NRR E-mail Capture - La Salle, 1 & 2 - Acceptance of Licensing Action License Amendment Request New Fuel Storage Vault and Spent Fuel Pool Criticality Methodologies, with Changes to TS Sections 4.3.1 and 5.6.5 (EPID-L-2021-LLA-0124)
ML21210A094
Person / Time
Site: LaSalle  Constellation icon.png
Issue date: 07/29/2021
From: Bhalchandra Vaidya
NRC/NRR/DORL/LPL3
To: Taken J
Exelon Generation Co
References
L-2021-LLA-0124
Download: ML21210A094 (3)


Text

From: Vaidya, Bhalchandra Sent: Thursday, July 29, 2021 7:38 AM To: 'Taken, Jason C.:(Exelon Nuclear)'; 'david.gullott@exeloncorp.com'

Subject:

La Salle, Unit Nos. 1 And 2 - Acceptance of Requested Licensing Action Re:

License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Pool Criticality Methodologies, with Changes to TS Sections 4.3.1 and 5.6.5 (EPID-L-2021-LLA-0124)

SUBJECT:

La Salle, Unit Nos. 1 And 2 - Acceptance Of Requested Licensing Action Re:

License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Storage Pool Criticality Methodologies, with Proposed Changes to Technical Specifications Sections 4.3.1 and 5.6.5 (EPID NO. EPID-L-2021-LLA-0124)

NRC Docket Nos. 50-373 and 50-374 By letter dated June 30 2021 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML21183A169), Exelon Generation Company, LLC (EGC) (

the licensee) submitted a license amendment request for La Salle, Unit Nos. 1 and 2. The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an application for an amendment to a license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.

Based on the information provided in your submittal, the NRC staff has estimated that this licensing request will take approximately 460 hours0.00532 days <br />0.128 hours <br />7.60582e-4 weeks <br />1.7503e-4 months <br /> to complete. The NRC staff expects to complete this review in approximately 12 months, which is July, 2022. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.

These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, unanticipated addition of scope to the review, and review by NRC advisory committees or hearing-related activities. For Relief Requests and other RLAs use: These estimates are based on the NRC staffs initial review of the application and they could change, due to several factors including requests for additional information, and unanticipated addition of scope to the review. Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.

If you have any questions, please contact me.

Bhalchandra K. Vaidya US Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Division of Operating Reactor Licensing LPL3 301-415-3308 Bhalchandra.vaidya@nrc.gov

Hearing Identifier: NRR_DRMA Email Number: 1295 Mail Envelope Properties (SJ0PR09MB64156FAEAC595B3EFDD417C78DEB9)

Subject:

La Salle, Unit Nos. 1 And 2 - Acceptance of Requested Licensing Action Re:

License Amendment Request Regarding New Fuel Storage Vault and Spent Fuel Pool Criticality Methodologies, with Changes to TS Sections 4.3.1 and 5.6.5 (EPID-L-2021-LLA-0124)

Sent Date: 7/29/2021 7:38:09 AM Received Date: 7/29/2021 7:38:00 AM From: Vaidya, Bhalchandra Created By: Bhalchandra.Vaidya@nrc.gov Recipients:

"'Taken, Jason C.:(Exelon Nuclear)'" <Jason.Taken@exeloncorp.com>

Tracking Status: None

"'david.gullott@exeloncorp.com'" <david.gullott@exeloncorp.com>

Tracking Status: None Post Office: SJ0PR09MB6415.namprd09.prod.outlook.com Files Size Date & Time MESSAGE 3227 7/29/2021 7:38:00 AM Options Priority: Normal Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: