ML16341F634

From kanterella
Jump to navigation Jump to search
Initial SALP Repts 50-275/89-32 & 50-323/89-32 for Aug 1988 - Dec 1989
ML16341F634
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 03/13/1990
From:
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML16341F633 List:
References
50-275-89-32, 50-323-89-32, NUDOCS 9003300035
Download: ML16341F634 (76)


See also: IR 05000275/1989032

Text

INITIALSALP BOARD REPORT

U.

S.

NUCLEAR REGULATORY COMMISSION

REGION V

SYSTEMATIC ASSESSMENT

OF

LICENSEE

PERFORMANCE

50-275/89-32

AND 50-323/89-32

PACIFIC GAS

AND ELECTRIC COMPANY

DIABLO CANYON NUCLEAR POWER

PLANT

AUGUST 1, 1988

THROUGH DECEMBER 31,

1989

0

TABLE OF

CONTENTS

I.

Introduction

II.

Summary of Results

A.

Overview

B.

Results of Board Assessment

C.

,Changes

in SALP Ratings

III. Criteria

IV.

Performance

Analysis

~Pa

e

A.

B.

C.

D.

E.

F.

G.

Plant Operations

Radiological Controls

Maintenance/Surveillance

Emergency

Preparedness

Security

Engineering/Technical

Support

Safety Assessment/equality

Verification

7

9

12

14

17

20

Y.

Supporting Data and Summaries

A.

B.

C.

D.

E.

F.

Licensee Activities

Direct Inspection

and Review Activities

Enforcement Activity

Confirmation of Action Letters

AEOD Events Analysis

OI Status

24

24

25

25

25

25

TABLES

Table 1 - Inspection Activities and Enforcement

Summary

Table

2 - Enforcement

Items

Table

3 - Synopsis of Licensee

Event Reports

Attachment

1 - The Office for Analysis and Evaluation of Operational

Data

Input to SALP Review

0

INTRODUCTION

The Systematic

Assessment

of Licensee

Performance

(SALP) program is an

integrated

NRC staff effort to collect available observations

and data

on

a periodic basis

and evaluate

the licensee's

performance

based

on this

information.

The program is supplemental

to normal regulatory processes

used to ensure

compliance with NRC rules

and regulations.

It is intended

to be sufficiently diagnostic to provide

a rational basis for allocating

NRC resources

and to provide meaningful

feedback to the licensee's

management

regarding the NRC's assessment

of their facility's performance

in each funct)onal area.

An NRC.SALP Board,

composed of the members listed below, met on February

15, 1990, to review the observations

and data

on performance in

accordance

with NRC Manual Chapter 0516, "Systematic

Assessment

of

Licensee

Performance."

The guidance

and evaluation criteria are

summarized in Section III.ofthis report.

The Board's findings and

recommendations

were forwarded to the

NRC Regional Administrator for

approval

and issuance.

This report is NRC's

SALP Board assessment

of the licensee's

safety

performance at the Diablo Canyon Nuclear

Power Plant, for the period

August 1, 1988 through December

31, 1989.

The

SALP Board for Diablo Canyon

was composed of:

R.

P.. Zimmerman, Director, Division of Reactor Safety and Projects

(Board Chairman)

R.

A. Scarano,

Director, Division of. Radiation Safety

and Safeguards

A.

E. Chaffee,

Deputy Director, Division of Reactor Safety

and Projects

S.

A. Richards,

Chief, Reactor Projects

Branch

C.

M. Trammell, Acting Director, Project Directorate

V,

NRR

H.

Rood,

NRR Project Manager

D: F. Kirsch, Chief, Reactor Safety Branch

M.

M, Mendonca,

Chief, Reactor Projects

Section

1

P.

P. Narbut, Senior Resident Inspector

Summar

of Results

A.

Overview

The Board found that the licensee

made notable progress

on a number

of issues

and programs

discussed

in last year's

SALP report.

Specifically:

.The licensee initiated efforts to reduce engineering errors

and

to improve their overall performance

in this area.

Licensee

engineering initiatives included

commencement

of a design basis

document reconstruction effort; continuing development of the

onsite engineering

program;

and the improvement of the

interface

between

the corporate

engineering staff and the site

staff.

I

0

2

o

The number of events related to procedural

compliance

and

communication

issues

have declined considerably.

o

guality Assurance

has successfully

implemented

improved

performance

based audit programs in the areas of system design,

design

changes

and

NSSS services.

The improved programs

produced meaningful

indepth technical findings.

In the above areas,

the licensee generally demonstrated

a solid

commitment to address

problems with adequate

resources

and

conservative

approaches.

However, the

SALP, Board,

as in the previous

SALP period,

found the

licensee's

identification of some problems

and the implementation of

corrective actions to often be slow.

For these

problems continual

attention from the

NRC appeared

to be required

such that the

licensee

recognized the problem,

reviewed the problem in a

comprehensive

manner,

and initiated meaningful corrective action.

Examples

discussed

in the report included problems with valve lineup

errors

and excessive

overtime usage.

At the root of this issue

seemed to be

a lack of problem ownership.

Mhereas

problems limited to,a single department

were usually

addressed

in a timely way, it appeared

that managers

and staff were

reluctant to take ownership of problems which involved multiple

departments'herefore,

the Board recommends

continued

management

attention to ensuring that direct responsibility for addressing

any

given problem is promptly identified,

and then ensuring that timely

action is initiated to address

the problem area.

Three

NRC inspections,

which occurred after the

SALP period,

were

considered

by the

SALP Board.

The first was

a security inspection

which identified several

problem areas,

the second inspection

was

a

team inspection of corrective action programs,

and the third was

a

routi.ne emergency

preparedness

inspection.

Results of Board Assessment

Overall, the

SALP Board found the performance of NRC licensed

activities by the licensee to be acceptable

and directed toward safe

operation.

The

SALP Board has

made specific recommendations

in most

functional areas for licensee

management

consideration.

The results

of the Board's

assessment

of the licensee's

performance

in each

functional area,

including the previous

assessments,

are

as follows:

Functional

Area

Rating

Last

Period

Rating

This

Period

Trende

A.

Plant Operations

B.

Radiological Controls

C.

Maintenance/Surveillance

D.

Emergency

Preparedness

Improving

0

E.

F.

G.

H.

Security

2

Engineering/Technical

Support

2

Safety Assessment/equality

2

Verification

Fire Protection

1

Improving

Improving

Improving

(No longer rated

separately)

The trend indicates

the

SALP Board's appraisal

of the

licensee's

direction of performance

in a functional area

such

that continuation of this trend may result in a change in

performance level.

Determination of the performance

trend is

made selectively

and is reserved for those

instances

when it is

necessary

to focus

NRC and licensee attention

on an area with a

declining performance trend, or to acknowledge

an improving

trend in licensee

performance.

It is not necessarily

a

comparison of performance

during the current period with the

previous period.

C.

Chan

es in SALP Ratin

s

The changes

to the

SALP ratings from the previous

SALP period were

a

Category

1 performance

in Operations

and improving trends in

Maintenance/Surveillance,

Security, Engineering/Technical

Support,

and Safety Assessment/equality

Verification.

The previous rating in the Operations

functional area

had been

a

Category

2 with an improving trend.

The Board determined that the

generally conservative

responses

by Operations

personnel

outweighed

concerns

in this area regarding

instances

of weak management

oversight

and slow problem identification and resolution,

such

as

the continuing problems

observed with valve alignments.

The improving trends in the previously mentioned functional areas

were primarily due to extensive

licensee

resources

applied in these

areas.

III. CRITERIA

Licensee

performance is assessed

in selected

functional areas,

depending

on whether the facility is in a construction or operational

phase.

Functional

areas

normally represent

areas significant to nuclear safety

and

the=- environment.

Some functional areas

may not be assessed

because

of little or no licensee activities or lack of meaningful observations.

Special

areas

may be added to highlight significant observations.

The following evaluation criteria were used,

as applicable to assess

each

functional area:

1.

Assurance

of quality, including management

involvement and control;

2.

Approach to the resolution of technical

issues

from a safety

standpoint;

3.

Responsiveness

to

NRC initiatives;

k

4.

Enforcement history;

5.

Operational

and construction

events (including response to, analyses

of, reporting of, and corrective actions for);

6.

Staffing (including management);

and

7.

Effectiveness

of the training and qualification program.

However, the

NRC is not limited to these criteria and others

may have

been

used where appropriate.

On the basis of the

NRC assessment,

each functional area evaluated is

rated according to three performance

categories.

The definitions of

these

performance

categories

are

as follows:

1.

Cate or

1.

Licensee

management 'attention

and involvement are

rea

1 y evident

and place

emphasis

on superior performance of

nuclear safety or safeguards

activities, with the resulting

erformance substantially

exceeding regulatory requirements.

icensee

resources

are

ample

and effectively used

so that

a high

level of plant and personnel

performance is being achieved.

Reduced

NRC attention

may be appropriate.

2.

Cate or

2.

Licensee

management

attention to and. involvement in the

per ormance of nuclear safety

or safeguards

activities are good.

The licensee

has attained

a level of performance

above that needed

to meet regulatory requirements.

Licensee

resources

are adequate

and reasonably

allocated

so that good plant and personnel

performance

is being achieved.

NRC attention

may be, maintained at

normal levels.

3.

Cate

or

3.

