Plan for the 2017 Selective Leaching of Aluminum Bronze Aging Management Program Regulatory Audit Regarding the South Texas Project, Units 1 and 2, License Renewal Application Review(Cac Nos. ME4936 and ME4937)
ML17017A148
Person / Time
Site: South Texas  STP Nuclear Operating Company icon.png
Issue date: 01/24/2017
From: Lois James
License Renewal Projects Branch 1
To: Gerry Powell
South Texas
Lois James, 301-415-3306
References
CAC ME4936, CAC ME4937
Download: ML17017A148 (7)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 24, 2017 Mr. G.T. Powell Site Vice President STP Nuclear Operating Company P.O. Box 289 Wadsworth, TX 77483

SUBJECT:

PLAN FOR THE 2017 SELECTIVE LEACHING OF ALUMINUM BRONZE AGING MANAGEMENT PROGRAM REGULATORY AUDIT REGARDING THE SOUTH TEXAS PROJECT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION REVIEW (CAC NOS. ME4936 AND ME4937)

Dear Mr. Powell:

By letter dated October 25, 2010, South Texas Project (STP) Nuclear Operating Company (STPNOC or the applicant) submitted an application for renewal of operating licenses NPF-76 and NPF-80 for STP, Units 1 and 2. The staff of the U.S. Nuclear Regulatory Commission (NRC or the staff) is reviewing this application in accordance with the guidance in NUREG-1800, Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants.

The staff plans to conduct a follow-up regulatory audit of your Selective Leaching of Aluminum Bronze Aging Management Program and associated issues from January 20, 2017, through March 3, 2017, in accordance with the enclosed regulatory audit plan. This audit may include onsite reviews, offsite reviews and in-office reviews. If you have any questions, please contact me by telephone at 301-415-3306 or by e-mail at lois.james@nrc.gov.

Sincerely,

/RA/

Lois M. James, Senior Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-498 and 50-499

Enclosure:

As stated cc w/encl: Listserv

Mr. G.T. Powell Site Vice President STP Nuclear Operating Company P.O. Box 289 Wadsworth, TX 77483

SUBJECT:

PLAN FOR THE 2017 SELECTIVE LEACHING OF ALUMINUM BRONZE AGING MANAGEMENT PROGRAM REGULATORY AUDIT REGARDING THE SOUTH TEXAS PROJECT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION REVIEW (CAC NOS. ME4936 AND ME4937)

Dear Mr. Powell:

By letter dated October 25, 2010, South Texas Project (STP) Nuclear Operating Company (STPNOC or the applicant) submitted an application for renewal of operating licenses NPF-76 and NPF-80 for STP, Units 1 and 2. The staff of the U.S. Nuclear Regulatory Commission (NRC or the staff) is reviewing this application in accordance with the guidance in NUREG-1800, Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants.

The staff plans to conduct a follow-up regulatory audit of your Selective Leaching of Aluminum Bronze Aging Management Program and associated issues from January 20, 2017, through March 3, 2017, in accordance with the enclosed regulatory audit plan. This audit may include onsite reviews, offsite reviews and in-office reviews. If you have any questions, please contact me by telephone at 301-415-3306 or by e-mail at lois.james@nrc.gov.

Sincerely,

/RA/

Lois M. James, Senior Project Manager Projects Branch 1 Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-498 and 50-499

Enclosure:

As stated cc w/encl: Listserv DISTRIBUTION:

See next page ADAMS Accession No.: ML17017A148 *Concurred via email OFFICE LA:RPB1:DLR PM:DLR/RPB1 PM:DLR/RARB PM:DLR/RARB NAME YEdmonds* LJames WHolston DMorey DATE 1/23/2017 1/23/2017 1/10/2017 1/23/2017

OFFICE BC:DLR/RPB1 PM:DLR/RPB1 NAME RChazell (a) LJames DATE 1/24/2017 1/24/2017 OFFICIAL RECORD COPY

Letter to G.T. Powell from Lois M. James dated January 24, 2017

SUBJECT:

PLAN FOR THE 2017 SELECTIVE LEACHING OF ALUMINUM-BRONZE AGING MANAGEMENT PROGRAM REGULATORY AUDIT REGARDING THE SOUTH TEXAS PROJECT, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION REVIEW (CAC NOS. ME4936 AND ME4937)

DISTRIBUTION:

E-MAIL:

PUBLIC RidsNrrDlr Resource RidsNrrDlrRpb1 Resource RidsNrrDlrRerp Resource RidsNrrDlrRsrg Resource RidsNrrPMSouthTexasProject Resource RidsOgcMailCenter


LJames, DLR RChazell, DLR TTran, DLR JRikhoff, DLR DMcIntyre, OPA LRegner, DORL NTaylor, RIV SMoney, RIV ASanchez, RIV NHernandez, RIV WMaier, RIV VDricks, RIV GPick, RIV SGraves, RIV GWerner, RIV ajaldridge@STPEGS.COM, STP rjgonzales@STPEGS.COM, STP lsterling@STPEGS.COM, STP mpmurray@STPEGS.COM, STP gtpowell@STPEGS.COM, STP

Audit Plan 2017 Follow-up Audit on Selective Leaching of Aluminum Bronze Aging Management Program for the South Texas Project, Units 1 and 2 License Renewal Application January 23, 2017 - March 3, 2017 Division of License Renewal Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission ENCLOSURE

License Renewal Aging Management Program Audit Plan Selective Leaching of Aluminum Bronze Aging Management Program South Texas Project

1. Background

By letter dated October 25, 2010, South Texas Project (STP) Nuclear Operating Company (STPNOC), submitted to the U.S. Nuclear Regulatory Commission (NRC or the staff) its application for renewal of Operating License Nos. NPF-76 and NPF-80 for STP or applicant, Units 1 and 2, respectively. The applicant requested renewal of the operating licenses for an additional 20 years beyond the 40-year current license terms, which expire on August 20, 2027, for Unit 1 and December 15, 2028, for Unit 2. The staff from the Division of License Renewal (DLR) and the Division of Engineering (DE) in the Office of Nuclear Reactor Regulation (NRR) will conduct a follow-up regulatory audit to gain a better understanding of the Time of Flight Defraction Technique (TOFD) Ultrasonic Testing (UT) Examination that will be used to conduct the extent of condition following the failure of a structural integrity analysis as part of the applicants Selective Leaching of Aluminum Bronze Aging Management Program (AMP), also referred to as Aluminum Bronze AMP. The TOFD UT Examination was initially discussed during the January 4, 2017, public teleconference (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML17005A104) and provided in the applicants response dated January 12, 2017, to the staffs December 5, 2016, request for additional information (RAI) regarding the Aluminum Bronze AMP. The audit will support review of the AMP B2.1.37, "Selective Leaching of Aluminum Bronze" and associated aging management reviews, bases, and documentation as applicable.

2. Regulatory Audit Bases License renewal requirements are specified in Title 10 of the Code of Federal Regulations (10 CFR), Part 54 (10 CFR Part 54), Requirements for Renewal of Operating Licenses for Nuclear Power Plants. Guidance is provided in NUREG-1800, Revision 2, Standard Review Plan for Review of License Renewal Applications for Nuclear Power Plants (SRP-LR), dated December 2010, and in NUREG-1801, Revision 2, Generic Aging Lessons Learned (GALL)

Report, dated December 2010.

3. Regulatory Audit Scope and Methodology The scope of this audit is to gain a better understanding of the TOFD UT Examination that will be used to conduct the extent of condition following the failure of a structural integrity analysis as part of the applicants Aluminum Bronze AMP. This audit will focus on the technical, analytical, and validation basis for the TOFD UT methodologys ability to identify and characterize aluminum bronze leaching. Results of this audit will be ultimately documented in the staffs SER.

During this audit, the staff will utilize the following scope as a guide. The staff may also examine the applicants program basis documents and related references for this AMP, review background calculations and evaluations as needed, and interview applicant representatives to obtain additional clarification related to the AMP.

SCOPE OF AUDIT

1. Review technical basis and validation methodology for the Time of Flight Defraction Technique (TOFD) to ensure that the staff understands the technique, the capability, and the applicability of this methodology to identifying aluminum bronze leaching, including but not limited to:
a. The Low Rigor level qualification in accordance with Section V, Article 14 of the 2004 Edition of the American Society of Mechanical Engineers (ASME), Boiler and Pressure Vessel Code (BPVC)
b. Confidence Level used to determine the sample size of welds subject to TOFD UT Examination
2. Review the personnel qualification for conducting the TOFD tests and assessing TOFD test results.
3. Review STPs criteria for determining when buried pipe inspections will be conducted subsequent to finding a weld that did not meet structural integrity requirements
4. Information and Other Material Necessary for the Regulatory Audit The project team will review the available information and supporting documentation, as well as the license renewal application (LRA) and other AMP-related basis documents, as appropriate.
5. Special Requests The staff emphasizes that, for a successful outcome, the applicant should make every effort to have available: (a) copies of relevant materials; (b) management; and (c) technical personnel with expertise in the TOFD UT Examination.
6. Team Assignments NRC Staff participation is projected as follows (some deletions, additions or substitutions may occur on an as-needed basis). Site access may be requested; however unescorted access is not expected to be necessary as long as the meeting place is outside of the protected area fence.

Area of Review Assigned Auditor Project Manager Lois M. James, DLR Technical Lead William Holston, DLR Technical Reviewer Stephen Cumblidge, DE Technical Reviewer Chris Hovanec, DE Technical Reviewer Carol Nove, DE

7. Logistics The parts of this audit may be conducted on location at the STP site, with rooms and space to be supplied by STPNOC, on location at STP supplied offices in the Rockville, Maryland, area, or in-office at the NRC Headquarters offices in Rockville, Maryland.
8. Deliverables RAI(s) may be issued as deemed necessary by the staff.

An audit summary report will be issued to the applicant, normally within 90 days from the end of the audit. Final evaluation of the Aluminum Bronze AMP as applied to the pipe-to-pipe welds and related issues will be presented in the staffs SER for the STP license renewal application.