ML12255A394

From kanterella
Jump to navigation Jump to search
IR 05000483-12-008; June 25, 2012 - July 13, 2012; Callaway Plant Biennial Baseline Inspection of the Identification and Resolution of Problems
ML12255A394
Person / Time
Site: Callaway Ameren icon.png
Issue date: 09/11/2012
From: Ray Kellar
Division of Reactor Safety IV
To: Heflin A
Union Electric Co
References
IR-12-008
Download: ML12255A394 (29)


See also: IR 05000483/2012008

Text

September 11, 2012

Mr. Adam C. Heflin, Senior Vice

President and Chief Nuclear Officer

Union Electric Company

P.O. Box 620

Fulton, MO 65251

SUBJECT:

CALLAWAY PLANT - NRC PROBLEM IDENTIFICATION AND RESOLUTION

INSPECTION REPORT 05000483/2012008

Dear Mr. Heflin:

On July 13, 2012, the U.S. Nuclear Regulatory Commission (NRC) completed a Problem

Identification and Resolution biennial inspection at your Callaway Plant. The enclosed

inspection report documents the inspection results, which the inspection team discussed on

July 13, 2012, with you and members of your staff.

This inspection was an examination of activities conducted under your license as they relate to

problem identification and resolution and to compliance with the Commissions rules and

regulations and the conditions of your license. Within these areas, the inspection involved

examination of selected procedures and representative records, observations of activities, and

interviews with personnel.

Based on the inspection sample, the inspection team concluded that the implementation of the

corrective action program and overall performance related to identifying, evaluating, and

resolving problems at Callaway Plant was effective. Your staff generally identified problems and

entered them into the corrective action program at a low threshold, though the team noted some

exceptions, as described in the attached report. Problems were effectively prioritized and

evaluated commensurate with the safety significance of the problems. Appropriate corrective

actions were identified for most problems and were generally implemented in a timely manner,

commensurate with their safety significance. Most corrective actions addressed the causes of

identified problems, though the team noted some exceptions. Lessons learned from industry

operating experience were generally reviewed and applied when appropriate. Audits and self-

assessments were effectively used to identify problems and appropriate corrective actions.

Finally, the team determined that the station maintains a safety conscious work environment

where employees feel free to raise nuclear safety concerns without fear of retaliation.

Two NRC-identified and two self-revealing findings of very low safety significance (Green) were

identified during this inspection. All four of these findings involved violations of NRC

requirements. The NRC is treating these violations as non-cited violations (NCVs) consistent

with Section 2.3.2.a of the NRCs Enforcement Policy.

UNITED STATES

NUCLEAR REGULATORY COMMISSION

RE G IO N I V

1600 EAST LAMAR BLVD

ARLINGTON, TEXAS 76011-4511

A. Heflin

- 2 -

If you contest these non-cited violations, you should provide a response within 30 days of the

date of this inspection report, with the basis for your denial, to the Nuclear Regulatory

Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with copies to the

Regional Administrator, Region IV; the Director, Office of Enforcement, United States Nuclear

Regulatory Commission, Washington, DC 20555-0001; and the NRC Resident Inspector at

Callaway Plant.

If you disagree with a cross-cutting aspect assignment in this report, you should provide a

response within 30 days of the date of this inspection report, with the basis for your

disagreement, to the Regional Administrator, Region IV, and the NRC Resident Inspector at

Callaway Plant

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRC's Agencywide Document Access and Management System (ADAMS). ADAMS is

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA/

Ray L. Kellar, P.E., Chief

Technical Support Branch

Division of Reactor Safety

Docket No.: 50-483

License No.: NPF-30

Enclosure: Inspection Report 05000483/2012008

w/attachments

cc w/ encl: Electronic Distribution

A. Heflin

- 3 -

DISTRIBUTION:

Electronic distribution by RIV:

Regional Administrator (Elmo.Collins@nrc.gov)

Deputy Regional Administrator (Art.Howell@nrc.gov)

DRP Director (Kriss.Kennedy@nrc.gov)

Acting DRP Deputy Director (Allen.Howe@nrc.gov)

Acting DRS Director (Tom.Blount@nrc.gov)

Acting DRS Deputy Director (Patrick.Louden@nrc.gov)

Senior Resident Inspector (Thomas.Hartman@nrc.gov)

Resident Inspector (Zachary.Hollcraft@nrc.gov)

Branch Chief, DRP/B (Neil.OKeefe@nrc.gov)

Senior Project Engineer, DRP/B (Leonard.Willoughby@nrc.gov)

Project Engineer, DRP/B (Nestor.Makris@nrc.gov)

CW Administrative Assistant (Dawn.Yancey@nrc.gov)

Public Affairs Officer (Victor.Dricks@nrc.gov)

Public Affairs Officer (Lara.Uselding@nrc.gov)

Project Manager (Fred.Lyon@nrc.gov)

Branch Chief, DRS/TSB (Ray.Kellar@nrc.gov)

RITS Coordinator (Marisa.Herrera@nrc.gov)

Regional Counsel (Karla.Fuller@nrc.gov)

Technical Support Assistant (Loretta.Williams@nrc.gov)

Congressional Affairs Officer (Jenny.Weil@nrc.gov)

OEMail Resource

ROPreports

RIV/ETA: OEDO (Silas.Kennedy@nrc.gov)

DRS/TSB STA (Dale.Powers@nrc.gov)

R:\\REACTORS\\CWY 2012008 RP EAR DRAFT.docx ML

SUNSI Rev Compl.

Yes No

ADAMS

Yes No

Reviewer Initials

EAR

Publicly Avail.

Yes No

Sensitive

Yes No

Sens. Type Initials

RIV/DRS/TSB

NRR/DRA/AHPB RIV/DRS/EB1

DRP/PBA

DRP/PBB

C:DRP/PBB

C:DRS/TSB

EARuesch

MJKeefe

CMDenissen MOHayes

ZRHollcraft

NFOKeefe

RLKellar

/RA/

/RA-E/

/RA-E/

/RA-T/

/RA-E/

/RA/

/RA/

9/10/12

7/31/12

8/2/12

8/20/12

8/20/12

9/10/12

9/11/12

OFFICIAL RECORD COPY

- 1 -

Enclosure

U.S. NUCLEAR REGULATORY COMMISSION

REGION IV

Docket:

50-483

License:

NPF-30

Report:

05000483/2012008

Licensee:

Union Electric Company

Facility:

Callaway Plant

Location:

Junction Hwy CC and Hwy O

Fulton, MO

Dates:

June 25 through July 13, 2012

Team Leader:

E. Ruesch, Senior Reactor Inspector

Inspectors:

C. Denissen, Reactor Inspector

M. Hayes, Resident Inspector

Z. Hollcraft, Resident Inspector

M. Keefe, Human Factors Specialist

Accompanying

Personnel:

R. Telson, Reactor Operations Engineer

K. Watanabe, Chief Inspector, Japan Nuclear Energy

Safety Organization (JNES)

Approved By:

R. Kellar, P.E., Chief

Technical Support Branch

Division of Reactor Safety

- 2 -

SUMMARY OF FINDINGS

IR 05000483/2012008; June 25, 2012 - July 13, 2012; Callaway Plant "Biennial Baseline

Inspection of the Identification and Resolution of Problems"

The team inspection was performed by one senior reactor inspector, one reactor inspector, two

resident inspectors, and one human factors specialist. Four Green non-cited violations of

significance were identified during this inspection. The significance of most findings is indicated

by their color (Green, White, Yellow, Red) using Inspection Manual Chapter 0609, "Significance

Determination Process". Findings for which the significance determination process does not

apply may be Green or be assigned a severity level after NRC management review. The NRC's

program for overseeing the safe operation of commercial nuclear power reactors is described in

NUREG 1649, "Reactor Oversight Process," Revision 4, dated December 2006.

Identification and Resolution of Problems

The team reviewed approximately 200 condition reports, work orders, engineering evaluations,

root and apparent cause evaluations, and other supporting documentation to determine if

problems were being properly identified, characterized, and entered into the corrective action

program for evaluation and resolution. The team reviewed a sample of system health reports,

self-assessments, trending reports and metrics, and various other documents related to the

corrective action program. The team concluded that with limited exceptions, the licensee

maintained a corrective action program in which issues were generally identified at an

appropriately low threshold. Issues entered into the corrective action program were

appropriately evaluated and timely addressed, commensurate with their safety significance.

Corrective actions were generally effective, addressing the causes and extents of condition of

problems.

