United States Nuclear Regulatory Commission Official Hearing Exhibit NYS000206 Entergy Nuclear Operations, Inc.
In the Matter of:
(Indian Point Nuclear Generating Units 2 and 3) Submitted: December 16, 2011 ASLBP #: 07-858-03-LR-BD01 Docket #: 05000247 l 05000286 Exhibit #: NYS000206-00-BD01 Identified: 10/15/2012 Admitted: 10/15/2012 Withdrawn:
Rejected: Stricken:
Other:
UNITED STATES NUCLEAR REGULATORY COMMISSION ATOMIC SAFETY AND LICENSING BOARD
x In re: Docket Nos. 50-247-LR; 50-286-LR License Renewal Application Submitted by ASLBP No. 07-858-03-LR-BD01 Entergy Nuclear Indian Point 2, LLC, DPR-26, DPR-64 Entergy Nuclear Indian Point 3, LLC, and Entergy Nuclear Operations, Inc. December 16, 2011
x STATE OF NEW YORK INITIAL STATEMENT OF POSITION CONTENTION NYS-16/16A/16B (NYS-16B)
Office of the Attorney General for the State of New York The Capitol State Street Albany, New York 12224
TABLE OF CONTENTS Page PRELIMINARY STATEMENT .....................................................................................................1
SUMMARY
OF ARGUMENT AND SUPPORTING EVIDENCE...............................................2 PROPOSED FINDINGS OF FACT ................................................................................................5 PROCEDURAL HISTORY.............................................................................................................6 LEGAL FRAMEWORK ...............................................................................................................10 ARGUMENT.................................................................................................................................14 THE FSEIS VIOLATES NEPA, NRC REGULATIONS, AND CEQ REGULATIONS BECAUSE IT ACCEPTS A SAMA ANALYSIS PREDICATED ON INACCURATE POPULATION ESTIMATES....................14 I. Entergys Population Estimates are Inaccurate..........................................14 II. NRC Staff Failed to Consider New Yorks Concerns Regarding Entergys Flawed SAMA Analysis and Instead Accepted the Flawed Analysis in Total.........................................18 III. By Accepting Entergys Flawed 2035 Population Estimate in the FSEIS, NRC Staff Has Relied Upon and Presented Inaccurate Information to the Public, Violating the Requirement that the FSEIS Contain Accurate Scientific Information and Disregarding the Informational Purpose of NEPA ..........................................................21 IV. By Accepting Entergys Flawed SAMA Analysis, NRC Staff Has Failed to Take the Requisite Hard Look Under NEPA and Violated NRCs Own Regulations Regarding SAMA Analyses.......................................................................22 CONCLUSION..............................................................................................................................23 i
State of New York Statement of Position Contention NYS-16/16A/16B PRELIMINARY STATEMENT In accordance with 10 C.F.R. Section 2.1207(a)(1) and the Atomic Safety and Licensing Boards (Board) July 1, 2010 Memorandum and Order, the State of New York (New York or the State) hereby submits its Initial Statement of Position on New Yorks admitted Contention 16/16A/16B (NYS-16B), concerning Entergys underestimation of the 2035 population within 50 miles of Indian Point likely to be exposed to radiation during a severe accident, the potential concomitant underestimation of the costs of a severe accident, and thus, the potential underestimation of the benefit of any given severe accident mitigation alternative (SAMA) that would reduce human exposures in the event of a severe accident. It is particularly important that NRC rely on accurate population estimates in the relicensing proceeding given the fact that the Commission has recognized that the population density surrounding Indian Point is higher than that surrounding any other plant in the United States, and that a severe release of radioactive materials at Indian Point could have more serious consequences than that same release at virtually any other NRC-licensed site. Consolidated Edison Company of New York (Indian Point, Unit 2) and Power Authority of the State of New York (Indian Point, Unit 3), CLI-85-6, 21 N.R.C. 1043, 1049-50 (1985). The Board should grant the element of Contention 16 challenging Entergys population estimate as improperly excluding commuters and failing to account for census undercount.1 In this proceeding, the State and other intervenor parties have satisfied the standards contained in 10 C.F.R. § 2.309 governing contention admissibilitystandards that NRC has described as strict by design. Dominion Nuclear Connecticut, Inc. (Millstone Nuclear Power 1
The State has chosen not to pursue the part of Contention 16 challenging Entergys air dispersion model.
1
State of New York Statement of Position Contention NYS-16/16A/16B Station, Units 2 & 3), CLI-01-24, 54 N.R.C. 349, 358 (2001), pet. for reconsideration denied, CLI-02-1, 55 N.R.C. 1 (2002). The State now submits this testimony to show that Entergys license renewal application (LRA) should be denied because NRC Staffs December 2010 Final Supplemental Environmental Impact Statement (FSEIS) is legally deficient due to its failure to reliably predict the potential exposed 2035 population, which in turn, led it to substantially understate the adverse environmental impacts from relicensing, thus violating the National Environmental Policy Act (NEPA), 42 U.S.C. § 4332, and the regulations implementing NEPA adopted by the Council on Environmental Quality (CEQ) and the Nuclear Regulatory Commission (NRC).2
SUMMARY
OF ARGUMENT AND SUPPORTING EVIDENCE Because of the enormous population surrounding the Indian Point nuclear reactors, reliably predicting how many people would be exposed to radiation in the event of a severe accident is of critical importance, particularly with respect to the FSEIS and the SAMA analysis.
