Application for Amend to License DPR-47,changing Tech Specs Re Reload Design Calculations for Cycle 7
ML16134A674
Person / Time
Site: Oconee Duke Energy icon.png
Issue date: 08/11/1982
From: Tucker H
DUKE POWER CO.
To: Harold Denton, Stolz J
Office of Nuclear Reactor Regulation
Shared Package
ML16134A675 List:
References
NUDOCS 8208240234
Download: ML16134A674 (4)


Text

REGULATORY NFORMATION DISTRIBUTION SEEM (RIDS)

ACCESSION NBR:8208240234 DOC.DATE: 82/08/11' NOTARIZED: YES DOCKET #

FACIL:50-287 Oconee Nuclear Station, Unit 3, D0uke Power Co. 05000287 AUTH.NAME AUTHOR AFFILIATION TUCGERHB, Duke Power Co.

RECIPNAME RECIPIENT AFFILIATION DENTONH.R. Office of Nuclear Reactor Regulation, Director STOLZJ.F. Operating Reactors Branch 4

SUBJECT:

Application for amend to License DPR-47,changing Tech Specs re reload design calculations for Cycle 7. 5& 0/ &

DISTRIBUTION CODE: AQO1S COPIES RECEIVED:LTR -. ENCLL0 SIZE:_- ,

TITLE: OR Submittal: General Distribution NOTES:AEOD/Ornstein:1cy, 05000287 C S-ra RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL 10 CODE/NAME LTTR ENCL ORB #4 BC 01 7 7 INTERNAL: ELD/HDS4 1 0 NRR/DHFS DEPYO8 1 1 NRR/DL DIR 1 1 ORAB 1 0 NRR/DSI/RAB I 1 EG FI 04 1 1 RGN2 1 1 EXTERNAL: ACRS 09 10 10 LPDR 03 1 1 NRC PDR 02 1 1 NSIC 05 1 1 NTIS 1 1 NOTES: 1 1 TOTAL NUMBER OF COPIES REQUIRED: LTTR 29 ENCL 27

DUKE POWER COMPANY P. 0. BOX 33189 TELEPHONE: AREA 704 GENERAL OFFIAES 373-4011 422 SOUTH CHURCH STREET CHARLOTTE, N. C. 28242 August 11, 1982 Mr. Harold R. Denton., Director Office 6f Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D. C. 20555 Attention: Mr. Johfi F: :Stolz, Chief Operating Reactors .Branch No. 4

Subject:

Oconee Nuclear Station Unit 3 Docket No. 50-287.

Dear Sir:

Pursuant to.10 CFR 50, 950.90, please find attached proposed changes to the Oconee Nuclear Station (ONS) Technical Specifications which are required to support the operation of Oconee Unit 3 at full rated power during Cycle 7. This submittal includes minor revisions to the reload results provided in our May 3, 1982 submittal. As indicated in the May 3, 1982 letter, Oconee Unit 3 was shut down to begin the refueling cycle 17 EFPD short of the Cycle 7 window as included in that report; thus, a reanalysis was required.

Startup testing of Oconee Unit 3, Cycle 7 will be performed in accordance with the report entitled, "Oconee Nuclear Station Generic Startup Physics Test Program",

initially approved by NRC letter dated March 23, 1981 and as modified by Duke letter dated May 29, 1981. The current schedule at Oconee is dictated by the repairs to the Auxiliary Feedwater Headers, but a review and response by Septem ber 27, 1982 is requested to ensure the unit can be restarted when the repairs are complete.

This proposed license amendment concerning the reload design.calculations for Oconee 3, Cycle 7 was conducted consistent with Duke Technical Report NFS-1001, "Oconee Nuclear Station Reload Design Methodology" which was reviewed and accepted by the Staff in a letter dated July 29, 1981. This submittal provides minor revisions to our May 3, 1982 submittal and thus, no additional fees are necessary.

Very truly yours, H. B. Tucker, Vice President Nuclear Production Department JFN/php Attachment 820 8 24O~A 0.

Mr. Harold R. Denton, Director August 11, 1982 Page 2 cc: Mr. James P.. O'Reilly, Regional Administrator 1U. S. Nuclear Regulatory -Commission Region II 101 Marietta Street, Suite 3100 Atlanta, Georgia 30303 Mr. W. T. Orders NRC Resident Inspector Oconee Nuclear Station

Mr. Harold R. Denton, Director August 11, 1982 Page 3 H. B. TUCKER, being duly sworn,, states that he is Vice President of Duke Power Company; that he is authorized on the part of said Company to sign and file with the Nuclear Regulatory Commission this request for amendment of the Oconee Nuclear Station Technical Specifications, Appendix A to Facility Operating Licenses DPR-38, DPR-47 and DPR-55; and that all statements and matters set forth therein are true and correct to the best of his knowledge.

H. B. Tucker, Vice President Subscribed and sworn to before me this 11th day of August, 1982 Notary Public My Commission Expires:

Febiuary 15, 1987