MONTHYEARML16172A0192016-07-25025 July 2016 STP Aluminum Bronze Selective Leaching Public Meeting - June 21, 2016 Project stage: Meeting ML16218A3672016-08-30030 August 2016 Summary of Public Teleconference Meeting with STP Nuclear Operating Company Discussing Revisions to License Renewal Application Aluminum Bronze Selective Leaching Aging Management Program and Background Document Project stage: Meeting ML16340A1022016-12-0505 December 2016 Requests for Additional Information for the Review of the South Texas Project License Renewal Application Project stage: RAI ML16343A0422016-12-0808 December 2016 Request for Additional Information for the Review of the South Texas Project, Units 1 and 2 License Renewal Application Project stage: RAI ML17017A1482017-01-24024 January 2017 Plan for the 2017 Selective Leaching of Aluminum Bronze Aging Management Program Regulatory Audit Regarding the South Texas Project, Units 1 and 2, License Renewal Application Review Project stage: Other ML17054C3632017-02-0909 February 2017 Revised Response Request for Additional Information for the Review of the South Texas Project License Renewal Application Project stage: Request NOC-AE-17003441, Revised Response Request for Additional Information for the Review of the South Texas Project License Renewal Application2017-02-0909 February 2017 Revised Response Request for Additional Information for the Review of the South Texas Project License Renewal Application Project stage: Request ML17068A2532017-03-23023 March 2017 Extend Timeframe for the 2017 Selective Leaching of Aluminum Bronze AMP Regulatory Audit Regarding the South Texas Project, Units 1 and 2, License Renewal Application Review Project stage: Other ML16334A4002017-03-24024 March 2017 Climate Change Review Analysis for South Texas Project, Units 1 and 2 - License Renewal Application Project stage: Other NOC-AE-17003454, Supplement to the License Renewal Application2017-03-30030 March 2017 Supplement to the License Renewal Application Project stage: Supplement ML17102B4152017-03-30030 March 2017 Supplement to the License Renewal Application Project stage: Supplement ML17121A0382017-04-19019 April 2017 Supplement to the License Renewal Application Re Aging Management Programs Project stage: Supplement NOC-AE-17003459, Supplement to the License Renewal Application Re Aging Management Programs2017-04-19019 April 2017 Supplement to the License Renewal Application Re Aging Management Programs Project stage: Supplement ML17123A0692017-05-0202 May 2017 Supplement to the License Renewal Application Project stage: Supplement NOC-AE-17003475, Supplement to the License Renewal Application2017-05-0202 May 2017 Supplement to the License Renewal Application Project stage: Supplement ML17172A0142017-05-0404 May 2017 STP Response to ACRS Questions Project stage: Other ML17107A3192017-05-16016 May 2017 Aluminum Bronze Selective Leaching Aging Management Program Audit Report Regarding the South Texas Project, Units 1 and 2, License Renewal Application Project stage: Other ML17146B2422017-06-0808 June 2017 Final Safety Evaluation Report Related to the License Renewal of South Texas Project, Units 1 and 2 - Volume 1 Project stage: Approval ML17142A2642017-06-0808 June 2017 Safety Evaluation Report Related to the License Renewal of South Texas Project, Units 1 and 2 Project stage: Approval ML17146B2242017-06-0808 June 2017 Final Safety Evaluation Report Related to the License Renewal of South Texas Project, Units 1 and 2 - Volume 2 Project stage: Approval ML17138A2762017-09-19019 September 2017 License Renewal Record of Decision Project stage: Other ML17191B1372017-09-28028 September 2017 Renewed Facility Operating License NPF-76 Project stage: Other ML17192A0182017-09-28028 September 2017 Renewed Facility Operating License and Appendices NPF-80 Project stage: Other ML17146B1672017-09-28028 September 2017 FRN for Issuance of the Renewed Operating Licenses for South Texas Project, Units 1 and 2 Project stage: Approval ML17146B0782017-09-28028 September 2017 Issuance of Renewed Facility Operating License Nos. NPF-76 and NPF-80 for South Texas Project, Units 1 and 2 Project stage: Approval 2017-03-24
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 June 8, 2017 Mr. G. T. Powell Site Vice President South Texas Project, Units 1 and 2 STP Nuclear Operating Company P. O. Box 289 Wadsworth, TX 77483
SUBJECT:
SAFETY EVALUATION REPORT RELATED TO THE LICENSE RENEWAL OF SOUTH TEXAS PROJECT, UNITS 1 AND 2 (CAC NOS. ME4936 AND ME4937)
Dear Mr. Powell:
By letter dated October 28, 2010, South Texas Project Nuclear Operating Company (the applicant) submitted a license renewal application (LRA) pursuant to Title 10 of the Code of Federal Regulations Part 54, to renew operating licenses NPF-76 and NPF-80 for South Texas Project (STP), Units 1 and 2, respectively for review by the U.S. Nuclear Regulatory Commission (the staff). The staff determined that the LRA was complete and acceptable for docketing on January 13, 2011.
Since that time, the staff has reviewed the STP LRA, performed onsite audits, in-office audits, and inspections, issued requests for additional information (RAIs), reviewed the applicants responses to the RAIs, developed a safety evaluation report (SER) with open items dated October 14, 2016, and subsequently met with the Advisory Committee on Reactor Safeguards (ACRS) Subcommittee on Plant License Renewal on November 17, 2016. The staff has closed the open items and has developed the enclosed SER (ADAMS Accession No. ML17146B242 for Volume 1 and No. ML17146B224 for Volume 2) to document its findings associated with the safety review of the LRA and supporting documentation for STP.
This SER is scheduled to be discussed with the ACRS Full Committee on July 12, 2017. If you have any questions regarding this matter, please contact the license renewal senior project manager, Ms. Lois M. James, at 301-415-3306 or by e-mail at Lois.James@nrc.gov.
Sincerely,
/RA/ JDonoghue for/
George A. Wilson, Jr., Director Division of License Renewal Office of Nuclear Reactor Regulation Docket Nos. 50-498 and 50-499
Enclosure:
As stated cc w/encl: Listserv
ML17142A263 (Package), ML17142A264 (Letter),
ML17146B242 (Safety Evaluation Report - Volume 1), ML17146B224 (Safety Evaluation Report - Volume 2)
- concurrence via e-mail OFFICE LA:RPB1:DLR Tech Editor (SER)*
PM:DLR:RPGB BC:DLR: RPGB BC:DLR:RARB NAME YEdmonds*
Idoneous Consulting LJames SSthuchell* on letter RChazell* on FM, Sect 1 & 2, & Vol 2 SBloom* on Sect 3 DMorey*
DATE 5/30/17 6/8/17 5/22/2017 5/31/2017 4/27/2017 OFFICE BC:DLR:RASB BC:DE:EMCB BC:DE:EEEB BC:DE:ENPB SLS:DLR NAME BWittick*
BRogers* on Sects.2 & 3 ABuford* on Sect. 4 JQuichocho KHsu* for JZimmerman*
DAlley*
AHiser DATE 5/22/2018 12/15/2016 12/19/2016 12/07/2016 5/26/2017 OFFICE BC:DRA:AFPB BC:DSS:SBPB BC:DSS:SRXB D:DE D:DSS NAME GCasto*
RDennig*
EOesterle*
JLubinski KCoyne* for Shelton* (A)
DATE 12/9/2016 5/22/2017 12/9/2016 4/28/2017 5/24/2017 OFFICE D:DRA OGC (NLO)
D:DLR NAME JGiitter*
MYoung GWilson (JDonoghue) for DATE 4/25/2017 6/6/2017 6/8/2017