Licensee

management

attention to and involvement in the

per ormance of nuclear safety or safeguards

activities are not

sufficient.

The licensee

s performance

does not significantly

exceed that needed to meet minimal regulatory requirements.

Licensee

resources

appear to be strained or not effectively used.

NRC attention

should be increased

above

normal levels.

IV.

PERFORMANCE ANALYSIS

The following is the Board's

assessment

of the licensee's

performance

in

each of the functional areas,

plus the Board's conclusions for each area

and its recommendations

with respect to licensee

actions

and management

emphasis.

A.

~PP tt

tt

1.

~Anal sis

During the assessment

period, the licensee's

plant operations

activities were observed routinely by both the resident inspectors

and the regional staff.

Additionally, in December

1989,

a team

inspection

was conducted to review emergency operating procedures

k

(EOPs).

A total of more than 1600 hours0.0185 days <br />0.444 hours <br />0.00265 weeks <br />6.088e-4 months <br /> of inspection effort was

devoted to this functional area..

The licensee's

performance in this functional area during the

previous

SALP period was rated

as Category 2, improving trend.

Prominent issues of the previous

SALP requiring attention in this

functional area included the effectiveness

of management

feedback

mechanisms,

the continued

need for emphasis

in communications

and

procedural

compliance,

and the slow movement towards establishing

formal root cause

reviews for appropriate

operational

events.

In

general,

the licensee's

efforts to address

these

issues

have

been

successful,

as discussed

below.

One remaining concern,

however, is

the licensee's

occasional

apparent inability to recognize

and

address

issues

in a timely manner.

During this

SALP period,

few significant operational

events

were

attributable to causes

relevant to this functional area.

In 1989,

Unit 1 completed

a record

399 day run,

and both Units 1 and

2 each

experienced

only one automatic trip.

The Unit 1 trip, which could

not have

been foreseen,

occurred

when work was authorized

on

instrumentation

which shared

a process

line with a plant protection

channel.

A contributory factor in the Unit 2 automatic trip, was

the unavailability of a circulating water

pump due to an equipment

alignment problem.

Unit 2 operators initiated three

manual reactor trips in 1989, which were conservative

responses

to abnormal plant

conditions

such

as condenser salt water intrusions.

Additionally,

it was noted that the licensee initiated comprehensive

data

gathering efforts to identify the root cause of the more significant

events.

Very early in the

SALP period, the facility experienced

three additional automatic plant trips.

A significant management

problem which developed during this rating

period was the lack of timely corrective action taken to address

repeated

valve and equipment lineup problems.

The valve lineup

problems contributed to one unplanned reactor trip, several

engineered

safety features

actuations,

and inoperable

instrumentation.

The equipment lineup problems resulted in the

issuance

of an escalated

enforcement, action and civil penalty.

Although subsequent

corrective actions

were extensive,

valve and

equipment lineup problems continued throughout the rating period.

At the end of the period, Operations

Management

was in the process

of reassessing

the equipment alignment program.

The licensee's

approach to the resolution of technical

issues

was

generally conservative with approaches

viable and generally

sound

and thorough.

This was evidenced

by the conservative

action to

shutdown Unit 2 to repair

a leaking pressurizer

safety .valve,

and by

the fact that the licensee

has

been at the forefront of safety valve

problem reviews and testing.

Also, the licensee's fire protection

enhancements

have

been well beyond

NRC minimum requirements,

e. g.,

the

use of the Plant Information Management

System to manage fire

barriers

and system configuration control.

Other examples of

conservative

actions

included rapid operator

assessments

on three

separate

occasions

of abnormal plant conditions,

and the appropriate

0

initiation of manual reactor trips of Unit 2,in each instance.

However, operations

personnel

have not responded

conservatively

nor

displayed appropriate instincts in all instances.

For example,

during the Unit 1 refueling outage,

fuel handling building radiation

alarms were not properly responded to by operations

personnel,

which

resulted in a violation included in the radiological controls

functional area.

The licensee is generally responsive to

NRC initiatives.

As an

example,

the

EOP inspection

observed that the licensee

was

self-critical and committed to improvements in that area.

Also, the

issues of communications

and procedural

compliance,

which have

been

discussed

in the last two SALP reports,

did not contribute

significantly to plant events.

However, the major issue

and

NRC

initiative of the last SALP, the need for timely problem recognition

and the initiation of corrective actions,

remains

a concern.

During the assessment

period there were two enforcement actions,

one

Severity Level III violation and one Severity Level IV violation,

and

18

LERs in the operations

area.

Additionally, although

enforcement action was not taken until after the end of the

SALP

period,

other',.escalated

enforcement actions

were identified during

the

SALP period, which involved: (1) the failure to perform adequate

containment

sump cleanliness

inspections;

and, (2) use of an

unlicensed individual as Shift Supervisor during .the Unit 2

refueling outage.

The importance of successfully'ommunicating

management

expectations

regarding personnel

verifications was

emphasized

at the enforcement

conference for the

sump violation, and

the importance of conservative

management

decisions

was emphasized

with regard to the unlicensed Shift Supervisor violation issue.

kith respect to operations staffing,

key positions were identified

and responsibilities

defined with key vacant positions usually

filled in a reasonable

time.

As previously mentioned,

a notable

exception to the above

was the use,

during the Unit 2 second

refueling outage,

of a management

individual with an expired senior

reactor operator license to fulfillthe then newly established

operations shift supervisor

s position, which normally requires

an

active

SRO license.

While on-shift staffing normally exceeded

regulatory requirements, it was noted during the

EOP team inspection

that a shortage

of office staffing for developing

and maintaining

EOPs

may have contributed to the slow resolution of identified

EOP

problems.

The licensee's

operations training program

was well defined and

implemented with dedicated

resources.

The overall pass

rate

on

qualification exams

was

94K and was considered well above average.

Also, feedback

from the training pro~ram was

used to upgrade

operations

procedures.

The licensee

s training facilities include

a

well maintained plant simulator.

The overall high quality of

operator training was consistently exhibited during not only the

EOP

inspection,

but also during emergency

preparedness

exercises.

Finally, inadequate

training was rarely the cause of plant events.

2.

3.

Performance

Ratin

Performance

Assessment - Category 1.

The

SALP Board deliberated at

length in considering whether

a Category

1 rating was warranted in

this functional area.

The Board ultimately concluded that the

overall performance in this functional area

outweighed concerns

raised primarily by valve alignment problems

and issues

involving

the operability of the containment

sumps.

Board Recommendations

Licensee

management

should focus attention

on ensuring that valve

alignment errors

are minimized and should

be sensitive to promptly

addressing

other developing problem areas,

prior to those problems

causing

a significant event.

Management

should continue to require

that operations

personnel

conduct their duties in a professional

and

conservative

manner.'.

Radiolo ical Controls

~Anal sis

,A total of six routine inspections

were performed in the area of

radiological controls,

examining aspects

of occupational

radiation

safety,

management

and organization,

radiological effluent control

and monitoring, radioactive waste

management,

transportation of

-radioactive materials, training and qualifications, confirmatory

measurements,

and licensee

events.

In addition, the resident

inspectors

provided continuing. observations

in this area.

Approximately 328 hours0.0038 days <br />0.0911 hours <br />5.42328e-4 weeks <br />1.24804e-4 months <br /> of inspection effort were performed in this

functional area.

The licensee's

performance rating in this functional area during the

previous

SALP period was Category 1.

SALP Board recommendations

in

the previous

SALP included assuring

personnel fully understand

ALARA

concepts,

radiological work practices,

and procedural

compliance

requirements.

In general,

the licensee's

efforts to address

these

recommendations

have

been successful,

with additional attention

needed in the management

of outage activities.

During this assessment

period, licensee

management

continued to

exhibit active involvement in the area of chemistry and radiological

controls.

Management

had developed

goals

and performance indicators

in several

areas;

including external

and internal

exposure control,

contamination minimization, material control

and waste reduction,

The staff's

awareness

of management's

goals

and expectations

was

evident.

During this assessment

period, there

was continued

management

support of the chemistry program.

For example,

the licensee

implemented

several

changes

in plant chemistry intended to minimize

crud buildup and corrosion.

These

changes

included:

use of

hydrazine in the secondary

system to scavenge

oxygen and secondary

system

low level boric acid feed to control

steam generator

tube

0

denting.

The licensee

also initiated elevated lithium chemistry in

the reactor coolant to increase

the pH.

These techniques

are

intended to reduce

steam generator

maintenance

and decrease

dose

rates

from reactor coolant system

components.

The licensee's

continued

commitment and support for the

implementation of a strong

and effective radiation protection

rogram was evident during this assessment

period.

As a result of

RC comments during the 1988 Unit 2 refueling outage,

and the

licensee's

internal= evaluation of past performance,

the licensee

completely revised their ALARA program in time to support the 1989

Unit 1 refueling outage.

In addition, the licensee

implemented

some

innovative concepts

which included "High Impact Teams"

(HIT) and

a

Management

Incentive

Program

(MIP) to enhance their ALARA program.

The HIT concept represented

a major commitment of manpower to the

outage planning and preparation

phases

during the Unit 1 refueling

outage.

The MIP provided the licensee's, staff with various types

and

levels of awards for maintaining exposures

at or below the

established

ALARA goals.

