ML13330B528

From kanterella
Jump to navigation Jump to search

Discusses Revised Submittal Schedule for Individual Plant Exam,Per 900802 &
ML13330B528
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 07/05/1991
From: Rosenblum R
Southern California Edison Co
To:
NRC/IRM
References
TAC-74463 NUDOCS 9107110104
Download: ML13330B528 (2)


Text

Southern California Edison Company 23 PARKER STREET IRVINE, CALIFORNIA 92718 R. M. ROSENBLUM TELEPHONE MANAGER OF (714) 454-4505 NUCLEAR REGULATORY AFFAIRS July 5, 1991 U. S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555 Gentlemen:

Subject:

Docket No. 50-206 Revised Submittal Schedule for Individual Plant Examination (TAC No. 74463)

San Onofre Nuclear Generating Station, Unit 1

References:

1. Letter, F. R. Nandy (SCE) to NRC Document Control Desk, "Submittal Schedules for Individual Plant Examinations (TAC Nos. 74463, 74464, and 74465)," August 2, 1990.
2. Letter, J. E. Tatum (NRC) to Harold B. Ray (SCE), "Review of 60-Day Response to Generic Letter 88-20, Individual Plant Examinations (TAC Nos. 74463, 74464, and 74465),"

March 12, 1990.

We committed in reference 1 to submit the results of the SONGS 1 Individual Plant Examination (IPE) to the NRC by January 2, 1992, approximately eight months earlier than our original schedule. This schedule improvement was made in response to an NRC request in reference 2 for assistance in avoiding potential delays in the NRC review process.

However, based on the work completed to date, the SONGS 1 IPE will require more effort to complete than we anticipated. This additional effort, in conjunction with the limited technical resources of our IPE contractor, requires that we reschedule the submittal date for the SONGS 1 IPE to April 1, 1992. This three month extension will allow us to complete the SONGS 1 IPE without affecting the performance of the SONGS 2/3 IPE.

Our revised IPE completion date of April 1, 1992, continues to represent a five month improvement over the schedule requirements of Generic Letter 88-20.

We hope this revised submittal schedule assists the NRC in its review of the backlog of IPEs expected in late 1992.

9107110104 910705 DR: ADOCK 05000206 PDR___

Document Control Desk

-2 Please contact me if you have any questions on this matter.

Very truly yours, cc: George Kalman, NRC Project Manager, San Onofre Unit 1 J. 0. Bradfute, NRC Project Manager, San Onofre Unit 1 J. B. Martin, Regional Administrator, NRC Region V C. Caldwell, NRC Senior Resident Inspector, San Onofre Units 1, 2 and 3