NRR E-mail Capture - LaSalle Commitment Audit
ML14220A442
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 08/08/2014
From: Blake Purnell
Plant Licensing Branch III
To: Simpson L
Exelon Corp
References
MF4531, MF4532
Download: ML14220A442 (2)


Text

NRR-PMDAPEm Resource From: Purnell, Blake Sent: Friday, August 08, 2014 9:58 AM To: Lisa Simpson (Lisa.Simpson@exeloncorp.com)

Subject:

LaSalle Commitment Audit (TAC Nos. MF4531 and MF4532)

Lisa, In accordance with LIC-105, Managing Regulatory Commitments Made by Licensees to the NRC, Revision 5 (ADAMS Accession No. ML13193A358), NRR/DORL project managers are expected to periodically perform an audit of the licensees commitment management program. The last audit at LaSalle was completed on December 21, 2011 (ADAMS Accession No. ML113350347).

I am starting the preparation for the LaSalle audit. Most of the initial activities (audit sample selection, review of program) will be done at my office and some portion of the audit may be done on site (e.g., review of documentation associated with implementation of a closed commitment).

To facilitate the initial stage of the audit, please provide the following information by September 8, 2014:

1. Copy of the commitment management procedure or program documents used at LaSalle and copies of evaluation documentation related to changes to the program/procedure since the last audit.
2. List of all open regulatory commitments.
3. List of all commitments that have been initiated or closed in the last 3 years.
4. List of commitments that have been changed (i.e., modified or deleted) for the last 3 years that were reported or will be reported to the NRC.
5. List of commitments that have been changed (i.e., modified or deleted) for the last 3 years that were evaluated as not needing to be reported to the NRC.

Note: For each commitment, as a minimum, the lists should include the tracking number and a description of the actual commitment.

Please let me know if you have any questions or have difficulty providing the information by the requested date.

Thank you, Blake Purnell, Project Manager Plant Licensing Branch III-2 and Planning and Analysis Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission ph: 301-415-1380 Docket Nos. 50-373 and 50-374 1

Hearing Identifier: NRR_PMDA Email Number: 1483 Mail Envelope Properties (Blake.Purnell@nrc.gov20140808095700)

Subject:

LaSalle Commitment Audit (TAC Nos. MF4531 and MF4532)

Sent Date: 8/8/2014 9:57:40 AM Received Date: 8/8/2014 9:57:00 AM From: Purnell, Blake Created By: Blake.Purnell@nrc.gov Recipients:

"Lisa Simpson (Lisa.Simpson@exeloncorp.com)" <Lisa.Simpson@exeloncorp.com>

Tracking Status: None Post Office:

Files Size Date & Time MESSAGE 2012 8/8/2014 9:57:00 AM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: