MONTHYEARML13247A2902013-08-28028 August 2013 First Six-Month Status Report in Response to the March 12, 2012, Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) for Browns Ferry Nuclear Plant Project stage: Other CNL-13-118, Change in Commitment Related to Interim Compensatory Measures to Reduce Fire Risk2013-11-22022 November 2013 Change in Commitment Related to Interim Compensatory Measures to Reduce Fire Risk Project stage: Request ML14015A4032013-11-22022 November 2013 Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs-TS-485 Project stage: Other ML14017A0782013-12-24024 December 2013 NRR E-mail Capture - Browns Ferry Nuclear Plant, Units 1, 2, and 3 � Acceptance of Requested Licensing Action Amendment (TAC Nos. MF3124, M3125, and MF3126) Project stage: Acceptance Review ML14051A7262014-02-28028 February 2014 Request of Additional Information Regarding Proposed Technical Specification Change to Revise the Leakage Rate Through Main Steam Isolation Valves -TS-485 Project stage: Other CNL-14-028, Second Six Month Status Report in Response to Order No. EA-12-051, Spent Fuel Pool Instrumentation2014-02-28028 February 2014 Second Six Month Status Report in Response to Order No. EA-12-051, Spent Fuel Pool Instrumentation Project stage: Other CNL-14-037, Response to NRC Request for Additional Information Regarding Proposed Technical Specification Change to Revise the Leakage Rate Through Main Steam Isolation Valves - TS-4852014-04-0404 April 2014 Response to NRC Request for Additional Information Regarding Proposed Technical Specification Change to Revise the Leakage Rate Through Main Steam Isolation Valves - TS-485 Project stage: Response to RAI ML14171A2882014-06-19019 June 2014 NRR E-mail Capture - RAIs Regarding Proposed Technical Specification Change to Revise the Leakage Rate Through Msivs � TS-485, TAC Nos. MF3124, MF3125, and MF3126 Project stage: RAI ML14183A0082014-07-0101 July 2014 NRR E-mail Capture - RAI for TACs MF8124, MF8125, and MF8126 for Browns Ferry Project stage: RAI CNL-14-106, Response to NRC Request for Additional Information Regarding Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs - TS-4852014-08-15015 August 2014 Response to NRC Request for Additional Information Regarding Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs - TS-485 Project stage: Response to RAI CNL-14-068, (Bfn), Units 1, 2 and 3 - Supplement to Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs (TS-485)2015-01-29029 January 2015 (Bfn), Units 1, 2 and 3 - Supplement to Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs (TS-485) Project stage: Supplement ML15057A3702015-02-26026 February 2015 March 5, 2015, Forthcoming Closed Meeting with Tennessee Valley Authority Browns Ferry Nuclear Plant Main Steam Isolation Valve Leakage Rate License Amendment Request Project stage: Meeting ML15070A5632015-03-18018 March 2015 March 18, 2015, Meeting Slide for Tennessee Valley Authority, Browns Ferry Nuclear Plant, Units 1, 2, and 3 Discussion of RAI 5-1 Project stage: Request ML15091A6842015-04-0808 April 2015 Request for Additional Information Regarding License Amendment Request to Revise Main Steam Isolation Valve Leakage Project stage: RAI ML15092A7022015-04-17017 April 2015 March 18, 2015, Summary of Closed Meeting with Tennessee Valley Authority to Discuss Draft Radiation Protection and Consequence RAI 5-1 Project stage: Draft RAI CNL-15-070, Withdrawal of Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs - TS-4852015-05-29029 May 2015 Withdrawal of Proposed Technical Specification Change to Revise the Leakage Rate Through MSIVs - TS-485 Project stage: Withdrawal ML15161A3442015-06-16016 June 2015 Withdrawal of an Amendment Request Project stage: Withdrawal ML15161A3542015-06-16016 June 2015 FRN Re. Withdrawal of an Amendment Request Project stage: Withdrawal 2014-08-15
[Table View] |
Text
1 NRR-PMDAPEm Resource From:
Saba, Farideh Sent:
Tuesday, July 01, 2014 1:51 PM To:
Williams, Gordon Robert (grwilliams1@tva.gov)
Cc:
Schrull, Edward Dustin (edschrull@tva.gov)
Subject:
RAI for TACs MF8124, MF8125, and MF8126 for Browns Ferry Importance:
High Hi Gordon, Below are RAIs from for the subject TACs. As we agreed during the clarification call today, please respond to these RAIs by August 15, 2014.
SCVB RAI-1 The license amendment request letter dated November 22, 2013 identified a commitment (#2) for periodic radiography inspection of the 0.1875-inch orifice (parallel to valve FCV-1-58) to be performed during refueling outages.
- a.
Is this frequency to be each refueling outage?
- b.
With an orifice area this size, debris big enough to bridge the opening and significantly obstruct could be very small. Is the radiography reasonably assured of being capable of detecting such debris?
- c.
Is the orifice flanged/bolted in place or welded? If flanged, why not remove and inspect the orifice/line rather than radiograph?
- d.
Is there any operational way to verify this orifice is unobstructed?
SCVB RAI-2 The license amendment request letter states the Main Steam Stop and Control Valves are included in the preventative maintenance program. As such, one Main Steam Stop and one Control Valve is refurbished each outage. These valves are also tested each refueling outage for leak tightness and are highly reliable. The letter also indicates that the Generic Flow Area to HP Turbine is 0.0288 square inches. Describe the main steam stop and control valve leakage testing that verifies the flow area to the HP turbine is 0.0288 square inches or less.
SCVB RAI-3 The license amendment request letter proposed SR 3.6.1.3.10 reads: Verify leakage rate through each MSIV is 60 scfh and that the combined leakage rate for all four main steam lines is 85 scfh when tested at 25 psig. The frequency is stated as: In accordance with the Primary Containment Leakage Rate Testing Program. How is the combined steam line leakage criterion evaluated? Minimum pathway for assessing past operability, maximum pathway for leaving cold shutdown? Some other basis?
- Thanks, Farideh Farideh E. Saba, P.E.
Senior Project Manager NRC/ADRO/NRR/DORL 301-415-1447 Mail Stop O-8G9A Farideh.Saba@NRC.GOV
Hearing Identifier:
NRR_PMDA Email Number:
1409 Mail Envelope Properties (Farideh.Saba@nrc.gov20140701135000)
Subject:
RAI for TACs MF8124, MF8125, and MF8126 for Browns Ferry Sent Date:
7/1/2014 1:50:58 PM Received Date:
7/1/2014 1:50:00 PM From:
Saba, Farideh Created By:
Farideh.Saba@nrc.gov Recipients:
"Schrull, Edward Dustin (edschrull@tva.gov)" <edschrull@tva.gov>
Tracking Status: None "Williams, Gordon Robert (grwilliams1@tva.gov)" <grwilliams1@tva.gov>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 2251 7/1/2014 1:50:00 PM Options Priority:
High Return Notification:
No Reply Requested:
Yes Sensitivity:
Normal Expiration Date:
Recipients Received:
ZZZ