Required Notification of Receipt of All Required Regulatory Approvals of the Proposed Direct Transfer Action
ML15210A049
Person / Time
Site: Harris, Brunswick  Duke Energy icon.png
Issue date: 07/29/2015
From: Repko R
Duke Energy Progress
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RA-15-0033, TAC MF5505, TAC MF5506, TAC MF5507
Download: ML15210A049 (4)


Text

(_~ DUKE Regis T. Repko 526 South Church Street ENERGY. Charlotte, NC 28202 Mailing Address:

Mail Code ECOlH / P.O. Box 1006 Charlotte, NC28201-1006 704-382-4126 Serial: RA-15-0033 July 29, 2015 U.S. Nuclear Regulatory Commission ATTN: Director- Office of Nuclear Reactor Regulation Washington, DC 20555-0001 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-325 AND 50-324 I RENEWED LICENSE NOS. DPR-71 AND DPR-62 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400 I RENEWED LICENSE NO. NPF-63

SUBJECT:

Required Notification of Receipt of All Required Regulatory Approvals of the Proposed Direct Transfer Action

REFERENCES:

1. Duke Energy letter, Application for Order Approving Transfer of Control of License and for Conforming License Amendment Pursuant to 10 CFR 50.80 and 10 CFR 50.90, dated December 22, 2014 (ADAMS Accession No. ML14358A253)
2. NRC letter, Orders Approving Direct Transfer of Control of Licenses and Conforming Amendments Related to Brunswick Steam Electric Plant, Units 1 and 2, and Shearon Harris Nuclear Power Plant, Unit 1 (TAC NOS. MF5505, MF5506, and MF5507), dated July 6, 2015 (ADAMS Accession No. ML15159A632)

On December 22, 2014, Duke Energy submitted to the Nuclear Regulatory Commission (NRC),

an Application for Order Approving Transfer of Control of License and for Conforming License Amendment Pursuant to 10 CFR 50.80 and 10 CFR 50.90 (Reference 1). Supplements to the Application were submitted to the NRC on March 4, 2015, June 1, 2015, June 10, 2015, and June 24, 2015.

The NRC approved the direct transfer of the licenses on July 6, 2015 (Reference 6). The July 6, 2015 letter included a requirement that Duke Energy inform the Director of the Office of Nuclear Reactor Regulation in writing of receipt of all required regulatory approvals of the proposed direct transfer action no later than two business days prior to the date of the closing of the direct transfer. The closing date of the acquisition and transfer is scheduled to occur on July 31 ,

2015. This letter fulfils that requirement.

This letter does not include any new or revised regulatory commitments.

U.S. Nuclear Regulatory Commission RA-15-0033 Page2 Should you have any questions concerning this letter, or require additional information, please contact Art Zaremba, Manager- Nuclear Fleet Licensing, at 980-373-2062.

Sincerely, Regis T. Repko Senior Vice President - Governance, Projects and Engineering NDE

U.S. Nuclear Regulatory Commission RA-15-0033 Page 3 cc: Document Control Desk USNRC Region II J. D. Austin, USNRC Resident Inspector- SHNPP M.P. Catts, USNRC Resident Inspector- BSEP Andrew L. Hon, NRR Project Manager- BSEP Martha C. Barillas, NRR Project Manager- SHNPP W. L. Cox, Ill, Chief, North Carolina Department of Health and Human Services, RP Section (NC}

S. E. Jenkins, Manager, Radioactive and Infectious Waste Management (SC}

Chairman, North Carolina Utilities Commission

U.S. Nuclear Regulatory Commission RA-15-0033 Page4 bee: Chris Nolan Art Zaremba Nicole Edwards Lara Nichols Kate Nolan File: (Corporate)

Electronic Licensing Library (ELL)

Randy Gideon Lee Grzeck Bill Murray (For BSEP Licensing/Nuclear Records Files)

Ben Waldrep John Caves Cindy Hereford (For SHNPP Licensing/Nuclear Records Files)