The licensee's

overall year to end exposure

for 1989 was approximately

3X less

than the man-rem goals that were

established

by the licensee.

However,

some poor health physics

and

work practices that were apparent

in the previous

outage

were not

effectively corrected during the latest outage.

During the

SALP period, only one Severity Level IV violation was

identified as

compared to the two Severity Level IV violations and

one deviation that were identified during the previous

SALP period.

The violation, previously mentioned in the operations

functional

area,

involved the failure to adequately instruct personnel

upon

receiving

an evacuation

alarm for the Fuel Handling Building Area

Radiation Monitor (ARM), RE-58.

A total of seven

Licensee

Event Reports

(LERs) were received in this

functional area during this

SALP period

The

NRC inspection of these

LERs did not result in any violations.

During this assessment

period, the licensee

continued to demonstrate

management

s involvement in ensuring quality; however, corrective

actions

were not always timely or effective in correcting the root

cause of the problem.

For example,

the untimely and ineffective

resolution of problems associated

with the spent fuel pool radiation

monitor alarms during core off load operations

contributed to a

violation of 10 CFR Part 19. 12, which was previously discussed.

The

licensee

has proposed

a Technical Specification

(TS) change to

increase

the setpoint of this monitor to prevent frequent Engineered

Safety Features

(ESF)

and alarm actuations.

The documentation

developed for the proposed setpoint

changes

was thorough.

Staffing considerations

for normal plant operations

and refueling

outages

were routinely evaluated

by the licensee.

Authorities and

responsibilities of the licensee's

staff were well delineated.

The

staff was highly qualified, with certified health physicists on-site

and at the corporate office. The normal plant staff turnover rate

was low.

A minimum of contractor assistance

was utilized.

Additions

0

2.

to the professional staff during this

SALP period have

added

increased

depth

and scope.

However, staffing of contractor

radiation protection technicians for the Unit 1 refuelinq outage

appeared

to be marginal at the onset of the outage

as evidenced

by

the poor health physics

and work practices that were identified.

The licensee's

training program for the technical staff and for the

radiation protection

and chemistry technicians

was considered

to be

another strength.

An industry accredited training program for

chemistry

and radiation protection technicians

has

been

implemented.

The subjects

addressed

include both refresher

and enrichment topics.

Additionally, the licensee

has set demanding

standards

for contract

technicians

providing assistance

during outages.

Senior radiation

protection technicians

employed for outages

must take

and pass

a 2-4

hour specific knowledge examination.

The licensee

reported that

this practice resulted in an increase

in the quality of the

technicians

sent to the plant.

The licensee

has also implemented

a

five month long, full time, technical staff training program.

This

program includes all aspects

of plant operation.

It is designed to

~

~

~

~

rovide a common base of knowledge to the technical staff.

adiation protection engineering staff members

have

been included in

this program.

Performance

Ratin

3.

Performance

Assessment - Category 1.

Board Recommendation

The licensee is encouraged

to continue the current aggressive

approach

being taken towards

ALARA and to improve the quality of

health physics

and work practices

during outages.

C.

Maintenance/Surveillance

~Ana1 sis

This functional area

was observed routinely during the assessment

period by both the resident

and regional

inspection staff.

Approximately 641 hours0.00742 days <br />0.178 hours <br />0.00106 weeks <br />2.439005e-4 months <br /> of inspection effort were devoted to this

functional area.

Issues

discussed

in the previous

SALP for this

functional area,

which was previously rated

a Category 2, were the

control of the maintenance

backlog, the continuing relatively large

number of personnel

errors,

the adequacy of I8C procedures,

engineering

involvement in plant activities,

and the slow

implementation of lessons

learned.

Management oversight of maintenance activities was generally

effective.

The issues

discussed

in the previous

SALP were not a

significant contributor to plant events during this

SALP period.

An

example of management's

effectiveness

in resolving long standing

problems

was the achievement of "black" control

room annunciator

boards for both Units 1 and 2.

The "outage coordination center"

has

also

been

used

as

an effective management

oversight tool.

The

0

10

concept is simply to make available in one

room all the appropriate

management

personnel

required to make decisions

necessary

to

expedite the resolution of problems during an outage.

The licensee's

survei,llance

program appeared

to be well established

and implemented.

Although several

missed surveillances

were

reported during the

SALP period,

most were either non-routine or

resu]ted

from mis-interpretation of Technical Specification

requirements.

The Inservice Inspection (ISI) program is likewise

well established

and implemented

by a qualified licensee staff.

However, it was noted that management

oversight

was insufficient in

the area of personnel

overtime.

That is, during the Unit 1 outage,

a large

number of plant personnel

working safety-related

jobs,

were

working hours in excess

of those allowed by the Technical

Specifications.

Periodic review of overtime records

by plant

management,

also required by the Technical Specifications,

was not

being accomplished.

The licensee

was not responsive to the

inspector

s findinq, and in the week following the first discussions

of excessive

overtime,

a number of additional

maintenance

personnel

exceeded

overtime restrictions.

Additionally, an effort to

determine

the scope of the overtime problem was not initiated for

three

weeks

and required continuing expressions

of NRC concern.

The licensee's

understanding

of technical

issues .in this functional

area

was generally apparent.

The licensee

has also taken

an

industry lead in a number of issues

related to this functional area.

Examples

include safety valve testing,

the detection of counterfeit

materials,

and the resolution of diesel

generator air start motor

problems.

Additionally, conservatism

was generally exhibited

as

was

the case

when Unit 2 was shut

down to repair

a leaking pressurizer

safety relief valve.

An understanding

of subtle technical

problems

was exhibited by maintenance

personnel

when the environmental

qualification of main steam isolation valve actuation

components

was

questioned.

t~

However,

some

known problems recur before they are effectively

addressed

and resolved.

Representative

of this was the use of

outdated

drawings to perform corrective maintenance

on the Unit 2

turbine driven auxiliary feedwater

pump overspeed

stop valve in

February

1989.

The drawings

had been previously recognized

as being

outdated during maintenance activities in November 1988.

Additionally, following identification by the inspector of a fire

door which had the latch function defeated,

corrective actions did

not preclude

maintenance

personnel

the following week from propping

the

same

door

open with a pair of pliers.

Although the licensee

tends to be slow to address

and respond to

NRC

concerns

and continued

NRC scrutiny is sometimes

necessary

to ensure

that the concerns

are appropriately considered,

responses

are

technically sound

and thorough in almost all cases.

This is

evidenced

by the licensee's

response

to issues

discussed

in the last

SALP period.

Long-standing

issues

which the licensee

had been

slow

to respond to, such

as configuration control,

IEC procedures,

and

11

the need for personnel

to stop in the face of uncertainty,

appeared

to have been well addressed

during this

SALP period.

However, the

licensee

has

been slow to address

some concerns

discussed

durinq

this period.

One example is the issue of plant material condit)on.

Although various aspects

of plant material condition had been

discussed

in a number of inspection reports in the second half of

the

SALP period,

e. g., the condition of -the intake structure

and

components,

the licensee

has not yet defined

a long range program

for dealing with such concerns.

During the

SALP period, the violations attributed to this functional

area

were minor and not repetitive,

and with the notable exception

of the overtime issue,

did not indicate

a programmatic

breakdown.

The licensee

at the start of the

SALP period experienced

a number of

less significant events

which could be attributable to maintenance

and surveillance

personnel

error-related activities.

However,

events

associated

with personnel

error were infrequent during the

second half of the

SALP period, indicating improvements in this

area,

Additionally, events attributable to procedure errors

and

procedure

compliance

were also infrequent.

In general,

the licensee

was adept at handling the root cause investigation of more

significant events

such

as reactor trips.

An example

was the

comprehensive

response

to the Unit 2 condenser

tube

1'eak of July

1989.

However, there were instances

of improperly performed maintenance

and surveillance

on safety-related

equipment.

An example

was the

improper maintenance

of the

AFM pump trip throttle valve.

Similarly, the identification of inadequate

surveillances

of

containment recirculation

sump cleanliness

by NRC inspection

activities highlighted the problem.

These findings indicate

an

increased

need for attention to assure plant design is appropriately

implemented through maintenance

and surveillance activities.

. Staffing issues

discussed

during the previous

SALP period appear to

have

been

addressed.

Specifically, noted

improvements

in

instrumentation

and control procedures,

as well as the achievement

of a "black board" for control

room annunciators

indicate that

attention

has

been placed in these

areas.

However, the need to use

extensive

overtime during outages

appears

to indicate that outage

staffing requirements

need to be reviewed if the licensee

continues

to pursue

ambitious

outage

schedules.

The licensee

maintains

a state of the art training facility for

maintenance

and testing personnel,

which demonstrates

that

management

is dedicated

to providing quality training.

One example

is the simulated solid state protection system

(SSPS).

Prior to

performing sensitive

maintenance activities

on the plant SSPS,

technicians

were able to train on the simulated

system.

Additionally, a diesel

generator similar to those installed in the

plant was purchased

dur>ng this

SALP period and

a training program

is being devised to utilize it.

Inadequate

training has not been

a

0

'12

2.

significant contributing factor to plant events

caused

during

construction,

maintenance

or surveillance

work.

Performance

Ratin

3.

D.

Emer

Performance

Assessment - Category 2, Improving Trend.

Board Recommendation

Management

should review outage activities which precipitated the

need to use extensive

overtime.