The licensee appropriately evaluated industry operating experience for relevance to the facility

and entered applicable items in the corrective action program. The licensee used industry

operating experience when performing root cause and apparent cause evaluations. The

licensee performed effective quality assurance audits and self-assessments, as demonstrated

by its self-identification of some minimally effective corrective action program performance and

identification of ineffective corrective actions.

The licensee maintained a safety-conscious work environment in which personnel felt free to

raise safety concerns without fear of retaliation. All individuals interviewed by the team were

willing to raise these concerns by at least one of the several methods available.

A. NRC-Identified and Self-Revealing Findings

Cornerstone: Mitigating Systems

Green. The team reviewed a Green self-revealing non-cited violation of 10 CFR Part 50,

Appendix B, Criterion XVI, Corrective Action, for the licensees failure to promptly

identify and correct a condition adverse to quality. During troubleshooting, the licensee

incorrectly identified a failed circuit card as the cause of an essential service water pump

room fan damper failure. The licensee returned the damper to service and declared the

associated pump operable without identifying the actual failurepinched wires

introduced during previous maintenance. This resulted in a subsequent failure.

- 3 -

The failure to identify that pinched wires had caused the damper failure and to correct

the condition before replacing the circuit card and declaring the system operable was a

performance deficiency. This performance deficiency was more than minor because it

adversely affected the equipment performance attribute of the Mitigating Systems

cornerstone objective to ensure the availability, reliability, and capability of systems that

respond to initiating events to prevent undesirable consequences. Using Inspection

Manual Chapter 0609.04, Phase 1 - Initial Screening and Characterization of Findings,

the team determined the finding to be of very low safety significance (Green) because it

did not result in the loss of the safety function of any system or train and did not screen

as potentially risk significant due to seismic, flooding, or severe weather initiating events.

This finding had a cross-cutting aspect in the decision-making component of the human

performance cross-cutting area because the licensee failed to conduct an effectiveness

review of safety-significant decisions to verify the validity of the underlying

assumptions or identify possible unintended consequences (H.1(b)).

(Section 4OA2.5.a)

Green. The team reviewed a non-cited violation of Technical Specification 5.4.1.a,

Procedures, for the licensees failure to provide maintenance instructions appropriate

for repair of the Train B emergency diesel generator supply fan. These inadequate

instructions resulted in maintenance technicians routing and restraining electrical cables

inappropriately during maintenance in July 2006. These cables later came loose and, in

August 2011, caused a failure of the Train B emergency diesel generator supply fan to

start on demand.

The failure to provide maintenance procedures appropriate to the circumstance was a

performance deficiency. This finding was more than minor because it affected the

equipment performance attribute of the Mitigating Systems Cornerstone objective to

ensure the availability, reliability, and capability of systems that respond to initiating

events to prevent undesirable consequences. Using Inspection Manual Chapter 0609.04, Phase 1 - Initial Screening and Characterization of Findings, the team

determined that the finding was of very low safety significance (Green) because it did not

result in the loss of the safety function of any system or train and did not screen as

potentially risk significant due to seismic, flooding, or severe weather initiating events.

The team determined that this performance deficiency was not indicative of current plant

performance because it was the result of repair instructions written and implemented in

2006. Therefore, no cross-cutting aspect was assigned. (Section 4OA2.5.b)

Green. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings, for the licensees failure, upon

discovery of an adverse condition, to initiate a Callaway Action Request, to notify the

shift manager, and to review the condition for, operability, functionality, and reportability

in accordance with APA-ZZ-00500, Corrective Action Program, revision 54. During

planned testing of tornado dampers for the emergency diesel generator rooms, the as-

found breakaway torque for the dampers was high out-of-specification. The licensee

failed to document this adverse condition in its corrective action program to evaluate it

for significance and to determine whether the operability of the emergency diesel

generator was adversely affected.

The failure to satisfy the guidance in APA-ZZ-00500 upon identification of high out-of-

specification torque measurements on safety-related tornado dampers by initiating a

Callaway Action Request, informing the shift manager, and evaluating the condition for

- 4 -

operability, functionality, and reportability was a performance deficiency. This

performance deficiency was more than minor because if left uncorrected, the licensees

continued failure to conform to APA-ZZ-00500 upon discovery of an adverse condition

impacting the EDG tornado protection system had the potential to lead to a more

significant safety concern. Using Inspection Manual Chapter 0609.04, Phase 1 - Initial

Screening and Characterization of Findings, the team determined that the finding was of

very low safety significance (Green) because it did not result in the loss of the safety

function of any system or train and did not screen as potentially risk significant due to

seismic, flooding, or severe weather initiating events. This finding had a cross-cutting

aspect in the corrective action program component of the problem identification and

resolution cross-cutting area because the licensee failed to completely, accurately, and

in a timely manner identify and fully evaluate an issue potentially impacting nuclear

safety (P.1(a)). (Section 4OA2.5.c)

Green. The team identified a Green non-cited violation of 10 CFR Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings, for the licensees failure to fully

implement the requirements of its fluid leak management procedure. The team identified

two instances where the licensee had not hung a fluid leak management tag on an

active fluid leak and several examples of fluid leak management tags not indicating

whether individual leaks were monitored. Further, the team found no evidence that

leakage indications were actively monitored and trended, as required by procedure both

before and after repairs were made. The licensee had previously determined that the

extent of condition of weaknesses in its boric acid corrosion control program included the

fluid leak management program. However, corrective actions only addressed the boric

acid corrosion control program.

The licensees failure to implement the requirements of its fluid leak management

procedure was a performance deficiency. The team determined that the performance

deficiency was more than minor because if left uncorrected, it had the potential to

become a more significant safety concern. Specifically, if the licensee continued to fail

to implement its fluid leak management procedure, leaks that adversely affect safety-

related equipment could go unmonitored, resulting in equipment degradation. Using

Inspection Manual Chapter 0609.04, Phase 1 - Initial Screening and Characterization of

Findings, the team determined the finding to be of very low safety significance (Green)

because it did not result in the loss of the safety function of any system or train and did

not screen as potentially risk significant due to seismic, flooding, or severe weather

initiating events. The team determined that the finding had a cross-cutting aspect in the

corrective action program component of the problem identification and resolution cross-

cutting area because the licensee failed to fully evaluate a problem such that the

resolution addressed the causes and extent of condition (P.1(c)). (Section 4OA2.5.d)

B. Licensee-Identified Violations

None

- 5 -

REPORT DETAILS

4.

OTHER ACTIVITIES (OA)

4OA2 Problem Identification and Resolution (71152)

The team based the following conclusions on the sample of corrective action documents

that were initiated during the assessment period, which ranged from October 18, 2010,

to the end of the on-site portion of this inspection on July 13, 2012.

.1

Assessment of the Corrective Action Program Effectiveness

a. Inspection Scope

The team reviewed approximately 200 Callaway Action Requests (CARs), including

associated root cause, apparent cause, and direct cause evaluations, from

approximately 13,000 that had been issued between October 18, 2010, and July 13,

2012, to determine if problems were being properly identified, characterized, and

entered into the corrective action program for evaluation and resolution. The team

reviewed a sample of system health reports, operability determinations,

self-assessments, trending reports and metrics, and various other documents related to

the corrective action program. The team evaluated the licensees efforts in establishing

the scope of problems by reviewing selected logs, work orders (Jobs), self-assessment

results, audits, system health reports, action plans, and results from surveillance tests

and preventive maintenance tasks. The team reviewed daily CARs and Jobs, and

attended the licensees daily CAR screening and leadership meetings to assess the

reporting threshold, prioritization efforts, and significance determination process, as well

as observing the interfaces with the operability assessment and work control processes

when applicable. The teams review included verification that the licensee considered

the full extent of cause and extent of condition for problems, as well as a review of how

the licensee assessed generic implications and previous occurrences. The team

assessed the timeliness and effectiveness of corrective actions, completed or planned,

and looked for additional examples of similar problems. The team conducted interviews

with plant personnel to identify other processes that may exist where problems may be

identified and addressed outside the corrective action program.

The team reviewed corrective action documents that addressed past NRC-identified

violations to ensure that corrective actions addressed the issues as described in the

inspection reports. The team reviewed a sample of corrective actions closed to other

corrective action documents to ensure that corrective actions remained appropriate and

timely.

The team considered risk insights from both the NRCs and Callaway Plants risk

assessments to focus the sample selection and plant tours on risk significant systems

and components. The team focused its sample on emergency core cooling systems and

selected the emergency diesel generator system for a five-year in-depth review. The

samples reviewed by the team focused on, but were not limited to, these systems. The

team conducted walkdowns of these systems to assess whether problems were

identified and entered into the corrective action program.