The purpose of preparing a FSEIS is to focus NRCs attention on the environmental consequences of relicensing so that important effects will not be overlooked or underestimated only to be discovered after resources have been committed or the die otherwise cast. Robertson 2
Any effort by NRC Staff to remedy this deficiency by either correcting the population estimates and environmental impacts, or requiring Entergy to revise its population estimates and environmental impacts to properly estimate the 2035 population within 50 miles of Indian Point, should be filed with the Board, and all parties should be given a reasonable opportunity to file new contentions based on Staffs or Entergys submittals. See 10 C.F.R. § 2.309(f)(2) (On issues arising under the National Environmental Policy Act, the petitioner shall file contentions based on the applicants environmental report. The petitioner may amend those contentions or file new contentions if there are data or conclusions in the NRC draft or final environmental impact statement, environmental assessment, or any supplements relating thereto, that differ significantly from the data or conclusions in the applicants documents.).
2
State of New York Statement of Position Contention NYS-16/16A/16B
- v. Methow Valley Citizens Council, 490 U.S. 332, 349 (1989).3 In addition to ensuring that the agency makes an informed decision, the FSEIS also serves as an informational tool for the public so that it may participate in the decision-making process. Methow, 490 U.S. at 349. However, if the FSEIS does not contain accurate information, it fails to serve either purpose because its informational value is lost.4 A central feature of the FSEIS is the consideration of alternatives, including the SAMA analysis. The purpose of a SAMA analysis is to ensure that any plant changesin hardware, procedures, or trainingthat have a potential for significantly improving severe accident safety performance are indentified and assessed. Duke Energy Corp. (McGuire Nuclear Station, Units 1 and 2; Catawba Nuclear Station, Units 1 and 2) CLI-02-17, 56 N.R.C. 1, 5 (2002). According to the Board, [T]he FSEIS must demonstrate that the NRC [S]taff has received sufficient information to take a hard look at SAMAs as required by 10 C.F.R. § 51.53(c)(3)(ii)(L), has in fact taken that hard look, and has adequately explained its conclusions . . . . Entergy Nuclear Operations, Inc. (Indian Point, Units 2 and 3), LBP-11-17, at 18 (July 14, 2011) (ML111950712)
(July 14, 2011 Board Order).
In a SAMA analysis, population is a key input that helps to determine the costs of a severe accident and the benefits of risk mitigation methods that reduce population exposures. If more people are assumed to be exposed to radiation released in a severe accident, the predicted 3
See also 40 C.F.R. § 1500.1(c) (The NEPA process is intended to help public officials make decisions that are based on understanding of environmental consequences, and take actions that protect, restore, and enhance the environment.).
4 To avoid duplication, the State respectfully refers the Board and the parties to the discussion of NEPA at pages 14-20 in the States Statement of Position in Support of Contention NYS-37 (filed Dec. 14, 2011).
3
State of New York Statement of Position Contention NYS-16/16A/16B costs of a severe accident may increase, and it may become more likely that a risk mitigation method that reduces those exposures will be cost-beneficial. Therefore, the accuracy of the SAMA analysis depends, in part, on the accuracy of the estimates of human population that would be exposed to radiation from a severe accident.
The FSEIS accepts Entergys estimate of the 2035 population within 50 miles of Indian Point despite two significant errors in Entergys estimate: (1) failure to account for census undercount5; and (2) failure to account for the commuter population present within the 50 mile zone. As shown in the December 16, 2011 Report of Dr. Stephen C. Sheppard, Ph.D. (Exh.
NYS000209) (Sheppard Report), these deficiencies cause the population at risk in the event of a severe accident to be substantially underestimated. Dr. Sheppard shows not only that Entergys estimate is inaccurate for failing to include census undercount and commuters, but also that the inclusion of those two factors leads to an increase of more than 1.2 million persons to Entergys estimate, which is approximately a 6.4% increase. Sheppard Report at 1, 7 (Exh. NYS000209).
An underestimate of 1.2 million people is significant.
NRC Staffs reliance on, and inclusion of, a flawed population estimate in the FSEIS renders that document legally deficient for two reasons. First, it fails to serve its NEPA-mandated purpose of providing accurate information to decision-makers and the public. The exclusion of over one million persons from the population estimate in not a mere oversightit is a significant discrepancy that affects relicensing decisions. Second, by accepting a SAMA analysis based on inaccurate data, the FSEIS does not take the NEPA-required hard look at 5
As explained in the Report of Dr. Stephen C. Sheppard, census undercount refers to the systematic undercount of the population by the U.S. Census Bureau. Sheppard Report at 4-5 (Exh. NYS000209).
4
State of New York Statement of Position Contention NYS-16/16A/16B mitigation alternatives to the proposed action. And so, for the reasons stated in this pleading and the accompanying Testimony of Dr. Stephen Sheppard (Exh. NYS000207), the State urges the Board to deny Entergys LRA.
PROPOSED FINDINGS OF FACT This Statement of Position, along with its supporting evidence, provide the bases for the Board finding the following facts regarding NYS-16B:
- 1. Since at least the 1990s, the census of population conducted by the U.S. Census Bureau has been subject to a systematic undercount;
- 2. Entergys population estimate, which relies solely on census data, fails to include this census undercount, resulting in an underestimation of the 2035 population within 50 miles of Indian Point likely to be exposed in the event of a severe accident;
- 3. Workers who reside outside of the 50 mile zone, but commute to workplaces within 50 miles of Indian Point are part of the population at risk of exposure due to a severe accident;
- 4. Entergys population estimate fails to include such commuters, resulting in further underestimation of the 2035 population within 50 miles of Indian Point likely to be exposed in the event of a severe accident;
- 5. NRC Staff accepted Entergys population estimates in the FSEIS without accounting for either census undercount or commuters;
- 6. Entergys underestimation of the 2035 population within 50 miles of Indian Point could lead to an underestimation of the costs of a severe accident; 5
State of New York Statement of Position Contention NYS-16/16A/16B
- 7. An underestimation of the costs of a severe accident could lead to an underestimation of the benefit obtained from implementing a SAMA, thus potentially excluding certain mitigation alternatives from full consideration; and
- 8. By uncritically accepting Entergys population estimates, with the attendant underestimation of the costs of a nuclear accident, the FSEIS presented inaccurate information and failed to take the requisite hard look at the SAMAs, and is legally deficient.
PROCEDURAL HISTORY A. New York State Contention 16 On November 30, 2007, the State of New York submitted to this Board a Petition to Intervene, which included proposed contentions regarding critical deficiencies in Entergys Indian Point relicensing application with respect to public safety, health, and the environment.
Among those proposed contentions was Contention 16 (NYS-16), which asserted that Entergys SAMA analysis for Indian Point Unit 2 and Unit 3 was flawed because it will not present an accurate estimate of the costs of human exposure. New York State Notice of Intention to Participate and Petition to Intervene, Contention 16, at 163 (Nov. 30, 2007)
(ML073400187).6 One of the bases for Contention 16 was that Entergys projections of the 6
The State also challenged Entergys air dispersion model as being used beyond its range of validity and not accurately predicting the geographic dispersion of radionuclides released in a severe accident. New York filed a motion for summary disposition for the part of the contention dealing with the air dispersion model. See State of New Yorks Motion for Summary Disposition on Use of Straight Line Gaussian Air Dispersion Model for the Environmental Impact Analysis of Significant Radiological Impacts at Indian Point and NYS Contention 16A (Aug. 28, 2008)
(ML092610906). That motion was denied because the Board found an issue of material fact.
Entergy Nuclear Operations, Inc. (Indian Point Nuclear Generating Units 2 and 3) ASLBP No.
6
State of New York Statement of Position Contention NYS-16/16A/16B 2035 population likely to be living within 50 miles of Indian Point are suspect and underestimate the potential exposed population, and that this underestimation might, in turn, lead to an underestimation of the benefit obtained from implementing a SAMA. Id. at 164 n.37.
While challenging the admissibility of Contention 16 on several grounds, neither Entergy nor NRC Staff addressed New Yorks argument that the population projections are suspect and underestimate the potential exposed population. Answer of Entergy Nuclear Operations Inc.
Opposing New York State Notice of Intention to Participate and Petition to Intervene at 109-113 (Jan. 22, 2008) (ML080300149) and NRC Staffs Response to Petitions for Leave to Intervene Filed by the State of New York and others at 56-58 (Jan. 22, 2008) (ML080230543). The Board admitted NYS-16 with respect to New Yorks argument that the population projections used by Entergy are underestimated, because population size is a question of model input data material to the making of accurate SAMA analyses. Entergy Nuclear Operations, Inc. (Indian Point, Units 2 and 3), LBP-08-13, 68 N.R.C. 43, 116 (Jul. 31, 2008) (ML082130436) (July 31, 2008 Board Decision).
B. New York State Contention 16A After NRC Staff released the Draft Supplemental Environmental Impact Statement (DSEIS), in which it failed to address any of the issues raised in NYS-16, New York submitted an amended contention, NYS-16A, to apply to the DSEIS. New York State Contentions Concerning Staffs Draft Supplemental Environmental Impact Statement at 10 n.4 (Feb. 27, 2009) (ML090690303). While Entergy opposed the admission of NYS-16A, it did not address New Yorks argument that the population projections are suspect and underestimate the 07-858-03-LR-BD01, slip op. at 14 (Nov. 3, 2009). As stated (p. 1), the State has chosen not to pursue this aspect of NYS-16.
7
State of New York Statement of Position Contention NYS-16/16A/16B potential exposed population. Answer of Entergy Nuclear Operations, Inc. Opposing New and Amended Environmental Contentions of New York State at 13-15 (Mar. 24, 2009)
(ML090930204). NRC Staff did not oppose the admission of NYS-16A to the extent that it applied NYS-16 to the DSEIS, and again, did not address New Yorks argument that Entergy had underestimated the population that would be exposed in the event of an accident. NRC Staffs Answer to Amended and New Contentions Filed by the State of New York and Riverkeeper, Inc., Concerning the Draft Supplemental Environmental Impact Statement at 12-13 (Mar. 24, 2009) (ML090840116). The Board admitted NYS-16As challenge to Entergys population projections. Entergy Nuclear Operations, Inc. (Indian Point, Units 2 and 3), at 4-7 (June 16, 2009) (ML091670435).7 C. New York State Contention 16B After Entergys December 2009 Reanalysis of Severe Accident Alternatives (SAMA Reanalysis) failed to address issues raised in admitted contention NYS-16/16A, New York submitted an amended contention, Contention 16B. State of New Yorks Motion for Leave to File New and Amended Contentions Concerning the December 2009 Reanalysis of Severe Accident Mitigation Alternatives (Mar. 11, 2010) (ML100780366). Among other things, Contention 16B argued that the population projections used by Entergy in its 2009 SAMA Reanalysis are suspect and underestimate the potential exposed population. See Id. at 8 n.3.
New York specified Entergys undercount of tourists and exclusion of commuters as examples of its underestimation. Id.
7 The Board did not admit the portion of NYS-16A challenging Entergys use of an air dispersion model that is not EPA-approved. Entergy Nuclear Operations, Inc. (Indian Point, Units 2 and 3), at 6 (June 16, 2009)(ML091670435).
8
State of New York Statement of Position Contention NYS-16/16A/16B For the first time in the proceeding, after opposing New Yorks contention in at least three pleadings, Entergy and NRC Staff finally acknowledged that New Yorkin every pleading since its Petition in 2007had challenged the population estimates used by Entergy in its environmental report and by NRC Staff in the DSEIS.8 However, Entergy mischaracterized New Yorks concern with population estimates as being with the economic impact of lost tourism and business, instead of as an input to the MACCS2 program. Applicants Answer to New York States New and Amended Contentions Concerning Entergys 2009 Revised SAMA Analysis at 19-20 (Apr. 5, 2010) (ML101450328). NRC Staff also opposed Contention 16B. NRC Staffs Answer to State of New Yorks New and Amended Contentions Concerning the December 2009 Severe Accident Mitigation Alternatives Reanalysis at 12-13 (Apr. 5, 2010) (ML100960165).
The Board rejected Entergy and Staffs arguments and admitted Contention 16B, finding that it does not address the loss of tourism, but instead, an input to the MACCS2 code used by Entergy in its SAMA analysis, and that the contention was timely because it arose out of the 2009 SAMA Reanalysis. Entergy Nuclear Operations, Inc. (Indian Point, Units 2 and 3), LBP-10-13, at 14-15 (June 30, 2010) (ML101810344) (June 30, 2010 Board Decision). The Board noted that its rulings on NYS-16 and NYS-16A had established the admissibility of the question whether the population projections used by Entergy are underestimated. Id. at 14. It concluded that Contention 16B is admissible because the absence of tourists and commuters might underestimate the exposed population in a severe accident and, in turn, underestimate the benefit achieved in implementing a SAMA. Id.
8 NRC Staff also acknowledged the States challenge to Entergys population estimates in Appendix G of the FSEIS. As explained below on pages 19-20, however, Staff did not question the assumptions on which Entergy based its population estimate.
9
State of New York Statement of Position Contention NYS-16/16A/16B LEGAL FRAMEWORK NEPA, 42 U.S.C. § 4332, and the CEQ regulations for implementing NEPA, 40 C.F.R. § 1502, require federal agencies to examine, in an environmental impact statement (EIS), the potential adverse environmental impacts of their major discretionary actions. The preparation of an EIS serves two purposes: first, it causes the agency to take the requisite hard look at the environmental impacts of the proposed action; and second, by making the relevant information publicly available, it allows the public to participate in the decision-making process. Hughes River Watershed Conservancy v. Glickman, 81 F.3d 437, 443 (4th Cir. 1996).
NEPA, NRCs own NEPA regulations, and CEQ regulations require that NRC Staff evaluate, in the EIS, a reasonable range of alternatives for reducing the adverse environmental impacts of relicensing. 42 U.S.C. § 4332(2)(C)(iii), 10 C.F.R. § 51.53(C)(3)(iii), and 40 C.F.R. § 1502.14. In doing so, NRC Staff must rely on accurate scientific data. 40 C.F.R. § 1500.1(b).
As part of its environmental obligations under NEPA, NRC Staff is obligated to conduct a site-specific SAMA analysis during the review of license renewal applications. 10 C.F.R. § 51.53(c)(3)(ii)(L); Part 51, Subpart A, Appendix B, Table B-1. This requirement dates back to 1989 when the U.S. Court of Appeals for the Third Circuit ruled that NEPA requires NRC to examine the environmental effects of significant accidents at nuclear power plants. Limerick Ecology Action, Inc. v. U.S. Nuclear Regulatory Commn, 869 F.2d 719, 729-31 (3d Cir. 1989).
Moreover, the court held that such evaluation must take place on a case-by-case basis, since differences in plant design and location will cause the risk and environmental impact of severe accidents to vary by plant. Id. at 738-39. Thereafter, NRC promulgated regulations requiring significant accident mitigation alternative analyses (SAMA analyses) during the Staffs review 10
State of New York Statement of Position Contention NYS-16/16A/16B of an application to renew a nuclear reactors operating license. That regulation provides: If the
[S]taff has not previously considered severe accident mitigation alternatives for the applicants plant in an environmental impact statement or in an environmental assessment, a consideration of alternatives to mitigate severe accidents must be provided. 10 C.F.R. § 51.53(c)(3)(ii)(L).9 Indian Point Unit 2 and Unit 3 were not subject to the SAMA analysis requirement when they received permission to operate in 1973 and 1975. See 21 Fed. Reg. 3,085 (May 9, 1956), 31 Fed.
Reg. 13,616-17 (Oct. 21, 1966), 34 Fed. Reg. 13,437 (Aug. 20, 1969). Accordingly, NRC regulations require that NRC Staff conduct a SAMA analysis during Staffs review of Entergys LRA for Indian Point and present the SAMA analysis in the supplemental environmental impact statement (SEIS, here the DSEIS and FSEIS) prepared as part of the license renewal process.
10 C.F.R. § 51.95(c)(4); see 10 C.F.R. §§ 51.53(c)(3)(ii)(L) and 51.71(d).10 NRC Staff was required to review the SAMA analysis Entergy submitted as part of its 2007 Environmental Report as well as the SAMA reanalysis Entergy submitted in December 2009.
In conducting a site-specific SAMA analysis, NEPA requires that NRC take a hard look at the potential environmental impacts of a severe accident, consider a reasonable range of alternatives, and provide a rational basis for rejecting alternatives that are decidedly cost-effective. Methow, 490 U.S. at 350; Limerick Ecology, 869 F.2d at 737; and see Bowman 9
The Staff is obligated to evaluate an applicants SAMA analysis and assure that it has been properly conducted pursuant to 10 C.F.R. § 51.95(c)(4).
10 See also NUREG-1555 Standard Review Plans for Environmental Reviews of Nuclear Power Plants Supplement 1 (October 1999) at 5.1.1-1 (Exh. NYS000220) (This environmental standard review plan (ESRP) directs the [S]taffs analysis and assessment of the severe accidents for the applicants plant . . . . The intent is to identify additional cases that might warrant either additional features or other actions that would prevent or mitigate the consequences of serious accidents).
11
State of New York Statement of Position Contention NYS-16/16A/16B Transp., Inc. v. Arkansas-Best Freight Sys., Inc. 419 U.S. 281, 285-86 (1974). According to the
- Board, Entergys licenses cannot be renewed unless and until the NRC Staff reviews Entergys completed SAMA analyses and either incorporates the result of these reviews into the FSEIS or, in the alternative, modifies its FSEIS to provide a valid reason for recommending the renewal of the licenses before the analysis of potentially cost effective SAMAs is complete and for not requiring the implementation of cost-beneficial SAMAs.
July 14, 2011 Board Order at 17.
NRCs obligation to take the requisite hard look required under NEPA is not met if NRC relies on incorrect assumptions or data provided by a licensee because accurate scientific analysis, expert agency comments, and public scrutiny are essential to implementing NEPA.
Native Ecosystems Council v. U.S. Forest Serv., 418 F.3d 953, 964-65 (9th Cir. 2005); see also 40 C.F.R. § 1500.1(b).11 Accordingly, NEPA requires that an EIS must contain high quality information and accurate scientific analysis,12 and furthermore obligates NRC Staff to independently evaluate and be responsible for the reliability of all information used in the draft 11 In a recent Commissioners Order, the Commission explained its position regarding the applicability of CEQ regulations to its decision-making processes: We look to CEQ regulations for guidance. . . [b]ut our longstanding policy is that the NRC, as an independent regulatory agency, is not bound by those portions of CEQs NEPA regulations that . . . have a substantive impact on the way in which the Commission performs its regulatory functions (internal citations omitted). Pacific Gas and Electric Co. (Diablo Canyon Nuclear Power Plant, Units 1 and 2),
CLI-11-11, 2011 WL 4896492, 10 (2011). The NRCs policy does not affect the applicability of CEQ regulation 40 C.F.R. § 1500.1(b) because that regulation does not substantively change the way in which the Commission performs its regulatory functions. The NRC has implemented NEPA § 102(2) through its regulations. See 10 C.F.R. § 51. 40 C.F.R. § 1500.1(b) does not substantively alter the requirements of NEPA § 102(2), but confirms the purpose of the NEPA requirementsto ensure that high quality information is available to decision-makers.
12 40 C.F.R. § 1500.1(b); Conservation Northwest v. Rey, 674 F. Supp. 2d 1232, 1249 (W.D.
Wash. 2009) (citing Ctr. for Biological Diversity v. U.S. Forest Serv., 349 F.3d 1157, 1167 (9th Cir. 2003).
12
State of New York Statement of Position Contention NYS-16/16A/16B environmental impact statement. 10 C.F.R. § 51.70(b); Native Ecosystems, 418 F.3d at 964-65.
See also 10 C.F.R. § 51.92(a); 40 C.F.R. § 1502.24 (Staff must ensure the professional integrity, including scientific integrity, of the discussions and analyses in environmental impact statements.).
According to NRC regulations, the FSEIS must respond to any comments on the draft environmental impact statement or on any supplement to the draft environmental impact statement. 10 C.F.R. § 51.91(a)(1); see also 40 C.F.R. § 1503.4(a). Responses may include the modification of alternatives, development of alternatives not previously given serious consideration, and factual corrections. 10 C.F.R. § 51.91(a)(1)(i)-(iv). If NRC Staff determines that certain comments do not warrant a further response, they must explain why and cite sources, authorities, or reasons that support this conclusion. 10 C.F.R. § 51.91(a)(1)(v).
Ultimately, the decision-makerin this proceeding, the NRCmust be able to use the NEPA analysis in evaluating a reasonable range of alternatives and providing a rational basis for its final decision.13 See 10 C.F.R. §§ 51.53(C)(3)(iii), 51.95(c)(4), and 51.103(a)(5). If the NEPA analysis inadequately evaluates the available evidence and/or ignores relevant facts, as the FSEIS does in this case, then the decision-maker cannot have a rational basis for the ultimate decision.
13 Thus the Board concluded elsewhere in these proceedings that the NRC would be acting arbitrarily and capriciously if it did not look at relevant data and sufficiently explain a rational nexus between the facts found in its review and the choice it makes as a result of that review.
July 14, 2011 Board Order at 11-12, citing ShieldAlloy Metallugical Corp. v. NRC, 624 F.3d 489, 492-93 (D.C. Cir. 2010) (citations omitted).
13
State of New York Statement of Position Contention NYS-16/16A/16B ARGUMENT THE FSEIS VIOLATES NEPA, NRC REGULATIONS, AND CEQ REGULATIONS BECAUSE IT ACCEPTS A SAMA ANALYSIS PREDICATED ON INACCURATE POPULATION ESTIMATES Since its initial pleading in 2007, New York has argued that Entergys SAMA analysis underestimated the 2035 population within 50 miles of Indian Point, which may have caused the benefits of implementing a SAMA to be understated. Yet, despite plain deficiencies in Entergys population estimate, which New York outlined in its initial and subsequent pleadings, and despite the fact that such deficiencies bring the adequacy of Entergys SAMA analysis into question, Staff uncritically accepted Entergys flawed estimates in the December 2010 FSEIS.
These deficiencies render the FSEIS legally deficient and incapable of supporting a decision on license renewal.
POINT I ENTERGYS POPULATION ESTIMATES ARE INACCURATE There are two clear and unambiguous deficiencies in Entergys population estimates:
(1) the failure to include census undercount; and (2) the exclusion of commuters residing outside of the 50 mile zone of Indian Point, whose workplaces are within the 50 mile zone, as a component of the transient population. Sheppard Report at 4 (Exh. NYS000209); Contention 16B at 8 n.3. Together these two deficiencies led Entergy to ignore 1.2 million persons at risk in the event of a severe accident at Indian Pointpersons whose radiation exposures may increase both the cost of a severe accident and the benefit to be obtained by reducing those exposures.
Entergy underestimated the population within 50 miles of Indian Point by failing to account for census undercount. Demographers have been aware of a systematic undercounting 14
State of New York Statement of Position Contention NYS-16/16A/16B of certain populations, especially minority subgroups, by government censuses. Sheppard Report at 4 (Exh. NYS000209). Although its causes are varied, census undercount is relatively higher in population centers with large minority populations, like New York City, and its effects have been accurately measured. See Id. at 4-5.14 Factoring census undercount into population estimates is uncontroversial, and, indeed, had Entergy conservatively adjusted for census undercount, its estimate would have been higher by approximately 230,000 persons. Id. at p.8, Table 1, column 5.
Entergy also underestimated the population within 50 miles of Indian Point by failing to include commuters. According to Dr. Sheppards report, approximately 1 million persons residing outside the 50 mile radius commute into the 50 mile radius of Indian Point, where their workplaces are located. Id. at 8, Table 1, column 6. This is a significant number of people who would be at risk in the event of an accident at Indian Point, yet they were not included in Entergys population estimate.
14 This portion of Dr. Sheppards report may also provide support for Clearwater EC-3, which asserts that Entergys Environmental Report fails to acknowledge or describe potential impacts upon the large minority and low-income populations that surround the plant. Entergy Nuclear Operations, Inc. (Indian Point, Units 2 and 3), LBP-08-13, 68 N.R.C. 43, 196 (Jul. 31, 2008).
15
State of New York Statement of Position Contention NYS-16/16A/16B Figure 1. Region within 50 miles of Indian Point. Sheppard Report at 3 (Exh.
NYS000209).
Moreover, documents disclosed by NRC Staff show that prevailing weather patterns could cause a severe accident at Indian Point, with the release of radionuclides, to have a disproportionate impact on the New York City Metropolitan population center located to the south of Indian Point.
16
State of New York Statement of Position Contention NYS-16/16A/16B Figure 2. Plot of Weather for Years 1999 - 2002 from the site 10 meter tower showing wind direction (percent by direction). Taken from NRC Staff email, from Robert Palla to Andrew Stuyvenberg, containing document on weather runs (Oct. 29, 2009)
(ML093020493) (Exh. NYS000221).
In order for sound environmental decisions to be made during the relicensing process, Entergy, NRC, and the public must have an accurate estimate of the population surrounding Indian Point that would be at risk in the event of a severe accident.15 Because population size is used to calculate the economic costs associated with a severe accident, which are ultimately compared to the economic costs of implementing each SAMA, Entergys underestimated population projections could lead to an underestimation of economic costs associated with a 15 As noted on p. 1, it is particularly important that NRC rely on accurate population estimates in the relicensing proceeding given the fact that the Commission has recognized that the population density surrounding Indian Point is higher than that surrounding any other plant in the United States, and that a severe release of radioactive materials at Indian Point could have more serious consequences than that same release at virtually any other NRC-licensed site. Consolidated Edison Company of New York (Indian Point, Unit 2) and Power Authority of the State of New York (Indian Point, Unit 3), CLI-85-6, 21 N.R.C. 1043, 1049-50 (1985).
17
State of New York Statement of Position Contention NYS-16/16A/16B severe accident and call into question the validity of its SAMA analysis. Sheppard Report at 7.
The Board admitted NYS-16 for that very reason, describing the challenge to Entergys population projections as a question of model input data material to the making of accurate SAMA analyses. July 31, 2008 Board Decision at 112.16 POINT II NRC STAFF FAILED TO CONSIDER NEW YORKS CONCERNS REGARDING ENTERGYS FLAWED SAMA ANALYSIS AND INSTEAD ACCEPTED THE FLAWED ANALYSIS IN TOTAL New York brought the issue of Entergys flawed population estimate to the attention of NRC Staff well before publication of the FSEIS, giving NRC Staff ample time to undertake additional analysis if required. Yet NRC Staff failed to address New Yorks concerns, thereby violating NEPA, NRC regulations, and CEQ regulations that obligate Staff to respond to comments on the DSEIS. Furthermore, Staff ignored NRCs own guidance17 on measuring transient populations around nuclear reactors.
In 2007, one year before NRCs publication of the DSEIS, New York brought Entergys population underestimation to the agencys attention. New York State Notice of Intention to Participate and Petition to Intervene, Contention 16, at 163 (Nov. 30, 2007) (ML073400187).
Nevertheless, NRC Staff did not address the States concerns in the DSEIS, and instead, it accepted, without questioning, Entergys population assumptions. DSEIS, Appendix G, at G-18 16 Furthermore, in its decision admitting Contention 16B, the Board stated, It is not clear that Entergys December 2009 SAMA Reanalysis adds the infusion of tourists and commuters in New York City to the population used for its SAMA analysisan absence that might underestimate the exposed population in a severe accident and, in turn, underestimate the benefit achieved in implementing a SAMA. June 30, 2010 Board Decision at 14.
17 See NRC, Standard Format and Content of Safety Analysis Reports for Nuclear Power Plants, LWR Edition, Part 1, at Section 2.1.3.3, at 2-4 (Nov. 1978) (ML011340072) (Exh. NYS000222).
18
State of New York Statement of Position Contention NYS-16/16A/16B (The NRC [S]taff considers the methods and assumptions for estimating population reasonable and acceptable for the purposes of the SAMA evaluation.) (Exh. NYS00132D).
Although New York again raised the issue of population underestimation in NYS-16A, Staff failed to question Entergys population estimates in the body of the FSEIS, and instead, merely repeated (nearly verbatim) the assessment it made of Entergys population estimates in the DSEIS. See FSEIS, Appendix G, at G-20 (Exh. NYS00133I). In FSEIS Appendix G, dedicated to addressing issues raised by New York Contentions 12 and 16, Staff purports to review Entergys baseline and projected population values and its population projection methodology. Id. at G-24. NRC Staff employed Sandia National Laboratories (Sandia)18 to verify both Entergys population base and the methodology by which it extrapolated that base population out to the year 2035, but neither NRC nor Sandia examined the assumptions through which Entergy arrived at its base populationassumptions, which, as described above, are invalid. First, both NRCs analysis of Entergys population estimates and Sandias independent population estimates rely on 2000 census data without factoring in the effects of census undercount. Id. at G-24. Second, despite referencing the very pleading in which New York argues that commuters must be included in any credible estimate of the population of the New 18 In April 2011, the State filed a motion to compel NRC Staff to disclose the Sandia documents they relied upon in the FSEIS. State of New York Motion to Compel NRC Staff to Produce Documents Relied Upon in Staffs Final Supplemental Environmental Impact Statement (April 22, 2011) (ML11132A149). After oral argument before the Board, NRC agreed to provide the documents to settle the States motion. See Letter from Sherwin E. Turk to Janice A. Dean (May 25, 2011) (ML11146A058). By letter dated November 2, 2011, NRC Staff indicated that they were not asserting deliberative process privilege over the Sandia documents that were provided.
Letter from Sherwin E. Turk to Janice A. Dean (November 2, 2011) (ML11306A125). The documents produced concerned various issues including population estimates and air dispersion.
19
State of New York Statement of Position Contention NYS-16/16A/16B York City metropolitan region, NRC Staff does not question Entergys exclusion of commuters from the transient population. Id.
NRC Staffs failure to respond to the population estimate concerns raised by the State in its comments19 on the DSEIS violates NRC and CEQ regulations that require Staff to respond, in the FSEIS, to comments on the DSEIS or any supplement to it. See 10 C.F.R. § 51.91(a)(1) and 40 C.F.R. § 1503.4(a) (requiring agencies to assess and respond to comments in FSEISs). These regulations specifically obligate NRC Staff to respond by making factual corrections, if called for, or to explain why the comments do not warrant further response, citing sources, authorities, or reasons for such a conclusion. 10 C.F.R. § 51.91(a)(1)(iv) & (v) and 40 C.F.R. § 1503.4(a)(1)-(5). Although New Yorks comments alerted NRC Staff to Entergys failure to include commuters in its population estimate, Staff failed to address this point in the FSEIS or explain why it does not warrant a response.
Moreover, NRC Staffs failure to consider the impact of commuters is contrary to NRC guidance, which directs licensees on the proper estimation of transient populations in their plants final safety analysis reports. Specifically:
If the plant is located in an area where significant population variations due to transient land use [recreational or industrial] are expected, additional tables of population distribution should be provided to indicate peak seasonal and daily populations.
19 See State of New York Supplemental Submission Concerning Draft Supplemental Environmental Impact Statement Regarding the License Renewal of Indian Point Units 2 and 3, and Recent Events Including the December 2009 Reanalysis of Severe Accident Mitigation Alternatives Analysis and the Federal Governments Decision to Withdraw the Application for Yucca Mountain at 28, n. 8 (March 19, 2010) (The December 2009 SAMA Reanalysis does not adequately take into account tourists and daily commuters - individuals who are not included in New York Citys resident population, but who nevertheless could be affected by a severe accident while they are in the City.).
20
State of New York Statement of Position Contention NYS-16/16A/16B NRC, Standard Format and Content of Safety Analysis Reports for Nuclear Power Plants, LWR Edition, Part 1, at Section 2.1.3.3, at 2-4 (Nov. 1978) (ML011340072) (Exh. NYS000222).
While this guidance is not binding on Entergy, it constitutes an admission by Staff (see Rule 801(d)(2) of the Federal Rules of Evidence), and thus, should be the basis for rejection of any contrary position now being taken by Staffat least so long as Staff does not provide a rational explanation of why its previous position was wrong and does not identify steps it took to withdraw the identified guidance as erroneous.
POINT III BY ACCEPTING ENTERGYS FLAWED 2035 POPULATION ESTIMATE IN THE FSEIS, NRC STAFF HAS RELIED UPON AND PRESENTED INACCURATE INFORMATION TO THE PUBLIC, VIOLATING THE REQUIREMENT THAT THE FSEIS CONTAIN ACCURATE SCIENTIFIC INFORMATION AND DISREGARDING THE INFORMATIONAL PURPOSE OF NEPA It is important for an EIS to contain accurate information or else it fails in its purpose of informing federal decision-makers and citizens of the environmental consequences of government actions. NEPAs implementing regulations, and federal and NRC case law have emphasized the NEPA requirement that agencies rely on high quality data in EISs. See Native Ecosystems, 418 F.3d at 964-65; 40 C.F.R. § 1500.1(b); and July 14, 2011 Board Order at 12-
- 13. The purpose of this requirement is not to create more paperwork for NRC but instead, to promote sound environmental decision-making by the agency. 40 C.F.R. § 1500.1(c).
By accepting Entergys population estimate, despite being alerted to its flaws, NRC Staff presented an inaccurate report of the environmental consequences of relicensing the Indian Point facility. Underestimating the at risk population by over a million persons is a significant 21
State of New York Statement of Position Contention NYS-16/16A/16B oversight, not a mere calculation error. If NEPA is to serve its purpose of promoting sound environmental decisions, NRC Staff must be discriminating in the data on which they rely.
POINT IV BY ACCEPTING ENTERGYS FLAWED SAMA ANALYSIS, NRC STAFF HAS FAILED TO TAKE THE REQUISITE HARD LOOK UNDER NEPA AND VIOLATED NRCS OWN REGULATIONS REGARDING SAMA ANALYSES The requirement that alternatives be studied, developed, and described under NEPA both guides the substance of environmental decision-making and provides evidence that the mandated decision-making process has actually taken place. Calvert Cliffs Coordinating Committee, Inc.
- v. United States Atomic Energy Commn, 449 F.2d 1109, 1114 (D.C. Cir. 1971). NRC regulations require a complete analysis of the cost of potentially cost-effective mitigation alternatives, i.e., SAMAs, in the FSEIS. Yet the FSEIS, by uncritically accepting Entergys population estimates, leaves the NEPA process incomplete and deprives NRC Staff of the ability to take a hard look at the consequences of severe accidents and to accurately evaluate whether SAMAs are cost-beneficial. See Methow, 490 U.S. at 350 (The sweeping policy goals announced in § 101 of NEPA are thus realized through a set of action-forcing procedures that require that agencies take a hard look at environmental consequences, and that provide for broad dissemination of relevant environmental information. (internal citations omitted)) and Limerick Ecology, 869 F.2d at 737 (First, to qualify, the [Final Environmental Impact Statement] must contain sufficient discussion of the relevant issues and opposing viewpoints to enable the decisionmaker to take a hard look at the environmental factors and to make a reasoned decision.).
22
State of New York Statement of Position Contention NYS-16/16A/16B As the preceding authorities amply demonstrate, there is clear legal support from NRC regulations and NRC and federal case law for the proposition that a legally sufficient SAMA analysis in the FSEIS must be based on high quality information or the NRC will be deprived of the of the ability to take a hard look at environmental impacts in evaluating SAMAs. See Methow, 490 U.S. at 350, and July 14, 2011 Board Decision at 17 ([T]he FSEIS must demonstrate that the NRC Staff has received sufficient information to take a hard look at SAMAs as required by 10 C.F.R. § 51.53(c)(3)(ii)(L) . . .).
NRC has not met this burden with respect to its review of Entergys SAMA analysis because it relies on clearly deficient population estimates.
CONCLUSION For the above reasons Entergys application to renew the operating licenses for Indian Point Unit 2 and Unit 3 should be denied.
Respectfully submitted, Signed (electronically) by Kathryn M. Liberatore John J. Sipos Adam Dobson Assistant Attorney General Assistant Attorneys General Office of the Attorney General for the State of New York Laura E. Heslin The Capitol J.D. (NY Admission Pending) Albany, New York 12227 (518) 402-2251 Dated: December 16, 2011 23