine Mile Point Unit 1

50-220/98-13

July 20-24, 1998

The management standards

and expectations for plant operators were appropriate

and clearly documented

in the Operations Manual.

Operations personnel

consistently adhered to expectations regarding communications, control room

access,

control board awareness,

and shift turnovers.

Log keeping and annunciator

response were acceptable.

Operations personnel were effectively tracking technical

specification equipment status but operators were unclear as to management

expectations

on the equipment status log entries.

The administrative guidance governing safety and configuration tagging was

appropriate to protect workers and the integrity of safety-related systems.

The

implementation of the safety,and configuration tagging administrative requirements

by plant operators was effective.

Plant operators. were effective in identifying deficient plant equipment and had

established

appropriate thresholds for including deficiencies in the corrective action

program.

However, the inspectors noted that a poor interface existed between

operations and the work planning organization in identifying and resolving deficient

or incomplete work packages.

The administrative guidance for temporary modifications, control room deficiencies,

and operator work-arounds was appropriate.

However, the effectiveness of the

implementation of the programs could not be determined,

as operators were still'in

the process of developing a comprehensive list of deficiencies and work-arounds.

Appropriate procedure guidance was available for the risk significant operator

actions reviewed.

The procedures were walked down in the field with licensed

operators and the operators were found to have a thorough understanding of the

procedure guidance.

The surveillance procedures

used for the tests observed were

of good quality.

Operators implementing several surveillance tests exhibited good procedure

adherence

skills. Operators interviewed were fully aware of management's

expectations for verbatim procedure compliance.

Control room and plant operators demonstrated

appropriate knowledge of plant

systems and administrative requirements necessary to safely operate the plant. All

operations and testing evolutions observed were conducted in a safe and controlled

manner.

The shift supervisor provided appropriate oversight of shift activities and pre-

evolution briefs were well managed.

Operations management was observed

providing appropriate oversight of control room activities.

Operations department management was proactive in initiating quality assurance

surveillances and establishing the mentoring program.

The self-assessment

and

quality assurance

audits were effective in identifying the recent decline in

operations performance.

The assessment

of DER trends, the mentoring program,

and quality assurance's

1997 audit of operations and recent surveillance collectively

provided a thorough assessment

of the operations organization performance.

The licensee appropriately resolved past inspection findings and appropriately

identified and acted on violations dealing with senior reactor operator duties in the

control room.

(NCV 50-222/98-13-01,02)

Re ort Details

~Back round

Nine Mile Unit 1 remained at rated power throughout the duration of this inspection.

The

inspectors directly observed approximately 50 hours5.787037e-4 days <br />0.0139 hours <br />8.267196e-5 weeks <br />1.9025e-5 months <br /> of operator performance during

routine plant operations and scheduled surveillance testing.

The objective of this

inspection was to verify the licensee was aware of the recent decline in Unit 1 operations

performance and was taking appropriate corrective actions to address the root causes.

Inspection Procedure (IP) 93802 was considered in the scope of review for each section of

this report and the staffing for this inspection was at a reduced level.

I. 0 erations

01

Conduct of Operations

01.1

Control Room Observations

a.

Ins ection Sco

e

The team verified that operators were meeting management expectations

in the

areas of communications, control room access,

control board awareness,

annunciator response, shift turnovers and operator log-keeping.

b.

Observations

and Findin s

General Comments

The inspectors found that plant management was cognizant of the decline in

performance and has taken corrective actions to address the causes.

A new

operations management team was recently established.

The new management

team had established

an Operations Manual (common to both Units

1 and 2) that

clearly established standards

and expectations for the operations staff. This

inspection verified overall that the operators were appropriately implementing the

standards

and expectations provided in the Operations Manual.

Communications and Control Room Access

The inspectors observed that the operator's consistently used 3-way

communications during routine evolutions, shift turnovers, and system surveillance

tests.

Control room decorum and professionalism was consistently maintained

during the team's observations.

Control room operators appropriately controlled the

access of non-operating personnel in the at-the-controls area of the control room.

Additionally, non-technical reading material, and other material not required for

station operation were not observed in the control room.

Control Board Awareness and Annunciator Res

onse

The inspectors reviewed the expectations contained in the Operations Manual

pertaining to control board awareness

and verified that the operators were alert and

attentive to control board indications during steady state conditions and surveillance

testing.

The inspectors observed that the control room operators properly responded to

alarms in accordance with the guidance in the Operations Manual with one minor

exception.

The Operations Manual recommends that the alarm response

procedure

be referenced for the first alarm occurrence each shift. The inspectors noted one

example

where the alarm response

procedure was not referenced

as recommended

by the Operations Manual ~ Operatio'n's management

had identified other examples

where this expectation was not satisfied and had reemphasized

the need to

reference the alarm response

procedure during the shift briefings.

Effectiveness of Shift Turnovers

The inspectors observed eight shift turnovers and found them to be consistent with

Nine Mile Point Unit 1 (NMP1) administrative requirements.

The responsible control

room and/or plant operators were knowledgeable of tagged equipment, unusual or

abnormal conditions, upcoming tests, and ongoing work in the plant.

The Senior

Shift Supervisor (SSS) and Assistant Senior Shift Supervisor (ASSS) elicited

participation from all crew members and reinforced safety and communication

standards

adherence

as part of each turnover.

On several occasions,

due to

background noise, some crew members had difficultyhearing information provided

during the turnover and in most cases requested the information to be repeated.

Lo

Kee in

The inspectors reviewed the previous month of ASSS and Chief Shift Operator

(CSO) narrative logs and the shift control room equipment status log. While the

inspectors found the ASSS logs to be consistent with established

standards,

the

CSO log entries were less consistent with those standards.

c.

Conclusions

The management

standards

and expectations for plant operators were appropriate

and clearly documented

in the Operations ManuaL

Operations personnel

consistently adhered to expectations

regarding communications, control room

access,

control board awareness,

and shift turnovers.

Log keeping and annunciator

response were acceptable.

/

3

02

Operational Status of Facilities and Equipment

02.1

Safet

Ta

in

and E ui ment Control

a.

Ins ection Sco

e,

.The inspectors reviewed the guidance and implementation of the safety tagging and

equipment control processes

for protecting workers and the integrity of safety-

related systems; general administrative procedure GAP-OPS-02, "Control of

Hazardous Energy and Configuration Tagging;" and additional guidance in the

Operations Manual pertaining to safety tagging to verify proper implementation and

that appropriate tagging requirements had been established.

'b.

Observations

and Findin s

The inspectors reviewed markups associated with the fuel pool cooling system and

the instrument air compressor,

and found them in compliance with administrative

procedure requirements.

Valves and control switches for the 102 emergency diesel

generator were properly aligned.

Labeling of some switches on panels located

outside the control room were occasionally different than the description in the

procedures.

A preventive maintenance

procedure had been recently implemented

to formally check the control room valve and switch positions every shift. This was

an appropriate corrective action for a recent failure to properly align a containment

spray valve in the control room.

However, the inspectors identified that there was

no similar expectation to periodically verify switches and valves located outside of

the control room.

In response,

license management

agreed to review this specific

area.

c.

Conclusions

The administrative guidance governing safety and configuration tagging was

appropriate to protect workers and the integrity of safety-related systems.

The

implementation of the safety and configuration tagging administrative requirements

by plant operators was effective.

The corrective actions for a valve alignment problem in the control room only

encompassed

control room operated equipment.

02.2

Corrective Actions and Work Controls

Ins ection Sco

e

The inspectors assessed

operator's threshold for including plant equipment

deficiencies into the corrective action program and also reviewed the interactions

between operations and planning and scheduling organization.

Observations

and Findin s

The inspectors conducted plant tours with auxiliary operators and found they were

knowledgeable of plant equipment deficiencies.

During the tours, the inspectors

noted several minor deficiencies nearly all of which had been previously identified

by the auxiliary operators and included in the corrective action program.