- 6 -

b. Assessments

1. Effectiveness of Problem Identification

The team concluded that in most cases, the licensee identified issues and adverse

conditions in accordance with its corrective action program guidance and with NRC

requirements. The team determined that the licensee generally identified these

problems at a low threshold and entered them into the corrective action program.

However, the team found several examples of deficiencies and received several

comments during interviews that indicated a reluctance of some plant personnel to

use the corrective action program to evaluate and resolve problems that they

perceived as minor.

During the 22-month inspection period, approximately 13,000 CARs were generated.

The licensees CAR generation rate of approximately 8000-8500 per year during

outage years and 6500-7000 per year during non-outage years had been relatively

constant over the previous four years. The team noted that because the licensee

maintained a separate system for the initiation of Jobs, not all problems were

required by licensee procedures to be entered into the corrective action program.

Lower-level conditions that did not meet the licensees requirement for initiation of a

CAR were addressed as Jobs. The team identified that most conditions that required

generation of a CAR by APA-ZZ-00500, Corrective Action Program, Revision 054,

and associated attachments were being appropriately entered into the corrective

action program. However, the team noted several exceptions:

In April 2012, as-found EDG building tornado damper torque measurements

were found high out of specification. The system engineer failed to write a

CAR for this condition as required by procedure. This performance deficiency

is further discussed in Section 4OA2.5.b of this report.

During observations of control room operations on June 28, 2012, the team

noted an under-instruction operator at the controls viewing photographs on his

mobile phone and sharing these photographs with a maintenance technician.

The team disagreed with the licensees assessment that this was not

distracting conduct, prohibited by ODP-ZZ-0001, Addendum 11, Control

Room Decorum. The licensee did not initiate a CAR related to this

observation.

During a plant walk-down on June 29, 2012, the team identified potential fluid

leaks that the licensee had not identified or documented in its corrective action

program. The licensee did not enter these conditions into its corrective action

program until July 11, 2012, after being questioned by the team.

Additionally, during other inspections conducted during the inspection period, the

NRC had documented three findings that were evaluated to have P.1(a) cross-

cutting aspects. These indicated potential deficiencies in the licensees effective

identification of problems:

On August 21, 2011, the number 3 alternate emergency power supply (AEPS)

diesel output breaker tripped open due to incorrect breaker relay settings.

- 7 -

Further investigation by the licensee revealed that all four of the diesel output

breakers had incorrect settings. The incorrect settings occurred due to the

limited range of the relay chosen for the application and the engineering

recommendations that prioritized protecting the diesel over limiting the margin

to unintended breaker trips. This was documented as FIN 2011004-02.

Following a trip of the supply breaker to an emergency diesel generator jacket

water keep warm pump on November 6, 2010, the NRC found that a previous

evaluation had shown a decrease in motor insulation resistance at a sufficient

rate such that there was a reasonable doubt that the motor would continue to

be reliable until the next performance evaluation. The licensee failed to

recognize this degradation and, as a result, did not enter the condition into the

corrective action program. This was documented as NCV 2010005-03.

On February 8 and March 16, 2011, the NRC identified two locations where

scaffold poles and a scaffold pin were less than the procedurally required 1

inch from the auxiliary building vent line, the train B emergency diesel lube oil

drain line, and the essential service water system piping in the Train B diesel

room. The licensee failed to properly install and inspect these scaffolds and did

not exhibit a low threshold for identifying scaffold issues. This was documented

as NCV 2011002-04.

The team concluded that these exceptions indicated a higher-than-normal threshold

for the formal identification of problems and entry into the corrective action problem

for evaluation. Nonetheless, the team noted that most problems were adequately

addressed through one of the licensees programs for the identification and

resolution of problems.

2. Assessment - Effectiveness of Prioritization and Evaluation of Issues

Once the licensee enters issues into the corrective action program, they are

generally screened to the appropriate level as required by APA-ZZ-00500,

Corrective Action Program, Revision 054, and associated attachments. While the

team noted some issues with the timeliness of corrective actions for issues, such as

inadequate plant lighting, actions were generally completed by their due dates; due

date extensions were generally reasonable and were not overused. However, the

team noted some issues with the licensees implementation of its program to identify

trends and with its evaluation of some identified adverse conditions:

The team identified a minor performance deficiency associated with the

licensees trending program. For adverse trends identified outside of the

quarterly trending program, including trends identified through audits, the

licensee failed to establish success criteria used to terminate performance

monitoring. This created the potential for a trend to be closed without

consideration for new data points and the possible need for continued

performance monitoring. This could adversely impact the stations ability to

use adverse trends as a prediction tool to address issues at a low level, prior to

escalating into a significant event. The licensee documented this observation

in CAR 201204897.

- 8 -

The past operability for the August 2011 essential service water train A fan

damper failure (CAR 201106551) declared the essential service water pump

operable based on a calculation of maximum room temperatures. In

performing this calculation, the licensee considered ambient temperatures for

the period from a previous failure in July until the August failure. The licensee

had identified that the degraded condition had been introduced during

maintenance in May 2011. However, the evaluation of past operability did not

consider the period from this time until the July failure. The licensee initiated

CAR 201204890 to update the past operability evaluation and to document the

issue.

MDP-ZZ-LM001, Fluid Leak Management, Revision 011, directs that for all

leakage indication other than boric acid, fluid leak management tags be

generated and hung on the leaking equipment and that the leaks be monitored.

During several walk-downs of safety-related plant equipment, the team noted

fluid leaks where either no tag was hanging or where it was unclear which of

multiple leaks was identified by a hanging tag. The team noted that in January

2012, a CAR had been written recommending the development of a program-

level procedure to govern plant response to leakage, but no action had been

taken. This performance deficiency is further discussed in Section 4OA2.5.d of

this report.

Additionally, during other inspections conducted during the inspection period, the

NRC had documented three findings that were evaluated to have a P.1(c) cross-

cutting aspects. These indicated potential deficiencies in the licensees prioritization

and evaluation of problems:

In September 2011, the NRC identified that Callaway Plant did not have

procedures that ensured that hand files and wire brushes designated for

stainless steel weld preparation were stored separately from hand files and

wire brushes used on carbon steel. The licensee previously identified

contaminated tools as the cause of rusting on the motor-driven auxiliary feed

pump room cooler stainless steel piping, but took no further action to identify

the cause of the contamination. This was documented as NCV 2011005-01.

On April 19, 2011, the NRC identified that the Callaway Plant failed to maintain

an adequate design control calculation for the flooding analysis of control

building room 3101. The licensee did not update the flooding analysis of

record to consider potential failures in new piping installed in 2009 as part of a

modification that replaced essential service water carbon steel piping with high

density polyethylene piping. This was documented as NCV 2011003-01.

Overall, the team determined that the licensee had a strong process for screening

and prioritizing issues that were entered into the corrective action program. All

departments were represented at CAR screening meetings. The departments took

clear ownership of the issues discussed and set appropriate due dates for evaluation

of the issues identified in the CARs, in accordance with APA-ZZ-00500, Corrective

Action Program, Revision 054, and associated attachments. The issues noted

above were related to the subsequent evaluation of these issues and the

prioritization of corrective actions.

- 9 -

3. Assessment - Effectiveness of Corrective Actions

When appropriate corrective actions were implemented, they were generally

effective. However, the team identified some examples of corrective actions not

addressing the entire cause or extent of condition.

After a failure of ESW room supply fan dampers in July 2011, the licensee

incorrectly evaluated the condition. The licensees evaluation presumed,

based on industry operating experience, that a circuit card had failed. The

licensee replaced the circuit card and returned the dampers to service.

However, the failure was the result of pinched wires; the circuit card was fully

functional. The failure recurred in August 2011. This performance deficiency is

further discussed in Section 4OA2.5.c of this report.

Root cause evaluation AUCA 12-002 (CAR 201104707) identified that

inadequate corrective actions from previous self-assessments contributed to a

security event in 2011. The corrective action for this condition was to require

subsequent self-assessments to review trends from previous self-assessments.

The licensee implemented a procedure modification to APA-ZZ-01400,

Appendix A, Callaway Self-Assessment and Benchmarking Program. The

team noted that Revision 014 to this procedure included prior self-assessments

as one of the considerations for topics to be included within the scope of

subsequent self-assessments. However, this review was not a requirement

and the procedure step was not referenced to the CAR or the root cause

evaluation. (A similar corrective action to add operating experience reviews to

a procedure had been implemented as designed.)

