Letter Sequence RAI |
---|
|
|
MONTHYEARML15022A6622014-05-31031 May 2014 Acoustic and Low Frequency Hydrodynamic Loads at 115% CLTP Target Power Level on Nine Mile Point Unit 2 Steam Dryer to 250 Hz Using ACM Rev. 4.1R, C.D.I. Report No. 14-09NP, Revision 1, Non-proprietary Version Project stage: Request ML14216A3472014-07-28028 July 2014 Submittal of Post Extended Power Uprate Steam Dryer Inspection Results in Accordance with Operating License Condition 2.C.(20)(f) and 2.C.(20)(g) Project stage: Request ML15022A6612014-07-31031 July 2014 Stress Re-Evaluation of Nine Mile Point Unit 2 Steam Dryer at 115% CLTP, CDI Report No. 14-08NP, Revision 0, Non-proprietary Version Project stage: Request ML14225A2222014-08-13013 August 2014 MF4559, Request for Additional Information Submittal of Post EPU Steam Dryer Inspection Results in Accordance with Operating License Condition 2.C.(20)(f) and 2.C.(20)(g) Project stage: RAI ML15023A0302015-01-14014 January 2015 Supplement to Response to Request for Additional Information - Nine Mile Point Unit 2, Submittal of Post Extended Power Uprate Steam Dryer Inspection Results in Accordance with Operating License Condition 2.C.(20)(f) and 2.C.(20)(g) Project stage: Supplement ML15027A2582015-02-0303 February 2015 Request for Withholding Information from Public Disclosure Submission Dated 1/14/15, for Supplement to Response to RAI - Submittal of Post Extended Power Uprate Steam Dryer Inspection Results (MF4559) Project stage: RAI ML15198A3592015-08-0505 August 2015 Request for Additional Information Regarding Post Extended Power Uprate Steam Dryer Inspection Results Project stage: RAI 2014-08-13
[Table View] |
|
---|
Category:Letter
MONTHYEARML24268A3382024-10-16016 October 2024 Issuance of Amendment No. 253 Regarding the Modification of TS Surveillance Requirement 4.3.6.a Related to Adoption of TSTF-425, Revision 3 RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing IR 05000220/20243022024-10-0303 October 2024 Initial Operator Licensing Examination Report 05000220/2024302 NMP1L3608, Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-09-20020 September 2024 Supplemental Information Letter No. 3 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation RS-24-090, Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-09-12012 September 2024 Response to Request for Additional Information - Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000220/20240052024-08-29029 August 2024 Updated Inspection Plan for Nine Mile Point Nuclear Station, Units 1 and 2 (Report 05000220/2024005 and 05000410/2024005) IR 05000220/20240102024-08-22022 August 2024 Age-Related Degradation Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3603, Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan2024-08-20020 August 2024 Submittal of Preliminary Decommissioning Cost Estimate and Irradiated Fuel Management Plan ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000220/20240022024-08-0505 August 2024 Integrated Inspection Report 05000220/2024002 and 05000410/2024002 ML24215A3002024-08-0202 August 2024 Operator Licensing Examination Approval ML24213A1412024-07-31031 July 2024 Requalification Program Inspection NMP1L3601, Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-07-31031 July 2024 Supplemental Information Letter No. 2 - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation NMP2L2883, Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations2024-07-24024 July 2024 Fourth Inservice Inspection Interval, Second Inservice Inspection Period 2024 Owner’S Activity Report for RFO-19 Inservice Examinations ML24198A0852024-07-16016 July 2024 Senior Reactor and Reactor Operator Initial License Examinations RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations NMP1L3584, License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling2024-06-13013 June 2024 License Amendment Request to Revise Technical Specifications to Adopt TSTF-230, Revision 1, Add New Condition B to LCO 3.6.2.3, RHR Suppression Pool Cooling IR 05000220/20244012024-05-30030 May 2024 Security Baseline Inspection Report 05000220/2024401 and 05000410/2024401(Cover Letter Only) ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 NMP1L3591, Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request2024-05-18018 May 2024 Response to Ny State Pollutant Discharge Elimination System (SPDES) Permit Request for Information & Modification Request NMP1L3589, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-05-16016 May 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable NMP1L3582, 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 22024-05-15015 May 2024 2023 Annual Radioactive Environmental Operating Report for Nine Mile Point Units 1 and 2 ML24158A2052024-05-15015 May 2024 Annual Radioactive Environmental Operating Report IR 05000220/20240012024-05-10010 May 2024 Integrated Inspection Report 05000220/2024001 and 05000410/2024001 RS-24-049, Updated Notice of Intent to Pursue Subsequent License Renewal Applications2024-05-0909 May 2024 Updated Notice of Intent to Pursue Subsequent License Renewal Applications RS-24-038, Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds2024-05-0202 May 2024 Relief Request Concerning Extension of Permanent Relief from Ultrasonic Examination of Reactor Pressure Vessel Circumferential Shell Welds NMP2L2880, Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum2024-05-0101 May 2024 Automatic Reactor Scram on Turbine Trip Due to Low Condenser Vacuum NMP1L3581, Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report2024-04-30030 April 2024 Independent Spent Fuel Storage Installation (ISFSI) - 2023 Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests NMP2L2877, 2023 Annual Environmental Operating Report2024-04-19019 April 2024 2023 Annual Environmental Operating Report NMP2L2878, Core Operating Limits Report2024-04-16016 April 2024 Core Operating Limits Report ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24092A3352024-04-0101 April 2024 NRC Office of Investigations Case No. 1-2023-002 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24074A2812024-03-14014 March 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000220/2024010 and 05000410/2024010 NMP1L3577, Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable2024-03-13013 March 2024 Special Report: Containment High Range Radiation Monitor Instrumentation Channel 12 Inoperable IR 05000220/20230062024-02-28028 February 2024 Annual Assessment Letter for Nine Mile Point Nuclear Station, Units 1 and 2, (Reports 05000220/2023006 and 05000410/2023006) NMP1L3570, Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation2024-02-0101 February 2024 Supplemental Information Letter - Revision to the Technical Specifications Design Features Sections to Remove the Nine Mile 3 Nuclear Project, LLC, Designation IR 05000220/20230042024-02-0101 February 2024 Integrated Inspection Report 05000220/2023004 and 05000410/2023004 05000410/LER-2023-001, Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater2024-01-30030 January 2024 Supplement to LER 2023-001-00, Automatic Reactor Scram on Low Level Due to Partial Loss of Feedwater NMP1L3569, CFR 50.46 Annual Report2024-01-26026 January 2024 CFR 50.46 Annual Report ML24004A2122024-01-0808 January 2024 Senior Reactor and Reactor Operator Initial License Examinations ML23354A0012024-01-0404 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0059 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) ML23278A1292023-12-14014 December 2023 Units 1 & 2; Limerick, Units 1 & 2; Nine Mile Point, Units 1 & 2; and Peach Bottom, Units 2 & 3 -Revision to Approved Alternatives to Use Boiling Water Reactor Vessel and Internals Project Guidelines NMP1L3566, Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station2023-12-14014 December 2023 Radiological Emergency Plan Document Revision. Includes EP-AA-1013, Revision 10, Radiological Emergency Plan Annex for Nine Mile Point Station IR 05000410/20243012023-12-14014 December 2023 Initial Operator Licensing Examination Report 05000410/2024301 ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 2024-09-04
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24074A2812024-03-14014 March 2024 Request for Information and Notification of Conduct of IP 71111.21.N.04, Age-Related Degradation, Reference Inspection Report 05000220/2024010 and 05000410/2024010 ML23264A7992023-09-21021 September 2023 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC Fleet Request License Amendment Request to Adopt TSTF-580, Revision 1 ML23205A2432023-07-19019 July 2023 NRC Staff Follow-up Question on Audit Question 18 TSTF-505 and 50.69 Regulatory Audit (E-mail Dated 7/19/2023) (EPIDs L-2022-LLA-0185 and L-2022-LLA-0186) ML23087A2912023-03-28028 March 2023 Request for Additional Information (3/28/2023 E-mail) - Proposed Emergent I5R-11 Alternative Associated with a Weld Overlay on RPV Recirculation Nozzle N2E DM Weld ML23061A0522023-03-0202 March 2023 Request for Additional Information (3/2/2023 E-mail) - Proposed Alternative Associated with a Weld Overlay Repair to the Torus ML23012A2002023-01-13013 January 2023 Information Request for the Cyber Security Baseline Inspection, Notification to Perform Inspection 05000220/2023401 and 05000410/2023401 ML22207A2162022-07-26026 July 2022 Information Request to Support Triennial Baseline Design-Basis Capability of Power-Operated Valves Inspection; Inspection Report 05000220/2022010 and 05000410/2022010 ML22194A9412022-07-13013 July 2022 Request for Additional Information Relief Request CS-PR-02 (7/13/2022 e-mail) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML22020A0642022-01-13013 January 2022 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative for Repair of Water Level Instrumentation Partial Penetration Nozzles ML21320A3472021-11-16016 November 2021 Request for Additional Information LAR to Revise TSs to Adopt TSTF-582, Revision 0 ML21306A3312021-11-0202 November 2021 Request for Additional Information Alternative Request GV-RR-10 (11/2/2021 e-mail) ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21125A1282021-05-0404 May 2021 OPC Document Request - Feb 2021 ML21110A5112021-04-20020 April 2021 Request for Additional Information Review of License Amendment Request to Revise Technical Specifications to Adopt TSTF-582 ML21088A2682021-03-30030 March 2021 Notification of Conduct of a Fire Protection Team Inspection ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML20365A0092020-12-30030 December 2020 Request for Additional Information Concerning Review of License Amendment Request and Relief Request to Change Excess Flow Check Valve Testing Frequency (EPIDs L-2020-LLA-0188 and L-2020-LLR-0114) ML20358A2602020-12-28028 December 2020 Changes to Draft Request for Additional Information Regarding License Amendment Request and Relief Request to Change Excess Flow Check Valve Testing Frequency ML20272A2802020-09-28028 September 2020 Withdrawal and Replacement of Request for Additional Information to Support Review of License Amendment Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times ML20248H5192020-09-28028 September 2020 Changes to Draft Request for Additional Information Regarding Request to Revise Technical Specifications to Adopt Risk-Informed Completion Times ML20246G6362020-09-0202 September 2020 Request for Additonal Information to Support Review of License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times NMP2L2739, Request for Additional Information for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 22020-08-28028 August 2020 Request for Additional Information for Nine Mile Point Nuclear Station, Unit 2, to Adopt TSTF-505, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, Revision 2 ML20239A7982020-08-25025 August 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet License Amendment Request to Adopt TSTF-568, Revision 2 ML20212L8702020-07-30030 July 2020 Request for Additonal Information Review of License Amendment Requests Regarding Riskinformed Categorization and Treatment of Structures, Systems and Components (L-2019-LLA-0290) ML20213A9352020-07-30030 July 2020 Request for Additional Information Review of License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times ML20153A7042020-06-0101 June 2020 NRR E-mail Capture - Preliminary RAI for Fleet Request to Use Alternative OMN-26 ML20135H1972020-05-14014 May 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Extend Safety Relief Valve Test Interval ML20045E3582020-02-14014 February 2020 Draft Request for Additional Information Regarding License Amendment Request to Increase Allowable MSIV Leakage Rates ML19296A1862019-10-23023 October 2019 Request for Additional Information Regarding License Amendment Request to Increase Allowable MSIV Leakage Rates (L-2019-LLA-0115) ML19275H1362019-10-0202 October 2019 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Use ASME Code Case N-879 ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML19151A8132019-05-31031 May 2019 Licensed Operator Positive Fitness-For-Duty Test ML19025A1572019-01-25025 January 2019 Request for Additional Information Regarding Primary Containment Oxygen Concentration License Amendment Request ML19025A1202019-01-24024 January 2019 NRR E-mail Capture - Calvert Cliffs, Fitzpatrick, and Nine Mile Point - Request for Additional Information Regarding License Amendment Request to Revise Emergency Response Organization Staffing ML18341A2212018-12-0707 December 2018 Request for Additional Information Regarding Emergency Tech Spec Change Re HPCS Completion Time (EPID -L-2018-LLA-0491) ML18228A6932018-08-15015 August 2018 Request for Additional Information Regarding Reactor Pressure Vessel Water Inventory Control License Amendment Request (L-2017-LLA-0426) ML18205A3922018-07-24024 July 2018 Request for Additional Information Regarding Reactor Pressure Vessel Water Inventory Control License Amendment Request (L-2017-LLA-0426) ML18184A2882018-07-0303 July 2018 Request for Additional Information Regarding Removal of Boraflex Credit from Spent Fuel Pool License Amendment Request(L-2018-LLA-0039) ML18102A2372018-04-12012 