MONTHYEARML13247A2902013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant Project stage: Other CNL-13-118, Change in Commitment Related to Interim Compensatory Measures to Reduce Fire Risk2013-11-22022 November 2013 Change in Commitment Related to Interim Compensatory Measures to Reduce Fire Risk Project stage: Request ML14015A4032013-11-22022 November 2013 Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs-TS-485 Project stage: Other ML14017A0782013-12-24024 December 2013 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 � Acceptance of Requested Licensing Action Amendment (TAC Nos. MF3124, M3125, and MF3126) Project stage: Acceptance Review ML14051A7262014-02-28028 February 2014 Request of Additional Information Regarding Proposed Technical Specification Change to Revise the Leakage Rate Through Main Steam Isolation Valves -TS-485 Project stage: Other CNL-14-028, Second Six Month Status Report in Response to Order No. EA-12-051, Spent Fuel Pool Instrumentation2014-02-28028 February 2014 Second Six Month Status Report in Response to Order No. EA-12-051, Spent Fuel Pool Instrumentation Project stage: Other CNL-14-037, Response to NRC Request for Additional Information Regarding Proposed Technical Specification Change to Revise the Leakage Rate Through Main Steam Isolation Valves - TS-4852014-04-0404 April 2014 Response to NRC Request for Additional Information Regarding Proposed Technical Specification Change to Revise the Leakage Rate Through Main Steam Isolation Valves - TS-485 Project stage: Response to RAI ML14171A2882014-06-19019 June 2014 NRR E-mail Capture - RAIs Regarding Proposed Technical Specification Change to Revise the Leakage Rate Through Msivs � TS-485, TAC Nos. MF3124, MF3125, and MF3126 Project stage: RAI ML14183A0082014-07-0101 July 2014 NRR E-mail Capture - RAI for TACs MF8124, MF8125, and MF8126 for Browns Ferry Project stage: RAI CNL-14-106, Response to NRC Request for Additional Information Regarding Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs - TS-4852014-08-15015 August 2014 Response to NRC Request for Additional Information Regarding Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs - TS-485 Project stage: Response to RAI CNL-14-068, (Bfn), Units 1, 2 and 3 - Supplement to Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs (TS-485)2015-01-29029 January 2015 (Bfn), Units 1, 2 and 3 - Supplement to Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs (TS-485) Project stage: Supplement ML15057A3702015-02-26026 February 2015 March 5, 2015, Forthcoming Closed Meeting with Tennessee Valley Authority Browns Ferry Nuclear Plant Main Steam Isolation Valve Leakage Rate License Amendment Request Project stage: Meeting ML15062A5402015-03-0303 March 2015 March 8, 2015, Rescheduled Forthcoming Closed Meeting with Tennessee Valley Authority Browns Ferry Nuclear Plant Main Steam Isolation Valve Leakage Rate License Amendment Request Project stage: Meeting ML15070A5632015-03-18018 March 2015 March 18, 2015, Meeting Slide for Tennessee Valley Authority, Browns Ferry Nuclear Plant, Units 1, 2, and 3 Discussion of RAI 5-1 Project stage: Request ML15091A6842015-04-0808 April 2015 Request for Additional Information Regarding License Amendment Request to Revise Main Steam Isolation Valve Leakage Project stage: RAI ML15092A7022015-04-17017 April 2015 March 18, 2015, Summary of Closed Meeting with Tennessee Valley Authority to Discuss Draft Radiation Protection and Consequence RAI 5-1 Project stage: Draft RAI CNL-15-070, Withdrawal of Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs - TS-4852015-05-29029 May 2015 Withdrawal of Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs - TS-485 Project stage: Withdrawal ML15161A3442015-06-16016 June 2015 Withdrawal of an Amendment Request Project stage: Withdrawal ML15161A3542015-06-16016 June 2015 FRN Re. Withdrawal of an Amendment Request Project stage: Withdrawal 2014-08-15
[Table View] |
Text
February 26, 2015 MEMORANDUM TO: Shana R. Helton, Chief Plant Licensing Branch II-2 Division of Operator Reactor Licensing Office of Nuclear Reactor Regulation FROM:
Farideh E. Saba, Senior Project Manager /RA/
Plant Licensing Branch II-2 Division of Operator Reactor Licensing Office of Nuclear Reactor Regulation
SUBJECT:
FORTHCOMING CLOSED MEETING WITH TENNESSEE VALLEY AUTHORITY (TVA) REGARDING BROWNS FERRY NUCLEAR PLANT MAIN STEAM ISOLATION VALVE LEAKAGE RATE LICENSE AMENDMENT REQUEST (TAC NOS. MF3124, MF3125, AND MF3126)
DATE AND TIME:
Thursday, March 5, 2015 1:00 p.m. - 3:30 p.m. (Eastern Time)
LOCATION:
U.S. Nuclear Regulatory Commission (NRC)
One White Flint North, Room O-10B06 11555 Rockville Pike Rockville, Maryland 20852 PURPOSE:
To discuss a draft Request for Additional Information regarding the methodology used to determine the main steam line removal coefficients.
Portions of this methodology are considered proprietary and were marked as such in Attachment 5 of the TVA submittal dated November 22, 2015 (ML14015A403). The affidavit in Attachment 11 of the original submittal describes the related proprietary information.
PARTICIPANTS:
Participants from the NRC include members from the Office of Nuclear Reactor Regulation (NRR) and TVA.
NRC/NRR TVA Mark Blumberg Ed Schrull Undine Shoop Dan Green Shana Helton Gerry Doyle Farideh Saba Doug Pollock Roger Pedersen Pete Donahue
CONTACTS:
Farideh Saba Andrew Hon farideh.saba@nrc.gov andrew.hon@nrc.gov 301-415-1447 301-415-8480 To receive a summary of this meeting and begin receiving other plant-specific e-mail distributions, you must subscribe to the Operating Reactor Correspondence electronic distribution for this plant via http://www.nrc.gov/public-involve/listserver/plants-by-region.html.
Once subscribed, if you wish to discontinue receiving electronic distribution, you may unsubscribe at any time by visiting the same Web address above.
Docket Nos. 50-259, 50-260, and 50-296
Enclosure:
Agenda cc w/enclosure: Distribution via Listserv
ML15057A370 OFFICE DORL/LPL2-2/PM DORL/LPL2-2/LAiT DORL/LPL2-2/LA DORL/LPL2-2/BC DORL/LPL2-2/PM NAME FSaba LRonewicz BClayton SHelton FSaba DATE 2/26/15 2/26/15 2/26/15 2/26/15 2/26/15
Enclosure AGENDA FORTHCOMING NUCLEAR REGULATORY COMMISSION (NRC) CLOSED MEETING WITH TENNESSEE VALLEY AUTHORITY (TVA)
REGARDING BROWNS FERRY NUCLEAR PLANT MAIN STEAM ISOLATION VALVE LEAKAGE RATE LICENSE AMENDMENT REQUEST BROWNS FERRY NUCLEAR PLANT, UNITS 1, 2, AND 3 THURSDAY, MARCH 5, 2015 Introduction Opening remarks NRC staffs concerns (Discussion of draft follow-up Request for Additional Information)
TVAs response to Request for Additional Information Discussion of the resolutions Path forward Action items Meeting adjourned