Discusses Status of Preparation of Emergency Power Sys Repts for Plant,Units 1,2 & 3
ML15238A368
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 02/18/1997
From: Labarge D
NRC (Affiliation Not Assigned)
To: Hampton J
DUKE POWER CO.
References
TAC-M93550, NUDOCS 9702200319
Download: ML15238A368 (4)


Text

pktREQ(41 UNITED STATES 0

NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 February 18, 1997 Mr. J. W. Hampton Vice President, Oconee Site Duke Power Company P. 0. Box 1439 Seneca, SC 29679

SUBJECT:

STATUS OF PREPARATION OF EMERGENCY POWER SYSTEM REPORTS OCONEE NUCLEAR STATION UNITS 1, 2, AND 3 (TAC NO. M93550)

Dear Mr. Hampton:

By letter dated July 8, 1996, the NRC issued draft reports from the Office of Nuclear Reactor Regulation (NRR) and the Office for Analysis and Evaluation of Operational Data (AEOD) for your comments. These draft reports contain analyses and recommendations regarding the testing, operation, design and reliability of the Oconee emergency power system and Standby Shutdown Facility. By letter dated October 31, 1996, you submitted a detailed response to the draft reports.

On January 2-5, 1997, a functional test was performed that was designed to demonstrate the adequacy of the emergency power system. By letter dated January 30, 1997, you outlined your schedule for submitting the results of the test. The first report, consisting of the functional test data and analysis, will be submitted by April 30, 1997, and the final report, consisting of a review of the CYME computer model, by December 31, 1997.

At present, the staff is reviewing the information you supplied in your letter of October 31, 1996, in order to close as many issues as possible. When the functional test data are received, they will be used to further address the issues. The results will be used to generate final documents addressing the issues and summarizing the acceptability of the Oconee emergency power system.

Since completion of these documents is dependent upon receipt of your April 30, 1997, submittal, it is expected that our review will be completed by May 30, 1997. In addition, since your information related to the CYME model will not be available for staff review until December 31, 1997, a supplement is planned to be issued by January 31, 1998, to document the results of our review of this information.

We fully expect that the result of this activity will close out most-of the issues; i.e., issues for which sufficient documentation and evidence exist for resolution. There will, however, be a small number of issues that cannot be closed out in these reports. For example, tests related to the concern of the adequacy of the reactor coolant pump seal flow when initiated from the Standby Shutdown Facility are planned, but will not be performed for all three Oconee units until the next Unit 3 refueling outage. Issues such as these will be addressed separately when the information is received and evaluated.

9702200319 970218 INC FLE CENTER COPY PDR ADOCK 05000269 P

PDR

Mr. J. W. Hampton

-2 Since completion of our actions is dependent on the dates and completeness of your submittals, we urge you to improve the target dates of your submittals, especially the latter one.

In addition, we note that you have, or will have, submitted additional documents related to this subject for staff approval, such as Oconee Technical Specification amendments. Although some of the issues are at least partially related to the topics in the reports, there are additional considerations in these submittals that are not addressed in the reports. These actions will, therefore, be reviewed on a separate schedule from those addressed in this letter.

Sincerely, David E. LaBarge, Senior Project Manager Project Directorate 11-2 Division of Reactor Projects -

I/II Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270 and 50-287 cc: See next page

Mr. J. W. Hampton February 18, 1997 Since completion of our actions is dependent on the dates and completeness of your submittals, we urge you to improve the target dates of your submittals, especially the latter one.

In addition, we note that you have, or will have, submitted additional documents related to this subject for staff approval, such as Oconee Technical Specification amendments. Although some of the issues are at least partially related to the topics in the reports, there are additional considerations in these submittals that are not addressed in the reports. These actions will, therefore, be reviewed on a separate schedule from those addressed in this letter.

Sincerely, Original signed by:

David E. LaBarge, Senior Project Manager Project Directorate 11-2 Division of Reactor Projects -

I/II Office of Nuclear Reactor Regulation Docket Nos. 50-269, 50-270 and 50-287 cc:

See next page Distribution:

Docket File PUBLIC PD 11-2 Rdg.

SVarga JZwol inski.

HBerkow LBerry DLaBarge 000 ACRS JJohnson, RH RCrlenjak, RH CCasto, RII JCalvo JRosenthal' To receive a copy of this document, inditate in the box:

"C" = Copy without'attachmen't/enclosure "E"

,='Copy with attachment/enclosure "N" = No copy A *See previods concurrence OFFICE PI I PDII-2/LA EELB AEOD PD NAME DLaBarlW:cn

,,LBerry.

Jr )

JCalvo*

Joet~,

H~rt DATE Iav 97JRosenth HB'er w

1A')

t/9

/1/97 2/14/97

,,l /'~

2/ i/97

Duke Power Company Oconee Nuclear Station cc:

Mr. Paul R. Newton Mr. Ed Burchfield Legal Department (PB05E)

Compliance Duke Power Company Duke Power Company 422 South Church Street Oconee Nuclear Site Charlotte, North Carolina 28242-0001 P. 0. Box 1439 Seneca, South Carolina 29679 J. Michael McGarry, III, Esquire Winston and Strawn Ms. Karen E. Long 1400 L Street, NW.

Assistant Attorney General Washington, DC 20005 North Carolina Department of Justice Mr. Robert B. Borsum P. 0. Box 629 Framatome Technologies Raleigh, North Carolina 27602 Suite 525 1700 Rockville Pike Mr. G. A. Copp Rockville, Maryland 20852-1631 Licensing - EC050 Duke Power Company Manager, LIS 526 South Church Street NUS Corporation Charlotte, North Carolina 28242-0001 2650 McCormick Drive, 3rd Floor Clearwater, Florida 34619-1035 Mr. Dayne H. Brown, Director Division of Radiation Protection Senior Resident Inspector North Carolina Department of U. S. Nuclear Regulatory Commission Environment, Health and Route 2, Box 610 Natural Resources Seneca, South Carolina 29678 P. 0. Box 27687 Raleigh, North Carolina 27611-7687 Regional Administrator, Region II U. S. Nuclear Regulatory Commission 101 Marietta Street, NW. Suite 2900 Atlanta, Georgia 30323 Max Batavia, Chief Bureau of Radiological Health South Carolina Department of Health and Environmental Control 2600 Bull Street Columbia, South Carolina 29201 County Supervisor of Oconee County Walhalla, South Carolina 29621