Other: ML13241A022, ML13337A594, ML14010A331, ML14335A642, ML15301A093, NL-13-043, Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation, NL-13-109, First Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation, NL-13-110, First Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, NL-13-114, Implementation of License Renewal Regulatory Commitments, NL-14-029, Second Six-Month Status Report for the Implementation of Order EA-12-051, Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, NL-14-031, Centers Second Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, NL-14-109, Third Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation, NL-14-110, Third Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, NL-15-025, Fourth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, NL-15-026, Fourth Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation, NL-15-059, Notification of Full Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order EA-12-051 Modifying Licenses with Regard, NL-15-111, Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation, NL-15-112, Fifth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, NL-16-024, Centers Sixth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, NL-16-089, Notification of Full Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order EA-12-051 Modifying Licenses with Regard .
|
MONTHYEARML13058A7632013-02-27027 February 2013 Joint Motion for Alteration to Filing Schedule Project stage: Request NL-13-043, Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation2013-02-27027 February 2013 Overall Integrated Plan in Response to March 12, 2012, Commission Order Modifying License with Regard to Reliable Spent Fuel Pool Instrumentation Project stage: Other ML13169A1272013-06-25025 June 2013 Request for Additional Information Regarding Reliable Spent Fuel Pool Instrumentation, Order No. EA-12-051 Project stage: RAI NL-13-108, Letter in Reply to Request for Additional Information Regarding the License Renewal Application2013-08-16016 August 2013 Letter in Reply to Request for Additional Information Regarding the License Renewal Application Project stage: Response to RAI NL-13-103, Response to Request for Additional Information (RAI) Regarding Reliable Spent Fuel Pool (SFP) Instrumentation (Order No, EA-12-051)2013-08-20020 August 2013 Response to Request for Additional Information (RAI) Regarding Reliable Spent Fuel Pool (SFP) Instrumentation (Order No, EA-12-051) Project stage: Response to RAI NL-13-110, First Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2013-08-27027 August 2013 First Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other NL-13-109, First Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation2013-08-27027 August 2013 First Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation Project stage: Other NL-13-114, Implementation of License Renewal Regulatory Commitments2013-08-28028 August 2013 Implementation of License Renewal Regulatory Commitments Project stage: Other ML13241A0222013-08-28028 August 2013 Lr Hearing - IPEC License Renewal - Implementation of Unit 2 License Renewal Regulatory Commitments - NL-13-114 Project stage: Other ML13248A4922013-09-0505 September 2013 Lr Hearing - RAI Set 2013-05 Project stage: Request ML13273A3482013-09-30030 September 2013 NRC Staff Hearing File Update 56 Project stage: Request ML13298A8052013-11-0808 November 2013 Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation (TAC Nos. MF0737 and Project stage: RAI ML14010A3312014-01-14014 January 2014 Mega-Tech Services, LLC Technical Evaluation Report Regarding the Overall Integrated Plan for Indian Point Energy Center, Units 2 and 3, TAC Nos.: MF0744 and MF0745 Project stage: Other ML13337A5942014-01-24024 January 2014 Interim Staff Evaluation and Audit Report Relating to Overall Integrated Plan in Response to Order EA-12-049 (Mitigation Strategies) Project stage: Other NL-14-031, Centers Second Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-02-27027 February 2014 Centers Second Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other NL-14-029, Second Six-Month Status Report for the Implementation of Order EA-12-051, Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation2014-02-27027 February 2014 Second Six-Month Status Report for the Implementation of Order EA-12-051, Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Project stage: Other NL-14-109, Third Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation2014-08-27027 August 2014 Third Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation Project stage: Other NL-14-110, Third Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2014-08-27027 August 2014 Third Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other NL-14-132, Response to 03/12/2012, Request for Information Pursuant to Title 10 of the Code of Federal Regulation 50.54(f) Regarding Recommendations of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dia-ichi2014-11-0303 November 2014 Response to 03/12/2012, Request for Information Pursuant to Title 10 of the Code of Federal Regulation 50.54(f) Regarding Recommendations of the Near-Term Task Force (NTTF) Review of Insights from the Fukushima Dia-ichi Project stage: Request ML14335A6422014-12-0909 December 2014 Report for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other NL-15-012, Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-01-28028 January 2015 Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request NL-15-026, Fourth Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation2015-02-27027 February 2015 Fourth Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation Project stage: Other NL-15-025, Fourth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-02-27027 February 2015 Fourth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other ML15085A0692015-03-16016 March 2015 Retraction of Entergys Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request NL-15-036, Retraction of Entergy'S Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-03-16016 March 2015 Retraction of Entergy'S Request for Relaxation from NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Request ML15079A3542015-03-24024 March 2015 Withdrawal of Request for Relaxation of the Schedule Requirements for Order EA-12-049,Issuance of Order to Modify Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis Events Project stage: Withdrawal NL-15-059, Notification of Full Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order EA-12-051 Modifying Licenses with Regard2015-05-20020 May 2015 Notification of Full Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order EA-12-051 Modifying Licenses with Regard Project stage: Other NL-15-112, Fifth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2015-08-28028 August 2015 Fifth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other NL-15-111, Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation2015-08-28028 August 2015 Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation Project stage: Other ML15301A0932015-10-30030 October 2015 Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 Project stage: Other NL-16-024, Centers Sixth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events2016-02-29029 February 2016 Centers Sixth Six-Month Status Report for the Implementation of Order EA-12-049 Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events Project stage: Other ML16155A0842016-04-29029 April 2016 APS Response to Request for Additional Information Regarding Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Lnstrumentation Project stage: Response to RAI NL-16-089, Notification of Full Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order EA-12-051 Modifying Licenses with Regard .2016-08-12012 August 2016 Notification of Full Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order EA-12-051 Modifying Licenses with Regard . Project stage: Other NL-16-115, Response to Request for Additional Information Regarding Review of Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events,2016-12-0202 December 2016 Response to Request for Additional Information Regarding Review of Compliance with Order EA-12-049 Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, Project stage: Response to RAI 2014-12-09
[Table View] |
Text
vEntergy Enterav Nuclear Northeast Indian Point Energy Center 450 Broadway, GSB P.O. Box 249 Buchanan, NY 10511-0249 Tel 914 254 6700 John A Ventosa Site Vice President Administration NL-13-109 August 27, 2013 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852-2738
SUBJECT:
References:
Indian Point Energy Center's First Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation (TAC Nos.
MF0737 and MF0738)
Indian Point Unit Numbers 2 and 3 Docket Nos. 50-247 and 50-286 License Nos. DPR-26 and DPR-64
- 1.
NRC Order Number EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated March 12, 2012 (ML12054A682)
- 2.
NRC Interim Staff Guidance JLD-ISG-2012-03, Compliance with Order EA-12-051, Reliable Spent Fuel Pool Instrumentation, Revision 0, dated August 29, 2012
- 3.
NEI 12-02, Industry Guidance for Compliance with NRC Order EA-12-051, "To Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation", Revision 1, dated August 2012
- 4.
Entergy letter to NRC (NL-12-145), Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051), dated October 29,2012
- 5.
Entergy letter to NRC (NL-13-043), Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated February 27, 2013
Dear Sir or Madam:
On March 12, 2012, the Nuclear Regulatory Commission ("NRC" or "Commission")
issued an order (Reference 1) to Entergy. Reference 1 was immediately effective and koo)
N 0-
NL-13-109 Dockets 50-247 and 50-286 Page 2 of 2 directs Entergy to install reliable spent fuel pool level instrumentation. Specific requirements are outlined in Attachment 2 of Reference 1.
Reference 1 required submission of an initial status report 60 days following issuance of the final interim staff guidance (Reference 2) and an overall integrated plan pursuant to Section IV, Condition C. Reference 2 endorses industry guidance document NEI 12-02, Revision 1 (Reference 3) with clarifications and exceptions identified in Reference 2.
Reference 4 provided the Entergy initial status report regarding spent fuel pool instrumentation. Reference 5 provided the Entergy overall integrated plan.
Reference 1 requires submission of a status report at six-month intervals following submittal of the overall integrated plan. Reference 3 provides direction regarding the content of the status reports. The purpose of this letter is to provide the first six-month status report pursuant to Section IV, Condition C.2, of Reference 1, that delineates progress made in implementing the requirements of Reference 1. The attached report provides an update of milestone accomplishments since the last status report, including any changes to the compliance method, schedule, or need for relief and the basis, if any.
There are no new commitments identified in this submittal. If you have any questions concerning the content of this letter, please contact Mr. Robert Walpole, Manager, Licensing at (914) 254-6710.
I declare under penalty of perjury that the foregoing is true and correct. Executed on August 5, 2013.
Respectfully,
Attachment:
Indian Point Energy Center's First Six-Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation cc:
Mr. Douglas V. Pickett, Senior Project Manager, NRC NRR DORL Mr. William M. Dean, Regional Administrator, NRC Region 1 NRC Resident Inspectors Office Mr. Francis J. Murray, Jr., President and CEO, NYSERDA Ms. Bridget Frymire, New York State Dept. of Public Service Ms. Jessica A. Kratchman NRC NSIR DPR DDEP IRIB
ATTACHMENT TO NL-1 3-109 ENTERGY'S FIRST SIX-MONTH STATUS REPORT FOR THE IMPLEMENTATION OF ORDER EA-12-051 MODIFYING LICENSES WITH REGARD TO REQUIREMENTS FOR TO RELIABLE SPENT FUEL POOL INSTRUMENTATION ENTERGY NUCLEAR OPERATIONS, INC.
INDIAN POINT NUCLEAR GENERATING UNIT NOS. 2 and 3 DOCKET NOS. 50-247 and 50-286
NL-13-109 Dockets 50-247 and 50-286 Attachment Page 1 of 2 Indian Point Energy Center's (IPEC) First Six Month Status Report for the Implementation of Order EA-12-051 Modifying Licenses with Regard to Requirements for to Reliable Spent Fuel Pool Instrumentation Introduction Entergy Nuclear Operations, Inc. (Entergy) developed an overall integrated plan (Reference 1) for Indian Point Energy Center (IPEC), documenting the requirements to install reliable spent fuel pool level instrumentation (SFPI), in response to Reference 2.
This attachment provides an update of milestone accomplishments since submittal of the overall integrated plan, including any changes to the compliance method, schedule, or need for relief/relaxation and the basis, if any.
Milestone Accomplishments None Milestone Schedule Status The following provides a line item update to milestone schedule to support the Overall Integrated Plan. It provides the activity status of each item, and whether the expected completion date has changed. The dates (current as of July 31, 2013) are planning dates subject to change as design and implementation details are developed.
Target Completion Revised Target Milestone Date Activity Status Completion Date Unit 3 Reliable SFPI Installed Spring 2015 Refueling In Progress Outage Unit 2 Reliable SFPI Installed Spring 2016 Refueling In Progress Outage Respond to NRC RAIs August 23, 2013 Complete (Received June 25, 2013)
(Reference 3)
Changes to Compliance Method The original OIP (Reference 1) indicated remote indication in the Control Room but this remote display will no longer be included. The following are the changes to the OIP based on this revision:.
Page 5 of 19 : Displays and signal processors will be located in the respective Fan Houses (FH) and CGRs for both Indian Point 2 (IP2) and Indian Point 3 (IP3) and will be readily accessible.
Page 8 of 19: Instrument power is derived from the display/processors. The locations of the electronics package and the credited displays for both Unit 2 and Unit 3's SFP
NL-13-109 Dockets 50-247 and 50-286 Attachment Page 2 of 2 instrument channels are within the respective Units' Fan Houses. in both Unit 2 and Unit 3, a remote display for both channels of instrumentation will be located in the respective Central Contol Room (CCR) via additional abling The FH &-,,R provides adequate protection against the effects of temperature, flood, humidity, radiation, seismic events, and missile hazards.
Page 9 of 19: The electronics packages are normally powered using 118/120VAC that is provided from separate panels that are powered from separate 480V buses at a minimum. On loss of normal AC power, each processor automatically continues to operate on its own dedicated backup battery supply. The backup batteries and associated UPS are located at the processor, seismically mounted, and qualified for the expected environment. The processor will also have connections designed to allow powering the processor from an external, portable power source.
Finally, the remote displays in each Unit's CCR will be powered via the current loop supplied by the e~ectronics pacskage.
Need for Relief/Relaxation and Basis for the Relief/Relaxation IPEC expects to comply with the Order implementation date and no relief/relaxation is required at this time.
Open Items from Overall Integrated Plan and Draft Safety Evaluation None.
Potential Draft Safety Evaluation Impacts The Draft Safety Evaluation has not been issued at this time.
References The following references support the updates to the overall integrated plan described in this attachment.
- 1. Entergy letter to NRC (NL-13-043), Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation, dated February 27, 2013 (ADAMS Accession No. ML13072A082).
- 2. NRC Order Number EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," dated March 12, 2012 (ADAMS Accession No. ML12054A682).
- 3. "Request for Additional Information Overall Integrated Plan in Response to Order EA 051, 'Reliable Spent Fuel Pool Instrumentation' Entergy Operations, Order No. EA-12-051 (TAC Nos. MF0737 and MF078)" Dated June 25, 2013 (ADAMS Accession No. ML13169A127).