Advises of Two Addl Changes to Inservice Testing Program for Pumps & Valves.Note 15 to Procedure SO1-V-215 Will Be Deleted & Alternate Vibration Test That Measures Units of Velocity Rather than Displacment Will Be Substituted
ML13324A433
Person / Time
Site: San Onofre Southern California Edison icon.png
Issue date: 09/11/1984
From: Medford M
Southern California Edison Co
To: Paulson W
Office of Nuclear Reactor Regulation
References
NUDOCS 8409130318
Download: ML13324A433 (7)


Text

Southern California Edison Company P. 0.

BOX 800 2244 WALNUT GROVE AVENUE ROSEMEAD, CALIFORNIA 91770 M.O. MEDFORD TELEPHONE MANAGER. NUCLEAR LICENSING September 11, 1984 2

-1749 Director, Office of Nuclear Reactor Regulation Attention:

Mr. W. A. Paulson, Acting Chief Operating Reactors Branch No. 5 Division of Licensing U. S. Nuclear Regulatory Commission Washington, D.C. 20555 Gentlemen:

Subject:

Docket No. 50-206 Changes to In-Service Testing Program for Pumps and Valves San Onofre Nuclear Generating Station Unit 1

References:

1) Letter, M. 0. Medford (SCE) to D. M. Crutchfield (NRC),

January 24, 1984, In-Service Testing Program for Pumps and Valves

2) Letter, M. 0. Medford (SCE) to D. M. Crutchfield (NRC),

June 15, 1984, In-Service Testing of Valves Program

3) Letter, R. W. Krieger (SCE) to 0. M. Crutchfield (NRC),

September 1, 1983, NUREG-0737, Reactor Coolant System Vents

4) Letter D. M. Crutchfield (NRC) to R. Dietch (SCE), August 29, 1983, NUREG-0737, Reactor Coolant System Vents By Reference 1, Southern California Edison Company submitted a revised In-Service Testing (IST) program for pumps and valves for the San Onofre Nuclear Generating Station, Unit 1. By Reference 2, we notified the NRC of a change in the IST program. This is to advise you of two further changes, as discussed below.
1. In fulfillment of our commitment in Reference 3, valves SV-2401 through SV-2404 and SV-3401 through SV-3404 in the reactor coolant gas vent system (RCVS) were included in IST Procedure SO1-V-2.15, to be full stroke tested and fail safe tested at cold shutdown.

However, Note 15 to IST Procedure S01-V-2.15 made this testing conditional as follows:

"The Reactor Coolant Gas Vent System has been installed in the plant. This valve will be included in the program once the NRC approves the use of the system."

8409130318 840911 PDR ADOCK 05000206 P

PDR i

Mr. W.

September 11,19 9 Based on the schedule outlined in 10 CFR 50.44(c)(3)(iii) and the NRC's clarification in Reference 4 as to the intent of this rule, we have now concluded that (1) it is not necessary to obtain NRC's approval for purpose of testing the RCVS valves during cold shutdown, and (2) such testing must be initiated prior to Unit 1 restart.

Therefore, Note 15 is not relevant and will be deleted.

2. Table 2 of IST Procedure SO1-V-2.14 requires a quarterly vibration test for spray chemical addition pumps G-200A and G-200B, in accordance with ASME Code,Section XI.
However, these are low, variable speed positive displacement pumps and the existing vibration monitoring equipment cannot meet the ASME Code,Section XI requirement to measure the displacement vibration amplitude, due to low pump speed. Therefore, an alternate vibration test that measures units of velocity rather than displacement will be substituted.

Revised insert pages for Procedures S01-V-2.14 and SO1-V-2.15, including a new Pump Relief Request No. 8, to reflect the two changes discussed above are enclosed herewith.

If you have any questions, please contact me.

Very truly yours, M. 0. Medford Manager, Nuclear Licensing Enclosure cc:

USNRC Document Control Desk, Washington, D.C.

20555 J. B. Martin (USNRC Regional Administrator, Region V)

A. E. Chaffee (USNRC Resident Inspector, Units 1, 2 and 3)

PUMP RELIEF REQUEST NO. 8 SYSTEM:

Containment Spray Hydrazine Addition COMPONENT:

Spray Chemical Addition Pumps G-200A, G-200B CLASS :

2 FUNCTION:

To provide hydrazine addition to containment spray TEST REQUIREMENT:

IWP-4510, At least one displacement vibration amplitude (peak-to-peak composite) shall be read during each in-service test.

IWP-4520(b), The frequency response range of the readout system, shall be from one-half minimum speed to at least maximum pump shaft rotational speed.

BASIS FOR RELIEF:

Existing vibration monitoring equipment cannot meet the Code requirement to measure the displacement vibration amplitude, due to a bandpass filter which deletes vibration input below 350 cycles per minute (350 rpm).

Pump speed is 77.5-155 rpm (variable speed).

Vibration probe sensitivity for available equipment is 120 to 9,000 rpm when measuring in units of velocity.

ALTERNATE TESTING:

Test in units of velocity using existing equipment at greater than or equal to 120 rpm. This will provide vibration monitoring at 1 times rpm where most rotating equipment malfunctions occur.

