ML17059B058

From kanterella
Jump to navigation Jump to search
Forwards Insp Repts 50-220/96-201 & 50-410/96-201 from 960116-26.Weaknesses Noted
ML17059B058
Person / Time
Site: Nine Mile Point  Constellation icon.png
Issue date: 02/16/1996
From: Mary Johnson
NRC (Affiliation Not Assigned)
To: Sylvia B
NIAGARA MOHAWK POWER CORP.
Shared Package
ML17059B059 List:
References
NUDOCS 9602260359
Download: ML17059B058 (32)


See also: IR 05000220/1996201

Text

.a

gP,R REC0

"o

Cy

O

I

0

IP

~O

++**+

UNITED STATES

NUCLEAR REGULATORY COMMISSION

WASHINGTON, D.C. 20555-0001

February

16,

1996

go -ZZ 0

Hr. B. Ralph Sylvia

Executive Vice President - Generation

Business

Group

Niagara

Mohawk Power Corporation

(NMPC)

Nine Mile Point Nuclear Station

P..O.

Box 63

Lycoming,

NY 13093

SUBJECT:

NINE MILE POINT STATION INTEGRATED PERFORMANCE ASSESSMENT

PROCESS

(IPAP)

PRELIMINARY ASSESSMENT

REPORT

(NRC INSPECTION

REPORT

NOS.

50-220/96-201

AND 50-410/96-201)

Dear Mr. Sylvia:

During the period from January

16 through January

26,

1996,

a team under the

direction of the Special

Inspection

Branch of the Office of Nuclear Reactor

Regulation

completed

the in-office review of an Integrated

Performance

Assessment

of the Nine Mile 'Point Nuclear Station.

This phase of the

assessment

consisted of an in-office review of the inspection record

and

performance history for a two year period spanning

January

1994 to December

1995.

The in-office review identifies performance

strengths

and weaknesses

in

the areas of Safety Assessment/Corrective

Action, Operations,

Engineering,

Maintenance,

and Plant Support.

The results

are

summarized

in the attached

report

and are depicted

on the attached

Preliminaty. Performance

Assessment/Inspection

Planning Tree.

The=second

phase of the assessment

will consist of a two week on-site

assessment

scheduled for the weeks of March 4 and March 18,

1996.

During this

phase of the assessment,

the team will validate its preliminary results

as

well as draw conclusions

in those

areas originally considered

to be

indeterminate.

The results of the on-site

assessment

will be evaluated

along

with those of the in-office review and documented

in a Final Assessment

Report.

The final results will also

be depicted

on

a Final Performance

Assessment/Inspection

Planning Tree.

This preliminary information. is being provided for your information only.

No

response

to this letter or the preliminary assessment

is required.

9602260359

960216

I

PDR

ADQCK 05000220,'

PDR,'umg

B~LI~ CEH7KK CSPV

B. Ralph Sylvia

Should you have

any questions

concerning this preliminary assessment,

or the

assessment

process

in general,

please

contact the assessment

team leader

Mr.

S.K. Malur at (301) 415-2963.

Sincerely,

Enclosure:

Inspection

Report

cc:

See next page.

Michael

R. Johns

n, Acting Chief

Special

Inspection

Branch

Division of Inspection

and Support

Programs

Office of Nuclear Reactor Regulation

Distribution:

Docket Files 50-220,

50-410

PSIB R/F

FPGillespie,

NRR

RHGallo,

NRR

MRJohnson,

NRR

DPNorkin,

NRR

CERossi,

AEOD

SAVarga,

NRR

LBHarsh,

NRR

GEEdison,

NRR

SLLittle, NRR

BNorris, SRI

HEPoteat

Regional Administrators

Regional Division Directors

Inspection

Team

PUBLIC

ACRS (3)

OGC (3)

1S Distribution

t

II

Hr. B. Ralph Sylvia

Niagara

Hohawk Power Corporation

Nine Mile Point

Hark J. Wetterhahn,

Esquire

Winston

E Strawn

1400

L Street,

NW

Washington,

DC

20005-3502

Supervisor

Town of Scriba

Route 8,

Box 382

Oswego,

NY

13126

Mr. Richard

B. Abbott

Vice President

Nuclear Generation

Niagara

Hohawk

Power

Corporation

Nine Mile Point Nuclear Station

P.O.

Box 63

Lycoming,

NY

13093

Resident

Inspector

U. S. Nuclear Regulatory

Commission

P.O.

Box 126

Lycoming,

NY

13093

Gary D. Wilson, Esquire

Niagara

Mohawk Power Corporation

300 Erie Boulevard

West

Syracuse,

NY

13202

Regional Administrator,

Region I

U. S. Nuclear Regulatory

Commission

475 Allendale

Road

King of Prussia,

PA

19406

Mr. F. William Valentino, President

New York State

Energy,

Research,

and Development Authority

2 Rockefeller Plaza

Albany,

NY

12223-1253

Hr. Martin J.

HcCormick, Jr.

Vice President

Nuclear Safety Assessment

and Support

Niagara

Mohawk Power Corporation

Nine Mile Point Nuclear Station

- P.O.

Box 63

Lycoming,

NY

13093

Hr. Norman L. Rademacher

Unit

1 Plant Manager

Nine Mile Point Nuclear Station,

P.O.

Box 63

Lycoming,

NY

13093

Hr. Kim A. Dahlberg

Plant Manager,

Unit 2

Nine Mile Point Nuclear Station

P.O.

Box 63

Lycoming,

NY

13093

Charles

Donaldson,

Esquire

Assistant Attorney General

New Yor k Department of Law

120 Broadway

New York,

NY

10271

Mr. Paul

D.

Eddy

State of New York Department of

Public Service

Power Division, System Operations

3 Empire State

Plaza

Albany,

NY

12223

Hs. Denise J. Wolniak

Hanager

Licensing

Niagara

Mohawk Power Corporation

Nine Mile Point Nuclear Station

P.O.

Box 63

Lycoming,

NY

13093

Mr. Richard Goldsmith

Syracuse University

College of Law

E. I. White Hall Campus

Syracuse,

NY

12223

Hr. Richard

H. Kessel

Chair and Executive Director

State

Consumer Protection

Board

99 Washington

Avenue

Albany,

NY '2210

Mr. John

V. Vinquist,

MATS Inc.

P.O.

Box 63

Lycoming,

NY

13093

U.S.

NUCLEAR REGULATORY COHHISSION

OFFICE

OF NUCLEAR REACTOR REGULATION

NRC Inspection

Report:

50-220/96-201

and 50-410/96-201

License

Nos.

DPR-63

and NPF-69

Docket Nos.:

50-220

and 50-410

Licensee:

Niagara

Hohawk Power Corporation

Facility Name:

Nine Hile Point, Units

1 and

2

Inspection

Conducted:

January

16 through 23,

1996

Inspection

Team:

S.K. Halur,

Team Leader, 'Special

Inspection

Branch

D.H. Barss,

Emergency

Preparedness

and Radiation

Protection

Branch

T.H. Boyce, Standardization

Project Directorate

T.Foley, Special

Inspection

Branch

J.A.

Isom, Special

Inspection

Branch

R.B. Hanili, Safeguards

Branch

R.K. Hathew,

Special

Inspection

Branch

D.J. Nelson,

Inspection

Program

Branch

H. Wang, Special

Inspection

Branch

J.E. Wigginton,

Emergency

Preparedness

and Radiation

Protection

Branch

Prepared

by:

S.K.

Ha ur,

Team Leader

Special

Inspection

Branch

Division of Inspection

and Support

Programs

Office of Nuclear Reactor Regulation

ate

Reviewed

by:

Donald

P. Norkin, Section Chief

Special

Inspection

Branch

Division of Inspection

and Support

Programs

Office of "Nuclear Reactor Regulation

Date

Approved by:

Hicha l R. Johnson,

cting Branch Chief

Special

Inspection

anch

Division of Inspect

on and Support

Programs

Office of Nuclear Reactor Regulation

ate

9602260365

9602'Lh

PDR

ADDCK 05000220

8

PDR

Enclosure

TABLE OF

CONTENTS

EXECUTIVE SUMMARY .

OVERALL ASSESSMENT

SCOPE

AND OBJECTIVES

.

ASSESSMENT

METHODOLOGY

1.0

SAFETY ASSESSMENT

AND CORRECTIVE ACTION .

1. 1

Problem Identification

1.2

Problem Analysis

and Evaluation

.

.

.

.

.

1.3

Problem Resolution

2. 0

OPERATIONS

2.1

2.2

2.3

2.4

Safety

Focus

Problem Identification/Problem Resolution

.

guality of Operations

.

Programs

and Procedures

.

.

3.0

ENGINEERING

.

3.1

3.2

3.3

3.4

Safety

Focus

Problem Identification/Problem

guality of Engineering

Work

.

.

Programs

and Procedures

.

.

.

.

~

~

1

~

~

~

Resolution

.

4. 0

MAINTENANCE

10

4,1

4.2

4.3

4.4

4.5

Safety

Focus

Problem Identification/Problem

Equipment Performance/Material

guality of Maintenance

Work

.

.

Programs

and Procedures

.

.

.

.

~

~

~

~

~

~

Resolution

.

Condition

10

10ll

11

12

5.0

PLANT SUPPORT

.

5.1

Safety

Focus

5.1.1

Radiological

Controls

.

5.1. 2

Security

5. 1.3

Emergency

Preparedness

5.2

Problem Identification/Problem Resolution

.

5.2. 1

Radiological Controls

.

5.2.2

Security

5.2.3

Emergency

Preparedness

12

12

12

13

13

14

14

14

15

5.3

equality of Plant Support

5.3.1

5.3.2

5.3.3

Radiological Controls

.

Security

Emergency

Preparedness

5.4

Programs

and Procedures

.

5.4. 1

Radiological Controls

.

.

.

5.4.2

Security

5.4.3

Emergency

Preparedness

APPENDIX A LIST OF

REFERENCES

.

APPENDIX

B PRELIHINARY PERFORHANCE ASSESSHENT/INSPECTION

PLANNING TREE.

15

15

16

17

17

17

17

A-1

B-1

EXECUTIVE SUMMARY

The in-office review phase of the integrated

performance

assessment

of both

units of the Nine Mile Point Nuclear Station

was conducted

by the Special

Inspection

Branch of the U.S. Nuclear Regulatory Commission's Office of

Nuclear Reactor Regulation during the weeks of January

16 and 22,

1996.

The

purpose of this in-office review was to develop

an integrated

perspective

of

performance

strengths

and weaknesses

based

upon

a review of inspection

reports,

event reports,

and other

NRC and licensee

generated

information.

The

assessment

covered

a two year period from January

1994 to December

1995.

A

two week on-site

assessment

scheduled for the weeks of March

4 and March 18,

1996, will be conducted to validate the results

from the in-office review.

In the area of Safety Assessment/Corrective

Action, the licensee

was effective

in problem identification, but problem analysis

and problem resolution were

indeterminate.

The deviation/event

reports

were utilized effectively in

problem identification by all levels of the organization,

as documented

in

several

NRC inspection reports

and licensee quality assurance

audits.

Root

cause

evaluations for significant issues

appeared

to be properly conducted,

and the quality and depth vary appropriately with the significance of issues.

Audits performed

by the quality assurance

branch

were thorough.

For example,

the corrective action program audits required

by the technical specifications,

radioactive liquid and gaseous

waste control

program audits,

maintenance

program audits,

and surveillance of the

MOV program were broad in scope

and

good in technical

depth.

However, the trending

and evaluation of data from

the

DER process

appeared

to be

an area that needed to be improved,

particularly in cause identification, trend

code application,

and

identification of preventive actions.

The disposition ofissues

in the

DER

process

generally

was thorough,

although

some

examples of weaknesses

were

identified.

Resolution of recurring problems with rod position indication at

Unit 2, repeated

repairs to the reactivity control

system,

and missed

TS

surveillances

appeared

to be not thorough.

The licensee's

performance

in the

analysis

and evaluation of problems,

implementation of recommendations

from

assessments,

and the effectiveness

of corrective actions, will be further

assessed

by the team during its on-site inspection.

The performance of the operations

management

and personnel

in response

to

events

was good,

and the licensee

displayed

a conservative

approach

to

operation of both units.

Operations

was generally attentive to degrading or

unusual

equipment conditions,

but operators

missed opportunities to identify

abnormal

conditions

such as,

valves not in their correct position,

and

an

inoperable

temperature

recorder for the safety relief valve tail pipe.

Procedural

weaknesses

and recurring personnel

errors

appeared

to have not been

completely addressed.

Operator

performance

during normal operation

was

satisfactory,

and operator

responses

during plant transients

was excellent.

Operations

programs

and procedures

including adequacy

and usage

where

indeterminate will be reviewed further during the site visit.

Generally,

the engineering staff demonstrated

proper safety perspective

in

thorough

and technically accurate operability evaluations of plant issues.

Engineering identified numerous plant problems

and resolved

them

appropriately,

although there were

a few instances

where problems

were not

noted

and properly evaluated.

For example,

Unit 2 emergency diesel

generators

had operated

outside their design basis

sitice initial plant startup

due to

a

design deficiency with the governor cooling water system,

and pressure

locking

and thermal

binding of risk significant motor operated

valves

(MOVs) in Unit 2

high pressure

core spray system were not identified for resolution.

Also, the

NRC had identified weaknesses

in the resolution of some of the plant issues

such

as the longstanding

problem of electrical

noise interference with neutron

monitoring system

and the corrective actions in response

to operational

experiences

regarding Agastat relay failures at Unit 1.

Plant modifications

and calculations

were technically sound,

and were properly documented.

However, design

changes

to the hydrogen

and oxygen systems

and installation of

a check valve in the service water line to a room cooler required further work

to make the equipment function acceptably.

Engineering

programs

and

procedures

including adequacy

and

usage

where indeterminate will be further

reviewed during the site visit.

The performance of maintenance

during the outages

at both units indicated

significant licensee

management

attention to the refueling

and outage

planning

activities.

Maintenance activities were generally well planned

and executed.

Pre-job briefings were generally satisfactory,

but where repetitive work was

being performed, briefings were not effective

as evidenced

by the

unintentional

reactor recirculation

pump runback incident.

Identification and

resolution of problems,

equipment

performance

and material condition,

and

programs

and procedures will be reviewed further on site.

In the Plant Support areas of Radiological Controls

and Security,

the licensee

demonstrated

strong performance

in safety focus, 'problem identification and

resolution,

and programs

and procedures.

Radiological

exposure

goals

were

met, thorough self-assessments

were performed,

and programs

and procedures

were effective.

The licensee

had thoroughly evaluated

the security program,

implemented corrective actions,

and the security plan

and procedures

were in

compliance with regulations.

Performance

in the area of Emergency

Preparedness

was weak as evidenced

by deficiencies

in the exercises

conducted

during the last two years.

During the October

1995 exercise,

the licensee

staff did not properly evaluate plant conditions

and did not recognize

and

properly classify the emergency

event in a timely manner

.

Also, dur ing the

October

1994 exercise,

the emergency

event

was incorrectly classified

due to

an error in the dose projection calculations.

OVERALL ASSESSMENT

SCOPE

AND OBJECTIVES

This Integrated

Performance

Assessment

of both units of the Nine Mile Point

Nuclear Station is being performed in accordance

with NRC Inspection

Procedure

93808 "Integrated

Performance

Assessment

Process."

The assessment

is divided

into:

an in-office review performed at

NRC headquarters;

an on-site

assessment

to validate the observations

from the in-office review;

and

a final analysis

of the results of the assessments

and development of inspection

recommendations.

The assessment

is being conducted

by the Special

Inspection

Branch of the Office of Nuclear Reactor Regulation.

The in-office review was

performed during the weeks of January

16 and January

22,

1996.

The on-site

assessment

is scheduled

to be performed during the weeks of March

4 and March

18,

1996.

The assessment

objectives

are to develop

an integrated

perspective

of licensee

performance

and arrive at recommendations

for future inspection

focus in the

areas of Safety Assessment/Corrective

Action, Operations,

Engineering,

Maintenance,

and Plant Support.