April 2018 NRR E-mail Capture - Calvert Cliffs, Ginna, and Nine Mile Point - Request for Additional Information Regarding License Amendment Request to Revise Emergency Action Level Schemes (EPID-L-2017-LLA-0237) ML18067A1482018-03-0808 March 2018 Enclosurequest for Additional Information (Letter to P. R. Simpson Request for Additional Information Regarding Exelon Generating Company, Llc'S Decommissioning Funding Plan Update for Independent Spent Fuel Storage Installation) ML17331B1342017-12-12012 December 2017 2, and R.E. Ginna Nuclear Power Plant - Request for Additional Information - Regarding ML17285B1962017-10-27027 October 2017 Request for Additional Information Regarding Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools. ML17272A0112017-10-10010 October 2017 Request for Additional Information Regarding License Amendment Concerning Reactor Pressure Vessel Water Inventory Control ML17234A3592017-08-30030 August 2017 Request for Additional Information Regarding Relief Request NMP-RR-001 to Utilize Code Case N-702 ML17241A2752017-08-29029 August 2017 Request for Additional Information Response MSA (MF7946,7) and FE (MG0087,8) E-mail Attachment 2024-07-12
[Table view] |
Text
OFFICIAL USE ONLY PROPRIETARY INFORMATION UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 August 5, 2015 Mr. Peter Orphanos Vice President Nine Mile Point Exelon Generation Company, LLC Nine Mile Point Nuclear Station, LLC P. 0. Box 63 Lycoming, NY 13093
SUBJECT:
NINE MILE POINT NUCLEAR STATION, UNIT 2 - REQUEST FOR ADDITIONAL INFORMATION REGARDING POST EXTENDED POWER UPRATE STEAM DRYER INSPECTION RESULTS (TAC NO. MF4559)
Dear Mr. Orphanos:
By letter dated July 28, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14216A347), as supplemented by letter dated January 14, 2015, (ADAMS Accession No. ML15023A030), Exelon Generation Company, LLC, submitted the post extended power uprate steam dryer inspection results, and the supporting reports for the Nine Mile Point Nuclear Station, Unit 2 (NMP2). The submittals were in accordance with operating license conditions 2.C.(20)(f) and 2.C.(2)(g).
The U.S. Nuclear Regulatory Commission (NRC) staff has reviewed the information provided in that letter and has determined that additional information is needed to complete its review.
Enclosed is the NRC staff's request for additional information (RAI). Enclosure 1 provides the non-proprietary version of the RAls, and Enclosure 2 provides the proprietary version of the RAls, identifying the proprietary information with text in double brackets ((( ... ))).
NOTICE: Enclosure 2 to this letter contains Proprietary information. Upon separation from Enclosure 2, this letter is DECONTROLLED.
OFFICIAL USE ONLY PROPRIETARY INFORMATION
OFFICIAL USE ONLY PROPRIETARY INFORMATION The RAI was discussed with your staff and additional information was provided in the January 14, 2015, supplement. The staff is requesting further additional information, and it was agreed that your response would be provided no later than August 20, 2015.
Please contact me if you have any questions.
Sincerely, Brenda L. Mozafari, Sr. Project Manager Plant Licensing Branch 1-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-41 O
Enclosures:
- 1. RAls (Non-Proprietary)
- 2. RAls (Proprietary) cc w/encl 1 only: Distribution via Listserv OFFICIAL USE ONLY PROPRIETARY INFORMATION
OFFICIAL USE ONLY PROPRIETARY INFORMATION ENCLOSURE 1 REQUEST FOR ADDITIONAL INFORMATION POST EXTENDED POWER UPRATE STEAM DRYER INSPECTION RESULTS AND SUPPORTING REPORTS NINE MILE POINT NUCLEAR STATION, LLC EXELON GENERATION COMPANY. LLC DOCKET NO. 50-410 NINE MILE POINT NUCLEAR STATION, UNIT 2 (NON-PROPRIETARY)
Proprietary information pursuant to Section 2. 390 of Title 10 of the Code of Federal Regulations has been redacted from this document.
Redacted information is identified by blank space enclosed within double brackets.
OFFICIAL USE ONLY PROPRIETARY INFORMATION
OFFICIAL USE ONLY PROPRIETARY INFORMATION REQUEST FOR ADDITIONAL INFORMATION POST EXTENDED POWER UPRATE STEAM DRYER INSPECTION RESULTS AND SUPPORTING REPORTS NINE MILE POINT NUCLEAR STATION, LLC EXELON GENERATION COMPANY, LLC DOCKET NO. 50-410 NINE MILE POINT NUCLEAR STATION, UNIT 2 (NON-PROPRIETARY)
By letter dated July 28, 2014 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML14216A347), as supplemented by letter dated January 14, 2015, (ADAMS Accession No. ML15023A030), Exelon Generation Company, LLC (the licensee),
submitted the post extended power uprate (EPU) steam dryer (SD) inspection results for Nine Mile Point Nuclear Station, Unit 2 (NMP2), in accordance with operating license condition 2.C.(20)(f) and 2.C.(20)(g).
