ML13331B088

From kanterella
Jump to navigation Jump to search
Proposed Tech Specs,Revising Tech Specs to Remove Administrative Limit for Loading of Diesel Generators & Allow Loading Up to Design Rating of 6,000 Kw
ML13331B088
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 11/11/1988
From:
SOUTHERN CALIFORNIA EDISON CO.
To:
Shared Package
ML13331B086 List:
References
NUDOCS 8811160222
Download: ML13331B088 (4)


Text

ATTACHMENT 2 PROPOSED TECHNICAL SPECIFICATION 4.4 SS11160222 881111 PDR ADOCK 05000206 p

PDC

4.4 EMERGENCY POWER SYSTEM PERIODIC TESTING APPLICABILITY:

Applies to testing of the Emergency Power System.

OBJECTIVE:

To verify that the Emergency Power System will respond promptly and properly when required.

SPECIFICATION:

A. The required offsite circuits shall be determined OPERABLE at least once per 7 days by verifying correct breaker alignments and power availability.

B. The required diesel generators shall be demonstrated OPERABLE:

1. At least once per 31 days on a STAGGERED TEST BASIS by:
a. Verifying the diesel performs a DG SLOW START from standby conditions,
b. Verifying a fuel transfer pump can be started and transfers fuel from the storage system to the day
tank,
c. Verifying the diesel generator is synchronized and running at > 6000 kW for > 60 minutes,
d. Verifying the diesel generator is aligned to provide standby power to the associated emergency
buses,
e. Verifying the day tank contains a minimum of 290 gallons of fuel, and
f. Verifying the fuel storage tank contains a minimum of 37,500 gallons of fuel.
2. At least once per 3 months by verifying that a sample of diesel fuel from the required fuel storage tanks is within the acceptable limits as specified by the supplier when checked for viscosity, water and sediment.

C. AC Distribution

1. The required buses specified in Technical Specification 3.7, Auxiliary Electrical Supply, shall be determined OPERABLE and energized from AC sources other than the diesel generators with tie breakers open between redundant buses at least once per 7 days by verifying correct breaker alignment and power availability.

0 0

2. Simulating SISLOP*, and:
a. Verifying operation of circuitry which locks out non-critical equipment,
b. Verifying the diesel performs a DG FAST START from standby condition on the auto-start signal, energizes the emergency buses with permanently connected loads and the auto connected emergency loads** through the load sequencer (with the exception of the feedwater, safety injection, charging and refueling water pumps whose respective breakers may be racked-out to the test position) and operates for > 5 minutes while its generator is loaded with the emergency loads,
c. Verifying that on the safety injection actuation signal, all diesel generator trips, except engine overspeed and generator differential, are automatically bypassed.
3. Verifying the generator capability to reject a load of 3220 kW without tripping.

SISLOP is the signal generated by coincident loss of offsite power (loss of voltage on Buses 1C and 2C) and demand for safety injection.

The sum of all loads on the engine shall not exceed 6000 kW.

Basis:

The normal plant Emergency Power System is normally in continuous operation, and periodically tested.( 1 )

The tests specified above will be completed without any preliminary preparation or repairs which might influence the results of the test except as required to perform the DG SLOW START test set forth in T.S. 4.4.B.l.a. The tests will demonstrate that components which are not normally required will respond properly when required.

DG SLOW STARTS are specified for the monthly surveillances in order to reduce the cumulative fatigue damage to the engine crankshafts to levels below the threshold of detection under a program of augmented inservice inspection. In the event that the DG SLOW START inadvertently achieves steady state voltage and frequency in less than 24 seconds, the surveillance will not be considered a failure and require restart of the diesel generator.

The surveillance requirements for demonstrating the OPERABILITY of the station batteries are based on the recommendations of Regulatory Guide 1.129, "Maintenance, Testing, and Replacement of Large Lead Storage Batteries for Nuclear Power Plants," February 1978, and IEEE Std 450-1980, "IEEE Recommended Practice for Maintenance, Testing, and Replacement of Large Lead Storage Batteries for Generating Stations and Substations."

Verifying average electrolyte temperature above the minimum for which the battery was sized, total battery terminal voltage on float charge, connection resistance values and the performance of battery service and discharge tests ensure the effectiveness of the charging system, the ability to handle high discharge rates and compares the battery capacity at that time with the rated capacity.

Table 4.4-1 specifies the normal limits for each designated pilot cell and each connected cell for electrolyte level, float voltage and specific gravity. The limits for the designated pilot cells float voltage and specific gravity, greater than 2.13 volts and.020 below normal full charge specific gravity or a battery charger current that has stabilized at a low value, is characteristic of a charged cell with adequate capacity. The normal limits for each