The items

that were not in the corrective action program were added,

The material condition

of the reactor building was good in that plant operators were cognizant of the

importance of maintaining good housekeeping

efforts.

Operators were not always aware of projected start and finish times for work

scheduled for safety-related equipment.

This may place an additional burden on

'operators to assess

the plant risk. associated with simultaneous work activities.

The

inspectors noted that the recently implemented daily management meeting to

review maintenance activities was helpful in establishing maintenance priorities.

The inspectors conducted interviews with operations personnel and reviewed

several deviation/event reports (DERs).

Based on the interviews, the inspectors

found that several operators were not confident with the quality of support provided

by the work planning organization.

The team noted two DERs (1-98-1740 and 1-

98-1972) had recently been written by operations in response to work packages

that contained deficiencies that were not identified until final review by the

operating shift for establishing safety markups.

DER 1-98-1740 was written due to

a work package for preventive maintenance

on a power supply that did not identify

that relay replacements

were required as part of the maintenance,

and subsequently

did not contain the necessary

parts.

DER 1-98-1972 was written due to a work

package for preventive maintenance

on a diesel generator heat exchanger that did

not contain plans or parts in the event of a failure while performing the

maintenance.

Both work packages

had been closed out, but neither of them

indicated that a DER had been generated

in response to the noted deficiencies.

It

appeared that the work planning personnel responsible for closing the work

packages were unaware that operations had generated

the DERs.

Conclusions

Plant operators were effective in identifying deficient plant equipment and had

established

appropriate thresholds for including deficiencies in the corrective action

program.

However, the inspectors noted that a poor interface existed between

operations and the work planning organization in identifying and resolving deficient

or incomplete work packages.

0

02.3

0 erabilit

Status of Safet -Related Com onents

a.

Ins ection Sco

e

The inspectors reviewed the processes

for tracking plant status and the operability

of safety-related equipment.

b.

Observations

and Findin s

The guidance for maintaining safety system configuration control was documented

in an Equipment Status Log (ESL). The inspectors interviewed operations personnel

regarding what the threshold was for,equipment to be included in the log. Some

operators indicated that only Technical Specification (TS) and maintenance

rule

equipment needed to be included in the log, while others indicated that all plant

equipment out-of-service be included in the log. The ESL was not being

appropriately maintained at. the start of the inspection due to a computer program

failure that occurred the week prior to the inspection.

However, actions to update

the log were completed during the inspection.

The inspectors noted that a status board was being maintained in the control room

to track TS limiting condition for operations (LCOs) as well as safety-related

equipment out of service.

The inspectors found that the status board was being

appropriately updated.

C.

Conclusions

Operations personnel were effectively tracking TS equipment status but operators

were unclear as to management's

expectations on ESL entries.

02.4

Tem ora

Modifications Control Room Deficiencies

and 0 erator Work-grounds

a.

Ins ection Sco

e

The inspectors reviewed the licensee's programs for temporary modifications (TMs),

control room deficiencies, and operator work-arounds to verify that operator

responsibilities for these programs were properly implemented.

li

b.

Observations

and Findin s

There were a total of 11 TMs installed, none of which affected safety-related

equipment.

The operators log, tagging, and approval of the TMs were all in

accordance with the administrative requirements.

The inspectors did not identify

any problems with operations implementation of the TM or annunciator processes.

The programs for tracking control room deficiencies and identifying and tracking

operator work-arounds had recently been incorporated into the Operations Manual.

There were 32 identified control room deficiencies and a computer database

was

used to track the status of each deficiency.

The program guidance for tracking

operator work-arounds was added to the Operations Manual one week before this

inspection.

The identification of operator work-arounds was discussed

during shift

briefings and the SSS encouraged

operators to evaluate current deficiencies for

inclusion into the program.

c.

Conclusions

The administrative guidance for temporary modifications, control room, deficiencies,

and operator work-arounds was appropriate.

However, the effectiveness of the

implementation of the programs could not be determined, as operators were still in

the process of developing a. comprehensive list of deficiencies and work-arounds.