The NRC Staff has reviewed the referenced documents provided by the licensee in response to EMCB-NMP2-MF4559-SD-First RFO Post EPU-RA/-3 pertaining to the acoustic circuit model (ACM) 4.1 R computer code revision, and changes to the acoustic damping values and bias uncertainties. The licensee is requested to provide the following additional information:
First Refueling Outage (RFO) Post EPU-RAl-4 The licensee has installed the bolted U-channel attached to upper dryer inner side plates connected to inner vane banks to structurally stiffen the steam dryer such that the minimum alternating stress ratio (SR-a) becomes greater than 2.0. The staff is requesting the following clarification regarding the implemented retrofit:
- a. Provide a comparison of stress ratios (SR-P and SR-a) for the 54 nodes listed in Table 17 (COi [Continuum Dynamics, Inc.] Report 14-0BP, Rev. 0) for the dryer with and without the U-channel stiffener and subject to N59 load (Drain Trap out of service).
- b. For the stiffened steam dryer, please provide cumulative stress distributions for the five locations on both the hood and skirt with the SR-a.
OFFICIAL USE ONLY PROPRIETARY INFORMATION Enclosure 1
OFFICIAL USE ONLY PROPRIETARY INFORMATION
- c. Explain how dryer alternating stresses due to Reactor Recirculation Pump (RRP) Vane Passing Frequency (VPF) tones are accounted for in the modified NMP2 dryer. The dryer structural modes may have shifted due to the addition of the U-channel so some may now align with VPF.
First RFO Post EPU-RAl-5
((
a.
b.
))
First RFO Post EPU-RAl-6
((
)) The staff is requesting the following clarifications related to the modified ACM 4.1 code (ACM 4.1 R code), and the associated Main Steam Line (MSL) signals.
- a. Explain why the unfiltered lower MSL C strain gage power spectral density (PSD) is so much higher than those of MSL A, B, and D (See Figures 3.1 a, b; and 3.2 a, b in CDI Report 14-09P). Confirm the data acquisition and calibration settings, along with the matching of strain gages and channel numbers.
- b. Explain the cause(s) of the sharp-125 Hz peaks in the PSDs of MSL D.
- c. ((
))
- d. ((
OFFICIAL USE ONLY PROPRIETARY INFORMATION
OFFICIAL USE ONLY PROPRIETARY INFORMATION (i)
(ii)
))
- e. ((
))
First RFO Post EPU-RAl-7
- a. ((
))
- b. ((
))
- c. What bias error and uncertainty are assigned to the dryer loading associated with the 89.3 Hz RCIC valve closure tone and (( ))?
Provide the same information for the -125 Hz peak in MSL D.
OFFICIAL USE ONLY PROPRIETARY INFORMATION
OFFICIAL USE ONLY PROPRIETARY INFORMATION
References:
- 1. CDI Report No.14-09P, "Acoustic and Low Frequency Hydrodynamic Loads at 115% CLTP [Current Licensed Thermal Power] Target Power Level on Nine Mile Point Unit 2 Steam Dryer to 250 Hz Using ACM 4.1 R" (ML15022A666).
- 2. CDI Report No.14-08P, "Stress Re-Evaluation of Nine Mile Point Unit 2 Steam Dryer at 115% CLTP" (ML15022A665).
- 3. CDI Report No.14-04P, "Computation of the Cumulative Usage Factor for the 115%
stress Re-Evaluation of Nine Mile Point Unit 2 Steam Dryer at 115% CLTP power level at Nine Mile Point Unit 2 with the Inboard RCIC valve closed" (ML15022A664).
OFFICIAL USE ONLY PROPRIETARY INFORMATION
PKG: ML15198A356 LTR: ML15198A359 Enc Iosure 2 : ML15198A363 *.
via e-ma1*1 d ae t d J Liiy I 13 2015 OFFICE DORL/LPLl-1 /PM DORL/LPLl-1/LA DE/EMBC/BC(A) DORL/LPLl-1/BC (A) DORL/LPLl-1 /PM (RGuzman for) (RGuzman for)
NAME KGoldstein YU* MDudek BMozafari BMozafari DATE 8/05/2015 7/29/2015 7/13/2015 8/04/2015 8/05/2015