The in-office review covers

NRC inspection

reports,

licensee

event reports

(LERs), enforcement history, regional

assessments,

and licensee

internal

and external

assessments.

The results of

the in-office review are included in this preliminary report.

The references

contained

in the report are listed in Appendix A.

The preliminary results

are

presented

on the Preliminary Performance

Assessment/Inspection

Planning Tree

in Appendix B.

Following the issuance

of this report,

the team will validate its observations

via a performance

based,

on-site

assessment.

The results of the on-site

assessment

and in-office review will be used. during the final analysis

and

development of inspection

recommendations

and will be documented

in a final

report to be issued after the conclusion of the on-site

assessment.

The final

assessment

report will include recommendations

on where to focus future

NRC

inspection effort,

and these

recommendations will be depicted

on

a Final

Performance

Assessment/Inspection

Planning Tree.

ASSESSMENT

METHODOLOGY

During the in-office review, the team evaluated

the Nine Mile Point inspection

record

and performance history for a two year period spanning

January

1994 to

December

1995.

Available licensee quality assurance

(gA) audit reports

and

other self-assessment

documents

were reviewed.

The review results

were

utilized to assign

performance ratings of either decreased,

normal, or

increased

inspection to the individual elements

in each

assessment

area.

Where the team's

review of inspection data

and licensee

information was

inconclusive,

or where sufficient information was not available to come to

meaningful

conclusions,

individual elements

were rated

as being indeterminate.

Ratings for the overall performance

in the areas of Safety

Assessments/Corrective

Action, Operations,

Engineering,

Maintenance,

and Plant

Support were not addressed

during the in-office review phase.

The results

obtained

from the in-office review will be used

by the assessment

team to develop individual on-site

assessment

plans for each of the assessment

areas.

During the on-site review, the team will focus

on those

areas

rated

as

indeterminate

and those

where the inspection or performance

data record

indicated potential

performance

weaknesses.

The team will also validate the

elements that were assigned

decreased

or normal inspection ratings.

Following

the on-site

phase of assessment,

the team will issue

a final assessment

report.

1.0

SAFETY ASSESSMENT

AND CORRECTIVE ACTION

1.1

Problem Identification

The licensee's

programs for identifying equipment,

human performance,

and

plant program deficiencies

are the deviation/event

report

(DER) process,

the

quality assurance

(gA) audits,

and self-assessments.

These

programs,

in

general,

were effective in identifying problems at both units.

On the basis of evaluation of about

40 safety-significant deviation/event

reports

(DERs),

an

NRC team determined that the

DER process

was

an effective

tool for identifying significant issues,

and the threshold for initiating DERs

used

by station shift supervisors

and other parts of the organization

was

appropriate

(ref. I).

Thousands

of DERs were written at the facility each

year by all levels of the licensee

organization.

In the first quarter of

1995,

945

DERs were written, of which about

13X were significant

and about

2X

required root cause

evaluations

to be performed (ref. 2).

Self-assessments

by line organizations

were effective in identifying problems.

For example,

in maintenance,

a self-assessment

on instrumentation

and controls

(I8C) post-job critiques identified that improvements

in feedback

on job

performance

and attention to detail

were needed (ref. 2).

Also, inspection

reports

noted that recent

self-assessments

of human errors

conducted

by each

department

were thorough

and critical.

Designated

branches

presented

findings

to-other branch

managers for peer review, identified predominant

and secondary

causes,

and trended

human errors (ref. 3).

Independent

assessments

by safety review groups,

including the Independent

Safety Engineering

Group (ISEG)(for Unit 2 only), the Station Operations

Review Committee

(SORC),

and the Safety Review and Audit Board

(SRAB) were

effective.

They reviewed

a considerable

number of plant activities

and

reports

such

as

DERs, licensee

event reports

(LERs), safety evaluations

and

proposed modifications, industry events,

NRC generic correspondence,

inspection reports, quality assurance

audit reports,

and other licensee

generated

reports.

The review activities

and final recommendations

were well

documented

(refs. I and 5).

The gA audits performed

by the Nuclear guality Assurance

Branch

appeared

to be

of particularly good quality and of sufficient depth to identify both failures

to comply with applicable requirements

and areas for improvement in the

licensee

programs

and management

oversight of the facility.

The gA audits for

the following were broad in scope

and good in technical

depth: radioactive

liquid and gaseous

waste control

programs (ref. 7);

maintenance

program (ref.

2);

and surveillance of the

HOV program (ref. 8).

A combined utility assessment

group

(CUAG) performed

an independent'assessment

of the effectiveness

of the licensee's

gA program.

The

CUAG review appeared

thorough, identifying weaknesses

in follow-up of gA findings that resulted

in

changes

to gA audit procedures

for post-audit evaluation of findings by the

audit team

and tracking of recommendations.

by the

gA branch (ref. 9).

The

ISEG reports for 1994

and

1995 covered all the plant activities,

and

provided many useful observations

and recommendations

regarding analysis of

plant activities

and operating. experience.

For example,

the

ISEG performed

periodic reviews .of the maintenance activities at Unit 2 and

made

recommendations

to correct long standing

unresolved

problems with the service

water strainers

(ref. 45).

Normal inspection

in this area is recommended.

1.2

Problem Analysis

and Evaluation

The licensee's

performance

in problem analysis

and evaluation

appeared

to be

satisfactory,

though weaknesses

in. evaluating repetitive problems

and

DER

evaluation

were noted;

Root cause evaluations'for significant events or those

directed

by the plant management

appeared

to be properly conducted,

and the

quality and depth of the evaluation varied appropriately with the significance

of the issue.

In general,

the analysis

and disposition of DERs were

effective.

Examples of effective dispositions

included

an analysis to support

the Unit 2 high pressure

core spray uni.t cooler operability concern (ref. 15),

and the review of the safety-related

issues

related to intergranular stress

corrosion cracking of the reactor

core shroud at Unit

1 (ref. 38).

The.DERs

evaluated

by the Unit .2 operations

department

were noted to be consistently

excellent (ref. 1).

However, several

DERs documented repetitive problems

which indicated that evaluation-and

resolution of problems were not always

effective.

Examples of these

included loss of rod position indication at Unit

2 (ref. 15), repeated

repairs to the redundant reactivity control

system (ref.

14), missed Technical Specification surveillances for leak rate testing the

personnel

airlock and emergency airlock (ref. 32),

and not identifying and

replacing Unit

1 Agastat relays before they were severely

degraded

(ref. 3).

Trending and'valuation of the

DER program appeared

to be

an area

where

improvements

were necessary,

based on'ssues .identified by the licensee

in gA

Audits and

ISEG reports.

The DER.program trends the conditions that led to

the initiation of the

DER using industry established

causal

factor codes.

This information was periodically evaluated .by th'e quality assurance

department

and presented

to the branch

managers

to assess

performance

trends.

The licensee identified errors in cause identification, trend code

application,

and identification of preventive actions in the

DER system.

The

licensee

also concluded that continued

management

attention

was

needed

to

assure that problem causes

were fully identified and that preventive actions

address

these

problems (ref. 9).

An NRC team noted that the most prevalent

causal

factors continued to be work practice failures, i.e.,

documents

not

followed correctly and poor self-checking.

Further,

some

gA assessments

identified the need to improve the quality of apparent

and root cause

determinations

because

some

DERs did not adequately

account for human

performance factors,

and thus did not provide actions that would prevent

recurrence

of the'vents

were not performed '(ref. 1).

Overall performance

in problem analyses

and evaluation is indeterminate

pending the team's on-site

assessment.

1.3

Problem Resolution

The dispositioning of DERs was generally timely, and the

DER backlog

appeared

to be satisfactorily managed

at both units.

For example,

although thousands

of DERs were issued

each year,

the backlog

was decreasing.

Prioritization and

periodic review, of the

DER backlog

was appropriate

to ensure that significant

safety issues

were promptly dispositioned (ref. 1).

In general",

the licensee's

corrective actions to resolve

issues

were

effective.

However, corrective actions

taken in response

to poor

human

performance

problems

appeared

to be not effective,

as evidenced

by continued

personnel

performance

issues

in the Unit

1 reactor recirculation

pump runback

event (ref. 22), Unit 2 reactor trip during swapping of battery chargers

(ref.

