MONTHYEARML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24131A0612024-05-10010 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Proposed Alternative to Utilize Code Case OMN-32 (L-2024-LLR-0030) ML24122B5072024-05-0101 May 2024 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-591, Revision 0 ML24073A3602024-03-13013 March 2024 Request for Additional Information (RAI) Alternative Request PR-03 Sixth Interval Inservice Testing Program ML24045A2892024-02-14014 February 2024 R. E. Ginna Nuclear Power Plant Acceptance Review: IST Relief Request for B Auxiliary Feedwater Pump ML23311A1692023-11-0707 November 2023 NRR E-mail Capture - Constellation - Fleet Request - Acceptance of Proposed Alternative for Examinations of Exam Categories B-B, B-D, and C-A SG Pressure Retaining Welds and Full Penetration Welded Nozzles (L-2023-LLR-0055 and L-2023-LLR-00 ML23312A1302023-11-0707 November 2023 Final Rci/Rai - Constellation R. E. Ginna Nuclear Power Plant - Exemption from Security Rule (EPID L-2023-LLE-0029) (Email) ML23311A1682023-11-0707 November 2023 NRR E-mail Capture - Constellation - Fleet Request - Acceptance of Proposed Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections (L-2023-LLR-0053 and L-2023-LLR-005 ML22354A2622022-12-20020 December 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of Request to Use Certain Provisions of the 2019 Edition of the ASME BPV Code, Section XI ML22325A0052022-11-18018 November 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request - Acceptance of License Amendment Request to Adopt TSTF-273-A, Revision 2 ML22339A0032022-09-28028 September 2022 R. E. Ginna Nuclear Power Plant - Ginna: Acceptance Review: to Revise Technical Specifications (TS) TS 5.6.5, Core Operating Limits Report ML22269A4522022-09-22022 September 2022 R. E. Ginna Nuclear Power Plant - Acceptance Review: to Revise Technical Specifications (TS) TS 5.6.5, Core Operating Limits Report (COLR) ML22255A0132022-09-0909 September 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood, Byron, Calvert Cliffs, Ginna - License Amendment Request to Adopt TSTF-577 ML22200A0782022-07-19019 July 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Fleet Request to Use Honeywell Mururoa V4F1 R Supplied Air Suits ML22138A1672022-05-16016 May 2022 R. E. Ginna Nuclear Power Plant - Acceptance Review TS to Revise Technical Specifications (TS) for the Spent Fuel Pool Charcoal System and Two (2) TS Administrative Changes (EPID-L-2022-LLA-0057) ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 ML22116A0242022-04-25025 April 2022 NRR E-mail Capture - NRC Acceptance Review of Braidwood, Byron, and Ginna Request to Adopt TSTF-246 ML22088A1562022-03-0202 March 2022 NRR E-mail Capture - Byron, Braidwood, Calvert Cliffs, and Ginna - Non-acceptance of Application to Revise Technical Specifications 5.6.5.b, the Core Operating Limits Report (COLR) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 ML21308A5592021-11-0404 November 2021 NRR E-mail Capture - NRC Request for Additional Information for Ginna Biennial EP Exercise Exemption Request ML21301A0672021-10-28028 October 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-541 ML21293A2342021-10-19019 October 2021 R. E. Ginna Nuclear Power Plant - Acceptance of Request for Exemption from the Biennial Emergency Preparedness Exercise Requirements in 10 CFR 50, Appendix E, Section IV.F.2.C ML21293A1332021-10-19019 October 2021 R. E. Ginna Nuclear Power Plant - Acceptance of Request for Exemption from the Biennial Emergency Preparedness Exercise Requirements in 10 CFR 50, Appendix E, Section IV.F.2.C ML21279A1122021-10-0606 October 2021 R. E. Ginna Nuclear Power Plant - Request for Exemption from the Biennial Emergency Preparedness Exercise Requirements in 10 CFR 50, Appendix E, Section IV.F.2.c ML21273A1092021-09-30030 September 2021 R. E. Ginna Nuclear Power Plant - Acceptance Review - Alternative for Examinations of Examination Category C-B Steam Generator Nozzle-to-Shell Welds and Nozzle Inside Radius Sections (EPID L-2021-LLR-0074 ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21215A3502021-08-0303 August 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Amendment Request to Adopt TSTF-554 ML21189A1602021-07-0808 July 2021 NRR E-mail Capture - Request for Additional Information - Braidwood, Byron, and Ginna - Amendment to Address the Issues in Westinghouse NSALs ML21172A2702021-06-22022 June 2021 E-Mail Acceptance of Application - Risk Informed Completion Times in Accordance with TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b, ML21172A2692021-06-22022 June 2021 E Mail Acceptance of Application to Adopt 10 CFR 50.69, _Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors (Epid_ L-2021-LLA-0092) ML21154A0142021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0132021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21154A0112021-05-28028 May 2021 NRR E-mail Capture - Extension of Comment Period for the Exelon Generation Company, LLC License Transfer Application ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21123A2442021-05-0303 May 2021 NRR E-mail Capture - NRC Acceptance Review of Braidwood/Byron/Ginna - Application to Address the Issues Identified in Westinghouse Documents NSAL-09-5 and NSAL-15-1 (L-2021-LLA-0066) ML21117A0442021-04-26026 April 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21084A2532021-03-24024 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Acceptance of License Transfer Application ML21076A5152021-03-17017 March 2021 R. E. Ginna Nuclear Power Plant - RAI Steam Generator LAR to Revise Technical Specifications for Steam Generator Tube Inspection Frequency (EPID L-2020-LLA-0207) (e-mail) ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21033A8552021-02-0202 February 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Alternative Request to Expand the Use ASME Codes Cases N-878 and N-880 ML21029A3302021-01-29029 January 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative Request to Use ASME Code Case N-885 ML20357A2232020-12-17017 December 2020 Update on Ginna POV - 3504A and 4562 (Email Request for Inspection Information) ML20350B5582020-12-14014 December 2020 NRR E-mail Capture - Exelon Generation Company, LLC -Alternative Request for Documentation of Replacement of Pressure Retaining Bolting ML20335A5692020-11-30030 November 2020 R. E. Ginna Nuclear Power Plant - Acceptance Review: Alternative to ASME Code, Section XI ML20325A1002020-11-20020 November 2020 Acceptance Review: Force-on-Force Temporary Exemption Request ML20294A4942020-10-20020 October 2020 R. E. Ginna Nuclear Power Plant - Acceptance Review: to Revise Technical Specifications for Steam Generator Tube Inspection Frequency ML20276A1032020-10-0202 October 2020 R. E. Ginna Nuclear Power Plant - Acceptance Review - Exemptions from 10 CFR 2.109(b), Effect of Timely Renewal Application ML20266G3032020-09-22022 September 2020 NRR E-mail Capture - Exelon Generation Company, LLC - Fleet Request to Use Paragraph IWA-5120 of the 2017 Edition of the ASME B&PV Code, Section XI 2024-07-12
[Table view] |
Text
NRR-PMDAPEm Resource From: Thadani, Mohan Sent: Wednesday, October 09, 2013 9:12 AM To: Jackson, Jarred A Cc: Harding Jr, Thomas (Thomas.HardingJr@cengllc.com); Robinson, Jay; Robinson, Jay
Subject:
RE: VOLUNTARY FIRE PROTECTION RISK INITIATIVE Attachments: Ginna RAI Response Timeline Table.docx Jarred:
As a follow-up to our emails regarding the RAIs for the subject action, we have prepared a timeline by which we would like to have the licensees responses. The timeline is provided in the Table below.
Considering that NRC is scheduled to shut down starting Friday, October 11, 2013, we will be unable to formally document our RAI prior to shutdown. Therefore please treat the attachment, summary of clarifications, and the NRC staffs timeline for receipt of the licensee responses in this email as our request. A formal letter documenting the agreed RAI and proposed timeline will be documented in our letter to the licensee, soon after the NRC staff returns to work.
Thank you for your cooperation.
Best regards, Mohan C Thadani Senior Project Manager FitzPatrick, Ginna, and Constellation Fleet Plants Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476 Mohan.Thadani@nrc.gov Ginna RAI Response Timeline Table RAIs Response Time Response Due Date FPE RAIs 01 through 08 60 Days December 17, 2013 SSA RAIs 01 through 04 Programmatic RAIs 01 through 03 FM RAIs 02 and 05 PRA RAIs 01, 02, 04 through 12, 13, 14, 16, 17, 20, 21, 23, 24, 26, 31, 32, 33, 34, 35, 37, 39, 43 FM RAIs 03, 04, 06 90 Days
- PRA RAIs 03, 15, 19, 22, 27, 28, 29, 30, 36, 38, 40, 41, 42, 44 90 and 120 Day Responses are given 2 week grace period to account for December resource issues.