Management

should also strive to

improve oversight in the area of problem identification and

resolution with an emphasis

on taking timely action.

Given the

relative age of Diablo Canyon

and the number of problems associated

with plant material condition, plant management

should put

additional effort into addressing

the maintenance

of plant material

condition.

The licensee

should continue to take actions to

strengthen

the maintenance

and operations staffs'nderstanding

of

the plant design,

and the sensitivities of the design to

deficiencies.

An improved understanding

may have prevented

the

operability issues

which occurred regarding the containment

sumps

and the auxiliary feedwater

pump trip valve.

enc

Pre aredness

~Anal sis

The previous

SALP analysis

included several

strengths

and

no

specifi,c weaknesses

associated

with the licensee's

emergency

preparedness

(EP) program.

Management

support of the

EP program

and

-.

the licensee's

conservative

approach to

EP issues

were ident>fied as

strengths.

The licensee

has

been rated

as

a

SALP Category

1

performer during the last four SALP appraisal

periods.

During the

last

SALP appraisal

period, the Board

recommended that the licensee

continue to maintain management

attention to ensure

a high level of

performance in this functional area.

During this

SALP appraisal

period,

Region

V conducted

two routine

inspections

and observed

two annual

EP exercises.

A Region

V Site

Team participated in the 1989 exercise.

The routine inspections

assessed

the operational

status of the

EP program, the licensee's

response

to previous inspection findings and the licensee's

activities involving the onsite

emergency

warning system.

Approximately 270 hours0.00313 days <br />0.075 hours <br />4.464286e-4 weeks <br />1.02735e-4 months <br /> of direct inspection effort were expended

in

the

EP functional area.

Strengths identified during this assessment

period included management

support of the

EP program,

responsiveness

to

NRC initiatives,

and the thoroughness

of the licensee's

corrective actions.

Areas needing

improvement were noted,

such as,

untimely corrective action

and the level of technical

(engineering)

staffing in the Technical

Support Center

(TSC) and Emergency

Operations Facility (EOF).

The TSC/EOF staffing issues

were

identified during the 1989 exercise.

0

13

. The inspections

conducted

during this appraisal

period found

strength in licensee

management

support of the

EP program.

For

example,

management

took aggressive

steps to escalate

corrective

actions after a guality Assurance

(gA) audit report identified the

existence of a long standing, internally identified problem with the

audibility of the site emergency signal.

Licensee

management

also

took immediate,

interim corrective action until the alarm devices

could be installed

and

made operational.

Strength in this area

was

also demonstrated

when the President of the

Company issued

a letter

which communicated

expectations

concerning

emergency

preparedness

training attendance.

In general,

the licensee's

approach to resolution of issues

from a

safety standpoint

was determined to be sound.

There was,

however,

an isolated

example

where the licensee's

corrective actions

were not

considered

.to be timely and the issue could have

had

an effect on

personnel

safety.

This issue also involved the audibility of the

site emergency

signal (i.e., the signal could not be heard in

several

locations

around the site), but in contrast to the strength

identified above,

a weakness

was identified because

the licensee

did

not take correct>ve action until it was identified. by gA,

approximately two years later.

As indicated

above,

licensee

management

was very responsive after the matter was brought to its

attention;

however,

the delay in correcting the matter indicated

that the problem did not get to the appropriate

levels of management

or that the matter was not considered

to be high 'in priority.

Once

. corrective actions

were taken,

they were considered to be thorough

and well thought-out.

A strength

was also identified'ith respect to the licensee's

responsiveness

to

NRC initiatives.

This strength

was demonstrated

when the licensee

responded

to

NRC concerns

about false siren

activations.

The licensee

showed

a sensitivity to the issues

and

initiated prompt, thorough corrective actions to reduce the number

of false activations.

No violations of NRC requirements

or LERs were identified in this

functional area during this assessment

period.

The licensee

had several

opportunities to implement its emergency

plan during this appraisal

period.

The most notable

examples

were

an earthquake

and the arcing in the main generator exciter,

both of

which occurred in October 1989.

The licensee's

response

in each

case

was. timely and in accordance

with procedures.

Notifications to

the offsite authorities

were

made in a timely manner.

The licensee

has continued to maintain

a stable

and effective staff

to implement its

EP program.

An area

needing

improvement,

involving

the emergency

response

staffing,

was identified during the 1989

annual

emergency

exercise.

Observations

made during the exercise

indicated

a need to strengthen

the engineering

support in the

TSC

and

EOF.

l

k

0

14

2.

3.

The inspections

conducted

during this appraisal

period showed that

the licensee's

training and qualification program

has

been

effective.

As stated

above,

the emergency plan has

been

implemented

correctly during real events.

Dose assessment

capabilities

were

assessed

during walkthrough interviews and found to be dependable

and

no major findings were identified during the 1988 and 1989

annual

emergency exercises.

A routine inspection

was conducted

immediately following the end of this

SALP appraisal

period.

The

inspection disclosed that the licensee

had not completed

a report

for a Health Physics drill conducted in April 1989.

The failure to

issue

a timely drill report could affect the licensee's ability to

correct training deficiencies identified during drills.

The

NRC staff has reviewed the changes

made to the Diablo Canyon

emergency

plan during the appraisal

period.

The changes

are

acceptable

and the licensee

continues to meet

NRC requirements.

Performance

Ratin

Performance

Assessment - Category l.

Board Recommendations

The licensee

should ensure that problems related to

EP are corrected

in a timely manner.

Licensee

management

should take the necessary

steps to strengthen

the engineering

support in the

TSC and

EOF,

and

ensure

a high level of EP is maintained

as

a result of management's

continued support.

E.

~Securit

~Anal sis

During this

SALP period Region

V conducted three physical security

inspections

and one material control

and accounting inspection.

Over 220 hours0.00255 days <br />0.0611 hours <br />3.637566e-4 weeks <br />8.371e-5 months <br /> of inspection effort were expended

by regional

safeguards

inspectors.

In addition, the resident inspectors

provided observations

in this area.

The previous

SALP rated the

licensee

a category

2 in the security functional area.

The last two SALP reports

encouraged

licensee

management

to become

more involved and resolve

an identified safety/security

issue

involving radio communication frequencies for security and

operations

personnel.

Last year's

SALP report indicated that the

licensee

was approximately

70K complete with this project.

During

this

SALP period, the licensee

completed modifications to the

security radio communications

equipment to avoid possible

interference with the radio communication

equipment of the Units 1

and

2 operations staff.

The previous

SALP report encouraged

licensee

management

to finalize

their modifications to the protected

area barrier and the perimeter

security alarms at the Intake Structure.

As discussed

below, after

recent redesign,

the licensee

has

completed the installation of

r

~

0

approximately

90X of the protected

area barriers

and associated

security alarms.

The previous

SALP report also encouraged

licensee

management

to minimize the deficiencies

and to improve the image

clarity of their closed circuit television

(CCTV) cameras.

As

discussed

below, this has

been completed.

Overall, for this SALP, the licensee's

security program was

acceptable,

and exceeded

minimum requirements

in the area of

security officer training and satisfied

minimum requirements

in

areas of compensatory

measures,

protected

area barriers

and

detection aids,

and alarm stations.

Mith regard to management

s involvement in assuring quality,

corporate

and plant management

continued to review the operation of

the overall security program.

They have generally

implemented

remedial

measures

to correct deficiencies

and weaknesses

identified

in the course of both internal

and

NRC security inspections.

In May

1989, the licensee

completed the expansion

and remodeling of their

security access

control building.

This improved facility provided

the capability of searching

and processing

personnel

entering the

protected

area -in a more effective and efficient manner,

and

assisted

in reducing the number of security log incidents.

Additionally, during this assessment

period, the licensee

resolved

security concerns identified in an earlier

NRC information notice by

completing modifications to their heating, ventilation and air

conditioning

(HVAC) ducts.

During this assessment

period, the licensee

resolved

long term image

deficiencies with their installed

CCTV cameras.

The additional

management

attention -directed at this issue resulted in changes

that

improved the

image of all required

CCTV cameras

to an acceptable

level.

Additionally, as

a result of a previous enforcement action,

the licensee

erected

new

CCTV cameras

to allow viewing of the entire

protected

area perimeter.

As a result of a November

1987 event,

the licensee

determined that

the electrical

design

1'oad of their security emergency

power supply

system

was inadequate

and initiated action to upgrade the capacity

of this system.

At the end of this

SALP period, the licensee

had

installed the necessary

equipment to complete this project.

This

equipment is scheduled for final acceptance-testing

in early 1990.

During the past five years,

the perimeter security alarms at the

Intake Structure

have

been inoperative

and the licensee

has

continued to provide long term compensatory

measures

at this area.

During this

SALP period, the licensee total.ly redesigned

the

placement of the protected

area barriers

and required security

alarms at the Intake Structure, with installation approximately

90X

complete.

The licensee

s resolution of identified technical

issues,

while

slow, appears

to have

been

adequate.

In November

1986, the

Regulatory Effectiveness

Review (RER) report identified a security

weakness

in CCTV alarm assessment

capability.

This weakness

4

0

16

involves the manner

in which the integrated security systems

(barriers,

perimeter alarms

and

CCTV cameras)

can be defeated.

During this

SALP period,

a Region

V inspection report again

identified this weakness.

The licensee is currently evaluating

means to correct this weakness.

The 1986

RER report also identified

inadequacies

with portions of the licensee's vital area barriers at

Units

1 and

2 pipe galleries.

The licensee

has completed their

evaluation

and has identified measures

to correct these barriers.

During this

SALP period,

two information notices

and one generic

letter related to security were issued.

The licensee's

responsiveness

and actions

as reviewed to date,

were found to be

acceptable.

The enforcement history for the

SALP period included one non-cited

violation related to the licensee's

discovery of a sleepinq security

officer who was acting as

a compensatory

measure for a perimeter

alarm at the main protected

area.

During the

SALP period,

each of the licensee's

eleven safeguards

events

were reported in the Licensee

Event Report

(LER) format;

seven

(64K) of these

events

were caused

by personnel

errors.

These

eleven events related to:

degraded

operation of alarm stations(4);

degraded vital area barriers(3);

drug related events(2);

failed

security compensatory

measures(1);

and miscellaneous

events(l).

The four LER's relating to the degraded

operation of the alarm

stations

were caused

by two instances

of temporary malfunctioning

computer equipment,

and two situations

involvinq extended

personnel

errors.

These personnel

errors included the failure to reactivate

(for several

hours)

a vital area

door alarm after testing;

and

allowing a security officer to repeatedly

respond to an incorrect

door

upon receipt of vital area door alarms.

Additionally, during

this

SALP period,

Region

V determined that the security alarm

station operators,

during their performance of assigned

duties in

the central

and secondary

alarm stations,

were rarely observed

by

their supervisors.

The licensee's

corrective action required

each

security shift lieutenant

and sergeant

to visit both alarm stations

once per'shift.

The overall effectiveness

of this corrective action

has not been evaluated

by the

NRC.

With respect to staffing,

key positions

and responsibi'lities

were

generally well defined.

The licensee's

overall security training

program exceeded

minimum requirements,

as evidenced

by their

development of a Tactical

Team Response

Training Course.

This 5-day

course

has

been presented

to all security officers.

Additionally,

the Fitness for Duty training was observed to be comprehensive

and

well presented.

In February

1990, six weeks following the end of this

SALP period,

a

routine security inspection included

a review of the licensee's

Safeguards

Events

Logs, from April through December

1989.

Events

recorded in these

logs identified multiple examples of weak

performance, i.e., lack of positive access

control, failed

/

0

17

2.

3.

compensatory

security measures,

and inadequate

protection of

safeguards

information.

. Initial review of inspection results also

indicate

a possible reduction in the overall safety/security

awareness

and attitude of plant employees.

Performance

Ratin

Performance

Assessment - Category 2, Improving Trend

Board Recommendations

Generally,

licensee resolutions

and corrective actions for hardware

items

have

been acceptable,

however,

licensee

management

is

encouraged

to finalize these matters

on a more timely basis.

Specifically, licensee

management

is encouraged

to resolve the

identified weakness

with the integrated security system (barriers,

perimeter

alarms

and

CCTV cameras).

Additionally, the licensee

is

encouraged

to finalize measures

to correct identified inadequacies

with portions of vital area barriers at Units

1 and

2 pipe

galleries.

Further, in an effort to reduce

extended

personnel

errors,

licensee

management

is encouraged

to examine the

effectiveness

of supervision of alarm station operations.

Based

upon the last

NRC inspection,

additional

management

attention is

also required in employee

awareness

towards compliance with

es.

~

~

~

~

safety/securi ty pr ocedur

'F.

En ineerin /Technical

Su

ort

~Anal sis

The licensee's

performance

in this area

was rated

as Category

2

during the previous

SALP period.

Significant issues

discussed

in

that evaluation included:

implementation of the design basis into

operations

and maintenance activities including various aspects

of

design

bases

documentation

and the availability of design

documents

to appropriate plant personnel;

implementation of the system

engineering

program,

including improving the interface

between the

corporate

and site engineering organizations;

and the

need for

management

to ensure that the fundamentals

of nuclear plant

operations

are more clearly understood

by engineering

personnel.

The above issues

were specifically addressed

during the

SALP period

by an

NRC SSFI team inspection.

The team identified continuing

weaknesses

in the following areas:

plant staff did not fully

This functional area

was reviewed routinely by both regional

inspectors

and the resident staff.

In this functional area,

a

Safety System Functional Inspection

(SSFI) was conducted in January

1989.

A total of 679 inspection

hours

was expended

in this

functional area.

These

reviews primarily focused

on the

San

Francisco

based

Nuclear Engineering

and Construction Services

(NECS), which is responsible for plant design activities,

and the

plant engineering

group, which includes

system engineering.

0

18

understand

the plant design basis;

the interface

between

NECS and

the site was weak;

and

some engineering

work was found to be

incomplete or inadequate.

Several violations resulted

from these

weaknesses

and escalated

enforcement

was taken,

based

upon findings

by both the team and the resident inspectors.

Licensee corrective

actions included:

reemphasis

of a comprehensive

configuration

management

program, including design basis

document construction;

reemphasis

of closer system engineer ties with their design

engineerinq counterparts;

a complete review of the

FSAR and other

design basss

correspondence

to assure

commitments

are being met;

and

a review of vendor manuals to ensure

important maintenance

activities are being accomplished.

The licensee

has dedicated

extensive

resources

towards the implementation of these corrective

actions;

however, the

SALP board concluded that continued strong

management

attention is needed in these

problem areas.

With respect to the assurance

of quality by engineering

management,

NECS has

lagged behind the plant in terms of developing

an attitude

of self-crit>cal assessment.

Nore emphasis

was put on this area in

1989, with greater

involvement by engineerinq quality services,

stronger ties. between

NECS and site engineer)ng

personnel,

and

PGEE

engineering

and corporate

management

spending

more time at the site

and more time with engineering

personnel.

Understanding of technical

issues

was generally apparent

and

conservatism

was generally exhibited.

One commendable

example

was

the Long-Term Seismic

Program.

However, in some instances

NECS'ngineering

failed to understand all implications of what were

viewed as minor changes

on actual plant operations.

An illustration

of this was the failure to recognize that the upgrading of sections

of heat tracing from non-safety related to safety related

on the

g-List had implications on the heat tracing already installed,

which

had not been treated

as safety related for several

years (e.g., this

raised considerations

of seismic qualification, procurement,

and

application of the quality assurance

program).

There

have

been

examples

where system engineering

has taken

a less

than thorough

approach to solving problems.

Problem investigations

have not

consistently

included fundamentals

such

as fact gathering,

proceduralizing,

organizing,

and documenting.

An example

was the

investigation of vibration in the charging

pump suction line, which

was ultimately attributed to a misapplied suction stabilizer for the

positive displacement

charging

pump.

The investigation took months

to complete

and was not considered well planned or controlled.

Engineering

has

been generally responsive

to

NRC and industry

initiatives and, while resolution is not generally timely, products

are of good quality.

In this regard,

the licensee

embarked

upon

improvement initiatives in the areas of Design Bases

Document

reconstruction,

Configuration Management,

and Plant/Systems

Engineering,

and

has

expended

considerable

resources

to make these

initiatives substantial

contributors to improved engineering

and

technical

work quality.

Although it took over a year from the time

that the licensee first initiated a design basis

document

program to

issue the first document,

the licensee

has

now completed

0

19

reconstruction of the design

bases for several

safety related

systems.

This work appears

to be a substantial effort to improve

design understanding

and consolidation.

Concerns identified during

the reconstruction

are being resolved in a responsible

manner.

Following the completion of the first 'few documents,

the licensee

conducted

SSFI type inspections

on certain systems

as part of the

verification and validation process.

These

SSFI examinations

appeared

to be substantial

and resulted in several

important

improvements.

Other licensee initiatives, such

as the onsite engineering

program,

have also received increased

attention.

In particular, the licensee

has

implemented

a number of initiatives to improve the performance

of Plant/System

engineers

in monitoring the performance of plant

systems,

improving relationships

between plant engineering

and

design engineering,

and involving design engineering

more fully into

day-to-day plant operations.

Most notable

among these

are:

(1)

quarterly system walkdowns by the plant system engineer

and the

design engineer,

with a state-of-the-system

report to licensee

management;

(2) rotation programs

between the plant system engineer

and design engineer;

(3) joint plant and design engineer

review and

consensus

on walkdown checklists

and trending program attributes;

and (4) more centralized trending

and tracking of system problems

and improvements.

In contrast to these initiatives, however, plant

management

appears

to be slow in focusing attention

on the issue of

plant material condition, although precursors

of this issue

have led

'to equipment inoperability (e.g., corrosion problems with the

ASM

system,

degradation

and failure of ASM cable,

and degradation

of the

centrifugal charging

pump lube oil systems).

Although conducted after the conclusion of this

SALP assessment

period,

a team inspection in January

and early February

1990 also

made observations

in this functional area.

The system

engineer/design

engineer effort was recognized

as

a significant

licensee initiative which had been substantially

implemented,

although the potential;for additional

improvement

was noted in some

cases

regarding system/design

engineer training and qualification,

definition of responsibilities,

and the interaction of design

engineers

with the system engineers

and the plant hardware.

The

team also noted that

NECS had more than

a year's worth of design

engineering

work identified for accomplishment

(about 25K related to

long-term capital

improvements),

although preliminarily this work

inventory appeared

to be well-managed

and effectively prioritized by

,NECS management.

The licensee

received

one escalated

enforcement action in this

functional area,

as discussed

ear1ier,

which indicated the

need for

programmatic attention to the design basis

and its implementation.

Other violations, although

more minor in nature,

indicated

a need

for additional attention in certain areas

(e. g., corrective action

follow-up, and training on applicable administrative

procedure

revisions prior to their implementation).

0

20

2.

3.

The licensee

engineerinq organization

was well staffed

as indicated

by the scope of work being performed in house.

The commitment to

the system engineering

program was also demonstrated

by assigning

the function of plant engineering to a separate

manager.

The licensee

has

made notable efforts to train technical staff in a

number of areas.

A large effort was

made to provide technical staff

with training in the application of 10 CFR 50.59 and root cause

determinations.

The licensee

also continues

to. commit resources

to

providing a sixteen

week plant system operation course to technical

staff.

Management

has demonstrated

significant interest in

engineering

improvement initiatives.

However,

a January

1990

corrective action program inspection

team identified weaknesses

in

the establishment

of a formal training program for design

system

engineers.

Performance

Ratin

Performance

Assessment - Category 2, Improving Trend.

Board Recommendation

The licensee

should continue to place

emphasis

on established

long

term programs

such

as the configuration management

and system

engineering

programs.

Attention should also continue to focus

on

the interface

between corporate

engineering

and the plant,

and the

formal resolution of plant problems.

Additionally, the licensee is encouraged

to be self critical,

emphasizing

the identification of problems early on and the

establishment

of aggressive

schedules

for corrective actions.

The

issue of plant material condition should also

be aggressively

assessed.

G.

Safet

Assessment/ ualit

Verification

~Ana1 sis

This functional area

was observed routinely during the assessment

period by both the resident

and regional inspection staffs.

Approximately 708 hours0.00819 days <br />0.197 hours <br />0.00117 weeks <br />2.69394e-4 months <br /> of inspect)on effort were devoted to this

functional area.

The performance of equality Assurance,

equality

Support (the onsite

gA branch),

onsite equality Control, the Onsite

Safety

Review Group

(OSRG),

and the Plant Staff Review Committee

were included in this assessment,

as well as the licensee

organizations

involved in the review of regulatory

and industry

in>tiatives.

During the previous

SALP period, the licensee's

performance

in this

area

was rated

as Category

2.

Issues

addressed

included:

the

need

to perform thorough evaluations

of plant problems;

the development

and implementation of well thought-out corrective

action/investigation

plans, with appropriate

assignment

of

management

responsibility; the

need to better include quality

21

organizations

in the review of events;

the need for improvements in

the quality of licensing submittals;

and the need for programmatic

assessments

of regulatory safety initiatives identified by

inspection findings to ensure

thorough and timely consideration.

Mith respect to management

involvement and control in the assurance

of quality, the gualsty Assurance

organizations

demonstrated

extremes of involvement and effectiveness.

On the one hand, the

gA

organization

has

been

on the forefront of the development of

performance

based

inspection activities with the implementation of

the Safety System Functional Audit and Reviews

(SSFAR) and the'audit

of their NSSS vendor.

On the other extreme,

management failed to

properly control

and monitor the performance of gA program audits of

safety related equipment suppliers.

This resulted

from a breakdown

of management

control

and overview within the gA department,

resulting in numerous audits which were inadequate

in both scope

and

content to meet

NRC requirements.

These deficiencies

also

emphasized

the failure of licensee

gA personnel

to implement

appropriate corrective action program requirements

(e.g.

issuance

of

NCRs) in that audit program deficiencies

had been noted over a

several

month period without implementation of any formal corrective

action program review.

Additionally, management failed to recognize

that allowing a non-licensed shift supervisor to stand watch

contradicted Technical Specification requirements.

Mith regard to resolution of technical

issues

from a safety

standpoint,

root cause

reviews appeared

to be technically sound

and

thorough in most cases.

A specific improvement,

which was apparent

in the quality of licensee

gA audits,

has

been the use of auditors

with direct experience

in the technical

areas

being audited.

This

has

been demonstrated

specifically in the

SSFARs

and

some recent

vendor audits.

On the other hand,

although

a clear understanding

of

technical

issues is normally demonstrated,

the Plant Staff Review

Committee failed to recognize

the significance of allowing work to

calibrate

a containment

sump indicator with the

sump access

open.

The licensee

has

been generally responsive

to

NRC initiatives.

One

NRC concern

from the last

SALP period that was well addressed

by the

licensee

involved the initiation of root cause evaluations

(equality

Evaluations

and Non-conformance

reports) for problems

on non-safety

related

systems

which could potentially challenge safety systems.

Also, the licensee

has continued to develop the Event Investigation

Team methodology for major events

and,

when used, results in good

products.

Overall, the licensee

has

implemented

a viable program

for conducting'in-depth

Event Analyses/Root

Cause evaluations.

The

licensee

has

been refining their criteria for screening

events to

more closely conform to industry standards.

This effort is expected

to result in selection of the more deserving

events for analyses,

appropriately exclude those

events of lesser significance,

and

improve the quality of event evaluations.

.Additionally, the

licensee

has assured that personnel

responsible for conducting event

evaluations

are appropriately trained

and qualified in the

techniques

of root cause

analy'ses.

\\

0

22

However, without the formal structure of an Event Investigation

Team,

where clear management

ownership

was defined, there

have

been

examples of problem reviews which have

been limited in scope

and

which have involved inadequate

corrective actions

and less than

timely implementation.

For example,

although

an

NRC inspector

had

identified overtime

usage in excess

of technical specification

limits, overtime abuses

continued for at least the following week

and management

did not initiate a review of the implementation of

the technical specification requirement for another three weeks.

An

additional

example involved incomplete

and untimely follow-up of NRC

concerns

dealing with safety evaluations

and administrative controls

for fire protection program components.

The licensee

responsiveness

to equipment lineup problems,

repeatedly the cause of minor events

and the subject of several

inspection reports,

was considered

inadequate,

resulting 'in escalated

enforcement action,

as previously

discussed.

The licensee

provided

a large amount of highly technical

information

in response

to staff questions

on the Long-Term Seismic

Program

(LTSP), which was conducted to completely reevaluate

the seismic

design basis for the plant, using state-of-the art seismic data

and

analysis

techniques,

including a full level I Probabilistic Risk

Assessment

(PRA).

Although the licensee's

efforts to provide the

staff with voluminous and detailed information about this program

have required

a significant allocation of company resources,

the

licensee

has

been quite responsive

to the NRC's requests

and

information has

been provided in a timely manner.

Although conducted after the conclusion of this

SALP assessment

period,

a team inspection in January

and early February

1990 focused

particular attention

on the licensee's

corrective actions

program.

This program is managed

on the Plant Information Management

System

(PIMS), a computer-based

tracking and communications

system

used for

essentially all types of items,

issues,

or problems which require

corrective action.

Malkdown of plant systems,

numerous

interviews,

and substantial

reviews of licensee

logs and records did not

identify any items reqUiring corrective action which had not been

entered into the

PIMS program.

Preliminarily, the team also did not

identify any safety-significant

problems which had not received

appropriate

and timely corrective action.

However, action on

several

items of apparent

lesser individual significance

had been

pending or under evaluation for as

much as

a few years,

and it was

not apparent that the licensee

had fully evaluated

the safety

significance of these

items.

The team also noted that each

organizational

group was responsible

for acting on items assigned

to

it (unless

or until it was reassigned),- but that

no group or person

appeared

to feel responsibility or "ownership" for managing the

overall

system.

Plant management

stated at the end of the team

inspection that,

based

on an assessment

previously in progress,

a

new organizational

group was being established

to provide oversight

of the corrective actions,

root cause, trip reduction,

and other

similar programs.

0

23

During this appraisal

period, the licensee

submitted nineteen

requests

for license

amendments,

and

a total of eighteen

license

amendments

were issued.

In addition, the licensee

resolved safety

issues

related to six generic letters

and three

NRC bulletins

requiring

NRR technical

review.

Also, three

TMI items involving NRR

review were resolved.

In general,

the licensee's

understanding

of

the technical

issues

involved in these actions

was apparent,

and in

most, cases,

the resolution

was timely.

Although there were

no enforcement

items specifically attributable

to this functional area during the

SALP period, aspects

of

enforcement

items discussed

in other functional areas

emphasize

the

need for management

and quality verification organizations

to more

fully involve themselves

in assuring that programmatic

problems

are

discovered early and addressed

in a comprehensive

and timely manner.

Examples of this have

been discussed

previously in this report and

include: the adequacy of vendor audits;

the use of excessive

overtime; the assignment of an unlicensed shift supervisor;

and

providing for effective corrective action,

as it related to valve

lineup problems.

Also symptomatic of a potential

problem in the

performance of the management

and quality verification groups is a

noted decline in plant housekeeping.

The quality verification organizations

appeared

to be adequately

staffed

and have evaluated

a substantial

percentage

of site

activities,

such

as engineerinq,

design

changes,

and operations.

Additionally, the gA organization

used contracted

help on a number

of audits to it s advantage,

finding technically qualified

individuals to round out audit teams

and utilize that expertise to

train their employees.

The licensee's

training and qualifications program

made

a positive

contribution in this functional area.