12), failure to verify logic circuit for the auto transfer feature of the

power board at Unit

1 (ref. 23),

and other instances

described

in the other

sections of this report.

The information available to the team was not

sufficient to assess

the licensee's

performance

in the implementation of

recommendations

from assessments

and the effectiveness

of corrective actions.

Overall performance

in this area is indeterminate.

2. 0

OPERATIONS

2. 1

Safety

Focus

Generally,

the operators

and the operations

department

management

made

conservative

operational

decisions

and displayed

a conservative

approach to

operations of both Unit

1 and Unit 2.

Shift supervisors

directed

and

managed

plant scrams

and other plant transients well.

For example,

the Unit 2 shift

supervisor displayed

good

command

and control after the reactor recirculation

pumps tripped when the redundant reactivity control

system

was de-energized

for troubleshooting

(ref.

14)

and in response

to a high main turbine vibration

during

a unit shutdown (ref. 15).

The 'licensee

management

provided

good support to the operations staff during

a

forced shutdown at Unit 2 to address

various oper'ational

issues

(ref. 16).

Senior station

management

provided direction during the recovery

phase of a

partial loss of offsite power event

when Unit 2 was in cold shutdown (ref.

14).

Effective and significant management

involvement in the oversight of the

licensed operator requalification training program was noted (ref. 17).

4

Alth'ough, in general,

responses

to events

by both operators

and operations

department

management

were conservative,

in a few instances

the decisions

were

not.

In one case,

reviews performed

by the senior reactor operator

and

operations

planning personnel

did not identify the potential Technical

Specifications

(TS) implications of the erroneous

rod position indication

system.

This resulted

in the Unit

1 remote

shutdown

panel

being inoperable

during power operation (ref. 18).

In another instance,

a division of service

water system

was placed in service at Unit 2 without an operable radioactivity

monitor or appropriate

compensatory

action

as required

by the

TS (ref. 19).

Further, the licensee

management

decided to postpone repairing

a valve, which

was part of a reactor coolant system pressure

boundary,

during the Unit 2

third refueling outage.

Subsequently,

the unit was required to be shutdown

due to increased

reactor coolant system leakage

from the valve (ref. 20).

Normal inspection is recommended

in this area.

2.2

Problem Identification/Problem Resolution

Inspection reports

indicated that operators

were attentive to equipment

conditions

and identified problems.

For example:

during the performance of a

monthly test

on the liquid poison

system,

Unit

1 operators

identified and

corrected

a problem with the test equipment (ref. 5); Unit

1 operators

identified arcing

on the exciter end of 413 reactor recirculation

pump motor

generator

set while completing turbine rounds (ref. 21);

and operators

properly identified

a plant process

computer failure at Unit

1 (ref. 21).

These

issues

were appropriately

documented

in DERs.

Though problem identification by operations

personnel

was generally good,

a

few instances

were noted where the control

room, operators

did not identify

conspicuous

deficiencies.

Unit 2 control

room operators failed to notice that

the safety relief valve

(SRV) tail pipe temperature

recorder

had

been

inoperable

because

of inadequate

monitoring of the recorder

by the operators

(ref. 14).

Also, the control

room operators

were not aware that the Unit

1

nitrogen tank low pressure

alarm did not come

on as designed

when the tank

remained

empty (ref.. 14)

and that one of the shutdown cooling system

temperature

control valves

was about

85X open instead of being shut during

power operations.

This condition was identified on. the control board

by an

NRC inspector

immediately following the operators'oard

walkdown during shift

turnover.

Subsequent

followup by the licensee identified that several

other

valves were out of position (ref. 13).

Throughout the period of review, the licensee

continued to experience

problems

attributed to operators'nvolvement

with the work control process.

During

the inspection of a reactor recirculation

pump

(RRP) runback event,

NRC

identified deficiencies

in operator review of the'ork order

and oversight of

the work (ref. 22).

A licensed operator misinterpreted

a procedure

step which

led to bearing

damage

on the Ill control rod drive pump (ref. 24).

Unit 2

lost shutdown cooling for fifteen minutes

due to an inadequate

review of a

markup (ref. 23).

The licensee

performance

in problem resolution,

and the

effectiveness

of corrective actions will be assessed

further on site.

Overall performance

in this area

was indeterminate.

2.3

guality of Operations

Numerous

examples of appropriate

operator

responses

to reactor

scrams

and

other plant transients

were noted.

For instance,

the operating

crew at Unit I

reacted

promptly and properly to a reactor

scram to minimize the transient

on

the plant (ref. 23).

Following the Unit I RRP runback event the operators

correctly assessed

plant conditions,

recognized

the low reactor core flow

conditions,

and reduced reactor

power level

away from the restricted

area of

the power-to-flow operating

map by inserting control rods (ref. 22).

The operators

generally demonstrated

adherence

to procedures,

displayed proper

communication,

followed effective self checking

and peer verification

techniques,

and demonstrated

a good questioning attitude.

Also, management

oversight created

a professional, efficient, safety-oriented

control

room

atmosphere.

The operations staff demonstrated

an excellent

knowledge of the

plant systems,

operating procedures,

and current plant status.

Shift

turnovers

and briefs, with few exceptions,

provided sufficient detail to

maintain proper continuity during ongoing evolutions

and to keep the

operations

crew knowledgeable

of current plant issues/problems

and upcoming

evolutions.

During special

evolutions,

systems

engineering staff and/or

operations staff provided

a technical brief and senior plant management

provided expectations

for the conduct of the evolution (ref. 25).

However, there were instances

of operator

performance that were not

satisfactory.

Examples include: Unit I reactor operators

had not performed

required voltage checks

across

an auto transfer logic circuit in accordance

with operating

procedures

which required additional operator actions to

restore reactor pressure

and water level following a reactor trip (ref. 23);

Unit I reactor operator did not properly position the reactor

mode switch

after

a reactor

scram (ref. 23); suppression

chamber

spray

mode of the

residual

heat

removal

system loop "A" at Unit 2 was disabled

because

the

reactor operator did not review the field copy to verify that each individual

valve had

been returned to the correct position (ref. 14);

and Unit 2 operator

inadvertently de-energized

an emergency

DC bus,

causing

both reactor

recirculation

pumps to trip (ref. 12).

In addition, the following examples of weaknesses

in operations

involvement

with the work control process

were noted:

inadequate

work order review and

control

room communication

which were partly responsible for Unit I

recirculation

pump runback

and turbine trip (ref. 22);

misinterpretation of a

procedure

step which led to bearing

damage

on the Ill control rod drive pump

(ref. 24);

lack of control

room operations

oversight at Unit I contributed to

a reactor

scram during performance of a surveillance

procedure

by maintenance

(ref. 41); loss of shutdown cooling at Unit 2 for fifteen minutes

due to an

inadequate

review of a markup (ref. 23);

and maintenance

was inappropriately

authorized

on two control rod hydraulic control units simultaneously

instead

of sequentially,

resulting in operations. failing to comply with a technical

specification action statement

at Unjt. 2 (ref. 26).

Normal inspection is recommended

in this area.

2.4

Programs

and Procedures

I

The licensee

had established

an effective operator training program.

For

example:

the training of the on-shift licensed

operators

was effective in

mitigating the consequences

of the recirculation

pumps runback event (ref.

22); senior reactor operator

(SRO)'and Unit

1 reactor operator applicants

exhibited very good performan'ce

during all parts of the examination with few

generic

weaknesses

(ref. 27); Unit 2

SRO applicant

crew briefs were complete

and concise,

and

command

and control

was strong (ref. 28).

There were examples. of inadequate

procedures

or inadequate

use of procedures

which have led to some errors

and operational

'events.

These included:

use of

a procedure that did not incorporate the.correct

system configuration led to

a

resin spill at Unit

1 (ref. 6); loss of .Unit 2 reactor recirculation

pumps

during

a reactor startup

and mispositioning Unit 2 suppression

pool spray

valve due to procedure

weaknesses

or inadequacies

(ref. 14);

and not

performing

TS surveillances

on 'primary containment isolation valves

because

operations

department

surveillance

procedure

was not updated (ref. 15).

Overall performance

in this area

was indeterminate,

pending further on-site

review of procedure

adequacy

and:usage.

3.0

ENGINEERING

3.1

Safety

Focus

The licensee's

engineering

management,

and engineering staff had established

a

go'od safety perspective

as demonstrated

by the thorough

and technically

accurate operability evaluations of plant issues.

Examples of conditions that

were evaluated

properly by engineering to determine that the plant could be

safely operated

included the following: core spray sparger rejectable

crack

indication at Unit

1 (ref. 12); incorrect fuse installation in Unit 2 reactor

protection

system (ref. 14);

and elevated

temperatures

at the termination

points

and fuses inside control

room panels

at Unit

1 (ref. 29).

The successful

implementation of the hardened

wetwell vent modification at

Unit

1 (ref. 30)

and the station blackout

(SBO) rule at Unit 2 (ref. 4)

demonstrated

management's

involvement in engineering activities.,

Although engineering activities were. performed well,

a few weaknesses

as

a

result. of inadequate

review or inattention

by management

were noted.

Examples

of such weaknesses

were:

NRC identified programmatic

weaknesses

in the Unit 2

Appendix J program

and Generic Letter (GL) 89-10 motor operated

valve

(HOV)

program (refs.

8 and 23);

and de'letion of the licensee's

commitment to install

R.G.

1.97 Category

1 instrumentation for drywell water level at Unit

1 without

proper review (ref. 32).

Normal inspection is recommended

in this area.

3.2

. Problem Identification/Problem Resolution

The engineering staff, in general,

were effective in identifying problems.

Specific. examples

included the following: the process

computer indication of

feedwater flow at Unit

1 was not consistent

with design calculations resulting

in operation at above the rated core thermal

power limit (ref. 15); the

reactor building integrity was not maintained at Unit

1 because

a secondary

containment

bypass flow path

was not accounted

for (refs.

16 and 33);

and part

of the control rod drive flow was'ot included in the heat balance

and core

thermal

power calculations resulting in operation

above Unit 2 rated core

thermal

power limit (refs.

3 and 34).

However, there were

a few examples

where the engineering staff failed to

identify plant issues

on

a proactive basis.

Examples of these

weaknesses

included the following:

Unit 2 emergency diesel

generators

(EDGs)

had

operated

outside their design basis

since initial plant startup

as

a result of

the inadequate

design of the governor cooling water system (ref. 12);

and

during the power ascension

testing associated

with the Unit 2 power uprate,

the reactor

had to be manually scrammed

because

of low flow to the stator

cool.ing heat

exchanger

because

of an inadequate

design review (ref. 10).

The licensee

implemented

a self-assessment

program to determine the

performance of nuclear engineering

and technical

support groups

and to

identify strengths

and weaknesses

of these

groups.

A review of Unit 2

DER

self-assessment

trends for the period July-September

1995 indicated. that. the

design configuration

and analysis

weaknesses

were the most frequent.

The

NRC

inspection reports

noted that the licensee's

self-assessments

of the

electrical distribution system

and the

SBO rule implementation

program at Unit

2 were comprehensive

and of high quality (ref. 4).

The gA audits of the

design. control

and configuration management

program were thorough (refs. Il,

29 and 35).

The

ISEG performed

adequate

oversight activities of the

licensee's

design

change

process

at Unit 2 (refs.

36 and 37).

In general,

the licensee's

engineering staff thoroughly evaluated

the

identified issues

and provided adequate

technical

support for resolving them.

For example:

ap analysis to resolve the Unit 2 high pressure

core spray system

switchgear unit cooler operability concern

was performed promptly (ref. 15);

safety-related

issues

related to intergranular stress

corrosion cracking of

the reactor core shroud at Unit

1 were thoroughly reviewed (ref. 38); steps

were initiated to improve the performance of Unit 2 service water system

and

to resolve deficiencies identified in a self-assessment

(ref. 15);

and issues

from the electrical distribution system functional inspection

(EDSFI) were

thoroughly evaluated

and corrective actions

were implemented (ref. 40).

However,

weaknesses

in the ability of the licensee's

engineering staff to

resolve plant problems effectively were noted.

The engineering staff was slow

in resolving the longstanding

problem of electrical

noise interference with

the Unit

1 neutron monitoring system (ref. 11).

The licensee's

corrective

actions in response

to operational

experiences

regarding Agastat

GP relay

failures

and potential

problems in using commercial-grade

7000 series

agastat

relays at Unit

1 were inadequate

(ref. 3).

Normal inspection is recommended

in this area.

3.3

guality of Engineering

Work

Both the engineering

and technical

support personnel

generally performed their

functions well and adequately

resolved plant problems.

Plant modifications

and calculations

were technically sound

and properly documented.

The safety

evaluations,

design input,

and technical

reviews were thorough (refs.

10, ll

and 35).

Good engineering

performance

was evident in the following: the

battery capacity

and effect of loss of ventilation calculations,

and safety

evaluations for Unit 2

SBO implementation (ref. 4); analysis for NRC

supplemental

information related to potential

problems with the

BWR water

level instrumentation (ref. 32);

and

APRH alarm and rod b1ock modification and

post-modification testing for Unit 2 (ref. 24).

However,

a few examples of less

than adequate

engineering

support were noted.

Examples of these

weaknesses

included the following: ineffective coordination

of Unit

1 hydrogen

and oxygen monitoring system modification that required

a

second modification to make the system functional.(ref. 35); ineffective

design

change for Unit 2 service water check valve replacement

that required

a

second

valve design

and replacement

(ref. 3);

and inadequate

consideration

of

system interactions for the modification to correct the Unit 2 'scram discharge

volume

(SDV) high-level alarm and control rod block signal that required

another modification to correct the problem (ref. 14);

and inadequate

evaluation of pressure

locking and thermal binding of NOVs resulting in not

identifying two risk significant Unit 2 high pressure

core spray system

NOVs

which were susceptible

to pressure

locking (ref. 18).

Normal inspection is recommended

in this area.

3.4

Programs

and Procedures

The licensee effectively implemented

several

engineering

programs at both

units.

Examples

included:

a program to monitor the corrosion of the Unit I

torus

and the corrosion residue

on containment

and core spray components

(ref.

ll); an acceptable

program for implementing the

SBO rule at Unit 2 (ref. 4);

a

comprehensive

design-basis

reconstitution

program at Unit

1 (ref. 29);

a

comprehensive

and effective training program for the engineering

and technical

support staff at both units (ref. 35);

a program to simplify and upgrade

the

engineering

procedures

at both units (ref. 29);

and

a good like-in-kind

replacement

program for component

replacements

(ref. 35).

The plant

modification procedures

at both units provided detailed guidance to ensure

that plant modifications were designed

and implemented

in a safe

and

controlled manner (ref. 35).

However,

programmatic

weaknesses

were identified in a few engineering

programs.

For example,

the

NRC identified several

weaknesses

in the

GL 89-10

motor operated

valve

(HOV) program at both units because

of inadequate

engineering justification and review (ref. 8).

Weaknesses

were also

identified in the implementing procedures

for the Appendix J program

and in

the surveillance

procedures

and their implementation for valves in the

inservice testing

(IST) program at Unit 2 (refs.

23 and 42).

Overall performance

in this area is indeterminate,

pending further review of

engineering

programs

and procedures.

4. 0

MAINTENANCE

4.1

Safety

Focus

The performance of maintenance

during the outages

at both units indicated

significant licensee

management

attention to the oversight of refueling

and

maintenance

outage planning.

Unplanned

outage delays

were minimized, backlog

of work orders

were reduced,

and outage

schedules

were adhered to.

The

licensee

met the pre-outage

goals for outage duration, radiation exposure,

industrial safety,

and contamination control.

The Unit

1 reactor core shroud

modificatio'ns were completed without any major difficulties, and maintenance

performance

and licensee

oversight of contractor activities were noted

as

satisfactory (ref. 12).

Though the reactor fuel vendor for Unit

1 had not

recommended

additional

inspections,

the licensee

was proactive in inspecting

all

new

GE ll fuel assembly

lower tie plates for possible debris

(machine

shavings)

because

GE 9 fuel assemblies

being fabricated for another utility

were reported to have

had debris

problems (ref. 44).

Although the licensee

management prioritized and completed

work to ensure

appropriate

safety equipment

performance

and reliability (ref. 35), instances

were noted where equipment

problems

were not effectively resolved.

Repetitive

and continuing control rod position indication problems at Unit 2 were not

aggressively

pursued (ref. 15).

The redundant reactivity control

system at

Unit 2 failed and was declared

operable

each time after repair,

because

the

root causes

and long-term solution were not determined until numerous failures

occurred (ref. 14).

Pre-job briefings generally were adequate,

however, for

repetitive work that was successfully

performed previously, briefings were not

adequate

as evidenced

by the unintentional

RRP runback incident at Unit

1

(ref. 22).

Normal inspection

in this area is recommended.

4.2

Problem Identification/Problem Resolution

The .licensee's

maintenance

department,

theISEG,

and

gA organizations

identified maintenance

related

problems through the use of the

DER process.

For example, electricians

at Unit 2 wrote

DERs to correct environmental

qualification discrepancies

noted

on solenoid operated

containment isolation

valves.

Thorough followup by the licensee

was evidenced

by inspection of all

similar valves, operability determinations,

and consultation with the vendor

(ref. 24).

The licensee

monitored

an increasing

trend in the Unit 2 emergency

diesel

generator start time, identified problems with the air starting

system,

and replaced

the system

components

to correct the problems (ref. 3).

The

licensee

management

promptly. resolved

problems with the master

power

10

connecting rod.on the Unit 2 emergency diesel

generators

after receipt of

vendor notification of the defect (ref. 16).

During a review of a completed preventive maintenance activity, gA identified

non safety-related

electrical

contacts

being

used in safety-related

applications.

This was promptly 'corrected

(ref. 21).

Also,

gA audits

identified and required the correction of deficiencies

in the implementation

and documentation of the

TS snubber examinations,

which were resolved

by the

licensee

through

a series of corrective actions (ref. 49).

Periodic reviews

of the maintenance activities at Unit'

were performed

by the

ISEG, including

review of maintenance

related

DERs, review'of hardware

problems,

assessment

of

work,packages,

and observation

of, ongoing'aintenance

work.

ISEG provided

recommendations

for resolving noted problems.

The licensee's

performance

in resolution of long standing

and repetitive

problems

was less

than adequate

in the following examples:

the loss of rod

position indication at Unit 2 (ref.

15)

and personnel

er'rors resulting in

missed

TS surveillances

(ref. 32).

Resolution of identified problems,

and

comprehensiveness

and tracking of corrective actions require further review.

Overall performance

in this area is indet'erminate,

4.3

Equipment Performance/Material

Condition

Equipment performance

problems

were identified such as,

inadequate

cooling of

Unit 2 emergency diesel

generator-governor

{ref. 12),

inoperable

hydrogen

recombiners

at Unit 2 due to obstruction in its flow path (ref. 46)

and

excessive

wear of the backwash

arm assembly of the service water self-cleaning

strainer at Unit 2 (ref. 45):

The licensee

implemented corrective actions to

resolve these. problems.

Equipment performance

and mater'ial condition problems

had caused

reactor

trips, forced shutdowns,

or plant transients

at both units.

Examples at Unit

I included electrical

noise in intermediate

range monitors (ref. 47),

steam

leaks in reheater

drain tank manway (ref. 23),

and failure of generator

protective relay (ref. 48).

Examples at Unit 2 included nitrogen leak from a

solenoid valve in drywell (ref. 25),

a switch failure in the turbine generator

electro hydraulic control system (ref. 25),

and inoperability of both

EDGs

because

of governor oil temperature

concerns (ref. 12).

Overall performance

in this area is. indeterminate,

pending the team's on-site

review equipment

p'erformance

and maintenance .history.

4.4

guality of Maintenance

Work

Maintenance

work practices,,communications,

direction

and control,

and

personnel

knowledge contributed to achieving pre-outage

goals during the

outages

at both units (refs.

2 and 23).

Examples of well planned

and executed

maintenance activities with good pre-job briefings, coordination,

supervisory

oversight,

and

ALARA considerations

were: Unit I reactor core shroud

modifications (ref.. 38); repairs to Unit I main steam line break temperature

switches (ref. 10); Unit 2 service water

pump discharge

check valve repairs

(ref. 24); installation of spent fuel racks in Unit

1 (ref. 24);

and

replacement

of the valve body of the solenoid-operated

pilot air supply

isolation valve at Unit 2 (ref. 21).

Post-outage

critiques identified such

areas for improvement

as,

planning,

implementation,

and outage oversight to

strengthen

the outage

process. for future outages

(ref. 23).

However,

a few examples of poor work practices

and inadequate

self-checking

and peer verification were identified.

These included:

catch containments

under leaking valves in Unit

1 were allowed to remain in place without active

work orders or assigned

problem identification numbe'rs (ref.,3); deficient

pre-job briefing, not following work order, lack of independent verification,

and deficient control

room communication during reactor recirculation

pump

controller mai'ntenance

at Unit

1 that caused

a plant transient (ref. 22); poor

work practices that allowed metal filings, grinding wheel dust,

and excessive

lubricant to remain in tubing during replacement

of flexible pneumatic

supply

lines to pilot solenoid valves

on safety relief valves (ref. 39);

and

fasteners

on environmentally qualified covers

on solenoid valves were missing,

loose,

or of the wrong type (ref. '24).

Normal inspection is recommended

in this area.

4.5

Programs

and Procedures

In general,

work orders,

maintenance

procedures,

and surveillance

procedures

were noted to be adequate

for the associated

activities.

Safety-related

work

packages

appropriately

documented

the work including proper verifications

and

material control (ref. 15).

Weaknesses

in procedure quality were noted in the inspection reports.

The

surveillance test procedure for reactor water level high/low level inputs to

the reactor protection

system at Unit

1 was poorly written and

cumbersome

to

use (ref. 21).

The program for Unit 2 emergency diesel

generator

governor oil

changeout

did not identify operating temperature limits and did not

incorporate. vendor recommendations

(ref.

12 and 50).

Personnel

errors

associated

with Unit

1 reactor recirculation

pump controller maintenance

were

caused,

in part,

by work order development

process

deficiencies

in format,

detail, direction, precautions,

and sequence/order

(ref. 22).

The licensee's

maintenance

programs

and procedures will be further examined during the on-

site assessment.

The licensee

performance

in this area is indeterminate.

5.0

PLANT SUPPORT

5.1

Safety

Focus

5. 1. 1

Radiological'Controls

The licensee

management

consistently

placed strong

emphasis

on improving the

material condition of the plant by actively reducing contaminated

areas.

This

enhanced

the general

working conditions for the plant staff and allowed easy

access

to* plant, areas

(refs.

2, 5,

10,

and 51).

The performance

in the

12

radiological controls

area continued to be generally strong

and met the

comprehensive

site radiation goals.

The radiological. exposure

goals at both

units were met or exceeded

(refs.

44 and 52).

The recent

outages

in both

units were well planned

and managed,

and were indicative of good communication

and cooperation

among the operations,

crafts,

and radiation controls staff

(refs.

5 and 54).

Reduced

inspection

in this area is recommended.

5.1.2

Secur ity

The'licensee

management

continued to provide strong support to the physical

security program at the site.

A Commitment to Excellence

Program

(CEP)

was

implemented

by the licensee to enhance

security performance.

Since February

1994, monthly management

CEP audits were performed in which different aspects

of the overall security program were evaluated

and analyzed

as to the adequacy

of the program.

Observations

and recommendations

were written and security

work requests

initiated.

These monthly audits further look for adverse

trends

or repeat

problems.

Although no safety issues

were identified in the licensee

reports,

NRC inspectors

noted that the licensee

should consider whether normal

security measures

or identified deviation reports

had

any impact on, station or

personnel

safety (ref. 56).

Reduced

inspection in this area is recommended.

5. 1.3

Emergency

Preparedness

The licensee

performed the required

emergency

preparedness

(EP) drills and

exercises

to demonstrate

the ability to protect the health

and safety of the

public by taking appropriate

actions to mitigate the effects of postulated

emergency

events

on the surrounding population.

The licensee

management

involvement

and proper safety focus were observed

as evidenced

by management's

involvement in

EP drill critiques (ref. 15).

However, during an exercise

in October

1994, the emergency

event

was

incorrectly classified

on the basis of an .erroneous

dose projection

calculation (ref. 15).

A failure to properly evaluate plant conditions

and to

recognize

and properly classify the emergency

event during the October

1995

exercise

was cited by the

NRC as

a violation.

This was

a further indication

of the. need for additional licensee

management

attention to the

EP program

(ref. 3).

The licensee's

emergency

response facilities were found to be well equipped

and consistent with facility descriptions

in the site emergency

plan.

Overall

these facilities were in very good operational

cohdition.

However,

two

portable air samplers

in the emergency

operational .facility (EOF) were found

to be out of calibration (ref. 57)

This was corrected

immediately

and

no

repeat

occurrences

were observed (ref. 15).

Normal inspection in this area is recommended.

13

5.2

Problem Identification/Problem Resolution

5.2. I

Radiological Controls

The gA audit programs for all areas of the radiological controls program

and

self-assessments

and surveillances

were thorough,

and incorporated

proper

technical

focus

and level of detail (refs.

7,

58,

and 59).

The licensee's

refueling outage reports

were good examples of the licensee's

thorough

and

self-critical assessments.

These reports describe

successes,

and note areas

needing

improvement in

a comprehensive,

detailed

manner (ref. 59).

Licensee

self-assessment

results

documented

in the

DER process,

continued to

report events

where contract, craft,

and operations

personnel

had not adhered

to site radiological

work controls procedures

and practices.

Examples

included failure to comply with radiation work permit

(RWP) requirements

and

failure to communicate properly and fully with the assigned

health physics

technicians

(ref. 51).

In addition,

the licensee

had identified minor issues

involving the performance of the radiation protection department

(ref. 60).

In response

to the above repetitive personnel

problems,

the licensee

had

increased

worker training, audits,

and surveillances.

The licensee

had taken

appropriate

short-term corrective actions to resolve

access

control problems,

and long-term corrective actions

were in progress

(ref. 51).

Reduced

inspection in'his area is recommended.

5.2.2

Security

The licensee

gA audits

were conducted within the time frame required

by

commitments,

and covered the security program, fitness-for-duty program,

and

safeguards

information controls.

The audit reports identified

a number of

inconsistencies

in the security plan

and procedures,

security systems,

training of security staff, fitness for duty program

and access

authorization

program concerning

adequacy,

and implementation of plan or procedure

commitments.

However, the security, fitness-for-'duty,

and access

authorization

programs

were determined

by the

NRC to be effectively

implemented

and in compliance with regulatory requirements.

None of the

findings appeared

to be programmatic

weaknesses

(ref. 56).

The licensee

issued

DERs for weaknesses

identified by audits

and took prompt

corrective actions that prevented repetition of these

problems.

Several

security personnel

were formally trained in root-cause

analysis,

and the

licensee

planned to use

them to conduct analysis of security issues

(ref. 56).

Reduced

inspection is recommended

in this area.

14

5.2.3

Emergency

Preparedness

The licensee's

critique process,

observation .and evaluation of performance

during an

EP drill'n August 1995,

and assessment

of the October

1995 exercise

were determined to be thorough

and critical (refs.

3 and 15).

The licensee's

quality assurance

organization

audited the emergency

preparedness

program.

These audits were thorough

and identified. such concerns

as',

weaknesses

in the

training program, failure to follow administrative

procedure

guidance,

out of

date procedures,

and missed or incomplete documentation of surveillances

(ref.

61).

Emergency

preparedness

drill or exercise'weaknesses

were prioritized and

assigned

to individuals for resolution,

and were tracked.

These

items were

generally completed within the prescribed

time period (refs.

15 and 57).

Most of the open findings from previous

NRC inspections

were resolved

by the

licensee

and were closed in subsequent

inspections

(ref.

13,

15

,

and 57).

Normal inspection

in this area is recommended.

5.3

equality of Plant Support

5.3. 1

Radiological

Controls

The radiological protection

program provided effective job coverage

and

support during normal operation

as well as during plant outages.

The licensee

initiated

a new, user, friendly, radiation work permit

(RWP) process

(ref. 2).

Especially noteworthy was the highly effective radiological

support for the

Unit

1 reactor core shroud inspection

and repair work (ref. 53).

The external

and internal

dose control programs. w'ere strong.

Some

examples

included:

reducing the number of respirators

used

from greater

than 3000 in 1993 to 54

in 1994

as

a result of the implementation of the revised

10 CFR Part 20;

and

the installation of closed circuit television

cameras

throughout the site to

remotely view high radiation areas

(ref. 44).

The use of local, close-capture

portable

HEPA filtration units was another

good example of the high quality

support provided to minimize workers'ntakes

by maintaining work area

airborne radioactivity levels

ALARA (ref. 60).

The licensee

supported

radiation protection. technician continuing training program

and provided

continued professional

devel.opment for the health physics

management staff.

One instance of a failure to properly survey

and evaluate

the need for posting

and controlling

a high radiation area in the Unit

1 old radwaste building

resulted

in a violation (ref. 54).

No recurrences

were noted during the

assessment

period.

I

Normal inspection effort in this area is recommen'ded.

5.3.2 Security

The licensee

was properly implementing the physical security plan

and

procedures.

The protected

area

and vital area barriers

were well maintained,

access

control for protected

and vital areas

were in accordance

with

procedures,

security posts

were adequately

staffed

and equipped,

fitness-for-

15

duty program was being

implemented properly, intrusion detection

systems

were

tested without deficiencies,

and personnel

were complying with the security

plan

and procedures

(refs.

32 and 56).

The

NRC conducted

an Operational

Safeguards

Response

Evaluation

(OSRE) during

October .1995, to determine the licensee's a";lity to respond to an external

threat.

The

OSRE team determined that the licensee security force

demonstrated

effective contingency

response

capabilities

based

on observations

during drills at site.

An NRC special

inspection

was conducted to verify corrective actions for

previously identified weaknesses

i.n the areas of maintenance

of security

equipment,

compensatory

measures,

training and qualification,

and access

control.

Malfunctioning equipment

was corrected

in a timely manner,

and

no

deficiencies

in compensatory

measures

were .noted.

Examination of a random

selection of records

indicated that all training and qualification information

was properly documented.

The

NRC noted that the licensee

needed to improve on

the consistency

and frequency of contingency drills.

In addition,

performance

testing of protected

area

access

con.rol

equipment

and intrusion detection

systems

were conducted,

and assessment

capabilities

and contingency

responses

were evaluated for their effectiveness.

The testing detected

no

vulnerabilities except in contingency drills (ref. 63).

Weaknesses

in the performance of security functions,

such

as unintentional

disclosure of safeguards

information in a public document (ref.

63 and 64)

and

a third instance

since August

1993 of a visitor entering the protected

area

without a proper escort (ref. 24), were identified.

The licensee

implemented

appropriate corrective actions (ref. 16).

Normal inspection is recommended

in this area.

5.3.3

Emergency

Preparedness

During the October

1995 exercise,

the licensee's

staff did not properly

evaluate plant conditions

and did not recognize

and properly classify the

emergency

event.

NRC issued

a notice of violation for licensee's

performance

during this exercise.

Also, problems

noted during the previous exercise

in

October

1994 indicated

a weakness

in the ability to accurately classify

emergency

events.

A communications

aide did not activate the pager

system

when the exercise

event escalated

to the alert level (ref. 13).

The control

of secondary

responder training, the adequacy of emergency director training

on dose

assessment

and protective action recommendations,

and the practice of

considering drill observation

as equivalent to drill participation

as

a

training event were assessed

as potential

weaknesses

(ref. 57).

Increased

inspection in this area is recommended.

16

5.4

Programs

and Procedures

5.4. 1

Radiological Controls

The licensee

had established

effluent and environmental

controls programs,

with detailed,

well written procedures

and supported

by a comprehensive

site

laboratory

gA/gC program (ref. 7, 62,

65,

and 66).

The offsite dose

calculation

manual

was well written and very detailed (ref. 66)., The radwaste

and transportation

programs at both units were judged to be well implemented,

and contained effective training

programs (ref. 69).

The licensee

properly

and effectively implemented

and integrated

the revised

10 CFR Part 20

requirements

into the site health .physics

programs (ref. 67).

Reduced

inspection in this area is recommended.

5.4.2

Security

The licensee's

security plan

and procedures

were in compliance with regulatory

requirements.

The licensee

security staff were trained in accordance

with

training and qualification plans

and

implemented security procedures

appropriately (ref.

55 and 56).

The fitness-for-duty program met the

established

policies

and procedures

(ref. 56).

Reduced

inspection in this area is recommended.

5.4.3

Emergency

Preparedness

The emergency

plan

and implementing procedures

were,

in general,

being

effectively implemented (ref. 57).

Procedures

have

been revised to eliminate

redundant

or. unnecessary

information and steps (ref. 57).

The licensee

revised the emergency

action levels

(EALs) to incorporate

the methodology

specified in NUMARC/NESP-007,

"Methodology for Development of Emergency Action

Levels."

Training on the

new EALs including table top exercises

was

considered

useful (ref. 10).

Due to an over sight, the licensee's

quality

assurance

audit for 1994 was not made available to state

and local officials

as required.

It was later provided to them,

and administrative

procedures

were changed to correct this over sight (ref. 57).

Normal inspection in this area is recommended.

17

'I

APPENDIX A

List of References

l.

2.

3.

4.

5.

6.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

18.

19.

20.

21.

22.

23.

24.

25.

26.

27.-

28.

29.

30.

31.

32.

33.

34.

35.

36.

37.

38.

39.

40.

41.

42.

43.

44.

45.

and 50-410/94-27

and 50-410/95-13

and 50-410/95-24

and 50-410/95-12

and 50-410/94-15

and 50-410/95-22

and 50-410/95-11

and 50-410/95-16

50-410/93-99

and 50-410/95-01

and 50-410/94-23

and 50-410/95-23

and 50-410/95-18

and 50-410/94-29

and 50-410/94-11

and 50-410/95-80

and 50-410/95-03

and 50'-410/94-18

and 50-410/94-05

and 50-410/94-06

and 50-410/95-02

and 50-410/94-31

and 50-410/94-07

and 50-.410/94-20

and 50-410/94-05

and 50-410/94-22

and 50-410/94/14

and 50-410/94-32

A-1

NRC Inspection

Reports

50-220/94-23

NRC Inspection

Reports

50-220/95-13

NRC Inspection

Reports

50-220/95-24

NRC Inspection

Report 50-410/95-07

NRC Inspection

Reports

50-220/95-12

NRC Inspection

Reports

50-220/94-13

NRC Inspection

Reports

50-220/95-22

NRC Inspection

Reports

50-220/95-11

NMPC NgA Audit No.

94017

NRC Inspection

Reports

50-220/95-16

NRC SALP Report

No. 50-220/93/99

and

NRC Inspection

Reports

50-220/95-01

NRC Inspection

Reports

50-220/94-21

NRC Inspection

Reports

50-220/95-23'RC

Inspection

Reports

50-220/95-18

NRC Inspection

Reports

50-220/94-26

NRC Inspection

Report 50-410/94-26

Unit

1 Licensee

Event Report 95-001

Unit 2 Licensee

Event Report 95-004

Unit 2 Licensee

Event Report 94-007

NRC Inspection

Reports

50-220/94-09

NRC Inspection

Reports

50-220/95-80

NRC Inspection

Reports

50-220/95-03

NRC Inspection

Reports

50-220/94-16

NRC Inspection

Reports

50-220/94-05

Unit 2 Licensee

Event Report 94-006

NRC Inspection

Report 50-220/94-25

NRC Inspection

Report 50-410/94-10

NRC Inspection

Reports

50-220/94-06

NRC Inspection

Reports

50-220/95-.02

NRC Inspection

Reports

50-220/94-28

NRC Inspection

Reports

50-220/94-07

Unit

1 Licensee

Event Report 94-006

Unit 2 Licensee

Event Report 95-011

NRC Inspection

Reports

50-220/94-18

NMPC

ISEG Report

No. 89461

NMPC ISEG Report

No. 89479

NRC Inspection

Report 50-220/95-09

.

NRC Inspection

Reports

50-220/94-05

NRC Inspection

Reports

50-220/94-20

Unit

1

LER 94-007

NRC Inspection

Reports

50-220/94-12

Unit 2 Licensee

Event Report 94-003

NRC Inspection

Reports

50-220/94-29

NMPC

ISEG Report

No. 89476

46.

Unit 2 Licensee

Event Report 95-009

47.

Unit

1 Licensee

Event Report 94-004

48.

Unit

1 Licensee

Event Report 95-002

49.

NRC Inspection

Report 50-410/94-09

50.

Unit 2 Licensee

Event Report 95-002

51.

NRC Inspection

Reports

50-220/95-10

52.

NRC Inspection

Reports

50-'220/95-04

53.

NRC Inspection

Reports .50-220/95-08

54.

NRC Inspection .Reports

50-220/94-11

55.

NRC Inspection

Reports

50-220/94-'01

56.

NRC Inspection

Reports 50-220/95-14

57.

NRC Inspection. Reports

50-. 220/94-15

58.

NRC Inspection

Reports

50-220/95-20

59.

NRC Inspection

Reports

50-.220/94-04

60.

NRC Inspection

Reports

50-220/94-19

61.

NMPC NgA Audit No.95010

62.

. NRC Inspection

Reports

50-220/94-17

63.

NRC Inspection

Reports

50-220/94-27

64.

Licensee

Event Report

94-.SOI

65.

NRC Inspection

Reports

50-220/95-17

66.

NRC Inspection

Reports

50-220/94-08

67.

NRC Inspection

Reports

50-220/94-24

68.

NMPC NgA Audit No. 95017

69.

NRC Inspection

Reports

50-220/94-16

and 50-410/95-10

and 50-410/95-04

and 50-410/95-08

and 50-410/94-13

and 50-410/94-01

and 50-410/95-14

and 50-410/94-17

and 50-410/95-20

and 50-410/94-04

and 50-410/94-21

and 50-410/94-19

and 50-410/94-30

and 50-410/95-17

and 50-410/94-08

and 50-410/94-28

and 50-410/94-18

A-2

NINE MILE POIN

UNITS

1 AND 2

PRELIMINARYPERFORMANCE ASSESSMENT/INSPECTION PLANNING TREE

1.0

SAFETY

ASSESSMENT/

CORRECTIVE

ACTION

2.0

OPERATIONS

3.0

ENGINEERING

4.0

MAINTENANCE

5.0

PLANT

SUPPORT

SAFETY FOCUS

3.1

SAFETY FOCUS

SAFETY FOCUS

5.1

SAFETY FOCUS

1.2

PROBLEM

IDENTIFICATION

2.2

PROBLEM

IDENTIFICATION Y

PROBLEM

RESOLUTION

Y

3.2

PROBLEM

IDENTIFICATION N

PROBLEM

RESOLUTION

N

PROBLEM

IDENTIFICATION Y

PROBLEM

RESOLUTION

RC

SEC

EP

G

G

N

5.2

PROBLEM

IDENTIFICATION

PROBLEM

RESOLUTION

PROBLEM

ANALYSIS

AND

EVALUATION

Y

QUALITY OF

OPERATIONS

3.3

QUALITY OF

ENGINEERING

WORK

EQUIP PERF/

MATL COND

RC

SEC

EP

G

G

N

QUALITY OF

1.3

PROBLEM

RESOLUTION

2.4

PROGRAMS

AND

PROCEDURES

Y

3.4

PROGRAMS

AND

PROCEDURES

Y

4.4

QUALITY OF

MAINTENANCE

WORK

RC

SEC

EP

N

N

B

O

REDUCED

INSPECTION

O

MAINTAIN

INSPECTION

O

INCREASED

INSPECTION

O

INDETERMINATE-MORE

INSPECTION REQUIRED

4.5

PROGRAMS

AND

PROCEDURES

Y

5.4

PROG & PROC

RC

SEC

EP

G

G

N

f'