03

Operations Procedures

and Documentation

03.1

General Observations

ae

Ins ection Sco

e

The inspectors assessed

the quality of selected operating procedures

and also

verified that risk significant operator actions, identified in the Individual Plant

Examination, were included as procedure instructions.

The inspectors verified that

operators appropriately complied with procedure requirements during plant

evolutions.

b.

Observations

and Findin s

The sections of the procedures reviewed were consistent with the licensee

procedure writers guide and the instructions were appropriate for conducting the

intended task.

The licensee was in the process of improving the shutdown from

outside the control room procedure by identifying steps that were described in the

licensing basis analysis for fires and those that were not credited for safe shutdown

of the plant.

The delineation between required and optional steps was important to

inform operators that optional operations performed may not have the benefit of

emergency area lighting and would only be performed provided that sufficient time

was available to complete required actions.

The inspectors determined that the

operations support staff was taking appropriate steps to include these procedure

enhancements.

The risk significant operator actions for station blackout, recovery

of offsite power, and evacuation of the control room were all properly incorporated

into the procedures.

Operators were aware of management expectations for procedure compliance and

they appropriately conducted operation and surveillance test procedures

in

compliance with the approved procedure instructions.

c.

Conclusions

Appropriate procedure guidance was available for the risk significant operator

actions reviewed.

The procedures were walked down in the field with licensed

operators and the operators were found to have a thorough understanding of the

procedure guidance.

The surveillance procedures

used for the tests observed were

of good quality.

Operators implementing several surveillance tests exhibited good procedure

adherence

skills. Operators interviewed were fully aware of management's

expectations for verbatim procedure compliance.

04

Operator Knowledge and Performance

04.1

General Observations

a0

Ins ection Sco

e

The inspectors observed operations personnel performing routine tasks and

surveillance testing to assess

operator knowledge of procedures,

systems,

and

administrative requirements.

The control room observations

also provided the

inspectors

a basis for assessing

the quality of shift supervision and assure that plant

management was providing clear expectations, setting proper standards,

and

conducting effective oversight of operations activities

b.

Observations and Findin s

The inspectors conducted operator interviews and determined that operators have a

good understanding of plant system operation, equipment status and administrative

requirements. The inspectors accompanied plant operators on four sets of rounds in

the reactor building and found all operators to be knowledgeable of systems and

familiar with the bases for the log readings they recorded.

The inspectors observed the SSS and ASSS conduct several shift turnover meetings

and pre-evolution briefings for surveillance tests.

The supervision and direction

giving to plant operators during the shift turnover and pre-evolution test briefings

was appropriate.

The shift supervisors were observed to discuss safety

considerations

and plant contingencies prior to performing testing evolutions.

The

shift supervisors effectively controlled work activities to minimize distractions for

the reactor operators.

The inspectors found that management standards were clearly defined in the

recently issued Operations Manual.

However, differing opinions exist among

operations personnel concerning whether the standards

were requirements or

guidelines. Operations management was frequently observed in the control room

discussing expectations

and standards with the shift operators.

c.

Conclusions

Control room and plant operators demonstrated

appropriate knowledge of plant

systems and administrative requirements necessary to safely operate the plant. All

operations and testing evolutions observed were conducted in a safe and controlled

manner.

The shift supervisor provided appropriate oversight of shift activities and pre-

evolution briefs were well organized.

Operations management was observed

providing appropriate oversight of control room activities.

Management

expectations were clearly articulated in the newly developed Operations Manual.

07

Quality Assurance in Operations

07.01 General Observations

a.

Ins ection Sco

e

The inspectors assessed

the quality of the self assessment

and independent

oversight of the operations organization.

b.

Findin s and Observations

At the request of the Operations Manager, the quality assurance

organization

conducted

a surveillance of the operations in June 1998. The quality assurance

staff used the NRC inspection procedure (93802) to conduct this review. The

scope of the surveillance was similar to this inspection.