The licensee

continued to

emphasize training in the area of root cause identification and

corrective actions.

Additionally, personnel

qualification was

a

contributor to the qual.ity of many gA and

gC audits.

The licensee,

also included

gA and

gC personnel

in the technical staff training

program, contributing to system understanding.

Performance

Ratin

Performance

Assessment - Category 2, Improving Trend.

Board Recommendations

The licensee is encouraged

to maintain the emphasis of the quality

verification programs

on performance

based audits,

using technical

expertise

and in depth reviews to identify problems.

The licensee

is also encouraged

to continue to increase

the emphasis

placed

on

the identification of problems.

In view of the recent problems

identified with the performance of vendor audits,

the licensee

should consider

actions to ensure that similar problems

do not exist

in other areas of the gA organization.

24

V.

SUPPORTING

DATA AND SUMMARIES

A.

Licensee Activities

In general,

both units operated

acceptably

during the assessment

period.

Specific operational activities are summarized

as follows:

Unit 1

At the beginning of the

SALP period, Unit 1 had just completed its.

second refueling outage.

Two automatic reactor trips were

experienced

in rapid succession

on August 30 and September

1, 1988.

Following these trips, Unit 1 operated for 399 continuous

days,

setting

a record for Westinghouse

four loop plants.

A trip on

October 6, 1989,

ended the run and the licensee initiated its third

refueling outage

a week early.

The refueling outage included

refueling the core with higher enrichment fuel, reactor coolant

pump

motor modifications, continuation of the snubber reduction program,

feedwater control system modifications,

and routine maintenance

work.

The outage

concluded

on December

14,

1989 and the Unit

returned to power operation.

Unit 2

Unit 2 commenced

the

SALP period at 100K power, experienced

a

reactor trip on September

1, 1988,

and was shutdown

on September

17,

1988, to commence its second refueling outage.

The refuelinq outage

scope

included reactor

coolant

pump motor modifications,

aux> liary

saltwater

pump overhauls,

routine maintenance,

and unplanned

maintenance

on one safety injection pump, which was

damaged

due to a

lineup problem.

The outage

concluded

on December 8, 1988.

Unit 2

operated

through the remainder of the

SALP period at essentially

100'ower with the exception of an outage to repair

a leaking

pressurizer

safety valve,

one automatic reactor trip, and three

manual trips.

Plant status at end of SALP

eriod

Diablo Canyon

ended the evaluation period with both units operating

at full power.

B.

Direct Ins ection

and Review Activities

A total of approximately

4450 hours0.0515 days <br />1.236 hours <br />0.00736 weeks <br />0.00169 months <br /> of direct inspection

were

performed during this

SALP period.

Table

1 provides

a summary of

those inspection activities.

Forty inspections,

including a Safety

System Functional

Inspection Overview team inspection,

two Emergency

Preparedness

exercise

team inspections,

an Emergency Operations

Procedures

team inspection,

and four management

meetings,

were

conducted

during this period.

Two resident inspectors

were assigned

during the

SALP assessment

period.

0

25

C.

Enforcement Activit

Along with a summary of inspection activities,

a summary of

enforcement

items resulting from those inspections is provided in

Table 1.

A description of the enforcement

items is provided in

Table 2.

During the

SALP period,

a two part escalated

enforcement

action ($75,000 Civil Penalty)

was identified concerning the failure

to implement or maintain design

bases

through engineering,

and the

failure to resolve identified problems in a timely, effective

manner.

Subsequent

to the

SALP period, but related to events within

the period,

an enforcement action ($50,000 Civil Penalty)

was issued

concerning the construction

and cleanliness

of the containment

sumps.

Additionally two level IV violations, regarding vendor

gA

audits,

and one level III violation (no civil penalty),

regarding

a

non-licensed shift supervisor,

were issued

subsequent

to the end of

the

SALP: period.

D.

Confirmation of Actions Letters

CALs

No CALs were issued during the appraisal

period.

E.

Office of Anal sis

and Evaluation of 0 erational

Data

AEOD) Event

~na

sos

AEOD reviewed the licensee's

events

and prepared a report which is

included

as Attachment l.

AEOD reviewed

LER s and significant

operating

events for quality of reporting and effectiveness

of

identified corrective actions.

F.

Office of Investi ation

OI) Status

On August 1, 1988,

relevant to Diablo

December

31, 1989,

December

31, 1989,

relevant to Diablo

OI had three matters that were open

and pending

Canyon.

During the period August 1, 1988 to

OI opened

two new investigative matters.

As of

five investigations

were open

and pending

Canyon.

t~

r

Table

1

INSPECTION ACTIVITIES AND ENFORCEMENT SUMMARY

08/01/88 - 12/31/89)

DIABLO CANYON UNIT 1

Inspections

Conducted

Enforcement

Items

Functional

Area

Inspection

Percent

Hours*

of Effort

Severit

Level**

D

1.

Plant Operations

2.

Radiological

Controls

3.

Maintenance/

Surveillance.

4.

Emergency

Prep.

5.

Security

789

203

362

76

160

34

Engineering/

Technical

Support

340

Safety Assessment/

396

equality Verification

Total s

15

17

2

2

Allocations of inspection

hours to each functional area are

~

approximations

based

upon

NRC form 766 data.

These

numbers

do not

include inspection

hours

by NRC contract personnel.

Severity levels are in accordance

with NRC Enforcement Policy (10 CFR Part 2, Appendix C).

r

0

Table 1 (continued)

INSPECTION ACTIVITIES AND ENFORCEMENT SUMMARY

08/01/88 - 12/31/89

DIABLO CANYON UNIT 2

Inspections

Conducted

Enforcement

Items

Functional

Area

1.

Plant Operations

Inspection

Percent

Hours*

-

of Effort

817

38

Severit

Level"*

D

2.

3.

Radiological

Controls

Maintenance/

Surveillance

125

279

13

4.

Emergency

Prep.

5.

Security

194

63

c

3

6.

Engineering/

Technical

Support

339

Safety Assessment/

312

equality Verification

16

15

8,

Fire Protection

Totals

Allocations of inspection

hours to each functional area are

approximations

based

upon

NRC form 766 data.

These

numbers

do not

include inspection

hours

by NRC contract personnel.

Severity levels are in accordance

with NRC Enforcement Policy (10 CFR Part 2, Appendix C).

0

TABLE 2

DIABLO CANYON UNIT 1 ENFORCEMENT ITEMS

08/01/88 - 12/31/89

Inspection

Re ort No.

~Sub 'ect

Severity

Level

Functional

Area

88-25

Failure to meet commitment to issue

Deviation

administrative procedure

on reading

test instruments.

89-01

89-01

89-01

89"15

89-15

A design

change

was modified by

General

Construction without

submitting

a field change to Diablo

Canyon

Power Plant

(DCPP) for approval.

480V power cable were installed

in the plant and attached to instru-

mentation cable without a safety

evaluation.

No information was available to

operators

on the buildup of carbon

dioxide in the control

room

Component Cooling Water/Auxiliary

Saltwater

(CCM/ASM) Systems

design

basis

not incorporated into plant

procedures;

two Auxiliary Feedwater

(AFM) pumps out of service greater than

6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />;

ASM pump overcurrent relay not

operable for design basis

reduced

bus

voltage;

ASM pump .,impeller replacement

did not consider Diesel

Fuel Oil (DFO)

storage for increased

horsepower;

AFM

overspeed trip mechanism - failure to

implement vendor recommendations

in

test

and preventive maintenance

procedures

Steam driven

AFM pump inoperable for

30 days

due to open

gauge line root

valve; untimely correct)ve actions

for compensatory

measures

for

missing

DFO transfer

pump vault

drain backwater

check valves.

IY

IV

Deviation

TABLE 2 (continued)

DIABLO CANYON UNIT 1

ENFORCEMENT ITEMS

08/01/88 - 12/31/89

Inspection

~Re ort Ro.

89-23

89-23

89-23

89-25

~Sub 'ect

Work was performed

on heat tracing

without applicable

gA requirements

translated

into the work specifica-

tions

Plant maintenance

personnel

perform-

ing safety related work worked in

excess of 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> in a 7 day period.

Valves for Hydrogen Purge

System did

not have power removed to satisfy

Containment Isolation Technical

Specification.

Inadequate

response

to fuel handling

building radiation monitor alarms.

Severity

Level

IV

IV

IV

IV

Functional

Area

0-

TABLE 2 (continued)

DIABLO CANYON UNIT 2

ENFORCEMENT ITEMS

08/01/88 - 12/31/89)

Inspection

~Re ort Ro.

89-29

89-01

89"01

89-01

89"01

89-01

89-01

~Sub 'ect

Failure to follow administrative

procedures

for oscillating gauge

during surveillance

and testing.

The

GE/GW ventilation system

was

declared operational

although

a

partial closure of the design

change

had not been completed

and a field

change

had not been

approved.

The Operations

Valve Identification

Diagrams for the auxiliary building

ventilation system were not updated

to include

a recent modification.

A Class

1 support

was not located

in accordance

with the approved

design.

Four flange bolts on Safety Injection

(SI) cooling water line and damper

fasteners

did not have full thread

engagement.

Bolts were replaced in the

GE/GW

ventilation system without written

work orders.

Nine GE/GW welds were not inspected

prior to the system being declared

= operable.

An anchor bolt on the ventilation

system

was identified as not meeting

the required torque - no action was

taken to evaluate

the discrepancy.

Numerous

obvious discrepancies

existed

with electrical conduits,

loose pipe

hangars

and missing nuts

and washers

on pipe hangers

on SI pump 2-2 that

were not reported

on an Action Request.

Severity

Functional

Level

Area

IV

6

IV

IV

IV

IV

IV

IV

IV

L

J

0'

TABLE 2 (continued)

DIABLO CANYON UNIT 2 ENFORCEMENT ITEMS

08/01/88 - 12/31/89

Inspection

~Re ort No.

89-05

89-21

~Sob 'ect

A spl it washer to the Unit 2

auxiliary feedwater

pump over-

speed

stop valve FCV-152,

was

modified without being processed

as

a design

change.

The fire door to the Unit 2

Residual

Heat Removal

(RHR)

Heat Exchanger

room was impaired.

Severity

Functi onal

Leve1

- Area

IV

IV

0

TABLE 3

DIABLO CANYON UNIT 1

SYNOPSIS

OF LICENSEE EVENT REPORTS

Functional

Area

SALP Cause

Code"

A

B

C

D

E

X

Totals

1.

Plant Operations

2.

Radiological Control s

3.

Maintenance/Surveillance

4.

Emergency

Preparedness

5.

Security

6.

Engineering/Technical

7.

Safety Assessment/

equality Verification

Totals

Cause

Codes:

1

1

5

1

6

2

1

1

4

10

. A:- Personnel

Error

8 - Design, Manufacturing or Installation Error

C - External

Cause

D - Defective Procedures

E - Component Failure

X - Other

0

TABLE 3

DIABLO CANYON UNIT 2

SYNOPSIS

OF LICENSEE EVENT REPORTS

Functional

Area

SALP Cause

Code*

A

B

C

D

E

X

Totals

1.

Plant Operations

2.

Radiological Controls

3.

Maintenance/Surveillance

4.

Emergency

Preparedness

5.

Security

6.

Engineering/Technical

7.

Safety Assessment/

equality Verification

Totals

3

3

1

1

1

3

2

12

13

3

Cause'Codes:

A..-, Personnel

Error

8 - Design, Manufacturing or Installation Error

C - External

Cause

0 " Defective Procedures

E - Component Failure

X - Other

/gj~

0

0

'

Attachment

1

AEOD Input to SALP Review for Diablo Canyon

During the assessment

period 54

LERs were reviewed:

Unit 1: 88-23 through 89-13

Unit 2: 88-08 through 89-10

l.

Important Operating

Events

L

Utilizing AEOD s screening

process,

the following seven Unit 1 and Unit 2

LERs were categorized

as important events:

Unit 1

50-275/88-28 "Entry Into Technical Specification 3.0.3

When

Two of Four

t'I

Iqtly)IM

I

p

bl

II

t

I

dq

t

Environmental gualification of Electrical Connections."

Two of four main

steam isolation valves

on each unit were declared

inoperable,

due to

inadequate

environmental qualification of electrical

surge suppressors

located across

terminal connections for the

MSIV solenoid control valves,

Short circuiting of surge

suppressors

could potentially blow control

power fuses

and preclude operator action to close the HSIVs during

certain accident scenarios.

Failure to meet the applicable technical

specification

(TS) action statement

resulted in entry into TS 3.0.3.

The

subject

surge

suppressors

and electrical

connections

were

removed

and

replaced with environmentally qualified splices.

50-275/89-02 "Failure to Reinstall

Backwater

Check Valves in Fuel Oil

pp

ItD

I gyt

D

I

I dq t

I t

tt

t

Contractor

Personnel."

Drain lines in the diesel fuel oil transfer

pump

vaults did not have backwater

check valves installed.

The backwater

check valves,

described

in the Updated Final Safety Analysis Report,

provide back flood protection for the diesel fuel oil transfer

pump

vaults in the event of blockage in the drain line concurrent with

flooding in another

headered

vault.

Loss of the transfer

pumps

due to

flooding would prohibit transfer of diesel fuel oil from the storage

tanks to the diesel

generator

day tanks.

As partial corrective action,

backwater

check valves were installed in drain lines from the transfer

pump vaults.

50-275/89-09 "Safety Injection and Reactor Trip From Steam

Line

P

gp

I

gig

I ."

A

t

tt

I ty I d tt

and reactor trip was initiated as

a result of plant personnel

creating

pressure

oscillations in a sensing line during testing.

The importance of this event is that at the time of the reactor trip, two

of the four atmospheric

steam

dump valves

(ADVs) had been

removed from

service.

This is permissible

by the plant technical specifications,

but

plant emergency

operating procedures

specified that the

ADVs be used for

reactor coolant system cooldown.

AEOD is evaluating the generic aspects

C~

0

of permitting equipment required by EOPs to be removed from services

without appropriate

clearance

controls.

50-275/89-10

"Thimble Tube Thinning Due to Flow-Induced Vibration."

In

~pgtt

0

11 tt

88-09,

ddy

t I

9 tl

f '

monitoring system thimble tubes

revealed

28 tubes exceeding

50 percent

through-wall degradation,

due to flow-induced vibration.

As partial

corrective action,

33 tubes

were replaced

and 12 tubes were repositioned.

Unit 2

50-323/88-08

"Reactor Trip and Subsequent

Safety Injection Following an

d

L

t

t

R

t

L

I tP 9220

t

Galling on the Threads of an Aluminum Stud."

Deterioration of a galled

aluminum electrical

connector for reactor coolant

pump (RCP) 2-2,

resulted in an electrical

ground fault, a manual reactor trip, and

a

RCP

2-2 manual trip.

Loss of 12

kV start-up (offsite) power was also

experienced

during the event.

Investigation of the trip revealed

several

associated

problems.

These

included 1) defective welds

on a fuse block for a grounding transformer,

2) routing of the heutral

cable for start-up transformer 2-1 grounding

bank along the top of the resistor

bank (subjecting the cable to intense

heat,

which resulted in burning of the cable insulation),

and 3)

inadvertent

blockage of air cooling to the resistor

bank.

Licensee corrective actions

included analyzing grounding resistor

heat

loadings,

cable rerouting, infa-red surveillance of RCP high voltage

connections,

and improved housekeeping

controls in the resistor

bank

area.

50 323/88-14 "Anchor Darling Check Valve Retaining Block Stud Breakage

g

I

St

0

I

0

kl g" (IRSCCP.

A

h

k

located in the residual

heat removal

(RKR) hot leg injection line, was

found to have two broken retaining block studs.

Incorrect manufacturer

heat treatment of the block.,studs

caused susceptibility to IGSCC.

The

licensee's

analysis

concluded the valve would remain operable with broken

studs.

The failed valve was repaired,

and other similar valves were

inspected for the

same concern.

50-323/88-15

"Residual

Heat Removal

Pump 2-2 Lower Motor Bearing Housing

t

I

d

8 t

8

8

g

t f th

Sh ft

N t L

kl

8 II

8

RHR pump 2-2 was declared

inoperable

when

a lock tab washer

on the

vertical motor rotor shaft rotated,

allowing the shaft thrust bearing nut

to loosen.

The loosened thrust bearing nut allowed the shaft to drop

axially and create

metal to metal contact with the lower motor bearing

housing causing mechanical failure of the oil reservoir

and subsequent

oil leakage

and

smoke generation.

Inadequate

design

and preventative

maintenance

were identified as root causes

of the failure.

Preliminary Notifications

Eight preliminary notifications

(PNs) pertaining to Units 1 and

2 were

issued

by Region

V during the assessment

period.

For those

events

r

O.

described in the

PNs which warranted

LERs from the licensee,

the

LERs

were verified to have

been submitted.

. No omissions

were identified.

3.

LER Overview

Causes

o

e even

s are

f th

t

distributed

among various categories,

however

on

U t 1

inordinate

number of the

LERs were associated

w>th p

ersonnel

nl

an lnor

error.

Procedural

inadequacies

were also prominent.

On Uni

U it 2

the

largest

number of events

were also personnel

errors,

and many were

similarly associated

with inadequate

procedures.

4.

5.

LER Timeliness

and guality

LERs submitted

by the licensee

were timely and of high quality, w>th the

exception of the following:

LER 50-323/88-20

"Containment Ventilation Isolation and Fuel Handling

Building Ventilation Shift to the Iodine Removal

Node," utilized terms

such

as

FCV-128,

FCV-111A, and

RH 28A without providing further component

t

'n

diaorams.

Additional clarification should

be

provided in the fElt when pTant specific designations

are utilized.

I

LER 50-323/87-20 "Entry Into Technical Specification 3.0.3

Due to Both

T

'

Auxiliary Building Ventilation Being Inoperable," indicated

a

supplement

would be issued.

The event dsd not

'

rains

0

evaluation period,

however, the supplemental

report was not issue

un

>

July 28, 1989.

This appears

to be

an inordinate

amount of time to

determine root cause

and corrective action,

and provide the supplemental

information to the

NRC.

Abnormal Occurrences

and Other Events of Interest

durin

this assessment

period were classified

as

th

NUREG-0090 report to Congress.

Abnormal Occurrences

for inclusion sn

e

6.

AEOD Reports

No AEOD reports

were issued

regard>ng

events occurri

g

rin

at Diablo Canyon

during this evaluation period.