Correction to Amendment Nos. 226 and 176 Change to Technical Specification 6.8.4.h, Containment Leakage Rate Testing Program.
ML15280A392
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 10/19/2015
From: Farideh Saba
Plant Licensing Branch II
To: Nazar M
Nextera Energy
Buckberg P, NRR/DORL, 415-1383
Shared Package
ML15280A377 List:
References
TAC MF4694, TAC MF4695, TAC MF6797, TAC MF6798
Download: ML15280A392 (5)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 19, 2015 Mr. Mano Nazar President and Chief Nuclear Officer Nuclear Division NextEra Energy P.O, Box 14000 Juno Beach, Florida 33408-0420

SUBJECT:

ST. LUCIE PLANT, UNIT 1 AND UNIT 2 - CORRECTION OF AMENDMENT NOS. 226 AND 176 REGARDING TECHNICAL SPECIFICATION 6.8.4.h, "CONTAINMENT LEAKAGE RATE TESTING PROGRAM" (TAC NOS. MF4694, MF4695, MF6797, AMO MF6798)

Dear Mr. Nazar:

On August 27, 2015, the Nuclear Regulatory Commission (NRC) staff issued Amendment Nos.

226 and 176, respectively (Agencywide Documents Access and Management System (ADAMS)

Accession No. ML15195A655) to St. Lucie Units 1 and 2. The amendment revised Technical Specifications 6.8.4.h, "Containment Leakage Rate Testing Program," to allow extension of the 10-year frequency of the containment Type A test to a 15-year frequency. Subsequent to the issuance, the NRC staff noted that an administrative error was made while processing the amendments, as described in the paragraph below.

To support the frequency extension, the licensee's original August 26, 2014, application (ADAMS Accession No. ML14241A496) referenced Nuclear Energy Institute (NEI) Topical Report NEI 94-01, Revision 3-A, "Industry Guideline for Implementing Performance-Based Option of 10 CFR [Code of Federal Regulations] Part 50, Appendix J." However, by letter dated January 14, 2015 (ADAMS Accession No. 15029A496), the licensee revised the reference to Revision 2-A of the same topical report. In issuing the amendment, the NRC staff inadvertently stated Revision 3-A instead of Revision 2-A.

We are issuing this letter to correct the error in accordance with the guidance stated in SECY-96-238, dated January 16, 1997 (ADAMS Legacy Library Accession No. ML9611250030), which was approved by the Commission on December 17, 1996, via a Staff Requirements Memorandum (ADAMS Accession No. ML003754054). Enclosed are the corrected TS pages 6-15b; please use these pages to replace corresponding pages issued by Amendment Nos. 226 and 176 for the units. This correction does not change any of the conclusions in the safety evaluation associated with the amendments.

M. Nazar If you have any questions regarding this matter, please call me at (301) 415-1447.

(?~sh Farideh E. Saba, Seni~ject Manager Plant Licensing Branch 11-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-335 and 50-389

Enclosures:

Corrected TS Page 6-15b for each unit cc: Distribution via Listserv

ADMINISTRATIVE CONTROLS (2) conform to the guidance of Appendix I to 10 CFR Part 50, and (3) include the following:

1) Monitoring, sampling, analysis, and reporting of radiation and radionuclides in the environment in accordance with the methodology and parameters in the ODCM.
2) A Land Use Census to ensure that changes in the use of areas at and beyond the SITE BOUNDARY are identified and that modifications to the monitoring program are made if required by the results of this census, and
3) Participation in a lnterlaboratory Comparison Program to ensure that independent checks on the precision and accuracy of the measurements of radioactive materials in environmental sample matrices are performed as part of the quality assurance program for environmental monitoring.
h. Containment Leakage Rate Testing Program A program to implement the leakage rate testing of the containment as required by 10 CFR 50.54(0) and 10 CFR 50 Appendix J, Option B, as modified by approved exemptions. This program is in accordance with the guidelines contained in NEI 94-01, Revision 2-A, "Industry Guideline for Implementing Performance-Based Option of 10 CFR Part 50, Appendix J," except that the next Type A test performed after the December 8, 2005 Type A test shall be performed no later than December 8, 2020.

The peak calculated containment irltl3triaf.pressure for the design basis loss of coolant accident Pa. is 42.8 psig. The containment design pressure is 44 psig.

The maximum allowed containment leakage rate, La. at Pa. shall be 0.50% of containment air weight per day.

Leakage rate acceptance criteria are:

a. Containment leakage rate acceptance criterion is~ 1.0 La. During the first unit startup following testing in accordance with this program, the leakage rate acceptance criteria are < 0.60 La for the Type B and C tests,

~ 0.75 La for Type A tests, and~ 0.096 La for secondary containment bypass leakage paths.

b. Air lock testing acceptance criteria are:
1) Overall air lock leakage rate is~ 0.05 La when tested at~ Pa.
2) For the personnel air lock door seal, leakage rate is < 0.01 La when pressurized to~ 1.0 Pa.
3) For the emergency air lock door seal, leakage rate is < 0.01 La when pressurized to~ 10 psig.

ST. LUCIE - UNIT 1 6-15b Amendment No. 69, 00, ~. 449, 487, 4-91-, ~. ~, 226 Corrected by letter dated 10/19/15

ADMINISTRATIVE CONTROLS than 8 days in gaseous effluents released from each unit to areas beyond the SITE BOUNDARY conforming to Appendix I to 10 CFR Part 50,

10) Limitations on the annual dose or dose commitment to any MEMBER OF THE PUBLIC, beyond the site boundary, due to releases of radioactivity and to radiation from uranium fuel cycle sources conforming to 40 CFR Part 190.

The provisions of Specifications 4.0.2 and 4.0.3 are applicable to the Radioactive Effluent Controls Program surveillance frequency.

g. Radiological Environmental Monitoring Program A program shall be provided to monitor the radiation and radionuclides in the environs of the plant. The program shall provide (1) representative measurements of radioactivity in the highest potential exposure pathways, and (2) verification of the accuracy of the effluent monitoring program and modeling of the environmental exposure pathways. The program shall (1) be contained in the ODCM, (2) conform to the guidance of Appendix I to 10 CFR Part 50, and (3) include the following:
1) Monitoring, sampling, analysis, and reporting of radiation and radionuclides in the environment in accordance with the methodology and parameters in the ODCM.
2) A Land Use Census to ensure that changes in the use of areas at and beyond the SITE BOUNDARY are identified and that modifications to the monitoring program are mad~f required by the results of this census, and
3) Participation in a lnterlaboratory Comparison Program to ensure that independent checks on the precision and accuracy of the measurements of radioactive materials in environmental sample matrices are performed as part of the quality assurance program for environmental monitoring.
h. Containment Leakage Rate Testing Program A program. to implement the leakage rate testing of the containment as required by 10 CFR 50.54(0) and 10 CFR 50 Appendix J, Option B, as modified by approved exemptions. This program is in accordance with the guidelines contained in NEI 94-01, Revision 2-A, "Industry Guideline for Implementing Performance-Based Option of 10 CFR Part 50, Appendix J," except that the next Type A test performed after the December 18, 2007 Type A test shall be performed no later than December 18, 2022.

The peak calculated containment internal pressure for the design basis loss of coolant accident Pa, is 43.48 psig. The containment design pressure is 44 psig.

The maximum allowed containment leakage rate, La, at Pa, shall be 0.50% of containment air weight per day.

ST. LUCIE - UNIT 2 6-15b Amendment No. ~. ~. ~. 44Q, 446, 4eJ ' 1 7 6 Corrected by letter dated 10/19/15

ML15280A377 (Pkg. ; ML15280A392 'Letter); ML15280A422 (TS)N RR-058 OFFICE LPL2-2/PM LPL2-2/PM LPL2-2/LA LPL2-2/BC LPL2-2/PM NAME PBuckberg PTam for BClayton SHelton PTam for FSaba FSaba DATE 10/15/2015 10/16/15 10/15115 10/19/15 10/19/15