ML13323A398

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-361/80-06 & 50-362/80-04 on 800301-31. Noncompliance Noted:Failure to Store High Strength Bolts in Manner Avoiding Corrosion & Failure to Control E7018 Welding Electrodes at 30 Ft Elevation
ML13323A398
Person / Time
Site: San Onofre  
Issue date: 04/24/1980
From: Dodds R, Pate R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML13323A394 List:
References
50-361-80-06, 50-361-80-6, 50-362-80-04, 50-362-80-4, NUDOCS 8007020191
Download: ML13323A398 (5)


See also: IR 05000361/1980006

Text

U. S. NUCLEAR REGULATORY COMMISSION

OFFICE OF INSPECTION AND ENFORCEMENT

REGION V

50-361/80-06

Report No.

50-362/80-04

Docket

No.

50-361, 50-362

License No. CPPR-97,

CPPR-98

Safeguards Group_

_

Licensee:

Southern California Edison Company

2244 Walnut Grove Avenue

Rosemead, California 91770

Facility Name:

San Onofre Units 2 and 3

Inspection at:

Construction Site, San Diego County, California

Inspection conducte :,, March 1-31,

1980

Inspectors:

___/_n

J. Pate, Resident Igipector

d ae Si ned

Date Signed

Date Signed

proved By:

R. T. Dodds, Chief, Engineering Support Section

/bate/Signed

Reactor Construction & Engineering Support Branch

Summary: Inspection on March 1-31, 1980 (Report Nos. 50-361/80-06 and 50-362/80-04)

Areas Inspected:

Routine, unannounced inspection by the resident inspector

of construction activities including: piping storage and fitup; reactor

pressure vessel and internals protection, storage of high strength fasteners;

weld rod control; licensee corrective actions on previous inspection

findings; and general work in progress. The inspection involved 34

inspector-hours onsite by one NRC. inspector.

Results:

Of the five areas inspected, ore item. of noncompliance and one

deviation.was identified.

RV Form 219 (2)

se e so39

~

DETAILS

1. Individuals Contacted

a. Southern California Edison Company .(SCE)

+*D. E. Nunn, Manager, Quality Assurance

+*P. A. Croy, Site Project Quality Assurance Supervisor

R. R. Hart, Construction Manager

D. B. Schone, Lead Engineering Site Representative

=*W.

L. Rossfeld, Construction Lead QA Engineer

b. Bechtel Power Corporation(Bechtel)

=+*C. A. Blum, Quality Control Manager

=+*R. H. Cutler, Project Field Engineer

+*J. E. Geiger, Project Quality Assurance

+*W. D. Nichols, Assistant Project Field Engineer

=+*L. W. Hurst, Project Field Quality Assurance Supervisor

R. W. Welcher, Project Quality Assurance Engineer

+ J. E. Bashore, Division Quality Assurance Manager

In addition, construction craftsmen, engineers and foremen were

contacted during the inspection.

  • Denotes attendees at management meeting on March 7, 1980

+Denotes attendees at management meeting on March 21; 1980

=Denotes attendees at management meeting on March 27, 1980

2. Construction Status

The licensee reported the site construction work is 78% complete as

of March 26, 1979.

The licensee's project management personnel

estimated that the construction of Units 2 and 3 was 90% and 61%

complete, respectively.

3. Storage of High Strenth Bolts

High strength bolts (A490, 1 1/2 inch diameter, 5 inches long) were

observed on March 5, 1980 in the iron workers' storage area at

Jap Mesa in a 5-gallon bucket that was half filled with water. The

bolts were coated with a film of red rust. There were approximately

100 other 5-gallon containers in the area also filled with nuts and

bolts. Most of these were covered with a large sheet of plastic.

Several buckets including the one noted above were not covered. It

appeared that the cover had been removed and not replaced, allowing

rain to fill the buckets. From the condition of the bolts it appeared

-2

that the bolts had been in the water for some time.

The use of a

plastic sheet to cover the buckets of bolts and nuts at the Jap Mesa

storaqe area was discussed at the weekly meeting on December 14,

1979.

The inspector noted the possible need for improving the storage conditions

at that time, but no action was taken.

The storage of high strength bolts in a manner that allows them to

become corroded is contrary to the requirement of ANSI Standard

N45.2.2-1972, Section 3.2.4(3) which states in part "Items subject

to detrimental corrosion, either internally or externally, shall be

suitably protected."

The SCE QA Plan, Chapter 13 and the Bechtel

QA Plan Procedure No. 13 both reference the requirement of ANSI

N45.2.2. The Bechtel construction procedure WPP/QCI 008 commits to the

requirements of ANSI N45.2.2-1972 as modified by Regulatory Guide

1.38.

