Meeting Agenda for Oconee External Flooding Team Meeting
ML14058A054
Person / Time
Site: Oconee  Duke Energy icon.png
Issue date: 04/20/2009
From:
Office of Information Services
To:
Shared Package
ML14055A421 List: ... further results
References
FOIA/PA-2012-0325
Download: ML14058A054 (3)


Text

Oconee Agenda for Team Meeting 04-20-2009.doe Meeting Agenda for Oconee External Flooding Team Meeting April 20th, 20099b)(6)

Bridge Line for meetings: 888-889-0760, Pass code 1.Status of the letter to Duke. Issuance TBD. Response to M.Galloway non-concurrence inprocess.

2.Discussion by Jeff Mitman and Andy Hutto of review of Duke mitigation strategy.

3.Discussion by Jeff Mitman of relative risk reduction of various modifications compared to addressing external flooding.

4.Actions Item Old Actions Due date Responsibility Status Comments No.

Complete basis for continued operation: Ae 01 Need to determine appropriate means to 223/09 Antonios Inconcurrence DRA and DE have concurred. Obtaining DORL concurrence.

document Write discussion describing NRC 2 NRO has committed to complete week of4320. Availability 02a independent review of breach size 2/17/09 Melanie G. Near completiondelay Draft to be placed inSharePoint.

08 Finalize document to Duke, coordinate with 449 Management Currently with Expected issuance 4/.?./2009 with heads up phone call to team and OE, OGC  ?? Management Duke. ML090570779 Define relative risk reduction of various D0fmodificationskc preductinof vaddreuss4 .9 RogersMand Drafted Revision 10 modifications compared to addressing Draftedf 424 nearly complete. Expected to be on Sharepoint by 41110109 Jeff M. 4/i4.

external flooding APP, Interagency Agreement, and Task Order inorder to 15 Initiate conactor relatioship and assign 2/2/09 Kamal, Raman Drafted obtain USBR's support to review the Jocassee Dam a sinundation studies, etc. isnow with PMDA for issuance.

16 Complete Dec. 4meeting summary 2/23/09 John Drafted Completed and placed inAdams. One correction need -to be revised, 17 Complete Q&A 2/9/09 Jeff C. Drafted One-pager for ET Meeting. Several already drafted.

1 C l Q2 0 eRemainder to be completed by April 23, 2009.

18 Complete PRA discussion 2W Jeff M. Drafted Revised.

3/13/09 Meeting currently scheduled for May 11, 2009. Licensee wants to discuss licensing basis. Will seek further 21a Duke presentation to HQ on HEC-RAS Week of DORL Inplanning clarification at 4/22 status call with Duke. Our approach ison model results 5/1/09 adequate protection rather than licensing basis. Need to develop opening talking points for J.Grobe.

22 . Backfit Analysis Jff C. Drafted Meeting planned with OGC (Cathy Marco and Kimberly 22 __Backfit__Analysis__ 3/13/09 1effC. Drained Sexton) on April 23,2009.

Page I of 3

Oconee Agenda for Team Meeting 04-20-2009.doc Received from Duke 3/5. Reviewed and comments collated with first-cut estimated failure probability of .9.On SharePoint.

New Actions Due date Owner Status Parking Lot Actions Due date Owner Status 20 Update cotnnunication plan John, Melanie W. Paused Current lcne Plan epnstisstill applicable. No change necessary until urn etrbigdald

" licensee responds to current letter being drafted.

21 Site visit and audit to inspect dam and its After licensee responds to our next letter documentation on relevant technical issues Completed Actions Due date Owner Status Obtain consensus understanding of NRC V" Ken, Kamal, Raman, Consensus not yet Potential insights from item I5may be helpful inresolving.

02 view of breach size-inadequacy of 575' 4 Bradley, others? obtained and assessed adequacy of 900-1100' 2/20/09 Assess and document evaluation associated Ken, Jim, Jeff C., Completed; Duke did not use Weather Service precipitation; did not 03 with overtopping and remaining questions of 1/13/09 documentation account for saturated soil; and appeared not to use sufficient Duke others? combined with 02a curve depicting runoff. Follow up with FERC anticipated on I __ PMF calculations.

Summarize key statements rom applicable V" Completed, InSharePoint and emailed to all division for review and 04 guidance 1/28/09 Fernando awaiting comment.

guidance 1/28/09comments. cmet Assess applicable guidance from referenced 05 ANSI1/13/09 Fernando Completed 06 Finalize questions inseismic area 1/28/09 Raman, Goutam Completed 06a How to incorporate seismic concerns into 1/23/09 Raman, Goutam Completed Questions dropped from letter.

next Duke written communication Engage FERC on breach size information to 07 further understand their process and needs 1/12/09 Melanie G., Dave Completed and why our needs while different do not conflict with theis_

Ken S.talked to Ken F.of FERC. Provide Ken's report on 07a Ken to follow-up at staff level with Ken 2 Ken Completed this and items 2a and 3to DE for review. To be placed in Fearon of FERC 2/20/09 SharePoint 0Th Call with Duke to follow-up on curve number V"30,09 2/20/09 Ken Cancelled Concerns not incorporated into current letter version 09 Provide list of Oconee's B.5.b actions 40M Jeff C. Completed 2/9/09 I1I Understand information inANS/ANSI 2.8 1/30/09 Fernando, Bradley, Completed

_____ Rarnan, Ken________ _______________________

Page 2of 3

p . * .

Oconee Agenda for Team Meeting 04-20-2009.doc, 12 Reengage DPR to draft adequate protection 1/26/09 Melanie G. Completed backfit write-up 1_26/09_MelanieG._Completed 13 Complete list of remaining questions which 13 need to be answered by Duke (see item 06) 1/30/09 Ken, Raman, Goutam Completed 14 Schedule failure modes call with licensee 1/30/09 John, Jim Vail Complete Call completed 1919___ Determine ifsecond letter or DFI iscorrect next approach Completed Completed Other Items

, RES isworking with NRO and NRR to revise RG 1.59. They plan to have aworking draft by the end of March. This has no affect on the OFI.

  • Information Notice being provided to DPR on IPEEE dam failure rate calculations. DPR provided comments. DRA revising to be sent back to DPR WHEN??.

Attended by Melanie Galloway -DRA Dave Skeen - DE Melanie Wong -DORL Robert Carroll - Rll DRP Jeff Circle- DRA Kamal Manoly -DE John Stang- DORL Bradley Davis - RII DCI Fernando Ferrante - DRA Raman Pichumani - DE Walt Rogers - RII DRS Jeff Mitman - DRA Juan Uribe -DE Ken See- NRO Jim Vail- DRA Meena Khanna -DE Goutam Bagchi -NRO Andy Hutto - RII DRP Antonios Zoulis -DRA Eric Riggs -RII DRP Page 3of 3