The conclusion of the

surveillance report stated that "overall, conduct of operations meets expectations."

The licensee's surveillance team found opportunities for improvement in the area of

operator log keeping, implementation of the Shift Technical Advisor (STA) function

and a lowering of the threshold for writing DERs.

The surveillance findings were

generally consistent with those noted during this inspection.

The licensee had initiated a control room mentoring program in June of 1998 to

provide feedback to the operators regarding performance expectations.

The

inspectors reviewed a select sample of the mentor's observation reports and found

that they were candid assessments

and met the program expectations.

Several

operators stated that they believed the mentoring program would assist in

understanding

and complying with management expectations.

An August 1997 Quality Assurance annual audit of operations identified a

"...general decline in Conduct of Operations."

The audit reviewed the conduct of

operators, management performance, administrative controls and procedures.

~

0

The inspectors reviewed the licensee's self assessment

program for operations.

The administrative controls for the program provided explicit observation area

objectives and standards.

Performance records were maintained for each

performance objective.

The 1998 performance records indicated that observations

were frequently conducted and were self critical. The operations department also

assesses

performance by trending DERs.

The DER trend reports indicated that the

1998 personnel error rate for operations was slightly higher than the business plan

goal and the trend was not declining.

The information in the trend report provided

operations management with a good basis for assessing

performance:

Operations

department management reviewed the quarterly trend'reports

and documented

an

assessment

of the data.

C.

Conclusions

Operations department management was proactive in initiating a quality assurance

surveillance and establishing the mentoring program.

The self-assessment

and

quality assurance

audits were effective in identifying the recent decline in

operations performance.

The assessment

of DER trends, the mentoring program,

and quality assurance's

1997 audit of operations and recent surveillance collectively

provided a thorough assessment

of the operations organization performance.

08

Miscellaneous Operations Issues

08.1

Closed

Violation 50-220 5 50-410 96-10-04: Multi le exam

les of failure to

follow rocedures

This violation cited three separate

examples of failure to follow procedures.

The

failures occurred during a surveillance test on the core spray topping pump (Unit 1),

during the installation of a markup on a hydraulic control unit (Unit 1) and during

maintenance

by ISC on the hydrogen/oxygen monitors (Unit 2). The inspectors

verified the completion of selected corrective actions provided in Niagara

Mohawk's, December 26, 1996, Notice of Violation response letter to the NRC.

The inspectors verified that Procedure Writer's Guide was revised and included

enhanced

guidance regarding independent verification of calculations.

Also,

surveillance test procedure (U1-ST-Q18) was revised to be consistent with the

guidance provided in the writer's guide.

The inspectors reviewed the Operations Manual to verify that appropriate guidance

was provided for independent verification during application and clearing of

markups.

Operations Manual, Section 3.10.3 recommends that when applying and

clearing markups on safety-related systems that independent verification is required.

The inspectors observed markups being applied and cleared and noted that the

operator's were conducting independent verifications in accordance with the

Operations Manual.

The inspectors observed the operators applying self checking

techniques provided in the Operations Manual which was instituted as an

enhancement to reduce human errors.

10

The licensee has recently set new standards for self checking and verification to

improve the personnel error rate and reduce the incidence of failure to follow

procedures.

The licensee monitors the personnel error rate on a quarterly basis and

has established

a business plan goal for personnel errors.

The inspectors

determined that the licensee's corrective actions to reduce personnel errors and the

trending and goal setting for reducing the personnel error rate provides an

appropriate basis for closure of this violation.

Closed

Violation 50-2205 50-410 97-06-01: Multi le exam

les of failure to

follow rocedures

The corrective actions implemented by the licensee in 1996 to reduce the instances

of failure to follow procedures were not completely successful.

In 1997, a second

NRC violation was written for additional examples of failure to follow procedures.

The 1997 violation cited four examples of failure to follow procedures that occurred

during the month of July. The examples included inadvertently operating the wrong

valve during a containment spray surveillance test, opening the wrong breaker

during an isolation of a motor generator set, not following test procedure steps

during fire system testing, and the failure to properly restore

a radiological waste

system to service.

The inspectors verified the completion of selected corrective

actions described in the Niagara Mohawk's, October 15, 1997, Notice of Violation

response letter to the NRC.

The inspectors conducted extensive observations of operators conducting

surveillance tests and the implementation of markups.

The operators were found to

be implementing good self checking and verification practices.

Management

expectations regarding self checking and verifications were clearly articulated in the

Operations Manual.

Pre-job briefings for these activities were thorough.

The labels

on the normal and maintenance supply breakers for the process computer were

appropriately revised.

The licensee now monitors the personnel error rate and has established

goals for

personnel errors.

Closure of this violation is based on the current inspection results

of strict adherence to procedures,

on the licensee's corrective actions to reduce

personnel errors, and on the trend of personnel error rate which appears to be

holding steady.

08.3

Closed

VIO 50-220 EA96-541-1013:

Failure to control reactor

ressure vessel

water level followin

a scram resultin

in water enterin

the main steam lines.

On November 5, 1996, following a reactor scram, a reactor vessel overfill occurred

'which resulted in fillingthe main steam lines with approximately 30,000 gallons of

water.

The details associated with this issue are documented

in NRC Inspection

Report 50-220/96-13. As a result, a notice of violation and proposed imposition of

civil penalties letter was issued by the NRC to Niagara Mohawk Power Corporation

(NMPC), dated April 10, 1997.

NMPC provided their response to the violation in

their letter dated May 12, 1997, to the NRC.

11

The inspectors conducted an on-site review to assess

and verify corrective and

preventive actions stated in the response

by NMPC in the areas of design change,

procedure, training, and organizational enhancement.

Specifically, the inspectors

conducted document reviews and interviewed the responsible engineer and general

supervisor of operations (GSO) and assessed

and verified the following:

~

New training scenarios which were developed and are currently in use to test

overfill events and the modification made to the high pressure coolant

injection (HPCI) and feedwater (FW) trip system.

~

Post trip reviews which were used to verify consistency between simulator

and plant response to events.

~

Plant operating procedures which were revised and now provide more

explicit direction for vessel level control and reflect the modification made to

the HPCI/FW trip system.

~

Technical specifications which were amended to reflect the reinstatement of

the GSO position to provide additional operations oversight.

Additionally, the inspectors reviewed five subsequent

plant shutdown post-trip

reviews and found no instances of level control problems.

The licensee's root

cause and analysis and related corrective and preventive actions were acceptable.

This violation is closed.

08.4

Licensee Event Re orts

LER 50-220 98-07and

LER 50-220 98-14:

Closed

On dut

SRO tern oraril

leaves the control room

LER 98-07

On April 24, 1998, with NMP1 at full power, the on duty ASSS left the control

room to discuss ongoing maintenance with an electrical technician; the SSS was

out of the control room attending to other business.

This resulted in no SRO in the

contiol room as required by TS 6.2.2.e.

After about two minutes, the ASSS

realized the error, returned to the control room, and immediately notified the SSS.

The ASSS was subsequently removed from licensed duties following a NMP1

management

investigation.

NMP1 management

initiated DER 1-98-0983 and

subsequent

LER 50-220/98-07to document the event and initiate a root cause

analysis.

The inspectors conducted an on-site review of the root cause analysis and

associated

corrective actions for this event.

The event was licensee identified.

Additionally, through review of past NMP1 and NMP2 LERs and interviews with

plant management,

the inspectors found that the event was an isolated case and

non-repetitive.

The inspectors concurred with the licensee's determination of root

,cause as inadequate

managerial methods and a contributing factor of inadequate

verbal communications., The inspectors selected associated

corrective actions for

review which included verification of physical barriers put in place to remind

operators of the control room envelope boundaries, review of an event notification 0

~

~

12

to all operating staff, and verification through training records that the individual

involved received additional training and developed

a lessons learned memo.