The team noted that corrective actions to address the sample of NRC non-cited

violations and findings since the last problem identification and resolution inspection

had been timely and effective.

Overall, the team concluded that the licensee generally developed appropriate

corrective actions to address identified problems. The licensee generally

implemented these corrective actions in a timely manner, commensurate with their

safety significance. Except for the issue with the trending program noted in Section

4OA2.1.b.2 above, the licensee generally had performed timely effectiveness

reviews of significant corrective actions to verify their adequacy.

.2

Assessment of the Use of Operating Experience

a. Inspection Scope

The team examined the licensee's program for reviewing industry operating experience,

including governing procedures and self-assessments and interviewed individuals

responsible for managing the operating experience and vendor equipment technical

information review programs. The team reviewed a sample of CARs compared to

operating experience documents issued by the NRC and the industry during the

assessment period to assess whether the licensee had entered those items into their

corrective action program. The team also examined whether the licensee had

appropriately evaluated external operating experience for relevance to the facility,

assigned appropriate and timely actions to address the issues, and performed

- 10 -

effectiveness reviews to ensure the actions were adequate. The team reviewed a

sample of root cause evaluations and significant condition reports to determine if the

licensee had appropriately reviewed industry operating experience for relevance. The

team observed management meetings and pre-job briefs that included internal and

external operating experience discussions and reviewed cause evaluations and event

review team meeting summaries that considered pertinent operating experience.

b. Assessment

The team noted that the licensee incorporated both internal and external operating

experience into lessons learned for training and into pre-job briefs, and the licensee

included a review of operating experience in its cause evaluations. However, the team

noted three indications of potential issues with the use of operating experience, one of

which the licensee had identified and corrected prior to this inspection:

In the licensees root cause evaluation for a security event in 2011, it identified that

weaknesses in the assessment and use of security-related operating experience

may have resulted in a failure to implement barriers that may have prevented the

event. The licensee identified this weakness, documented it in CAR 201104707,

and took corrective action to improve its use of security operating experience.

Two non-cited violations from the most recent integrated inspection report,

05000483/20120003, were related to the proper application of operating

experience. One had a cross-cutting aspect of P.2(b) for failure to properly

implement operating experience and the second involved failing to consider/take

appropriate action on an NRC Information Notice during the periodic Maintenance

Rule assessment.

During focus group interviews, some licensee personnel expressed frustrations

with the implementation of operating experience in day-to-day work package

preparation and briefing. Some interviewees indicated that applicable operating

experience was not always provided or, when it was, it was sometimes limited.

Overall, the team determined that the licensee had appropriately evaluated industry and

vendor operating experience for relevance to the facility, had entered applicable items

into the corrective action program, and where appropriate, had incorporated lessons

learned into station programs, processes, or procedures.

.3

Assessment of Self-Assessments and Audits

a. Inspection Scope

The team reviewed a sample of licensee self-assessments and audits to assess whether

the licensee was regularly identifying performance trends and effectively addressing

them. The team also reviewed audit reports to assess the effectiveness of assessments

in specific areas. The self-assessments and audits reviewed are listed in the attachment.

b. Assessment

The team concluded that the licensee had an effective self-assessment process.

Licensee management was involved in developing the topics and objectives of self-

- 11 -

assessments. Attention was given to assigning team members with the proper skills and

experience to perform effective self-assessments and to include people from outside

organizations. Audits were self-critical, thorough, and identified new performance

deficiencies in addition to evaluating known performance deficiencies across key

functional areas. Callaway Action Requests were generated to document deficiencies

and improvement opportunities identified through audits and corrective actions were

implemented. The team identified one weakness in individual departments missing

opportunities to identify adverse trends, as evidenced in the high number of adverse

trends identified by Nuclear Oversight through audits. However, the team did not identify

any significant adverse trends that had not been identified by at least one licensee

process.

.4

Assessment of Safety-Conscious Work Environment

a. Inspection Scope

The team interviewed forty-three individuals in seven focus groups to evaluate their

willingness to raise nuclear safety issues. These individuals were from the Operations,

Maintenance, Security, Engineering, Radiation Protection, Chemistry, and Nuclear

Oversight departments. The individuals were selected randomly based on availability

from these departments. Additionally, the team interviewed the Employee Concerns

Program (ECP) manager to assess her perception of the site employees willingness to

raise nuclear safety concerns. The team also reviewed selected documents to assess

the safety-conscious work environment (SCWE) at the site.

b. Assessment

1. Willingness to Raise Nuclear Safety Issues

The individuals interviewed indicated they did not have any hesitancy in raising

nuclear safety issues. Most feel that their management is receptive to the concerns,

and is willing to address them. Most of the interviewees also stated that if they were

not satisfied with the response from their immediate supervisor, they would feel free

to escalate the concern. In most cases, interviewees had raised issues and

concerns to their supervisors and then followed the supervisors recommendation,

which often involved entering the issue into the corrective action program. All the

individuals interviewed expressed positive experiences for bringing issues to their

supervisors and could name several other avenues for raising concerns. The

majority of interviewees explained that going through the supervisor and using the

corrective action program had been effective in their experience. Therefore, they

had not had the need to use other avenues.

2. Employee Concerns Program

All the interviewees were aware of the Employee Concerns Program. Most

explained that they have heard about the program through various means, such as

posters, ECP mailers, presentations, and discussion by supervisors or management

at meetings. Most did not have any personal experience with the ECP because, as

noted above, they felt free to raise safety concerns to their supervisors; they did not

need to use the ECP in these cases. However, there was a favorable impression of

the program: everyone interviewed stated that they would use the program if they

- 12 -

felt they needed to. Of those who had brought issues to the ECP in the past, all

indicated that the experience was positive and that they would use the ECP again if

needed. Everyone interviewed also stated that they had not heard of any issues

dealing with breaches of confidentiality.

3. Preventing or Mitigating Perceptions of Retaliation

When asked if there have been any instances where individuals experienced

retaliation or other negative reaction for raising issues, all individuals interviewed

stated that they had neither experienced nor heard of any issues of retaliation,

harassment, intimidation or discrimination at the site. The team determined that the

processes in place to mitigate these issues were being successfully implemented.

.5

Findings

a. Failure to identify and correct the failure mode of an essential service water pump

Introduction. The team reviewed a green self-revealing non-cited violation of

10 CFR Part 50, Appendix B, Criterion XVI, Corrective Action, for the licensees failure

to promptly identify and correct a condition adverse to quality. During troubleshooting,

the licensee incorrectly identified a failed circuit card as the cause of an essential service

water pump room fan damper failure. The licensee returned the damper to service and

declared the associated pump operable without identifying the actual failurepinched

wires introduced during previous maintenance. This resulted in a subsequent failure.

Description. On July 13, 2011, an air damper associated with the essential service

water train A supply fan failed to open as required during pump operation. The licensee

declared the associated pump inoperable, took compensatory actions to manually

reposition and de-energize the damper in its safety-related position, and declared the

pump operable. The licensee then performed troubleshooting on the Foxboro circuit

card associated with the damper per Job 11003848. The licensee failed to use

troubleshooting procedure MDP-ZZ-TR001, Planning and Execution of Troubleshooting

Activities, Revision 7, as guidance in preparing and conducting the troubleshooting. A

technician initially identified an intermittent ground and postulated that it may have been

associated with the field wiring. However, a second technician retested the field wiring

and determined that no ground existed. Based on these readings and on operating

experience indicating a history of problems with these cards, the cognizant engineer

elected to replace the Foxboro circuit card. Contrary to the instructions in

Job 11003848, the licensee performed no testing on the removed card to confirm it was

the cause and to document that cause. The licensee replaced the card and retested the

damper satisfactorily.

On August 17, 2011, the damper failed again. The licensee identified this as a repeat

occurrence and performed formal troubleshooting on this second failure in accordance

with procedure MDP-ZZ-TR001. The licensee again identified the ground on the field

wires initially detected following the July failure. The licensee inspected these wires and

discovered that two pinched field wires inside the hydramotor junction box, causing the

ground. In 2005, the licensee had removed this hydramotor actuator, refurbished it, and

placed it in storage. The licensee determined that during the refurbishment, the terminal

board had been positioned too close to the junction box housing. As a result, when the

licensee removed the actuator from storage and installed it back into the plant on

- 13 -

May 24, 2011, a threaded cap pinched the wires on the terminal board. Following this

discovery, the circuit was rewired and retested satisfactorily. The licensee performed an

evaluation of past operability that demonstrated, given the ambient temperatures during

the time of the failure, the essential service water pump had been operable despite the

damper failure.