2194F

SAN ONOFRE NUCLEAR GENERATING STATION ENGINEERING PROCEDURE SO1-V-2.15 UNIT 1 REVISION 4 PAGE 6 OF 7 ATTACHMENT 8.1 IN-SERVICE TESTING PROGRAM ASME-CLASS 1, 2, & 3 VALVES SAN ONOFRE NUCLEAR GENERATING STATION UNIT 1 MAX.

STROKE VALVE VALVE VALVE VALVE ACTR.

NORMAL STROKE TEST TIME RELIEF NUMBER COORD. CLASS CATEGORY SIZE TYPE TYPE POSITION DIRECTION TEST MODE (Sec.)

REQUEST REMARKS EXPLANATION OF NOTES (Continued)

NOTES:

15.

(Deleted)

16.

This valve Is a remotely operated hand control valve. A maximum stroke time is not required for this valve.

17 Per General Design Criteria (GDC)57, these valves are not required to be automtic and will not be seat.leak tested.

18 867 a, b, and c assume leak tightness of the Safety Injection System (Technical Specification 4.2.2).

Therefore, these valves will not be seat leak tested.

EXPLANATION OF ABBREVIATIONS GA GATE GL GLOBE CK CHECK SV SAFETY RV RELIEF BTF BUTTERFLY BALL BALL SO SOLENOID AO AIR OPERATOR SA SELF ACTUATED HY HYDRAULIC MO MOTOR OPERATOR M

MANUAL AT SEAT LEAK TEST BT FULL STROKE EXERCISE TEST BTP PARTIAL STROKE EXERCISE TEST CVT CHECK VALVE EXERCISE TEST

SAN ONOFRE NUCLEAR GENERATING STATION UNIT 1 ENGINEERING PROCEDURE SOI-V-2.15,

.TREVISION It PACE 1 OF 24 ATTACHMLN[ 8.2 IN-SERVICE TESTING PROGRAM ASME-CLASS 1, 2 & 3 VALVLS SAN ONOFRE NUCLEAR GENERATING SIATION UNIT 1 MAX.

VALVE NOPMAI /

STOKE VALVE VALVE SIZE VALVE ACiR.

[Ailli STROKE TEST TIME RELIEF NUMBER COORD.

CLASS CATEGORY (INCHES) TYPE TYPE POS I LION DIRECTION TEST MODE (Sec.)

REQUEST REMARKS REACTOR COOLANT SYSTEM P &

ID # 568766-17 (includes CC #26)

CV-530 C-2 1

B 2

GL AO 0/0 O&C BT OP 5-0 Notes 2, FST CS 15-C VRR-6 9,

PIT RR CV-531 B-2 1

B 2

GL AO 0/0 O&C 1T OP 5-0 Notes 2, FST CS 15-C VRR-6 9,

PIT RR CV-532 C-11 2

A 3/4 BALL AO O/C O&C AT RR 5-0 Notes 2, BT OP 5-C 10 FST CS VRR-6 PIT RR CV-533 C-11 2

A 2

BALL AO O/C C

AT RR 20 Notes 2, 10 1T OP FST CS VRR-6 PIT RR CV-534 C-11 2

A 2

BALL AO O/C C

AT RR 10 Notes 2 & 10 l3T OP FST OP PIT RR CV-545 B-2 1

B 2

GL AO C/C C

BT CS 5

Notes 2 FST CS

& 9 PIT RR CV-546 C-2 1

B 2

GL AO C/C C

DT CS 5

Notes 2 FST CS

& 9 PIT RR RV-532 A-3 1

C 3x6 RV SA C

RVT RR Note 7 PIT RR RV-533 A-3 1

C 3x6 RV SA C

RVT RR Note 7 PIT RR 1"-600-239 C-11 2

AC 1

CK SA C

O&C AT RR Note 10 CVT CS REACTOR COOLANT GAS VENT P & 10 #

568766-17 (includes CC #26)

SV-2401 F-8 2

B 3/4 CA SO C/C O

BT CS 2

Notes 2, 9,

FST CS PIT RR See Attachment 8.3

SAN ONOFRE NUCLEAR GENERATING STATION ENGINEERING PROCEDURE SO1-V-2.15 UNIT 1 REVISION 4 PAGE 2 OF 24 AITACHMENT 8.2 IN-SERVICE TESTING PROGRAM ASME-CLASS 1, 2 & 3 VALVLS SAN ONOFRE NUCLEAR CENERATING STATION UNIT 1 MAX.

VALVE N.

STOKE VALVE VALVE SIZE VALVE ACTI<.

IA S1ROKE TEST lIME RELIEF NUMBER COORD.

CLASS CATEGORY (_INCHESA TYPE TYPE I

DIRECTION TEST MODE (Sec.)

REQUEST REMARKS REACTOR COOLANT GAS VENT P & ID 15l8766-17 (includes CC #261 (Contnuaie)

SV-2402 E-8 3

B 3/4 GA SO C/C 0

fi CS 2

Notes 2, I S CS 9,

PIT RR SV-2403 A-7 2

B 3/4 GA SO C/C 0

BT CS 2

Notes 2, FST CS 9,

PIT RR SV-2404 A-7 3

B 3/4 GA SO C/C 0

BT CS 2

Notes 2, FST CS 9,

PIT RR SV-3401 F-8 2

B 3/4 GA SO C/C.