The

team determined the corrective actions to be acceptable

and this LER met the

requirements of 10CFR50.73.

The inspectors concluded that LER 98-07 is closed

and the event was a violation of NMP1 TS 6.2.2.e.

(NCV 50-220/98-13-01)

0 en

On dut

SRO fails to satisf

trainin

re uirement

LER 98-14

On June 16, 1998, with NMP1 at full power, an unqualified SRO assumed the

position of ASSS for approximately four hours and was the only SRO in the control

room for approximately 45 minutes during that time. The SRO was not qualified

because

on the previous day, June 15, 1998, the SRO had failed an evaluated

requalification simulator exam and per NMPC training procedure NTP-TQS-102,

"Licensed Operator Requalification Training," Section 3.5.7.b.3, completion of

remediation is required prior to an individual resuming licensed duties following a

failure. The required remediation was not completed when the SRO assumed the

position of ASSS for 4-hours.

Therefore, the TS 6.6.2.e. requirement for having a

qualified SRO in the control room during power operation was not satisfied during

the 45 minute period when the SSS was out of the control room to attend the

morning meeting.

Also, the NRC identified that the "unqualified" ASSS did not

meet the requirement of TS 6.6.2.a.

The SRO was assigned to the ASSS position by the GSO to allow the normally

scheduled ASSS to attend an offsite meeting.

Additionally, the GSO and SRO were

aware of the failure when the assignment was made, but did not realize at the time

that the failure should preclude the SRO from assuming the position of ASSS until

remediation was complete.

The event was brought to the attention of NMPC

management

on June 17,1998,

by a trainer who had been observing the shift on

June 16,1998, as part of the operations mentoring program. NMPC initiated DER 1-

98-1882 and subsequent

LER 50-220/98-14to document the event, initiate a root

cause analysis, and develop corrective actions.

The inspectors conducted

an on-site review of the root cause analysis and

associated

corrective actions for the event described in LER 50-220/98-14and

DER

1-98-1882. The team noted the event was licensee identified. The inspectors

concurred with the licensee's determination of inadequate

managerial methods.

However, the inspectors determined that an additional root cause was inadequate

verbal communications which the licensee had stated in their LER was a

contributing factor to the event.

The inspectors reviewed selected corrective

actions to assure that both root causes were addressed.

The inspectors verified

that:

a crew remediation and successful reevaluation were performed, a lessons

learned memo was distributed to all operations staff, and training procedure NTP-

TQS-102 "Licensed Operator Requal Training" was revised to provide more explicit

and formal direction regarding the communication and notification process for crew

and individual failures.

Due to the complexity of this event, additional review will

be conducted by the NRC to verify that all root causes

are identified and corrected.

LER 98-014 willremain open pending that review.

13

Conclusion for Followu

of LERS 50-220 98-07and 98-14

The inspectors determined that both events occurred under distinctly different

circumstances

and causes.

For both events, the same NMP1 requirements for

control room SRO staffing as specified in TS 6.2.2.a and e applied.

V. IVlana ement Meetin

s

X1

Exit Meeting Summary

On July 24, 1998, a meeting was held to discuss the findings of this inspection.

NMPC

management at the exit meeting did not dispute any of the team's findings or conclusions.

Based on the NRC Region

I review of this report, and discussions with NMPC

representatives,

it was determined that this report does not contain safeguards

or

proprietary information.

PARTIALLIST OF PERSONS CONTACTED

B. Booth

J. Conway

J.