Analysis. The failure to identify that pinched wires had caused the damper failure and to

correct the condition before replacing the circuit card and declaring the system operable

was a performance deficiency. This performance deficiency was more than minor

because it adversely affected the equipment performance attribute of the Mitigating

Systems cornerstone objective to ensure the availability, reliability, and capability of

systems that respond to initiating events to prevent undesirable consequences. Using

Inspection Manual Chapter 0609.04, Phase 1 - Initial Screening and Characterization of

Findings, the team determined the finding to be of very low safety significance (Green)

because it did not result in the loss of the safety function of any system or train and did

not screen as potentially risk significant due to seismic, flooding, or severe weather

initiating events. This finding has a cross-cutting aspect in the decision-making

component of the human performance cross-cutting area because the licensee failed to

conduct an effectiveness review of safety-significant decisions to verify the validity of

the underlying assumptions or identify possible unintended consequences (H.1(b)).

Enforcement. Title 10 of the Code of Federal Regulations Part 50, Appendix B,

Criterion XVI, Corrective Actions, requires, in part, that measures shall be established

to assure that conditions adverse to quality, such as failures, malfunctions, deficiencies,

deviations, defective material and equipment, and nonconformances are promptly

identified and corrected. Contrary to the above, between July 13 and August 17, 2011,

the licensee failed to establish measures to assure that conditions adverse to quality

were promptly identified and corrected. Specifically, the licensee failed to identify that

pinched wires were causing grounds on the train A essential service water pump room

fan damper resulting in the pump being inoperable. Because it was of very low safety

significance and had been entered into the licensees corrective action program as

Callaway Action Requests 201106551 and 201110845, this violation is being treated as

a non-cited violation consistent with Section 2.3.2 of the Enforcement Policy:

NCV 05000483/2012008-01, Failure to identify and correct the failure mode of an

essential service water pump.

b. Failure to Provide Adequate Maintenance Instructions

Introduction: The team reviewed a non-cited violation of Technical Specification 5.4.1.a,

Procedures, for the licensees failure to provide maintenance instructions appropriate

for repair of the Train B emergency diesel generator supply fan. These inadequate

instructions resulted in maintenance technicians routing and restraining electrical cables

inappropriately during maintenance in July 2006. These cables later came loose and, in

August 2011, caused a failure of the train B emergency diesel generator supply fan to

start on demand.

Description: On August 30, 2011, while performing scheduled emergency diesel

generator surveillances, the train B emergency diesel generator ventilation supply fan

breaker tripped unexpectedly resulting in the licensee declaring the train B emergency

diesel generator inoperable. The licensee performed troubleshooting activities and

determined the supply fan motor stator winding lead grounded to the rotor shaft shorting

- 14 -

the 480 volt supply leads to ground. The leads had been extended in July 2006 in

response to a failure of the fan while running. The cause of the failure in 2006 was due

to the motor leads pulling apart due to tension in the wires. During initial construction,

the leads were cut too short which caused undue tension. The remedy for this 2006

event was to cut off and extend the motor leads. These new extended leads were then

tucked inside the airspace between the stator and the motor housing within the end-bell

of the motor. Between July 2006 and August 2011 the motor leads inside the end-bell

came out of their tucked position and draped across the motor shaft. During operation of

the fan, the rotor shaft rubbed a hole in the motor lead insulation. On August 31, 2011,

the bare copper leads contacted the shaft and went to ground. The team reviewed the

work package used to extend the motor leads in 2006 and noted there were no specific

steps to route the extended cables. The cables should have been routed underneath

the stator and this would have prevented the failure on August 30, 2011.

Analysis: The failure to provide maintenance procedures appropriate to the

circumstance is a performance deficiency. This finding was more than minor because it

affected the equipment performance attribute of the Mitigating Systems Cornerstone

objective to ensure the availability, reliability, and capability of systems that respond to

initiating events to prevent undesirable consequences. Using Inspection Manual

Chapter 0609.04, Phase 1 - Initial Screening and Characterization of Findings, the

team determined that the finding was of very low safety significance (Green) because it

did not result in the loss of the safety function of any system or train and did not screen

as potentially risk significant due to seismic, flooding, or severe weather initiating events.

The team determined that this performance deficiency was not indicative of current plant

performance because it was the result of repair instructions written and implemented in

2006. Therefore, no cross-cutting aspect was assigned.

Enforcement: Technical Specification 5.4.1.a requires, in part, that written procedures

shall be established, implemented, and maintained covering the applicable procedures

recommended in Regulatory Guide 1.33, Revision 2, Appendix A, dated February 1978.

Paragraph 9.a of this appendix requires, in part, that maintenance that can affect the

performance of safety-related equipment should be properly pre-planned and performed

in accordance with written procedures appropriate to the circumstances. Contrary to the

above, on July 11, 2006, the licensee failed to properly plan and perform maintenance

that could affect the performance of safety-related equipment with written procedures

appropriate for the circumstance. Specifically, the inadequate instructions resulted in

maintenance technicians routing and restraining electrical cables inappropriately during

maintenance in July 2006, which later caused a failure of the train B emergency diesel

generator supply fan to start on demand. Because this finding is of very low safety

significance and was entered into the licensees corrective action program as

Callaway Action Request 201106905, this violation is being treated as a non-cited

violation consistent with Section 2.3.2 of the NRC Enforcement Policy:

NCV 05000483/2012008-02, Failure to provide adequate maintenance instructions.

c. Failure to Initiate a Corrective Action Document

Introduction. The team identified a non-cited violation of 10 CFR Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings, for the licensees failure, upon

discovery of an adverse condition, to initiate a Callaway Action Request, to notify the

shift manager, and to review the condition for, operability, functionality, and reportability

as required by APA-ZZ-00500, Corrective Action Program, revision 054.

- 15 -

Description. Emergency diesel generator tornado dampers are safety-related

components. They have an active safety function to automatically reposition during

tornado conditions to protect the emergency diesel generator. During the licensees

performance of Job 05514809.500, Lubricate and Inspect Damper GMD0004, on April

24, 2012, the as-found breakaway torque measurement for the train A emergency diesel

generator tornado dampers was 25.7 percent higher than the shop value. This

exceeded the vendor-recommended torque range of plus-or-minus 20 percent for a

properly functioning damper.

Procedure APA-ZZ-00500 Appendix 22, Corrective Action Program Definitions,

revision 007, includes in its definition of condition adverse to quality, a non-

conformance of safety-related equipment or the potential inability of safety-related

equipment to perform its safety function. In addition, APA-ZZ-00500 Appendix 22

defines adverse condition as an encompassing term that includes, among other

examples, a condition that could credibly impact nuclear safety, a condition not in

compliance with design specifications, or a condition adverse to quality.

Procedure APA-ZZ-00500, Corrective Action Program, revision 054, requires that any

individual discovering an adverse condition promptly initiate a CAR; promptly is defined

to be within the same shift. Further, when initiating a CAR for an equipment issue, APA-

ZZ-00500 requires the originator to notify the shift manager, and requires the shift

manager to review the condition for operability, functionality, and reportability.

On April 24, 2012, the as-found breakaway torque of the train A emergency diesel

generator tornado damper exceeded the vendor-recommended torque range. This

represented a non-conformance of safety-related equipment, in that it was not in

compliance with design specifications, and a potential inability of safety-related

equipment to perform its safety function. The identification of this adverse condition

required the initiation of a CAR, notification of the shift manager, and evaluation of the

condition by the shift manager. Upon discovery of this condition, the licensee failed to

initiate a CAR, notify the shift manager, or review the condition for operability,

functionality, or reportability.

On June 27, 2012, after identification of this condition by the team, licensee engineering

staff analyzed the as-found breakaway torque for the emergency diesel generator

tornado damper. This analysis determined that though the breakaway torque was

outside the acceptance band provided by the vendor, it was below the maximum

breakaway torque under which the dampers could successfully close against the

maximum differential pressure the ductwork is designed to withstand. The operations

department subsequently declared the train A emergency diesel generators operable

and performed an extent of condition review, determining the opposite train tornado

dampers to be operable as well. The licensee documented the teams concerns in CAR

201204571.