1
From: Jackson, Jarred A [1]
Sent: Monday, October 07, 2013 3:15 PM To: Thadani, Mohan Cc: Harding Jr, Thomas; Robinson, Jay; Lilley, Michael; Charland, Kenneth
Subject:
RE: VOLUNTARY FIRE PROTECTION RISK INITIATIVE
- Mohan, The NFPA-805 project manager at Ginna indicates that the questions are acceptable as written and we have no further comments.
Thank You, Jarred Jackson Licensing Supervisor R.E. Ginna Nuclear Power Plant 585-771-3605 (Office) 585-278-7281 (Cell)
From: Thadani, Mohan Sent: Monday, October 07, 2013 2:05 PM To: 'Jackson, Jarred A' Cc: Harding Jr, Thomas (Thomas.HardingJr@cengllc.com); Robinson, Jay
Subject:
RE: VOLUNTARY FIRE PROTECTION RISK INITIATIVE Jarred:
We have now updated the RAIs (see attached Ginna Audit RAIs Edited), and addressed all of the clarification questions discussed in the previous email traffic. Also attached is an RAI Response Timeline Table. The NRC staff agrees to the licensees proposed response timeline. The clarifications/changes are summarized below.
- 1. SSA RAI 02.f was revised to read: The description of the NPO review for the LAR does not identify locations where key safety functions are achieved via recovery actions or for which instrumentation, not already included in the at-power analysis, is needed to support recovery actions required to meet the key safety functions.
- 2. PRA RAIs were renumbered beginning at number 14. 14 became 13, 15 became 14, and so on. PRA RAIs end in number 44.
- 3. The NRC prefers to have each PRA RAI individually addressed and to have the sensitivity analysis results provided for each individual RAI and is agreeable to the 120 day response time for the approximately 18 affected PRA RAIs.
- 4. SSA RAI 02.b was revised to read: For those components which had not previously been analyzed in support of the at-power analysis or whose functional requirements may have been different for the non-power analysis, provide a list of the additional components and a list of those at-power components that have a different functional requirement for NPO. In addition, based on further NRC staff review, PRA RAI 02.a was also revised to read: LAR Section 4.3.2 states that based on incorporation of the recommendations from the pinch point evaluations into appropriate plant procedures, the performance goals for non-power operations will be fulfilled and the requirements of NFPA 805 will be met.
- 5. PRA RAI 39 (formerly RAI 40) was revised to include Table S-3, Implementation Items of Attachment S.
2
Please review and confirm that the agreed changes are correctly reflected. If you have any questions , please contact me.
Best regards, Mohan C Thadani Senior Project Manager FitzPatrick, Ginna, and Constellation Fleet Plants Plant Licensing Branch I-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation (301) 415-1476 Mohan.Thadani@nrc.gov 3
Hearing Identifier: NRR_PMDA Email Number: 868 Mail Envelope Properties (Mohan.Thadani@nrc.gov20131009091100)
Subject:
RE: VOLUNTARY FIRE PROTECTION RISK INITIATIVE Sent Date: 10/9/2013 9:11:59 AM Received Date: 10/9/2013 9:11:00 AM From: Thadani, Mohan Created By: Mohan.Thadani@nrc.gov Recipients:
"Harding Jr, Thomas (Thomas.HardingJr@cengllc.com)" <Thomas.HardingJr@cengllc.com>
Tracking Status: None "Robinson, Jay" <Jay.Robinson@nrc.gov>
Tracking Status: None "Robinson, Jay" <Jay.Robinson@nrc.gov>
Tracking Status: None "Jackson, Jarred A" <Jarred.Jackson@cengllc.com>
Tracking Status: None Post Office:
Files Size Date & Time MESSAGE 4845 10/9/2013 9:11:00 AM Ginna RAI Response Timeline Table.docx 19378 Options Priority: Standard Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date:
Recipients Received:
Ginna RAI Response Timeline Table RAIs Response Time FPE RAIs 01 through 08 60 Days SSA RAIs 01 through 04 Programmatic RAIs 01 through 03 FM RAIs 02 and 05 PRA RAIs 01, 02, 04 through 12, 13, 14, 16, 17, 20, 21, 23, 24, 26, 31, 32, 33, 34, 35, 37, 39, 43 FM RAIs 03, 04, 06 90 Days PRA RAIs 18, 25, FM RAI 01 120 Days PRA RAIs 03, 15, 19, 22, 27, 28, 29, 30, 36, 38, 40, 41, 42, 44