NRR E-mail Capture - Acceptance Review Results Regarding Calvert Cliffs 1 & 2 - As-found Lift Tolerance Modification in the Pressurizer Safety Valve Surveillance Requirement Amd
ML14168A000
Person / Time
Site: Calvert Cliffs  Constellation icon.png
Issue date: 06/16/2014
From: Nadiyah Morgan
Division of Operating Reactor Licensing
To: Furio P
Exelon Corp
References
MF3541, MF3542
Download: ML14168A000 (2)


Text

NRR-PMDAPEm Resource From: Morgan, Nadiyah Sent: Monday, June 16, 2014 3:23 PM To: Furio, Patricia S:(CCNPP) (patricia.furio@exeloncorp.com)

Subject:

Acceptance Review Results Regarding CALVERT CLIFFS 1 & 2 - As-found Lift Tolerance Modification in the Pressurizer Safety Valve Surveillance Requirement AMD (TAC NOS.

MF3541 and MF3542)

Pat, By letter dated February 13, 2014 (Agencywide Documents Access and Management System Accession No. ML14050A374), Calvert Cliffs Nuclear Power Plant, LLC submitted a license amendment request (LAR) that would modify the as-found lift tolerances in the surveillance requirement for the pressurizer safety valves for Calvert Cliffs Nuclear Power Plant, Unit Nos. 1 and 2. The purpose of this e-mail is to provide the results of the Nuclear Regulatory Commission (NRC) staffs acceptance review of this LAR and its supplement. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.

The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.

If you have any questions, please contact me.

Thanks, Dee Nadiyah S. Morgan Calvert Cliffs and Pilgrim Project Manager, NRR US Nuclear Regulatory Commission O-8F4 (301) 415-1016 Nadiyah.Morgan@NRC.GOV 1

Hearing Identifier: NRR_PMDA Email Number: 1380 Mail Envelope Properties (9C2386A0C0BC584684916F7A0482B6CAFD0D916300)

Subject:

Acceptance Review Results Regarding CALVERT CLIFFS 1 & 2 - As-found Lift Tolerance Modification in the Pressurizer Safety Valve Surveillance Requirement AMD (TAC NOS.

MF3541 and MF3542)

Sent Date: 6/16/2014 3:22:31 PM Received Date: 6/16/2014 3:22:00 PM From: Morgan, Nadiyah Created By: Nadiyah.Morgan@nrc.gov Recipients:

"Furio, Patricia S:(CCNPP) (patricia.furio@exeloncorp.com)" <patricia.furio@exeloncorp.com>

Tracking Status: None Post Office: HQCLSTR02.nrc.gov Files Size Date & Time MESSAGE 1998 6/16/2014 3:22:00 PM Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:

Recipients Received: