U.S. Nuclear Regulatory Commission Site-Specific RO Written Examination Applicant Information Name:

Date: Facility/Unit: MCGUIRE Region: jj III IV Reactor Type: CE BW GE Start Time: Finish Tim:

Instructions Use the answer sheets provided to document your answers. Staple this cover sheet on top of the answer sheets. To pass the examination, you must achieve a final grade of at least 80.00 percent. Examination papers will be collected 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> after the examination begins.

Applicant Certification All work done on this examination is my own. I have neither given nor received aid.

Applicants Signature Results Examination Value Points Applicants Score Points Applicants Grade Percent

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination I

(1 point)

With Unit 1 operating at 50% RTP, a Reactor Trip signal will be generated on a Turbine trip provided 2/3 Auto Stop Oil pressures lower below the setpoint, which is (1) PSIG,OR 4/4 (2) are closed.

Which ONE (1) of the following completes the statement above?

A. 1.45

2. Throttle valves B. 1.75
2. Throttle valves C. 1.45
2. Governor valves D. 1.75
2. Governor valves Page 1 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examinalion 2

(1 point)

Given the following conditions on Unit 1:

  • The unit is at 100% RTP
  • An inadvertent Phase A Containment Isolation occurs Based on the conditions above:

NC Pump Seal Water NC Pump RN Return Flow is Flow is A. isolated isolated B. isolated NOT isolated C. NOT isolated isolated D. NOT isolated NOT isolated Page 2 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 3

(1 point)

Unit 2 is operating at 100% RTP.

The NC System boron concentration will DECREASE if Letdown temper ature is (1) by 10°F.

If LD Hx outlet temperature reaches (2) 2NV-127A (LD Hx Outlet 3-Way Temp Cntrl) will AUTO divert letdown flow to the VCT.

Which ONE (1) of the following completes the statement above?

A. 1. LOWERED

2. 120°F B. 1. LOWERED
2. 138°F C. 1. RAISED
2. 120°F D. 1. RAISED
2. 138°F Page 3 of 75

McGuire Nuclear Station Question: 4 2012 MNS RO NRC Examination (1 point)

Unit I was operating at 100% RTP when a LOCA occurred. Given the follow ing events and conditions:

  • The crew attempted to align IA Train of the ND system to supply Contai nment Spray
  • 1NS-43A (IA ND Hx Outlet to NS Cont Outside Isol) failed to open Which ONE (1) of the following statements describes the interlock that preven ted I NS-43A from opening?

A. I NI-I 73A (IA ND to A & B Cold Legs Cont Outside Isol) was not closed B. I ND-58A (Train A ND to NV & NI Pumps) was not closed.

C. I NI-I 85A (RB Sump to Train A ND & NS) was not open.

D. CPCS signal was not present.

Page 4 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 5

(1 point)

Given the following conditions on Unit 2:

  • A small break LOCA has occurred
  • Bus 2EMXB-4 is locked out on protective relay actuation
  • The crew is performing ES-I .2 (Post LOCA Coo down and Depressurizat ion)

In accordance with ES-I.2, during the NC system cooldown and depressurizat ion, the Operators will isolate Cold Leg Accumulators (CLAs) (I) and depressurize CLAs (2)

Which ONE (I) of the following completes the statement above?

A. I.AandC

2. BandD B. I. AandB
2. CandD C. I. BandD
2. AandC D. I. CandD
2. AandB PageS of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 6

(1 point)

Given the following conditions on Unft 1:

. UnitisinMode5

. Preparations for refueling are in progress

. The crew is preparing to perform a Nitrogen purge of the VCT for an NC system Degas

. There is a bubble in the Pressurizer In accordance with OPIIIAJ6I 00/SD-I 0 (NC System, PRT and NCDT Degas)

Nitrogen is aligned to the VCT from (I )

The purpose for performing the Nitrogen purge is to (2)

Which ONE (I) ofthe following completes the statements above?

A. I. Bulk Nitrogen

2. Remove air and non- condensable gases from the NC System in preparation for taking the plant solid.

B. I. Bulk Nitrogen

2. Remove Dissolved Hydrogen from the NC System to prevent format ion of an explosive Hydrogen / Oxygen mixture.

C. I. Shutdown Waste Gas Decay Tank B

2. Remove air and non- condensable gases from the NC System in preparation for taking the plant solid.

D. I. Shutdown Waste Gas Decay Tank B

2. Remove Dissolved Hydrogen from the NC System to prevent formation of an explosive Hydrogen / Oxygen mixture.

Page 6 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 7

(1 point)

Given the following conditions on Unit I:

. The unit is at 100% RTP

. B Train components are in service

. The crew implements AP-21 (Loss of KC or KC System Leakage) due to a loss ofthelBl KCpump At 0800 the following temperatures are observed on all NC pumps:

Parameter Temperature Increase Lower Motor Bearings 177°F +1 .5°F/mm Upper Motor Bearings 182°F +1 .0°F/mm Pump Lower Radial Bearings 180°F +1.OF/min Based on the conditions above, and considering that the trend does not change:

The NC pumps (1) Motor bearings will be the FIRST motor bearings to reach an operating limit.

The NC Pumps Lower Radial Bearing temperatures with reach their operati ng limit at (2)

Which ONE (1) of the following completes the statements above?

A. 1. Lower

2. 0820 B. 1. Upper
2. 0820 C. 1. Lower
2. 0845 D. 1. Upper
2. 0845 Page 7 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 8

(1 point)

Given the following conditions on Unit 2:

. The unit is initially operating at I 00% RTP

. A Train components are in service

. The 2B sequencer is in TEST

  • An SI signal is received on BOTH Unit 2 ESF Trains
1) After load sequencing is complete (with no operator actions), which KC pumps are running?
2) Each train of KC pumps has a recirc valve which discharges to Which ONE (1) of the following completes the statements above?

A. 1. 2A1 and 2A2 KC pumps ONLY

2. the KC Surge tank B. 1. 2A1 and 2A2 KC pumps ONLY
2. its respective trains suction line C. 1. 2A1, 2A2, 2B1 and 2B2 KC pumps
2. the KC Surge tank D. 1. 2A1, 2A2, 2B1 and 2B2 KC pumps
2. its respective trains suction line Page 8 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 9

(1 point)

Regarding the design of the Pressurizer:

I ) Why are the Pressurizer Spray lines connected to the NC System cold legs?

2) Why is a constantflow maintained through the PZR spray lines?

A. I To provide a differential pressure between the surge line and the spray lines.

2. Prevents large differential temperature buildup across the spray nozzles.

B. I To provide a differential pressure between the surge line and the spray lines.

2. Reduce the number of valve cycles (open/closed) and resulting fatigue stress concerns on the valve internals.

C. 1. Turbulent flow at the NCP discharge provides better mixing of NC system for a more uniform boron concentration and pH control.

2. Prevents large differential temperature buildup across the spray nozzles.

D. 1. Turbulent flow at the NCP discharge provides better mixing of NC system for a more uniform boron concentration and pH control.

2. Reduce the number of valve cycles (open/closed) and resulting fatigue stress concerns on the valve internals.

Page 9 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 10 (1 point)

Unit I is operating at 30% RTP. Given the following events and conditions:

. Main Turbine MW Loop is in service

  • IC NC pump trips
  • No operator action has been taken After 15 minutes, with unit load unchanged, total steam flow from all Steam Generators (S/G) will be approximately (I) as compared to total steam flow from all S/Gs prior to the NC pump trip AND Pressure in S/Gs IA, lB and ID will be approximately (2) as compared to the pressure in those S/Gs prior to the NC pump trip.

Which ONE (1) of the following completes the statements above?

A. 1. lower

2. lower B. 1. the same
2. lower C. I. lower
2. the same D. 1. the same
2. the same Page 10 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 11 (1 point)

Given the following conditions on Unit 1:

  • Unit is operating at 70% RTP
  • The OATC determines that AUTO rod withdrawal is not functioning
  • Further investigation reveals that manual rod withdrawal is functioning normally
  • Control Bank D rods are currently at 190 steps Which ONE (1) of the following failures has caused this condition?

A. Turbine Impulse Pressure Channel II fails low.

B. Turbine Impulse Pressure Channel I fails low.

C. Loop 2 LXTChannelfails high.

D. PR Channel N-41 fails high.

Page 11 of75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 12 (1 point)

Given the following conditions on Unit 1:

  • A Reactor Trip and Safety Injection have occurred due to a LOCA inside Containment Based on the following FWST level trend:

TIME 1500 1515 1530 1545 r FWST LEVEL c1 &

FWST LEVEL

(-f 1 r FWST LEVEL OH 1 Which ONE (1) of the following is the EARLIEST time a signal would be generated to automatically swap the ND pump suction to the Containment Sump?

A. 1500 B. 1515 C. 1530 D. 1545 Page 12 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 13 (1 point)

Given the following conditions on Unit 1:

  • The unit is operating at 100% RTP
  • Containment pressure Channel II fails HIGH
  • The Channel II Containment Pressure High B/S has been TRIPPED
  • The Channel II Containment Pressure High High B/S has been BYPASSED Which ONE (1) of the following identifies the correct ESF actuation logic for the REMAINING Containment Pressure channels?

A. Safety Injection 1/2; Phase B 1/3 B. Safety Injection 1/2; Phase B-2/3 C. Safety Injection 1/3; Phase B 1/3 D. Safety Injection 1/3; Phase B-213 Page 13 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 14 (1 point)

Given the following initial conditions on Unit 1:

. The unitwas operating at 100% RTP

. A leak on the RV system occurs inside Containment

. The crew isolates RV to Containment to stop the leak Subsequently, the following occurs:

. A steam break occurs on the I A S/G

  • Containment pressure peaked at 3.2 PSIG and is currently 1.5 PSIG
  • The IA S/G has been isolated in accordance with E-2 (Faulted SIG Isolation)
  • The crew has transitioned to ES-I .I(SI Terminaton) and is currently evaluating SI termination criteria The crew (I) have to use adverse Containment value for Subcooling.

The crew (2) have to use adverse Containment value for PZR level.

Which ONE (1) of the following completes the statements above?

A. 1. WILL

2. WILL B. 1. WILL NOT
2. WILL C. 1. WILL
2. WILL NOT D. 1. WILL NOT
2. WILL NOT Page 14 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 15 (1 point)

Given the following conditions on Unit 1:

. NCS temperature is 205°F

. A plant heatup to normal operating temperature is in progress

. Annunciator IAD-9, A/S (ICE COND LOWER INLET DOORS OPEN) is lit

. A NEO reports that ONE ofthe Ice Condenser Lower Inlet doors is partially 0 pen

. An HVAC maintenance technician is dispatched to inspect the door and has determined that the door will open but cannot be closed

. The Ice Condenser Chart Recorder (INPRC-5000) indicates temperature for the affected ice bed is 19°F and slowly increasing

. No other annunciator alarms are present Based on the given conditions:

1) Based on the conditions above, Technical Specification (TS) LCO 3.6.12 (Ice Bed) LCO actions required to be taken.
2) The primary concern with the increasing ice bed temperature is Which ONE (1) of the following completes the statements above?

A. 1. are

2. increased ice bed sublimation B. 1. are NOT
2. increased ice bed sublimation C. 1. are
2. blockage of air flow due to volumetric expansion of the ice beds D. 1. are NOT
2. blockage of air flow due to volumetric expansion of the ice beds Page 15 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 16 (1 point)

Given the following conditions on Unit I:

  • The unit was initially operating at 100% RTP
  • A LOCA occurs inside Containment
1) To MANUALLY start the Containment Air Return Fans (CARFs) a CPCS signal required.
2) In addition to other signals, an AUTOMATIC start of the CARFs requires a/an Which ONE (1) of the following completes the statements above?

A. 1. is

2. S signal (no associated time delay required)

B. 1. is not

2. time delay after S signal generated C. 1. is
2. time delay after S signal generated D. 1. is not
2. S signal (no associated time delay required)

Page 16 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 17 (1 point)

Given the following conditions on Unit I:

  • A LOCA has occurred inside Containment
  • ES-I .3 (Transfer to Cold Leg Recirc) has been implemented
  • Containment pressure is 3.2 PSIG As a MINIMUM, to MANUALLY START the A Train NS Pump:

I) CPCS Train A pressure must be greater than the setpoint value of (I)

AND

2) (2) A Train NS Pump Discharge valve(s) must be OPEN.

Which ONE of the following completes the statements above?

A. I. 0.80 PSIG

2. ONE B. 1. 0.35 PSIG
2. ONE C. 1. 0.80 PSIG
2. BOTH D. 1. 0.35 PSIG
2. BOTH Page 17 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 18 (1 point)

Unit I is in Mode 3 conducting a plant cooldown and depressurization in accordance with OPIIIAI6I OOISD-2 (Cooldown to 400°F).

The following conditions exist:

. NC System pressure 1900 PSIG

. NCSystemtemperature 557°F

  • Low Pressure SI and Low Pressure Steamline Isolation have been blocked
  • The operator has just begun an 80°F/hour cooldown.

Which ONE (1) of the following conditions would automatically close all four Main Steam Isolation Valves?

A. NC Pressure increases to 2000 PSIG.

B. Containment Pressure increases to 1.3 PSIG.

C. IA Steam Generator Pressure drops to 900 PSIG in 2 seconds.

D. I B Steam Generator Pressure drops to 700 PSIG over the next 30 minutes.

Page 18 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 19 (1 point)

The following conditions exist on Unit 1:

  • The plant is at 20% RTP
  • Power increase in progress The CF Control Bypass valves receive a full close demand signal from DCS when steam flow increases to a MINIMUM of (1)

The CF Control Bypass valves receive a full open demand signal from DCS when steam flow increases to a MINIMUM of (2)

Which ONE (1) of the following completes the statement above?

A. 1. 25%

2. 75%

B. 1. 25%

2. 85%

C. 1. 30%

2.75%

D. 1. 30%

2. 85%

Page 19 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 20 (1 point)

Given the following on Unit 2:

  • The TD CA pump tripped on overspeed upon starting
  • Bus 2ETB locked out due to a ground fault on the bus If no operator action has adjusted CA flow rates, which ONE (1) of the following describes which S/Gs are currently being fed and the associated flow rates?

A. C and D S/Gs at 450 GPM to each SIG B. C and D S/Gs at 450 GPM total flow C. A and B S/Gs at 450 GPM to each SIG D. A and B S/Gs at 450 GPM total flow Page 20 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 21 (1 point)

Given the following conditions on Unit 1:

. The unit is atlOO% RTP

. B train equipment is in service

. 1 ETA Normal incoming breaker trips OPEN

  • IA DIG starts and comes up to speed and voltage, but its output breaker does NOT close
  • An NEO reports that an 86N Relay is J on Bus IETA lAW AP-07 (Loss of Electrical Power) Case II, Thermal Barrier Isolation Valves on (1) must be Ensured OPEN.

Based on the conditions above, if the BOP operator attempts to manually close the IA DIG Output Breaker, the breaker (2) close.

Which ONE (1) of the following completes the statements above?

A. 1. Train B ONLY

2. WILL B. 1. Train BONLY
2. WILL NOT C. 1. TrainAandTrainB
2. WILL D. I. TrainAandTrainB
2. WILL NOT Page 21 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 22 (1 point)

Given the following initial conditions on Unit 1:

  • The unit is at 100% RTP
  • All NCPs are powered from their normal sources.
  • Each 6.9 KV bus Mode Select switch is in Auto.

Subsequently the following occurs:

  • A Generator Switchyard protective lockout occurs on I B Bus Line Based on the given conditions:
1) NCPIB
2) Bus ITB automatically to its alternate power supply.

Which ONE (1) of the following completes the statements above?

A. 1. trips

2. fast B. 1. trips
2. slow C. 1. continues to run
2. fast D. 1. continues to run
2. slow Page 22 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 23 (1 point)

Given the following plant conditions:

  • Both Units are operating at 100% RTP
  • Battery IDP is aligned for equalizing charge
  • The DC Output breaker for Charger I DS has tripped open Based on the conditions above, with no operator action, Bus I DP is Which ONE (I) of the following completes the statement above?

A. energized from Charger IDP and Battery IDP B. energized from Chargers IDP and 2DP C. energized from Charger IDP ONLY D. de-energized Page 23 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 24 (1 point)

Given the following conditions on Unit I:

  • The IA DIG has been placed in operation to facilitate a power swap on IETA from IATC to SATA
  • Indicated load is 400 KW and 75 KVARS
  • IA DG is currently powering I ETA with the I ETA Normal Breaker and I ETA Stdby Breaker OPEN When the IA D/G Gov Cntrl Raise pushbutton is depressed, frequency will (1)

When the IA D/G Volt Adjust is rotated to Raise, indicated KVARs will (2)

Which ONE (1) of the following completes the statements above?

A. 1. Increase

2. Remain the same B. I. Remain the same
2. Remain the same C. I. Increase
2. Increase D. I. Remain the same
2. Increase Page 24 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 25 (1 point)

While performing daily surveillance checks on I EMF-33 (CondenserAir Ejector Exhaust), it is determined that the OPERATE light is OFF.

Which ONE (I) of the following actions is required in accordance with PT/I /A/46001003 B (Daily Surveillance Items)?

A. Perform a source check of I EMF-33.

B. Verify operability of I EMF-36L (Unit Vent Gas Monitor) by checking OPERATE light lit and LOSS OF SAMPLE FLOW annunciator NOT in alarm.

C. Depress CLR (Clear) on the I EMF-33 touch controls.

D. Place the sample Pump in OFF, and then depress the RUN pushbutton for a MINIMUM of 5 seconds.

Page 25 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 26 (1 point)

Given the following conditions:

  • Unit 2 is at 100% RTP
  • A Loss of Offsite Power occurs on both Units I and 2 Based on the given conditions, if no operator actions occur, which ONE (1) of the following provides the assured source of cooling water to the Unit 2 Containment AHUs?

A. BOTH 2A AND 2B RN pumps B. RV pump selected in Auto C. 2A RN pump ONLY D. 2B RN pump ONLY Page 26 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 27 (1 point)

Given the following plant conditions:

  • Both units are operating at 100% RTP
  • An instrument air system leak develops in the Unit I Turbine Building
  • The Diesel VI Compressors (G & H) AUTO/OFF-RESET selector switches are in AUTO.

The following indications are observed in the Control Room:

rvrTi 100- -100

-50 Based on the indications above, the Diesel VI Compressors (G & H) are (1)

AND IVI-1 812 (VI Air Dryer Bypass Filter Isol) is (2)

Which ONE (1) of the following completes the statement above?

A. 1. NOTrunning

2. closed B. 1. running
2. closed C. 1. NOTrunning
2. open D. 1. running
2. open Page 27 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 28 (1 point)

Given the following conditions:

  • Fuel reload is in progress on Unit I
  • IEMF-16 (Containment Refueling Bridge) display goes dark due to a loss of Bus KRA Which ONE (1) of the following describes the procedure required to be implemented AND the effect of IEMF-16 on the Containment Evacuation alarm?

Procedure Containment Evacuation Alarm A. AP-07 (Loss of Electrical Power) Defeated B. AP-07 (Loss of Electrical Power) Actuated C. AP-1 5 (Loss of Vital or Aux Control Power) Defeated D. AR-I 5 (Loss of Vital or Aux Control Power) Actuated Page 28 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 29 (1 point)

A reactor start-up is in progress on Unit 2

. Reactor power is 2%

. The OATC is withdrawing control rods

. Another RO is monitoring/controlling SG level, steam dumps, and feedwater flow Based on the conditions above:

I . To control NCS temperature, OP/2/A/61 00/003 (Controlling Procedure for Unit Operation) Enclosure 4.1 (Power Increase) directs the operators to maintain within the desired range by adjusting steam dump control.

2. If the steam dump controller setpoint is not changed, with each rod pull SG pressure increases Which ONE (1) of the following completes the statements above?

A. 1. Tcold

2. initially, then returns to approximately the original value before the rod pull B. 1. Tave
2. initially, then returns to approximately the original value before the rod pull C. 1. Tcold
2. and stabilizes at a higher steam pressure than before the rod pull D. 1. Tave
2. and stabilizes at a higher steam pressure than before the rod pull Page 29 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 30 (1 point)

Given the foflowing conditbns on Unit 2:

. The unit is currently at 100% RTP, with pressurizer pressure control and level control in auto.

  • NC system pressure is decreasing slowly due to a leaking Pressurizer Code Safety valve (2NC-2)
  • At 1500, PRT pressure is INITIALLY at 3 PSIG and increasing at I PSIG I mm Over the next 30 minutes, if the reactor does NOT trip, the temperature indication on 2NCP-5960 (PZR Relief Valve Temperature 2NC-2) will (1) AND the rate of NC system depressurization will (2)

Which ONE (1) of the following completes the statement above?

A. 1. increase

2. decrease B. 1. remain the same
2. remain the same C. 1. increase
2. remain the same D. 1. remain the same
2. decrease Page 30 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 31 (1 point)

Given the following conditions:

. Unit I is responding to a LOCA

. All sources of feedwater have been lost, S/G NR levels are I 7% and decreasing

. NC pumps are secured

. FR-C.1 (Response to Inadequate Core Cooling) has been implemented

. NI and NV pumps are unavailable

. Peak Containment pressure reached 2.5 PSIG

. S/G depressurization has failed to restore adequate core cooling

. Core Exit Thermocouples are currently indicating 12 10°F

. NC pump support requirements can NOT be met

. The ICCM Subcooling Margin Monitors (5MM) indicate:

0 Train A (-)25°F 0 Train B (-)35°F The reason for the difference in subcooling indication is that Train A Wide Range Loop pressureinputhasfailed (1)

Based on the conditions above, the NEXT major action required by FR-C.1 is to (2)

Which ONE (1) of the following completes the statements above?

A. 1. LOW

2. restart NC pumps one ata time until CETs are less than 1200°F B. 1. HIGH
2. restart NC pumps one ata time until CETs are less than 1200°F C. 1. LOW
2. open all PZR PORVs and head vents to depressurize the NC system D. 1. HIGH
2. open all PZR PORVs and head vents to depressurize the NC system Page 31 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 32 (1 point)

Given the following conditions on Unit 1:

  • A LOCA has occurred inside Containment
  • During the recovery Containment is vented to the annulus and an Annulus Ventilation (VE) fan is to be started for Iodine removal
  • When the BOP attempts to start the IA VE Fan, it will not start To which ONE (1) of the following locations should a NEO be dispatched to inspec t

the feeder breaker for the IA VE Fan?

A. IMXJ B. IMXK C. IEMXC D. IEMXD Page 32 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 33 (1 point)

Given the following conditions on Unit 2:

. A LOCA has occurred inside Containment

. Containment pressure peaked at 3.2 PSIG

. Containment pressure is currently 2.8 PSIG and LOWERING slowly

  • Ann ulus pressure is -4.0 WG and LOWERING (more negative)

Based on the given conditions above:

1) What is the current discharge flowpath of the VE (Annulus Ventilation) fans?
2) If annulus pressure continues to lower with no operator actions, at what pressure setpoint will a signal be generated to change the discharge flowpath of the VEfans?

Which ONE (1) of the following answers the questions above?

A. 1. UnitVent

2. -4.2WG B. 1. Annulus
2. -7.0WG C. 1. UnitVent
2. -7.0WG D. 1. Annulus
2. -4.2WG Page 33 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 34 (1 point)

Given the following conditions on Unit 2:

. The core has been off-loaded to the Spent Fuel Pool

. 2A KF Pump is running

. 2BKFPumpisoff

. A Loss of Off-Site Power occurs

  • 2A and 2B D/Gs start and load normally
  • 30 minutes after the loss of power, a Spent Fuel Pool Hi Temperature alarm is received Which ONE (1) of the following is the cause of this condition?

A. The 2A or 2B KF pump was not manually started (Sequencer reset required).

B. The 2A or 2B KF pump was not manually started (Sequencer reset NOT required).

C. The 2A KF pump ONLY did not automatically load on the Blackout sequence as designed.

D. The 2A and 2B KF pumps did not automatically load during the Blackout sequence as designed.

Page 34 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 35 (1 point)

Given the foIIowng conditions on Unit 2:

. The unit is currently in MODE 5

. Spent Fuel Pool fuel handling operations were secured 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> ago

. VF system is operating normally in accordance with 0P12/A/64501004 (Fuel Pool Ventilation System)

Subsequently:

  • 2EMF-42 (Fuel Building Ventilation Radiation Monitor) is in Trip 2 Based on the given conditions, which ONE (1) of the following describes the AUTOMATIC response of the Fuel Handling Building Ventilation system (VF) to the 2EMF-42 condition?

A. The Outside Air damper (D-1) will close.

B. The Exhaust Filter Bypass damper (D-5) will close.

C. The Supply fan AND Exhaust fans will stop.

D. The Supply fan will stop. The Exhaust fans will NOT stop.

Page 35 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 36 (1 point)

Given the following indications/conditions on Unit 1:

1

. The unit is operating at 100% RTP

. A loss of lEKVAoccurs

. NO Operator actions have been taken Based on the conditions above, what is the MINIMUM number of ADDITIONAL channels on S/G IA that must trip to cause a/an:

1) Feedwater Isolation Actuation?
2) Auxiliary Feedwater Actuation?

Feedwater Isolation Aux Feedwater Actuation A. 2 2 B. 2 I C. 1 2 D. I I Page 36 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 37 (1 point)

Given the following conditions on Unit 1:

. Unit shutdown in progress

. Power = 80% RTP and DECREASING

. lASGTube Leak=2OGPM

. Due to high activity, the Turbine Building Sump (TBS) is being pumped to the RC Discharge Based on the given plant conditions:

I. Which ONE (1)of the following would present a more significant radiation hazard to a member of the public at the site boundary due to the release?

2. What EMF Trip 2 automatic action(s) would ensure the release of radioactive material is ALARA?

A. I. Beta radiation from the decay of Tritium

2. TBS pump trips B. I. Beta radiation from the decay of Tritium
2. IWP-35 (WMT & VU CDT to RC Cntri) closes C. I. Gamma radiation from the decay of Nitrogen-I 6
2. TBS pump trips D. I. Gamma radiation from the decay of Nitrogen-I6
2. IWP-35 (WMT & VUCDT to RC Cntrl) closes Page 37 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 38 (1 point)

Given the following:

. The Instrument Air (VI) system is in a normal alignment and cross-connected to the Station Air (VS) system

. A leak occurs on the Instrument Air (VI) header

  • The VI header begins to slowly depressurize
  • The crew has implemented AP-22 (Loss of VI)

As the VI header depressurizes, the VI header will be isolated from the VS header by (1)

The VS air compressor (2) to maintain VS header pressure.

Which ONE (1) of the following completes the statements above?

A. a manual isolation valve will start automatically B. a manual isolation valve must be manually started C. an automatic isolation valve will start automatically D. an automatic isolation valve must be manually started Page 38 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 39 (1 point)

A Reactor trip has occurred on Unit I In accordance with the Immed ate Actions of E-O (Reactor Trip or Safety Injection):

One indication listed in the procedure that is used to verify that the reactor is tripped is (1)

If the turbine does not trip automatically and will not trip manually, the procedure willNEXTdirecttheoperatorto (2)

Which ONE (1) of the following completes the statements above?

A. 1. IR SUR ZERO OR NEGATIVE

2. close the MSIVs AND MSIV bypasses B. 1. IRAMPS-GOING DOWN
2. close the MSIVs AND MSIV bypasses C. 1. IRSUR-ZEROOR NEGATIVE
2. place the turbine in MANUAL AND close the governor valves in fast action D. 1. lR AMPS GOING DOWN
2. place the turbine in MANUAL AND close the governor valves in fast action Page 39 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 40 (1 point)

Given the following conditions on Unit 2:

  • The unit is operating at 100% RTP
  • One PZR PORV is leaking past its seat
  • Pressurizer pressure is 2235 PSIG
  • Pressurizer Steam Space temperature is 653° F
  • PRT pressure is 15 PSIG Which ONE (1) of the following is the approximate expected temperature downstream of the leaking PZR PORV?

REFERENCE PROVIDED A 220°F B. 240°F C. 250°F D. 300°F Page 40 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 41 (1 point)

Given the following conditions on Unit I:

. The operating crew initiated a manual SI due to a small break LOCA.

  • Equipment failures resulted in a RED condition on the Integrity CSF Status Tree.
  • NC Cooldown rate was approximately 220°F per hour
  • NC System temperature is currently 240°F
  • The crew is performing a soak in accordance with FR-P.1 (Response to Imminent Pressurized Thermal Shock Condition).

Based on the conditions given, which ONE (1) of the following actions is permitted by FR-P.1 during the soak?

A. Energize PZR heaters B. Start an additional NV Pump C. Place Auxiliary Spray in service D. Initiate a cooldown at less than 50°F per hour Page 41 of 75

McGu ire Nuclear Station Question:

2012 MNS RO NRC Examination 42 (1 point)

Unit I was operating at 100% RTP when a Large-Break LOCA occurred.

1) What is the MINIMUM time following the LOCA that E-1 (Loss of Reactor or Secondary Coolant) directs an initiation of hot leg recirculation?
2) Which ECCS pumps are CAPABLE of being aligned to inject into the hot legs per ES-I .4 (Transfer to Hot Leg Recirculation)?

A. 1. 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />

2. NI ONLY B. 1. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />
2. NDandNI C. 1. 4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br />
2. NDandNI D. 1. 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br />
2. NI ONLY Page 42 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 43 (1 point)

Given the following conditions on Unit 2:

  • A load rejection from 100% RTP has occurred due to the trip of 2A CF pump
  • Pressurizer level is greater than setpoint
  • 2NV-238 (Charging Line Flow Control) is in AUTOMATIC and CLOSING
  • Annunciator 2AD-7, JIl (NC PUMP SEAL INJ LO FLOW) is LIT The setpoint forAnnunciator2AD-7, JI1 is (1) GPM.

To clearthe Annunciator, the BOP must throttle 2NV-241 (Seal Injection Flow Control) in the (2) direction.

Which ONE of the following completes the statements above?

A. 1.6

2. OPEN B. 1.6
2. CLOSED C. 1.7
2. OPEN D. 1.7
2. CLOSED Page 43 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 44 (1 point)

Unit I was operating at 100%. Given the following events and conditions:

. 02 1 0 reactor tripped d ue to a LOCA

. 0300 crew enters ECA-1.2, (LOCA Outside Containment)

. 0320 crew enters ECA-1.1, (Loss of Emergency Coolant Recirc)

. 0330 The crew is at step 18.b of ECA-1 .1

. Current conditions:

0 IA NI pump is running, indicating 185 GPM 0 lB NI pump is running, indicating 165 GPM o Both NV pumps are running, indicating 340 GPM (Consider that the NV pumps have equal capacity) o Subcooling is +35°F Based on the conditions above, at time 0330:

I) Which ONE (I) of the following describes the actions that will meet requirements of ECA-I.I?

AND

2) Flow from the remaining ECCS pumps will be greater than the MINIMUM required flow rate of_______

REFERENCE PROVIDED A. I. StopbothNVpumps.

2. 345GPM B. I. Stop the I B NI pump AND one NV pump.
2. 345GPM C. I. Stop the IA NI pump AND one NV pump.
2. 330 GPM D. I. Stop both NI pumps.
2. 330 GPM Page 44 of 75

McGuire Nuclear Station Question:

2012 MNS RO NRC Examination 45 (1 point)

Given the following conditions on Unit 1:

. The unit is in HOT SHUTDOWN on ND Cooling (Both Train A and B)

. B Train KC is aligned to supply Reactor and Aux Bldg Non-Essential Headers with both IBI and 1B2 pumps in operation

  • A Train KC is aligned to supply the A ND HX Header with both IAI and 1A2 pumps in operation
  • The IAI KC pump has just tripped In accordance with the Limits and Precautions of 0 PIIIA/640 0/005 (Component Cooling Water System), KC flow through the IA ND Heat Exchanger shall be throttle d

to less than a MAXIMUM of Which ONE (1) of the following completes the statement above?

A. 2000 GPM B. 4000 GPM C. 5000 GPM D. 6000 GPM Page 45 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 46 (1 point)

Given the following conditions on Unit 2:

. A failure ofthe Pressurizer Pressure Master Controller occurs

. All Pressurizer heaters energize due to the failure

  • NC system pressure is currently 2310 PSIG
  • All Pressurizer Pressure control components are in AUTO Based on the given conditions, if NO operator actions are taken, which ONE (1) of the following is the effect on the PZR Surge Line temperature AND the position of the Pressurizer Spray valves, as compared to the conditions before the Pressurizer Pressure Master Controller failure?

PZR Surge Line Temperature PZR Spray Valve Position A. INCREASED CLOSED B. DECREASED CLOSED C. INCREASED OPEN D. DECREASED OPEN Page 46 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 47 (1 point)

Given the following conditions on Unit 1:

. An ATWS has occurred

. FR-S.1 (Response to Nuclear Power Generation /ATWS) has been implemented

1) When the turbine is tripped, the amount of negative reactivity added will be greater ifthe unit is at
2) The basis for immediately tripping the turbine during an ATWS event is to Which ONE (1) of the following completes the statements above?

A. 1. EOLascomparedtoBOL

2. generate a redundant reactor trip signal B. 1. BOLascomparedtoEOL
2. generate a redundant reactor trip signal C. 1. EOLascomparedtoBOL
2. maintain SIG inventory if the initiating event is a simultaneous loss of all fee dwate r D. 1. BOLascomparedtoEOL
2. maintain SIG inventory if the initiating event is a simultaneous loss of all fee dwate r Page 47 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 48 (1 point)

Given the foIIowng initial conditions on Unit 2:

. A SGTR has occurred on the 2D SG

. A Steam Line break occurred on the 2B SG

  • Containment pressure peaked at 3.1 PSIG Current conditions:
  • Containment pressure is 0.9 PSIG and STABLE Based on the current conditions, E3 (Steam Generator Tube Rupture) requires that 2D SG NR level be maintained greater than a MINIMUM of (1)

AND E-3 will require the crew to FIRST attempt to depressunze the NC system using (2)

Which ONE (1) of the following completes the statements above?

A. 1. 11%

2. one PZR PORV B. 1. 32%
2. one PZR PORV C. 1. 11%
2. Auxiliary Spray D. 1. 32%
2. Auxiliary Spray Page 48 of 75

McGu ire Nuclear Station 2012 MNS RO NRC Examination Question: 49 (1 point)

Given the following conditions on Unit 1:

  • The unit was initially at 100% RTP
  • A steam line break occurs inside Containment
  • Containment pressure is currently 3.5 PSIG Based on the conditions above, with no operator action:

Both CF Pumpsare (1)

AND The CF to CA Nozzle Valves are (2)

Which ONE (1) of the following completes the statements above?

A. 1. tripped

2. CLOSED B. 1. tripped
2. OPEN C. 1. running at 2800 RPM
2. CLOSED D. 1. runningat2800 RPM
2. OPEN Page 49 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 50 (1 point)

Given the following conditions on Unit 1:

UnitisatlOO%RTP Regarding the operation of the CA system:

1) ONLY the Motor-Driven CA pump(s) will start if a occurs.
2) The CA system is capable of supplying sufficient flow to maintain S/G inventory provided reactor power is less than a MAXIMUM of Which ONE (1) of the following completes the statements above?

A. 1. Blackout signal on I ETA and/or I ETB

2. 3%

B. I. Tripofboth CF pumps

2. 3%

C. I. Blackout signal on I ETA and/or I ETB

2. 5%

D. I. Tripofboth CF pumps

2. 5%

Page 50 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 51 (1 point)

Given the following conditions:

. A Loss ofAll AC power has occurred on Unit I

. Crew has implemented ECA-O.O (Loss ofAll AC Power)

. The Unit I Standby Make Up pump has failed

. Subcooling Margin Monitor indicates subcooling is 5°F In accordance with ECA-O.O:

I) What is the reason for depressurizing the S/Gs to 290 PSIG?

2) What is the reason for NOT allowing S/Gs to depressurize to lessthan 190 PSIG?

A. I . Reduce NC system pressure to initiate Cold Leg Accumulator injection to restore subcooling

2. Prevent excessive thermal shock of Reactor Vessel cold leg nozzles B. I. Reduce NC system temperature and pressure to reduce NC pump seal leakage and minimize NC system inventory loss
2. Prevent excessive thermal shock of Reactor Vessel cold leg nozzles C. I. Reduce NC system pressure to initiate Cold Leg Accumulator injection to restore subcooling
2. Prevent nitrogen from the Cold Leg Accumulators from injecting into the NC system D. 1. Reduce NC system temperature and pressure to reduce NC pump seal leakage and minimize NC system inventory loss
2. Prevent nitrogen from the Cold Leg Accumulators from injecting into the NC system Page 51 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 52 (1 point)

Given the following conditions on Unit I:

. A Loss of Offsite Power has occurred

  • During the recovery, it is determined that a natural circulation cooldown needs to be performed Which ONE (1) of the following indicates that natural circulation is occurring per Generic Enclosure 33 (Natural Circulation Parameters)?

NC System Cold Leg NC System Hot Leg Temperatures: Temperatures:

A. Going DOWN At saturation temperature for SIG pressure B. At saturation temperature for Going DOWN S/G pressure C. Going DOWN Going DOWN D. At saturation temperature for At saturation temperature for S/G pressure S/G pressure Page 52 of 75

McGu ire Nuclear Station 2012 MNS RO NRC Examination Question: 53 (1 point)

A sustained loss of power to Vital AC Panelboard will req uire that operators manually transfer NV Pump suction from the VCT to the FWST per AP-1 5 (Loss of Vital or Aux Control Power).

Which ONE of the following completes the statement above?

A. IEKVA B. IEKVB C. IEKVC D. IEKVD Page 53 of 75

McGu ire Nuclear Station 2012 MNS RO NRC Examination Question: 54 (1 point)

Given the following conditions on Unit 1:

  • The I B DC is running due to an inadvertent Blackout signal during testing
  • IRN-171B (B DG HX Supply Isolation Valve) did NOT open
1) Based on the conditions above, if the Lube Oil High Temperature trip setpoint is reached, will the DG trip?
2) What is the DG Lube Oil High Temperature trip setpoint?

A. 1. Yes

2. 190°F B. 1.No
2. 190°F C. 1. Yes
2. 200°F D. 1.No
2. 200°F Page 54 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 55 (1 point)

Unit I was initially at 100% RTP:

. A Safety Injection has occurred due to a LOCA on IA Train of ND

. ECA-1 .2 (LOCA Outside Containment) has been implemented The overall mitigating strategy of ECA-1 .2 includes:

Cooldown the NCS (I) and then depressurize the NCS to allow the (2)

Which ONE (1) of the following completes the statement above?

A. 1. while maintaining a cooldown rate in NC Tcolds less than 100°F/hr

2. Cold Leg Accumulators to inject B. 1. at maximum rate while attempting to avoid a Main Steam Isolation
2. Cold Leg Accumulators to inject C. 1. while maintaining a cooldown rate in NC Tcolds less than 100°F/hr
2. ND isolation valves (INI-173A and INI-178B) to close D. 1. at maximum rate while attempting to avoid a Main Steam Isolation
2. ND isolation valves (1 NI-I 73A and I NI-178B) to close Page 55 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 56 (1 point)

Unit I has tripped from 100% RTP with the following conditions:

. The crew has implemented FR-H.1 (Response to Loss of Secondary Heat Sink)

  • All attem pts to restore CA flow have been unsuccessful Which ONE (1) of the following identifies the next source of feedwater that FR-H.1 will prioritize for restoration AND when attempts to restore feedwater will be terminated?

A. Condensate (CM); AND When Feed and Bleed has been established.

B. Condensate (CM); AND When a Secondary Heat Sink is restored.

C. Main Feedwater(CF); AND When Feed and Bleed has been established.

D. Main Feedwater (CF); AND When a Secondary Heat Sink is restored.

Page 56 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 57 (1 point)

Given the following conditions on Unit 1:

. The Reactor is shutdown

. Tave is 556°F and STABLE

. OATC is moving Shutdown Bank A rods for testing Current Conditions:

. Shutdown rod B4 drops halfway into the core

. The OATC immediately stops moving rods

. DRPI for rod B4 reads 30 steps

. DRPI and Group Step Counters for all other rods in Shutdown Bank A read 66 steps

  • Exceptfor Shutdown BankA, all other rod bottom lights are LIT Based on the current conditions, Technical Specification (TS) 3.1.4 (Rod Group Alignment Limits) LCO actions (I) required to be taken.

OP/I /A/61001003 (Controlling Procedure for Unit Operation) states that MODE 2 may be declared when (2) Banks are initially withdrawn from the fully inserted position.

Which ONE (I) of the following completes the statements above?

A. I.ARENOT

2. Control B. 1. ARE NOT
2. Shutdown C. I. ARE
2. Control D. 1. ARE
2. Shutdown Page 57 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 58 (1 point)

Given the following conditions on Unit 1:

. Afterwithdrawing Control Bank D, the RO identifies that Control Rod M-4 (Control Bank D, Group 2) indicates 92 steps on DRPI

  • Bank D Group Step Counters indicate 100 steps on both banks
  • l&E has determined that Control Rod M-4 stopped moving due to a failed Lift Coil Disconnect switch
  • The failed switch has been replaced and the Operating crew is ready to realign Control Rod M-4
  • As Control Rod M-4 begins to move, annunciator IAD-2, A/I 0 (Rod Control Urgent Failure) alarms The cause of this alarm is an Urgent Failure in Power Cabinet Which ONE (1) of the following completes the statement above?

A. IAC B. 2AC C. IBD D. 2BD Page 58 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 59 (1 point)

Given the following conditions on Unit 1:

  • An ATWS has occurred on the unit
  • FRS.1 (Response to Nuclear Power Generation IATWS) has been implemented
  • Emergency Boration has been initiated FR-S.1 requires the operator to:
1) verify a MINIMUM Emergency Boration flow of________

AND

2) check that charging flow Which ONE (1) of the following completes the statements above?

A. 1. 2OGPM

2. isgreaterthan boration flow B. 1. 3OGPM
2. isgreaterthan boration flow C. 1. 2OGPM
2. does not exceed VCT makeup capability D. 1. 3OGPM
2. does not exceed VCT makeup capability Page 59 of 75

McGu ire Nuclear Station 2012 MNS RO NRC Examination Question: 60 (1 point)

Unit I is operating at 97% RTP when a Reactor Trip occurs.

Given the following conditions:

Channel Flux Level SUR SRN3I OCPS ODPM SR N32 0 CPS 0 DPM IRN35 1.1x10°AMPS -1/3DPM lR N36 9.5x1 0h1 AMPS -1/3 DPM PRN4I 12%

PR N42 0%

PR N43 0%

PR N44 0%

Which ONE (1) of the following statements descnbes why the Source Range Nuclear Instruments are NOT indicating?

A. P-I 0 (Nuclear at Power) status light is LIT.

B. P-6 (S/R Block Permissive) status light is LIT.

C. P-I0 (Nuclear at Power) status light is DARK.

D. P.6 (S/R Block Permissive) status light is DARK.

Page 60 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 61 (1 point)

Given the following conditions on Unit I:

  • A Reactor startup is in progress
  • Based on the following indications, the startup has been placed on hold:

o N-31 indicates 3.1x10 cps 4

o N-32 indicates 4 cps 3.0x10 o N-35 indicates 9 amps 1.5x10 o N-36 indicates ° amps 1

1.0x10

  • Rods are in manual with no rod motion
  • SR and IR Nis are slowly increasing
  • Tave is holding steady Which ONE of the following is the reason for placing the startup on hold?

A. N-35 compensating voltage is set too high B. N-35 compensating voltage is set too low C. N-36 compensating voltage is set too high D. N-36 compensating voltage is set too low Page 61 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 62 (1 point)

Given the following conditions on Unit 2:

. EPI2IAI5000IFR-C.2 (Response to Degraded Core Cooling) is in progress

. Reactor coolant pumps (NCP) 2A and 2C are in service

. Reactor vessel dynamic DIP is decreasing and is 3% less than required

  • The crew has just completed depressurizing the S/Gs to 190 PSIG What is the mitigation strategy in accordance with EP/2/A/5000/FR-C.2?

A. Shutdown all NCPs. Depressurize the NC system by depressurizing the steam generators to atmospheric pressure.

B. Shutdown all NCPs. Do not depressurize the steam generators further.

C. Continue to run both NCPs. Depressurize the NC system by depressurizing the steam generators to atmospheric pressure.

D. Continue to run both NCPs. Do not depressurize the steam generators further.

Page 62 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 63 (1 point)

Given the following on Unit 1:

. The Fire Detection system computer indicates a fire in Zone 70 (AB 716 Unit I M/D CA Pump Room)

. An Operator dispatched to the area reports that there is smoke and some cables with glowing embers but, NO visible flames I) In accordance with AP-45 (Plant Fire) and the conditions above, this classified as an ACTIVE fire.

2) In accordance with RP-25 (Fire Brigade Response), in addition to making an announcement on the Fire Brigade Radio AND activating the Fire Brigade Pagers, a Plant PA announcement required when dispatching the Fire Brigade.

Which ONE (I) of the following completes the statements above?

A. I. is

2. is B. I.is
2. is NOT C. I. is NOT
2. is D. I. is NOT
2. is NOT Page 63 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 64 (1 point)

Given the following sequence of events on Unit I:

Time = 1000 Unit 1 was operating at 100% RTP Time = 1001 A technician setting up poles for temporary lighting in the Control Room inadvertently actuates Train B of Containment Isolation PhaseA Time = 1002 An automatic Reactor trip occurs when the A MSIV spuriously closes Time = 1003 Unit I loses all offsite power Current conditions at Time = I 010:

. SI is NOT actuated

. Train B of Phase A has NOT been reset

  • Buses I ETA and I ETB are powered from their respective D/Gs
  • Operators are implementing FR-H.2 (Response to S/G Overpressure)
  • S/G status:

A S/G B S/G C S/G D S/G NR Level [%]: 77 67 65 70 S/GPressure[PSIG]: 1270 1180 1176 1182 Based on the current conditions, in accordance with FR-H.2, which ONE (1) of the following will be required to mitigate the overpressure condition?

A. Start the TDCA pump B. Open the A SM PORV C. Place the S/G Blowdown system (BB) in service D. Commence a 100°F/hr NC system cooldown using condenser steam dumps Page 64 of 75

McGu ire Nuclear Station 2012 MNS RO NRC Examination Question: 65 (1 point)

Which ONE (1) of the following is NOT a major action category of procedure FR-Z.3 (Response to High Containment Radiation)?

A. Place VE (Annulus Ventilation) system in operation.

B. Place VX (Containment Air Return) system in operation.

C. Check Containment Ventilation Isolation.

D. Notify Station Management of Containment Radiation levels.

Page 65 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 66 (1 point)

Given the following conditions on Unit I:

. The crew has implemented E-O (Reactor Trip or Safety Injection) due to a LOCA

. The OATC is performing supplementary action steps in E-O

. The BOP is manually adjusting CA flow to the S/Gs

. An alarm annunciates on the electrical relay back panel behind the main control boards (IADI 1-E8, Transfer Trip System B Trouble)

In accordance with SOMP 01 -04 (Conduct of Operations) Attachment 7.6 (Reactor Operator Responsibilities), which ONE (1) ofthe following is the correct response by the OATC regarding the annunciator alarm?

A. The OATC can investigate the alarm, because the requirements for remaining in the surveillance area do not apply during implementation of EOPs.

B. The OATC can investigate the alarm because the electrical relay panel is within the OATC defined surveillance area.

C. The OATC is required to remain within the surveillance area during implementation of EOPs. The annunciator alarm can NOT be investigated by the OATC, another operator must investigate the alarm.

D. The OATC is allowed to momentarily leave the surveillance area to investigate the alarm in the event of an emergency affecting the safety of plant operations.

Page 66 of 75

McGu ire Nuclear Station 2012 MNS RO NRC Examination Question: 67 (1 point)

SOMP 01-04 (Conduct of Operations), Attachment 7.15 (Control Room Conduct)

Step 2 (Starting or Operating Large Components) specifically requires an announcement using the plant paging system prior to initiation of Which ONE (1) of the following completes the statement above?

A. Excess Letdown B. Normal Letdown C. Steam Generator Blowdown D. Radioactive Waste Liquid Release Page 67 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 68 (1 point)

Given the following conditions on Unit I:

. The WCC SRO has dispatched two NEOs (Doer I Documenter) to perform valve manipulations inside a contaminated area in accordance with an Operating Procedure

. The Doer is inside the contaminated area and is in direct communication with the Documenter outside the contaminated area

. The Documenter is reading each procedure step sequentially

. The Documenter can NOT see the valve manipulations being performed If the Doer does NOT have the procedure in hand as he performs the steps, what are the requirements of NSD 704 (Technical Procedure Use and Adherence), regarding the sign off for each step?

A. The Documenter checks off each step as the step is completed. The Doer initials each step upon completion of the task.

B. The Doer signs off the steps using his own initials upon completion of the task after leaving the contaminated area.

C. The Documenter signs off each step as the step is completed using his own initials AND the initials of the Doer.

D. The Documenter signs off each step as the step is completed using his own initials ONLY.

Page 68 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 69 (1 point)

With Unit I conducting a plant startup the following conditions exist:

. Reactor is at 40% RTP

. Impulse Pressure Channel I is 295 PSIG

. Impulse Pressure Channel 2 is 305 PSIG

. All AMSAC S/G LOW FLOW status lights are DARK

. The S/G PATH CLSD > 30 SEC annunciator is DARK

. The AMSAC UNBLOCK light is DARK Which ONE (1) ofthe following describes the operation ofthe AMSAC System, AND describes the action that should be taken in accordance with OP/11N61 00/003, Enclosure 4.1 (Power Increase)?

A. AMSAC has NOT failed to automatically unblock; Co nti nu e with th e power i n crease a nd AMSAC will auto matically u nblock wh en BOTH Impulse Pressure channels rise above a MINIMUM of 360 P51G.

B. AMSAC has NOT failed to automatically unblock; Continue with the power increase and AMSAC will automatically unblock when Impulse Pressure Channel I rises above a MINIMUM of 300 PS 1G.

C. AMSAC has failed to automatically unblock; Suspend the power increase until the failure has been resolved.

D. AMSAC has failed to automatically unblock; Depress the AMSAC Unblock Pushbutton, verify the Unblock light is jjI, and continue with the power increase.

Page 69 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 70 (1 point)

Given the following plant conditions:

. It is the end of a shift and there is an outstanding Configuration Control Card (CCC) that is being maintained in the Control Room

. The component being tracked on the CCC can NOT be returned to its AS FOUND position before the end of shift In accordance with SOMP 02-01 (Safety Tagging and Configuration Control), which ONE (1) of the foIloMng describes the required disposition of the CCC?

A. Document the CCC as part of yourturnover at shift relief.

B. Return the CCC to the OSM. An R&R will be issued prior to shift turnover.

C. Return the CCC to the CRS to determine whether it should be turned over, or if a procedure change will be required.

D. Return the CCC to the WCC SRO. The CCC will be tracked as open until the component can be repositioned to its AS FOUND position.

Page 70 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 71 (1 point)

Regarding the use of Electronic Dosimeters (ED):

. If a DOSE alarm setpoint is exceeded, the alarm will (1 )

. If a DOSE RATE alarm setpoint is exceeded, the alarm will (2)

Which ONE (1) of the following completes the statements above?

A. 1. notclearuntiltheEDisreset

2. clear when the dose rate drops below the alarm setpoint B. 1. notclearuntiltheEDisreset
2. not clear until the ED is reset C. 1. clear after pressing and holding the Dose/Dose Rate toggle button on the ED for 10 seconds
2. clear when the dose rate drops below the alarm setpoint D. 1. clear after pressing and holding the Dose/Dose Rate toggle button on the ED for 10 seconds
2. not clear until the ED is reset Page 71 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 72 (1 point)

A radiation worker is repainng a valve in a contaminated area, which has the following radiological characteristics:

. The workers present exposure is I 938 MREM for the year

. The RWP states:

0 General area dose rate = 30 MREM/hr 0 Airborne contamination concentration = I 0. 0 DAC The job will take 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> if the worker wears a full-face respirator. The 2-hour time for work with a respirator includes the respirator-induced inefficiency factor. It will only take I hour if the worker does not wear the respirator.

lfthe RP Manager grants all applicable dose extensions, which ONE (1) of the following choices for completing this job would maintain the workers exposure within the station administrative requirements and the principles of ALARA AND why is that action appropnate?

A. The worker must wear the respirator.

He will exceed DAC limits if he does NOT wear one.

B. The worker must wear the respirator.

The calculated TEDE dose received will be less than if he does NOT wear one.

C. The worker should NOT wear the respirator.

The calculated TEDE dose received will be less than if he does wear one.

D. The worker should NOT wear the respirator.

The dose received wearing a respirator will exceed site annual personnel dose limits.

Page 72 of 75

McGu ire Nuclear Station 2012 MNS RO NRC Examination Question: 73 (1 point)

Unit I is operating at 8% RTP.

Which ONE (1) of the following conditions will result in an automatic Reactor trip signal? (Consider each indication separately)

A. Intermediate Range channel N-35 indicates 1O AMPS B. IA NC Loop Flow I NCP-5000 (Channel I) indicates 90%

C. Pressurizer Level INCP-5160 (Channel I) and INCP-5151 (Channel 2) indicate 100%

D. IC SIG NR Level ICFP-5560 (Channel 3) and ICFP-5550 (Channel 4) indicate 82%

Page 73 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 74 (1 point)

Given the following plant conditions:

. Chlorine gas is entering the Control Room due to a dropped gas cylinder

. AP-17 (Loss of Control Room) has been implemented

. I ETA and I ETB are energized In accordance with AP-17:

The RO dispatched to the CA Pump panels is first directed to (1)

At the CA Pump panels, the RO is directed to control S/G WR levels between (2)

Which ONE (1) of the following completes the statements above?

A. 1. locally stop the Reactor Makeup Water pumps if a dilution is in progress

2. 80-90%

B. 1. locally stop the Reactor Makeup Water pumps if a dilution is in progress

2. 55-65%

C. 1. close the MSIVs by opening the breakers in the vital battery room if a coold own is occurring

2. 80-90%

D. 1. close the MSIVs by opening the breakers in the vital battery room if a coold own is occurring

2. 55-65%

Page 74 of 75

McGuire Nuclear Station 2012 MNS RO NRC Examination Question: 75 (1 point)

Given the following initial conditions on Unit 1:

. Theunitisat45% RTP Current conditions:

. I AD-4 I A3 (SIG C FLOW MISMATCH LO STM FLOW) LIT -

. IAD-4 I B3 (S/G C LEVEL DEVIATION) LIT -

. IAD-6 I BlO (T-REFIT-AVG ABNORMAL) LIT -

. I AD-6 I Dl 0 (LOOP T-AVG DEVIATION) LIT -

. IAD-6 I ElO (LOOP D/T DEVIATION) LIT -

. IAD-6 I F3 (C NC PUMP LO FLO ALERT) LIT -

. IAD-6/E11 (NC PUMP HI VIBRATION)-LIT

. IAD-6/ Fil (NC PUMP HI HIVIBRATION)- LIT

. The Safety breaker AND the Feeder breaker for I C NC pump indicate CLOSED

. The unit remains at 45% RTP Based on the above conditions, which ONE (I) of the following actions is required to be performed?

A. Immediately trip the IC NC pump and THEN shutdown the unit in accordance with OP/I /A/6100/003 (Controlling Procedure for Unit Operation).

B. Place the IC S/G CF Control valve in Manual and reduce feed flow.

C. Manually trip the reactor, stop the I C NCP, and then go to E-O (Reactor Trip or Safety Injection).

D. Place the Unit I DIT DEFEAT switch to the I C position per the Annunciator Response Procedure for IAD-6 / ElO.

Page 75 of 75

Reference Listfor: 2012 MNS RO NRC Examination Steam Tables EPIIIAI5000IECA-1.1 (Step 18)

EP/1 IAI5000IECA-l .1 (Enclosure 9)

Printed 8/28/2012 8:42:53 AM Page 1 of 1

MNS LOSS OF EMERGENCY COOLANT REC1RC PAGE NO.

EPIIIN5000JECA-ii 18 of 101 UNIT1 Rev.15 F AT1C!T/EXPECTED RESPONSE PESONSE NYT O3TAINED

18. Check if SII can be terminated:

a Check RVLIS indication: _a. iQLQStep24.

. IF all NC pumps off, THEN check REACTOR VESSEL LR LEVEL -

GREATER THAN 60%.

OR

_ . IF at least one NC pump on, J1JEN check REACTOR VESSEL DIP -

GREATER THAN REQUIRED DELTA P FROM Enclosure 7 (Minimum Dynamic RVLIS Indication).

b. NC subcooling based on core exit TICs b. Perform the following:

- GREATER THAN 50°F.

1) Determine minimum S/I flow required fR Enclosure 9 (Flow Required to Match Decay Heat).
2) Minimize S/I flow by stc>pping one or more S/i pumps while maintaining greater than or equal to flow required by Enclosure 9 (Flow Required to Match Decay Heat).
3) QIQ Step 24.
19. Reset the following:

. Phase A Isolation

. Phase B lsolation.

MNS LOSS OF EMERGENCY COOLANT RECIRC PAGE NO.

EPI1IN5OOOIECA1 I Enclosure 9 Page 1 of 1 Rev. 5 tNIT I Flow Required to Match Decay Heat 600- - - - -

M5OO\E

[1 400 M

_ i- -

S - --

F 300- i::: i::

L - - -

0 w

R A 200

-r E

G p

M ioo 0

. 6:* .: .3 4 Z .

10 100 1000 10000 TIME AFTER REACTOR TRP (MINLJTES

Examination KEYfor: 2012 MNS RO NRC Examination Question Answer Number A

2 B 3 B 4 C 5 A 6 D 7 C 8 C 9 A 10 B 11 B 12 C 13 B 14 B 15 B 16 C 17 B 18 C 19 D 20 D 21 B 22 C 23 B 24 A 25 A Printed 8/28/2012 8:43:38 AM Page 1 of3

Examination KEYfor: 2012 MNS RO NRC Examination Question Answer Number 26 C 27 B 28 D 29 A 30 A 31 B 32 C 33 A 34 B 35 B 36 B 37 A 38 D 39 D 40 C 41 C 42 B 43 D 44 C 45 B 46 A 47 C 48 B 49 A 50 B Printed 8/28/2012 8:43 :38 AM Page 2 of3

Examination KEYfor: 2012 MNS RO NRC Examination Question Answer Number 51 D 52 B 53 A 54 B 55 D 56 D 57 A 58 C 59 B 60 B 61 B 62 A 63 C 64 B 65 B 66 D 67 C 68 C 69 D 70 B 71 A 72 C 73 A 74 B 75 C Printed 8/28/2012 8:43:38 AM Page 3 of3