This is an apparent deviation.

(50-361/80-06/01)

4. Weld Rod Control

Four E7018 (Low Hydrogen) welding electrodes were found in the

Unit 3 High Pressure Safety Injection (HPSI) pump room (RM-015)

on 3/13/80. No one was working in the room at the time and the shift

was not over. The inspector returned to the HPSI pump room the

next morning (3/14/80) and the rod had not been returned to the rod

room or discarded by bending.

The SCE QA management personnel was

immediately advised and this was discussed with SCE management personnel

at the Friday weekly meeting 3/21/80. The inspector was advised that

SCE and Bechtel had done several surveillances during the week and had

found no additional incidence of weld electrodes not being properly

controlled.

SCE concluded that the electrodes found by the inspector

were an isolated case.

On March 24, 1980, after completion of the work shift nineteen (19)

E7018 welding electrodes were found uncontrolled at elevation 30 feet,

next to stairway in containment for Unit No. 3, and on March 26, 1980,

unbent E7018 welding electrodes were retrieved from the rod stub

barrel outside of welding rod room No. 3.

Bechtel Work Plan Procedure/Quality Control Instructions (WPP/QCI)

No. 200, Control of Welding Filler Material, Rev. 11.0, Paragraph 6.1.6

states that "At the completion of the welder's work shift, the

portable rod warmer, container pouch, all unused filler material and

the welder copy of the WR-6, WR-7 or WR-99 forms shall be returned to

the Rod Room attendant;" Paragraph 8.1.1 states that, "Electrodes

returned to the rod room and not intended for re-issue shall be bent

180' and placed in a suitable trash barrel by the rod room attendant."

This is an apparent item of noncompliance (50-361/80-06/02).

-3

5. Reactor Vessel and Internal Installation and Storage

Site activities for storage of the Units 2 and 3 reactor pressure

vessels and internals were observed. Both vessels are installed and

installation of Unit 2 internals is essentially complete. Installation

of Unit 3 internals is nearly complete.

No items of noncompliance or deviations were identified.

6. Reactor Coolant Pressure Boundary and Safety-Related Piping

The piping related activities listed below were observed to ascertain

compliance with applicable construction specifications and procedures.

Activity

System

Identification No.

Weld Fitup

Safety Injection

S2-1204-ML-032

Rev. 13

Storage

Component Cooling Water

S3-CC-084-2

Storage

Component Cooling Water

S3-CC-078-2

No items of noncompliance or deviations were identified.

7. Plant Tour

The inspector toured both Units 2 and 3 several times each week

during the inspection report period. Particular attention was directed

to observing work in progress, availability of supervision and

quality control inspectors at the work areas, housekeeping and

preservation of equipment.

During the tour, the following additional items were observed:

A. One of the four anchor bolts used on pipe hanger S2-RC-157-H-OOA

(supports a 3/4 inch sample line from the reactor coolant system)

was of a different type than the other three bolts. Additional

followup revealed that three of the anchor bolts were per the

drawing and the fourth was a stud which was not properly marked.

The stud was removed and a shell type concrete anchor was found

properly installed. The construction specification allows

substitution of a shell anchor for an expansion anchor. The

inspector also observed that the shell anchor was installed at a

slight angle. The construction specification CS-C8 did not

have an acceptance criteria for concrete anchors installed at an

angle. The licensee was requested to provide acceptance criteria

or explain why acceptance criteria was not needed. (50-361/80-06/03)

-4

B. The flange on the reactor coolant pump loop 1B bleedoff line,

S2-1201-ML-043, to the flow indicator 2FI-0160 was observed to

be highly magnetic although the attached piping was non-magnetic.

It appears from the specification that the pipe and the flange

should be stainless steel.

SCE management personnel were asked

to determine whether or not the flange was nonconforming.

(50-361/80-06/04).

C. The inspector observed the setup for grinding the upper core

support key ways (slots) per Field Action Request (FAR)

No. 1370-183. The slots had to be reground as a result of the

shrinkage that resulted from welding the flow channel extensions

on to the fuel alignment plate.

No items of noncompliance or deviations were identified.

8. Management Interview

The inspector met with the licensee representatives (denoted in

Paragraph 1) on March 7, 21 and 27, 1980. The scope of the inspections

and the inspector's findings were discussed. The licensee representatives

made the following commitments.

A. The high strength bolts stored at Jap Mesa would be placed

under a permanent cover. See Paragraph 3.

B. A new weld rod control program will be implemented for

better accountability for weld rod that has been issued.

See Paragraph 4.

C. The material specification for the reactor coolant pump

bleedoff line will be reviewed for acceptability of magnetic

material.

See Paragraph 7.B.