Analysis. The failure to satisfy the requirements of APA-ZZ-00500 upon identification of

high out-of-specification torque measurements on safety-related tornado dampers by

initiating a Callaway Action Request, informing the shift manager, and evaluating the

condition for operability, functionality, and reportability was a performance deficiency

related to the mitigating systems cornerstone. This performance deficiency was more

than minor because if left uncorrected, the licensees continued failure to conform to

- 16 -

APA-ZZ-00500 upon discovery of an adverse condition impacting the EDG tornado

protection system would have the potential to lead to a more significant safety concern.

Using Inspection Manual Chapter 0609.04, Phase 1 - Initial Screening and

Characterization of Findings, the team determined that the finding was of very low

safety significance (Green) because it did not result in the loss of the safety function of

any system or train and did not screen as potentially risk significant due to seismic,

flooding, or severe weather initiating events. This finding had a cross-cutting aspect in

the corrective action program component of the problem identification and resolution

cross-cutting area because the licensee failed to completely, accurately, and in a timely

manner identify and fully evaluate an issue potentially impacting nuclear safety (P.1(a)).

Enforcement. Title 10 of the Code of Federal Regulations, Part 50, Appendix B,

Criterion V, Instructions, Procedures, and Drawings, requires, in part, that activities

affecting quality shall be prescribed by documented instructions, procedures, or

drawings of a type appropriate to the circumstances and shall be accomplished in

accordance with these instructions, procedures, or drawings. Procedure APA-ZZ-00500,

Corrective Action Program, revision 54, required initiation of a Callaway Action

Request within the same shift as the identification of an adverse condition. Further,

APA-ZZ-00500 required that the shift manager be notified of all adverse conditions

affecting equipment and that the shift manager review the condition for operability,

functionality, and reportability.

Contrary to the above, from April 24, 2012 until June 26, 2012, licensee staff failed to

accomplish an activity affecting quality in accordance with documented procedures.

Specifically, the licensee failed to initiate a CAR within a shift after discovery of an

adverse condition, as required by APA-ZZ-00500, failed to notify the shift manager of an

adverse condition affecting plant equipment, and failed to evaluate the condition for

operability, functionality, and reportability. Because this finding is of very low safety

significance and was entered into the licensees corrective action program as Callaway

Action Request 201204571, the violation is being treated as a non-cited violation

consistent with Section 2.3.2 of the NRC Enforcement Policy: NCV 05000483/2012008-

03, Failure to initiate a corrective action document.

d. Failure to Implement Procedure Requirements

Introduction. The team identified a Green non-cited violation of 10 CFR Part 50,

Appendix B, Criterion V, Instructions, Procedures, and Drawings, for the licensees

failure to fully implement the requirements of its fluid leak management procedure. The

team identified two instances where the licensee had not hung a fluid leak management

tag on an active fluid leak and several examples of fluid leak management tags not

indicating whether individual leaks were monitored. Further, the team found that the

licensee did not always document leakage monitoring, making trending difficult.

Description. Procedure MDP-ZZ-LM001, Fluid Leak Management, revision 011, was

established by the licensee as its process for the timely identification, investigation, and

repair of fluid leaks in plant systems and components, including those involving nuclear

safety, fire hazards, spread of contamination, and equipment damage. For all

indications of leakage of non-boric-acid fluids (except in the reactor building), this

procedure directed that a Job be initiated and a fluid leak management tag be generated

and hung for monitoring and trending purposes. The procedure further directed that,

- 17 -

once repairs were accomplished, repaired leaks be monitored for two months to ensure

the leak was corrected. During walk-downs of safety-related plant equipment on June

27 and June 29, 2012, the team noted four examples of fluid leak indications that were

not being managed in accordance with this procedure:

Safety injection pump B (PEM01B) had multiple small oil leaks that appeared to

be coming from threaded fittings. No fluid leak management tag was hanging

and no Job had been initiated for evaluation and repair. The licensee stated that

recent repairs had been made to this piping and a previously hanging fluid leak

management tag had been removed upon completion of those repairs, prior to

the end of the two-month monitoring window required by procedure.

Fire protection valve KCV0084 had a packing leak with a catch device in place to

collect the leaking fluid. No fluid leak management tag was hanging, though the

licensee had initiated Job 12003073 to adjust the packing.

Component cooling water pump B (PEG01B) had water leaks from both pump

bearing housings and evidence of an oil leak in the pump skid. One fluid leak

management tag related to Job 06114561, to replace the pump bearing

housings, was hanging on the pump motor identifying an oil leak; other leaks

were not tracked.

Containment spray pump B (PEN01B) had a puddle of oil on top of the pump

flange, inside the motor housing. No fluid leak management tag was hanging

and no Job had been initiated to evaluate the source of the oil. The licensee

stated that the oil appears to be residual spill from oil changes on the motor in

December 2011. Job 12003518 was initiated to clean the oil; no Job was

initiated to confirm the source of the oil or to monitor for potential leakage.

In discussions with the team on June 29, 2012, an individual responsible for the

implementation of the fluid leak management program acknowledged some inconsistent

adherence to the fluid leak management program procedure by station personnel.

Further, though the team discussed the safety injection pump B oil leaks with the

licensee on June 29, 2012, the licensee did not document these leaks at the earliest

possible stages in accordance with MDP-ZZ-LM001 instructions. During follow-up

discussions on July 9, 2012, the team questioned why this leak had not yet been

documented. On July 11, 2012, the licensee initiated Job 12003542 and CAR

201204882 to evaluate and track the leak. The team concluded that the inconsistent

application of procedural requirements and inconsistent identification of the source of

leaks when fluid leak management tags were hung, indicated programmatic deficiencies

in the licensees process for identifying, investigating, and repairing fluid leaks.

The team further noted that in September 2011, the licensee completed a self-

assessment of its boric acid corrosion control program, which at the time was part of the

fluid leak management program. In its self-assessment, the licensee noted similar

weaknesses in implementation of the boric acid corrosion control program. The licensee

documented in CAR 201107657 that the extent of condition of these weaknesses

included both the boric acid corrosion control program and the fluid leak management

program for non-boric acid leaks. The licensee took corrective actions to address the

deficiencies in the boric acid corrosion control program, but did not address the fluid leak

management program deficiencies. On January 10, 2012, the licensee initiated CAR

201200272, recommending the development of a program-level procedure to govern

- 18 -

plant response to leakage. At the conclusion of this inspection, this CAR remained open

with no actions taken.

Analysis. The licensees failure to fully implement the requirements of its fluid leak

management procedure was a performance deficiency. The team determined that the

performance deficiency was more than minor because if left uncorrected, it had the

potential to become a more significant safety concern. Specifically, if the licensee

continued to fail to implement its fluid leak management procedure, leaks that adversely

affect safety-related equipment could go unmonitored, resulting in undetected equipment

degradation. Using Inspection Manual Chapter 0609.04, Phase 1 - Initial Screening

and Characterization of Findings, the team determined the finding to be of very low

safety significance (Green) because it did not result in the loss of the safety function of

any system or train and did not screen as potentially risk significant due to seismic,

flooding, or severe weather initiating events. The team determined that the finding had a

cross-cutting aspect in the corrective action program component of the problem

identification and resolution cross-cutting area because the licensee failed to fully

evaluate a problem such that the resolution addressed the causes and extent of

condition (P.1(c)).

Enforcement. Title 10 CFR 50, Appendix B, Criterion V, Instructions, Procedures, and

Drawings, requires in part that activities affecting quality be prescribed by documented

instructions, procedures, or drawings, and be accomplished in accordance with these

instructions, procedures, and drawings. Contrary to this requirement, on June 27, 2012,

the licensee failed to accomplish activities affecting quality in accordance with prescribed

instructions, procedures, and drawings. Specifically, the licensee failed to fully

implement the requirements of MDP-ZZ-LM001, Fluid Leak Management Program,

Revision 011, to identify, evaluate, document, mitigate, and monitor leakage from safety-

related structures, systems, and components. Because this finding was of very low

safety significance (Green) and was entered into the licensees corrective action

program as Callaway Action Request 201204929, the violation is being treated as a non-

cited violation consistent with Section 2.3.2 of the Enforcement Policy: NCV 05000483/2012008-04, Failure to fully implement fluid leak management program.

4OA6 Meetings

.1

Exit Meeting Summary

On July 13, 2012, the team presented the inspection results to Mr. Adam C. Heflin,

Senior Vice President and Chief Nuclear Officer, and other members of the licensee

staff. The licensee acknowledged the issues presented. The team noted that

proprietary information had been included electronically in the response to the initial

information request and that this information would be destroyed. The licensee

acknowledged that other proprietary information that the team reviewed had been

returned.

.2

Other Management Meetings

On August 1, 2012, August 21, 2012, and September 11. 2012, Mr. Scott Maglio and

other licensee personnel discussed NCV 05000483/2012008-04 with the team lead and

the Branch Chief, Technical Support Branch. Licensee management reiterated its

position that the Fluid Leak Management program was being fully implemented. The

- 19 -

team acknowledged and considered the licensees position and discussed it with NRR

Program Office personnel, but for the reasons listed in Section 4OA5.5.d above, did not

agree.

ATTACHMENTS:

1. Supplemental Information

2. Information Request

3. Supplemental Information Request

Attachment 1

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

F. Bianco, Assistant Operations Manager (Support)

M. Daly, Corrective Action Program Supervisor

M. Dunbar, Manager, Maintenance (Acting)

S. Edwards, Employee Concerns Manager

S. Enloe, Mechanical Maintenance Technician

T. Fugate, Manager, Maintenance

S. Maglio, Regulatory Affairs Manager

B. Miller, Performance Improvement Manager (Acting)

H. Osborn, Regulatory Affairs Specialist

D. Rickard, Root Cause Coordinator

L. Sandbothe, Manager Plant Support

A. Schnitz, Engineer, Regulatory Affairs

NRC personnel

D. Powers, Senior Technical Advisor, Technical Support Branch

LIST OF ITEMS OPENED, CLOSED AND DISCUSSED

Opened and Closed 05000483/2012008-01

NCV

Failure to identify and correct the failure mode of an

essential service water pump (Section 4OA2.5.a)05000483/2012008-02

NCV

Failure to provide adequate maintenance instructions

(Section 4OA2.5.b)05000483/2012008-03

NCV

Failure to initiate a corrective action document (Section

4OA2.5.c)05000483/2012008-04

NCV

Failure to fully implement fluid leak management program

(Section 4OA2.5.d)

Discussed

None

LIST OF DOCUMENTS REVIEWED

CALLAWAY ACTION REQUESTS (CARS)

200409580

200901515

201005401

201102588

201107460

201201587

201203507

200700100

200901831

201005616

201103219

201107657

201201652

201203559

200701415

200903102

201005654

201104132

201107679

201201712

201203562

200702872

200903204

201006376

201104403

201107759

201201790

201203576

200703247

200905171

201007711

201104475

201107761

201201851

201203586

200703260

200906859

201008001

201104654

201107762

201202058

201203593

200703313

200908108

201008153

201104707

201107763

201202157

201203637

200703331

200908133

201008230

201104775

201108091

201202169

201203709

200705117

200908262

201009423

201104836

201108586

201202224

201203767

200705410

200909091

201009719

201105121

201108775

201202273

201204094

200706042

200909120

201009922

201105137

201109194

201202333

201204467

200706307

200909455

201010145

201105210

201109257

201202340

201204482

200706804

200909951

201010266

201105273

201109259

201202561

201204529

200706892

200910153

201010432

201105282

201109441

201202632

201204542

200707394

201001515

201010472

201105331

201109490

201202717

201204548

200709539

201001529

201010530

201105365

201109521

201202909

201204571

200709540

201002281

201010634

201105477

201109562

201202922

201204586

200711788

201002456

201010635

201105534

201109569

201203103

201204692

200800175

201002599

201011161

201105601

201109621

201203140

201204702

200801069

201002675

201011278

201105700

201109732

201203144

201204777

200801146

201002916

201100526

201105727

201109894

201203223

201204803

200801270

201003236

201101042

201105768

201109948

201203232

201204805

200804103

201003472

201101192

201105831

201110797

201203319

201204882

200804164

201003813

201101583

201105861

201110845

201203347

201204885

200804337

201004071

201101755

201105886

201110929

201203434

201204890

200805586

201004250

201101769

201105927

201200272

201203453

201204896

200810335

201004294

201101835

201105965

201200336

201203469

201206157

200810902

201004687

201102064

201106369

201200577

201203484

200812985

201005233

201102129

201106551

201200905

201203501

200900986

201005328

201102329

201106905

201201245

201203502

JOBS

11003848

11004803

11006688

PROCEDURES

NUMBER

TITLE

REVISION

APA-ZZ-00101

Processing Procedures, Manuals, and Desktop

Instructions

061

APA-ZZ-00101 App. D

Manuals, Desktop Instructions, Handbooks, Forms

and Policies

011

APA-ZZ-00107

Review of Current Industry Operating Experience

015

APA-ZZ-00203

Forms Management

013

APA-ZZ-00303

Classification of Systems

013

APA-ZZ-00303 App. 1

Callaway Director Plant System Classification Data

010

APA-ZZ-00304

Control of Callaway Equipment List

035

APA-ZZ-00500

Corrective Action Program

054

APA-ZZ-00500 App. 1

Operability and Functionality Determinations

017

APA-ZZ-00500 App. 10

Trending Program

005

APA-ZZ-00500 App. 11

Regulatory Issue Summary 2005-20 Degraded and

Nonconforming Condition Resolution

006

APA-ZZ-00500 App. 12

Significant Adverse Condition - Significance Level 1

014

APA-ZZ-00500 App. 13

Adverse Condition - Significance Level 2

014

APA-ZZ-00500 App. 14

Adverse Condition - Significance Level 3

012

APA-ZZ-00500 App. 15

Adverse Condition - Significance Level 4

012

APA-ZZ-00500 App. 16

Adverse Condition - Significance Level 5

009

APA-ZZ-00500 App. 17

Screening Process Guidelines

014

APA-ZZ-00500 App. 18

Equipment Performance Evaluation

006

APA-ZZ-00500 App. 2

Non-Conforming Materials Report (NMR)

012

APA-ZZ-00500 App. 21

Other Issues - Significance Level 6

012

APA-ZZ-00500 App. 3

Past Operability & Reportability Evaluations (REPO)

014

APA-ZZ-00500 App. 5

Maintenance Rule (MR)

012

APA-ZZ-00500 App. 7

Effectiveness Reviews

009

APA-ZZ-00500 App. 9

Mitigating Systems Performance Index (MSPI)

004

NUMBER

TITLE

REVISION

APA-ZZ-00542

Event Review and Post Transient Evaluation

016

APA-ZZ-00542 App. 1

Event Review Team

011

APA-ZZ-00605

Temporary System Modifications

028

APA-ZZ-00905

Limitation of Callaway Plant Staff Working Hours

15

APA-ZZ-00911

Fatigue Management

2

APA-ZZ-00930

Employee Concerns Program

014

APA-ZZ-00932

Nuclear Safety Culture Monitoring

000

APA-ZZ-01400

Performance Improvement Program

013

APA-ZZ-01400 App. A

Callaway Self-Assessment and Benchmarking

Program

014

APA-ZZ-01400 App. E

Operating Experience

010

APA-ZZ-01400 App. H

Performance Review Group

013

APA-ZZ-01400 App. N

006

EDP-ZZ-04100

Review, Planning, Implementation & Closure Of

Modification Packages

022

EDP-ZZ-06000

Vendor Equipment Technical Information Review

Program

017

GDP-ZZ-01810

Nuclear Oversight Assessment Coverage

044

ITL-KJ-00P24

LOOP-PRESS; Diesel Engine (KKJ01A) Crankcase

Exit Pressure

4

ITP-KJ-00001

Emergency DG A Trip Checks

8

LDP-ZZ-00500

Corrective Action Review Board

021

MDP-ZZ-LM001

Fluid Leak Management Program

011

MDP-ZZ-TR001

Planning and Execution of Troubleshooting Activities 007

MDP-ZZ-TR001

Planning and Execution of Troubleshooting Activities 009

MPE-ZZ-QY210

Emergency Diesel Generator NE01 and NE02

Protective Relay Inspection, Test and Calibration

6

MSE-NB-QY002

Operational Test Sequence of 4.16KV Diesel

Generator NE01 Air Circuit Breaker 152NB0111

11

ODP-ZZ-00001

Operations Department - Code of Conduct

076

ODP-ZZ-00001 Add. 04

Operating Experience

002

ODP-ZZ-00001 Add. 11

Control Room Decorum

011

OTHER

NUMBER

TITLE

REVISION

1Q11 Quarterly Trend Report Attachment 1

5/17/2011

1Q12 Quarterly Trend Report Attachment 1

4/24/2012

2Q11 Quarterly Trend Report Attachment 1

8/23/2011

3Q11 Quarterly Trend Report Attachment 1

11/29/2011

4Q11 Quarterly Trend Report Attachment 1

2/17/2012

Brochure: Employee Concerns Program

08/24/11

Callaway Procedure Writers Manual

012

Nuclear Safety Culture Assessment

Operating Quality Assurance Manual (OQAM)

028c

Plant Status Control Events List

Surveillance Report SP12-010

5/31/2012

Surveillance Report SP12-011

6/18/2012

Surveillance Report SP12-013

6/22/2012

201200167-05

Employee Concerns Program Self-Assessment

AP11-001

Radiation Protection Audit

1/4/2011

AP11-002

Operations Audit

4/28/2011

AP11-003

Information Management Audit

3/15/2011

AP11-004

Operations Training Audit

6/13/2011

AP11-005

Access Authorization Audit

8/11/2011

AP11-006

Maintenance Audit

8/24/2011

AP11-007

Independent Quality Program Audit

8/2/2011

AP11-008

Emergency Preparedness Audit

8/15/2011

AP11-009

Corrective Action Program Audit

11/5/2011

AP12-001

Material Services Audit

3/6/2012

AP12-002

Configuration Management Audit

3/28/2012

AP12-003

Fire Protection Program Audit

5/7/2012

POL0017

Safety Conscious Work Environment Policy

007

POL0048

Executive Review Board Policy

004

SP12-007

Functional Area Performance Assessment Report for

March 1 to March 15, 2012

3/29/12

NUMBER

TITLE

REVISION

SP12-008

Functional Area Performance Assessment Report for

February 23 to March 31, 2012

4/29/12

SP12-010

Functional Area Performance Assessment Report for

April 15 to 30, 2012

4/31/12

T51.0092 6

Safety Conscious Work Environment and Managing

Protected Employees- training slide presentation

05/31/2012

TM 08-0004

Temporary Modification Request and Authorization

11/3/2008

TM 09-0002

Temporary Modification Request and Authorization

2/6/2009

Attachment 2

Information Request

May 4, 2012

Biennial Problem Identification and Resolution Inspection

June 25 - July 13, 2012

Callaway Plant

Inspection Report 50-483/2012-008

This inspection will cover the period from October 18, 2010 to July 13, 2012. All requested

information should be limited to this period or to the date of this request unless otherwise

specified. To the extent possible, the requested information should be provided electronically in

Adobe PDF or Microsoft Office format. Lists of documents should be provided in Microsoft

Excel or a similar sortable format.

Please provide the following no later than June 1, 2012:

1.

Document Lists

Note: For these summary lists, please include the document/reference number, the

document title, initiation date, current status, and long-text description of the issue.

a.

Summary list of all corrective action documents related to significant conditions

adverse to quality that were opened, closed, or evaluated during the period

b.

Summary list of all corrective action documents related to conditions adverse to

quality that were opened or closed during the period

c.

Summary lists of all corrective action documents which were upgraded or

downgraded in priority/significance during the period

d.

Summary list of all corrective action documents that subsume or roll up one or

more smaller issues for the period

e.

Summary lists of operator workarounds, engineering review requests and/or

operability evaluations, temporary modifications, and control room and safety

system deficiencies opened, closed, or evaluated during the period

f.

Summary list of plant safety issues raised or addressed by the Employee

Concerns Program (or equivalent)

g.

Summary list of all Apparent Cause Evaluations completed during the period

h.

Summary list of all Root Cause Evaluations planned or in progress but not

complete at the end of the period

2.

Full Documents with Attachments

a.

Root Cause Evaluations completed during the period

b.

Quality assurance audits performed during the period

c.

All audits/surveillances performed during the period of the Corrective Action

Program, of individual corrective actions, and of cause evaluations

d.

Corrective action activity reports, functional area self-assessments, and non-

NRC third party assessments completed during the period (do not include INPO

assessments)

e.

Corrective action documents generated during the period for the following:

i.

All Cited and Non-Cited Violations issued to Callaway Plant

ii.

All Licensee Event Reports issued by Callaway Plant

f.

Corrective action documents generated for the following, if they were determined

to be applicable to Callaway Plant (for those that were evaluated but determined

not to be applicable, provide a summary list):

i.

NRC Information Notices, Bulletins, and Generic Letters issued or

evaluated during the period

ii.

Part 21 reports issued or evaluated during the period

iii.

Vendor safety information letters (or equivalent) issued or evaluated

during the period

iv.

Other external events and/or Operating Experience evaluated for

applicability during the period

g.

Corrective action documents generated for the following:

i.

Emergency planning drills and tabletop exercises performed during the

period

ii.

Maintenance preventable functional failures which occurred or were

evaluated during the period

iii.

Adverse trends in equipment, processes, procedures, or programs which

were evaluated during the period

iv.

Action items generated or addressed by plant safety review committees

during the period

3.

Logs and Reports

a.

Corrective action performance trending/tracking information generated during the

period and broken down by functional organization

b.

Corrective action effectiveness review reports generated during the period

c.

Current system health reports or similar information

d.

Radiation protection event logs during the period

e.

Security event logs and security incidents during the period (sensitive information

can be provided by hard copy during first week on site)

f.

Employee Concern Program (or equivalent) logs (sensitive information can be

provided by hard copy during first week on site)

g.

List of Training deficiencies, requests for training improvements, and simulator

deficiencies for the period

4.

Procedures

a.

Corrective action program procedures, to include initiation and evaluation

procedures, operability determination procedures, apparent and root cause

evaluation/determination procedures, and any other procedures which implement

the corrective action program at Callaway Plant

b.

Quality Assurance program procedures

c.

Employee Concerns Program (or equivalent) procedures

d.

Procedures which implement/maintain a Safety Conscious Work Environment

5.

Other

a.

List of risk significant components and systems

b.

Organization charts for plant staff and long-term/permanent contractors

Note: Corrective action documents refers to condition reports, notifications, action requests,

cause evaluations, and/or other similar documents, as applicable to Callaway Plant.

All requested documents should be provided electronically. Regardless of whether they are

uploaded to an internet-based file library (e.g., Certrecs IMS), please provide copies on CD or

DVD. Four copies of the CD or DVD should be sent to the team lead at the following address,

to arrive no later than June 1, 2012:

Eric A. Ruesch

U.S. NRC Region IV

1600 East Lamar Blvd.

Arlington, TX 76011-4511

Attachment 3

Supplemental Information Request

June 21, 2012

Biennial Problem Identification and Resolution Inspection

June 25 - July 13, 2012

Callaway Plant

Inspection Report 50-483/2012-008

This request supplements the original information request. Where possible, the information

should be available to the inspection team immediately following the entrance meeting. This

inspection will cover the period from October 18, 2010 to July 13, 2012. All requested

information should be limited to this period unless otherwise specified.

Please provide the following:

1. Electronic copies of the FSAR, technical specifications, and technical specification bases

2. For each week the team is on site,

Planned work/maintenance schedule for the station

Schedule of management or corrective action review meetings (e.g., CARB,

MRM, CAR screening meetings, etc.)

Agendas for these meetings

3. As part of the inspection, the team will do a five-year in-depth review of emergency

diesel generator issues and corrective actions. The following documents are to support

this review (electronic format preferred):

Copies of upper and lower tier cause evaluations performed on emergency diesel

generators and alternate emergency diesel generators within the last 5 years

List of all surveillances run on the emergency diesel generators within the last

five years, sortable by individual diesel generator and including acceptance

criteria

List of all corrective maintenance work orders performed on the emergency

diesel generators and alternate emergency diesel generators within the last

5 years

List of maintenance rule functional failure assessmentsregardless of the

resultperformed on the emergency diesel generators and alternate emergency

diesel generators within the last 5 years

System training manual for emergency diesel generators and alternate

emergency diesel generators

4. The team will also review the stations implementation of the fatigue rule. These

documents support this review:

List of all fatigue assessments performed during the inspection period separated

by department

List of all work hour rule waivers and violations during the inspection period

separated by department

Fatigue rule implementing procedures

5. Specific documents:

Conduct of Operations procedure

APA-ZZ-00605 Temporary Modifications

APA-ZZ-00107 OE Review

APA-ZZ-00520, Reporting Requirements and Responsibilities

APA-ZZ-00152, Emergent Issue Response

Job 10006321

Job 10006322

Job 10007548

Job 10007549

HI 2007013

CA2847 Long Term Corrective Action (LTCA) Request Form

Callaway Action Requests (CARs):

o 201107759

o 201107761

o 201107762

o 201003813

o 201105331

o 201105768

o 201105273

Temporary modification packages:

o 08-0004

o 09-0001

o 09-0002

o 09-0072

o 10-0003

o 10-0004

o 10-0007

o 10-0008