Dreyfuss

D. Topley

General Supervisor of Operations, Unit 1

Vice President, Nuclear Generation

Operations Support

Operations Manager

INSPECTION PROCEDURES USED

IP 93802

Operational Safety Team Inspection

Administrative Procedures

PROCEDURES REVIEWED

4

GAP-OPS-01,

GAP-OPS-02,

GAP-OPS-03,

GAP-DES-03,

GAP-PHS-03,

GAP-PSH-01,

GAP-PSH-03,

Rev. 9

Rev. 9

Rev. 3

Rev. 7

Rev. 2

Rev. 18

Rev 2

Administration of Operations

Control of Hazardous Energy and Configuration Tagging

Control of Operator Aids

Control of Temporary Modifications

Control of On-line Work Activities

Work Control

Control of On-line Work Activities

S-400-ND D-CON

'-500-ND D-OPS

Configuration Management

Operations

NIP-ECA-01

NIP-OUT-'01

Deviation Event Report

Shutdown Safety

N1-PM-S5

Control Room System Lineup Verification

14

0 erations De artment Procedures

N1-ODP-OPS-0101, Rev.10

Operations Manual

Shift Turnover and Brief

Effective Date 4/17/98

0 eratin

Procedures

N1-0P-13, Rev. 29

N1-OP-45, Rev. 23

N1-OP-38C, Rev. 15

N1-OP-40, Rev. 12

N1-OP-43B, Rev. 0

N1-OP-43A, Rev. 4

Emergency Cooling System

Emergency Diesel Generators

LPRM/APRM

Reactor Protection 5 ATWS Systems

Balance of Plant Startup tk Shutdown

Reactivity Control

S ecial 0 eratin

Procedures

N1-SOP-18, Rev. 5

N1-SOP-9.1, Rev. 4

N1-SOP-5, Rev. 9

N1-SOP-7, Rev. 4

N1-SOP-1, Rev. 9

Station Blackout

Control Room Evacuation

Loss of 115 KV

Service Water Failure/Low Intake Level

Reactor Scram

Deviation Event Re orts

1-98-0983

1-98-1 882

1-98-0632

1-98-0008

1-98-0708

1-98-0143

1-98-0204

1-98-0323

1-98-0965

1-98-1094

1-98-091 9

1-98-2006

SRO left the control. room

Failure to comply with NRP-TQS-102

Avoidable loss of EDG availability hours

Inappropriate Operator Action

Trending DER for EDG 103.fuel oil tank level

Procedure inadequacy

FSAR discrepancy - Manual spray initiation does not

agree with EOP

Procedure inconsistency N1-SOP-9.1 (Control Room

Evacuation)

Failure to implement TS action statement

Procedure violation - failure to follow n1-OP-43A

Unrecognized violations of secondary containment

Incomplete procedure change review

Qualit

Oversi ht

Audit Report 97009, Operations, Surveillance and Test

Surveillance Report 98-0066-1, Unit 1 Operations Branch Assessment

Deviation Event Report Program - Trend Summary Report Second Quarter 1998

Deviation Event Report Program - Trend Summary Report First Quarter 1998

NMP1 Operations - Evaluation of DER Trend Report First Quarter 1998

Unit One Operations - Performance Observation Report

Control Room Mentoring Program

15

ITEMS OPENED, CLOSED, AND UPDATED

Closed

50-220 8L 410/96-010-04

50-220 8t 410/97-06-01

VIO

VIO

Multiple examples of failure to follow

procedures

Multiple examples of failure to follow

procedures

50-220/EA96-541-1 01 3

EEI

Vessel overfill event

50-220/97-03-01, 50-220/

98-07

NCV/LER

On duty SRO temporarily leaves control

room

~Udated

50-220/98-14

LER

On duty SRO fails to satisfy training

requirements

LIST OF ACRONYMS USED

APRM

ASSS

CFR

CSO

DER

ESL

FW

GSO

LCO

HPCI

LER

NMPC

NMP1

NMP2

NRC

OSTI

SSS

SAT

TM

Average Power Range Monitor

Assistant Station Shift Supervisor

Code of Federal Regulations

Chief Shift Operator

Deviation/Event Report

Equipment Status Log

Feedwater System

General Supervisor of Operations

Limiting Condition for Operation

High Pressure

Coolant Injection

Licensee Event Report

'iagara Mohawk Power Corporation

Nine Mile Point Unit 1

Nine Mile Point Unit 2

Nuclear Regulatory Commission

Operational Safety Team Inspection

Station Shift Supervisor

Shift Technical Advisor

Temporary Modification