ML13319A760
| ML13319A760 | |
| Person / Time | |
|---|---|
| Site: | San Onofre |
| Issue date: | 07/20/1981 |
| From: | Chaffee A NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V) |
| To: | Wilber H NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV) |
| References | |
| NUDOCS 8107270061 | |
| Download: ML13319A760 (8) | |
Text
JUL 2 0 1981 g
Docket No. 50-206 JE FILE COpy MEMORANDUM FOR: H. A. Wilber, Chief, Reactor Projects Section, Regions II, IV, and V, RRRI, IE:HQ THRU:
J. L. Crews, Director, Division of Resident, Reactor Project and Engineering Inspection, IE:RV FROM:
A. E. Chaffee, Regional Reactor Inspector, San Onofre Unit 1
SUBJECT:
(SALP) ITEM:
SURVEILLANCE REVIEW OF SAN ONOFRE UNIT 1 As a result of concerns addressed in the SALP Review Board conducted in 1980, a preliminary review was done of San Onofre Unit 1 Technical Specifications (Amendment 56) versus the Westinghouse Standard Technical Specifications (NUREG 0452, Rev. 3).
This review was focused on surveillance requirements.
It revealed a large number (101) of surveillance items which are not covered by Songs 1 Technical Specifications. Many of these items appear to be significant. Enclosure 1 is forwarded for your review and action.
Qriginal signed by A. E. Chaffee A. E. Chaffee Regional Reactor Inspector
Enclosure:
List of Surveillance Items of Potential Concern Sent to DMB for DCS Processing Distributed by RV:
RV PDR Engelken (1tr)
State of CA (Hahn, Johnson)
Resident Inspector 8107270061 810720 PDR ADOCK 05000206 P
PDR OFFICEO RV/db/mm/ a SURNAMEO T
gf a f e L..
. E rews DATE 8
c..
e 00 NRC FORM 318 (10/80) NRCM 0240 OFFICIAL RECORD COPY
~USGPO:
1980-329-824
e e
Listing of (W) Standard Technical Specification Surveillance Items Incompletely Covered in San Onofre Unit 1 Technical Specifications Applicable Technical Surveillance Specification Item #
Comments Requirement Importance Reactivity Control Systems 4.1.1.1.1 Shutdown Margin for Tavg > 2000F No 3
4.1.1.1.2 Actual reactivity balance 4.8 3
compared to predicted 4.1.1.2 Shutdown Margin for Tavg < 200oF No 3
4.1.1.3 Verification of MTC No 3
4.1.1.4.
Tavg within limits 2.1(2) 2 3.1.3D 4.1.2.1 Boration System Flow Path shutdown 3.2A 1
4.1.2.2 Boration System Flow Path critical 3.2B 1
4.1.2.3.2 Remaining charging pump inoperability No 1*
to allow 1 PORV to prevent pressure transient (Modes 5 and 6) 4.1.2.4.2 See 4.1.2.3.2 (Mode 4)
No 1*
4.1.2.5 Borated water source (needs clarification) 3.3.3, 1
(Modes 5 and 6) 4.1 (Table 4.1.2, Item 2) 4.1.2.6 Verification of Two Boration water sources 3.3.3, 4.1 1
(Modes 1, 2, 3, and 4)
(Table 4.1.2, Item 2),
3.2 A(3) 4.1.3.4b Rod drop times after maintenance No 3
or modification 4.1.3.5 Verify shutdown rods fully withdrawn No*
1*
(Modes 1 and 2)
-2 Applicable Technical Surveillance Specification Item #
Comments Requirement Importance Power Distribution Limits 4.2.1.1 Verify Axial flux difference within 3.11 1
limits 4.2.2.2 Fxy No 3
4.2.2.3 F
Q(z)
No 3
4.2.3.2 Verify reactor coolant flow rate 3.1.2 E 2
adequate 4.2.3.3 (note different frequency) 3.1.2 E 2
4.2.3.5 Measurement of RCS flow rate No 1
4.2.4.1 Quadrant Power Tilt Ratio No 3
4.2.4.2 Quadrant Power Tilt Ratio No 3
4.2.5 Verify Tavg and Press are less 2.1 1
Instrumentation 4.3.1.1 Reactor Trip Interlocks No 1
(e.g., p-8 and p-7) 4.3.1.2 Reactor Trip Response Times No 1
4.3.2.1 ESFAS Manual Switches No 1
4.3.2.2 ESFAS Response Times No 1
4.3.3.1 Radiation Monitors (could be 4.1 (Table 4.1.1, 3
more specific)
Item 18) 4.3.3.2 Verification of Operability of 3.10 1
Incore Detectors 4.3.3.3.1 Operability of Seismic Event No 2
Monitoring Equipment 4.3.3.3.2 (note: after Seismic Event)
No 2
4.3.3.4 Operability of Meteorological No 1
Monitoring equipment 4.3.3.5 Calibration of Remote Shutdown No 1
Instrumentation
Applicable Technical Sureveillance Specification Item #
Comments Requirement Importance 4.3.3.6 Accident Monitoring Instrumentation No Note: Subcooling Meter will be installed prior to S/U (This item is TMI related.)
(Licensee has submitted proposed Tech. Spec.
Change Amend. 97, letter dated May 7, 1981,to Licensing.)
4.3.3.8.2 Supervisory circuits for fire No protection circuits (not sure if (see letter dated applicable to Songs 1)
October 23, 1979, page 2) 4.3.3.8.3 Fire Protection (None No 1
Supervised Circuits) 4.3.4.2 Turbine overspeed protection No 1
Reactor Coolant System 4.4.1.1 3.1.2 D 2
4.4.1.2.1 Reactor Coolant loop operability 3.1.2 E 2
4.4.1.2.2 verification for different modes of 3.1.2 F 2
4.4.1.3.1 operation (includes operability 2
4.4.1.3.2 of S/G in hot shutdown) 1 4.4.1.3.3 1
4.4.1.4 RHR loop operability 3.3.1 A(1)d 1
4.4.4.1 Pzr water level No 3
4.4.4.2 Pzr heaters emergency power No 2
(TMI) 4.4.5.1 PORV Operability 4.1 (Table 4.1.2, 1
Item 7) 4.4.5.2 Operability of block valve No 1
4.4.5.3 Emergency power supply for PORV's No 1
block valves operability 4.4.7.1 a,b,c Leak detection system operability 3.1.4 bases 2
4.4.7.2.1 Verification of leakage rate 3.1.4 A 2
a,b,c,d,e
-4 Applicable Technical Surveillance Specification Item #
Comments Requirement Importance 4.4.7.2.2 Additional isolation valve leakage No 2
verification requirements 4.4.8 Reactor Coolant Chemistry verification No 2
4.4.10.1.1 RCS Temp and press within 2.1(2) 2 limits verification 3.1.3 4.4.10.1.2 Brittle Fracture Curve update 3.1.3 B 3
4.4.10.2 Pzr temp limitations 3.1.3 C 1
4.4.10.3.1 Pressure protectiog for No 3
RCS low Tavg < 200 F 4.4.11 RCP Flywheel Insp.
No 2
Emergency Core Cooling System 4.5.2 ESF operability Tavg >350oF 3.3.1 A 1
a,b,c,d(2) g,h 4.5.3.1 ESF operability Tavg < 3500F 3.3.1 A 1
4.5.3.2 ESF operability Tavg ( 3500F 3.3.1 A 1
4.5.5a Refueling Water Storage Tank 3.3.1 A(1)a, 4.1 1
Boron Concentration & level surveillance (Table 4.1.2, Item 2)
Westinghouse Atmospheric Containment (Section A) 4.6.1.1 a,b Verification of Containment Integrity 3.6 B 4.6.1.3 a,c Airlock operability (Note: Licensee has 3.6 B, 1.0 1*
had repeated problems with personnel access hatch. LER 79-15 and 81-10) 4.6.1.5 Containment Internal Pressure Band 3.6 C 2
(Note: Licensee is presently evaluating proper band) 4.6.1.6 Containment Air Temp Limit No 2
4.6.1.8 Ventilation System:
Purge and TMI Item 2
Exhaust Valves Shut (Note:
II.E.4.l(6)
This item is pending.I)
-5 Applicable Technical Surveillance Specification Item #
Comments Requirement Importance 4.6.2.1 Containment Spray System 3.3.1 A(2) and a,c(2)
A(3), (4.2.1 I B) 4.6.2.2 Containment Spray 3.3.1 A(2)c, 3.3.4, a,bl,c Additive system 4.2.1.I.B, 4.6.4.1 Containment Isolation Valves 4.3 II C 1*
Operability (isolation times)
(needs to be more specific) 4.6.4.2 Containment Isolation Valves 4.3 II C 1*
Phase A, Phase B (needs to be more specific) 4.6.4.3 Containment Isolation Valves 4.7 2
inservice test (isolation time) 4.6.4.4 Purge Valves TMI Item 2
II.E.4.2(6) 4.6.5.1 Containment Hydrogen Analyzers No 2
4.6.5.3 Hydrogen Purge Cleanup System TMI Item 2
(see licensee letters dated 3/25/80 II.E.4.1 to NRR and NRR letter dtd 5/2/80)
Plant Systems 4.7.1.2 Operability of Aux. feed pumps:
3.4.1(2), 4.4 E 1
see licensee's proposed Amendment 97 (dated May 7, 1981) 4.7.1.3.1 Condensate Storage Tank operability 3.4.1(3) 1 4.7.1.3.2 Alternate Water Source for Aux. feed 3.4.1(3) 4.7.2 S/G Pressure/Temp Limitations 3.1.2 C(2) 2 (may not apply to Songs 1) 4.7.3 Component Cooling Water System MOV-720A and MOV-720B 3.3.1 A(1)g 2
4.7.4 Salt Water Cooling System No 1*
Operability 4.7.11.4 Halon System License 2
(4KV room will have system requirement 6/15/81)
FPSER
9 C Applicable Technical Surveillance Specification Item #
Comments Requirement Importance 4.7.12 Fire Barrier Penetrations License Require-2 ment FPSER Electrical Power Systems 4.8.1.1.1b A.C. Sources demonstrate transfer 3.7.1.A 1
capability 4.8.1.1.2d Diesel Generator Operability No 3
(simultaneous start) 4.8.3.1 Electrical Equipment Protective Devices No 2
4.8.3.2 MOV thermal overload or bypass No 2
Refueling Operations 4.9.1.1 Reactivity condition prior to refueling 3.8 A.4 2
4.9.1.2 Boron Concentration during refueling 3.8.A.4, 4.1 2
(needs to be more specific)
(Table 4.1.2, Item la.5) 4.9.2 Source Range Inst.
3.8.A.2 1
4.9.4 Verification of Containment 3.6 B(2) and (3) 2 Integrity during refueling 4.9.5 Communications (refueling)
No 1*
4.9.6.1 Manipulator Crane operability No 2
4.9.6.2 Auxiliary Hoist for RCC Handling No 2
4.9.8.1 RHR Loop operability 3.8.A.3 2
4.9.9 Containment Purge and Exhaust 3.6.B(2) and (3)
Valve operability 1.0 Defn 2
4.9.10 Refueling Pit minimum 3.8.A.6 2
water level 4.9.11 Water level storage pool 3.8.B.2 1
4.9.12 Storage Pool Air Cleanup System No 2
-7 Note:
Of approximately 150 surveillance requirements in standard Technical Specification which are applicable to San Onofre Unit 1, San Onofre has only 49. This means Songs is lacking approximately 67 percent of the applicable surveillance requirements in the standard technical specifications.
Note:
Technical Specification beginning with "4" are surveillance requirements. All others are LCOs.
- These items are of particular concern.