0 BT CS 2

Notes 2, FST CS 9,

PIT RR SV-3402 E-8 3

B 3/4 GA SO C/C 0

BT CS 2

Notes 2, FST CS 9,

PIT RR SV-3403 B-7 2

8 3/4 GA SO C/C 0

BT CS 2

Notes 2, FST CS 9,

PIT RR SV-3004 B-7 3

B 3/4 CA SO C/C 0

BT CS 2

Notes 2, FST CS 9,

PIT RR CHEMICAL AND VOLUME CONTROL SYSTEM P & ID # 568767-21 (includes CC #18)

CV-202 B-2 1

B 2

GL AO O&C/C C

BT OP Notes 5 FST CS VRR-6 PIT RR CV-203 B-3 1

B 2

GL AO O&C/C C

BT OP Notes 5 FST CS VRR-6 PIT RR CV-204 C-2 1

8 2

GL AO O&C/C C

BT OP Notes 5 FST CS VRR-6 PIT RR CV-276 D-3 2

B 3/4 GL AO 0/0 O&C BT CS 20-0 Note 2 FST CS 20-C PIT RR CV-304 C-2 1

B 2

GL AO O/C O&C BT CS 100-0 Note 2 FST CS 80-C PIT RR

SAN ONOFRE NUCLEAR GENERATING STATION ENGINEERING PROCEDURE S01-V-2.3 UNIT I REVISION 5 PAGE 1 OF 3 ATTACHMENT 8.2 TABLE 2 ASME-CLASS 1, 2 AND 3 PUMPS (UNIT 1)

PUMP PUMP NAME CLASS P & ID AND TEST PARAMETERS NUMBER COORDINATES INLET DIFF FLOW VIBRA BEARING LUBE TEST SPEED PRESS PRESS RATE TION TEMP LEVEL FREQUENCY NOTES G1OS AUX. FEEDWATER PUMP (ELECT) 2 5159570 B-5 N/A YES YES NO YES YES YES MONTHLY 3, PRR-6 G-10 AUX. FEEDWATER PUMP (STEAM) 2 5159570 D-5 YES YES YES NO YES YES YES MONTHLY 3, PRR-6 C-15A COMPONENT COOLING PUMP 3

568768 C-8 N/A YES YES YES YES YES YES QUARTERLY 3

G-158 COMPONENT COOLING PUMP 3

568768 C-8 N/A YES YES YES YES YES YES QUARTERLY 3,6 G-15C COMPONENT COOLING PUMP 3

568768 C-8 N/A YES YES YES YES YES YES QUARTERLY 6

G-74A DIESEL FUEL TRANSFER PUMP 3

5154026 H-5 N/A YES YES YES NO NO NO QUARTERLY 6, PRR-2 G-748 DIESEL FUEL TRANSFER PUMP 3

5154026 H-4 N/A YES YES YES NO NO NO QUARTERLY 6, PRR-2 G-75A DIESEL FUEL TRANSFER PUMP 3

5154031 H-7 N/A YES YES YES NO NO NO QUARTERLY 6, PRR-2 G-75B DIESEL FUEL TRANSFER PUMP 3

5154031 H-8 N/A YES YES YES NO NO NO QUARTERLY 6, PRRJ-2 G-50A SAFETY INJECTION PUMP 2

568769 B-11 N/A YES YES NO YES YES YES QUARTERLY 3,6,PRR-6 G-50B SAFETY INJECTION PUMP 2

568769 D-11 N/A YES YES NO YES YES YES QUARTERLY 3,6,PRR-6 G-45A SAFETY INJECTION 2

568769 H-2 MOTOR NO NO NO NO NO NO QUARTERLY 4,

PRR-3 RECIRCULATION PUMP AMPS

& VOLTS G-458 SAFETY INJECTION 2

568769 H-3 MOTOR NO NO NO NO NO NO QUARTERLY 4, PRR-3 RECIRCULATION PUMP AMPS

& VOLTS G-27N REFUELING WATER PUMP 2

568776 H-5 N/A YES YES NO YES YES YES QUARTERLY 3,6,PRR-6 G-27S REFUELING WATER PUMP 2

568776 H-5 N/A YES YES NO YES YES YES QUARTERLY 3,6,PRR-6 G-200A SPRAY CHEMICAL ADDITION PUMP 2

568777 H-11 YES YES YES YES YES YES YES QUARTERLY 3,6, PRR-8 G-200B SPRAY CHEMICAL ADDITION PUMP 2

568777 G-11 YES YES YES YES YES YES YES QUARTERLY 3,6, PRR-8 G-13A SALT WATER COOLING PUMP 3

568775 B-6 N/A YES YES YES YES YES YES MONTHLY 3,6,PRR-7 G-13B SALT WATER COOLING PUMP 3

568775 C-6 N/A YES YES YES YES YES YES MONTHLY 3,6,PRR-7