MONTHYEARW3F1-2011-0061, Commitment to Provide 10 CFR 50.48(c) License Amendment Request and Request for Continued Enforcement Discretion2011-07-26026 July 2011 Commitment to Provide 10 CFR 50.48(c) License Amendment Request and Request for Continued Enforcement Discretion Project stage: Request ML1120916372011-07-28028 July 2011 Biweekly Notice - Applications and Amendments to Facility Operating Licenses Involving No Significant Hazards Considerations Project stage: Other W3F1-2011-0074, License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)2011-11-17017 November 2011 License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition) Project stage: Request ML1200304302012-01-0303 January 2012 Email PRA Peer Review Report Project stage: Other ML1200304372012-01-0303 January 2012 Fpra Pr Position Paper Final Project stage: Other ML1201205332012-01-12012 January 2012 Email, Supplemental Information Needed for Acceptance of Requested Licensing Action, License Amendment Request to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light-Water Reactor Generating Plants Project stage: Acceptance Review W3F1-2012-0005, Supplemental Information in Support of the NRC Acceptance Review of Waterford 3 License Amendment Request to Adopt NFPA 8052012-01-26026 January 2012 Supplemental Information in Support of the NRC Acceptance Review of Waterford 3 License Amendment Request to Adopt NFPA 805 Project stage: Supplement ML1203401282012-02-0303 February 2012 Acceptance Review Email, License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Acceptance Review ML1203802572012-03-0909 March 2012 Request to Reinstate Enforcement Discretion License Amendment Request to Adopt NFPA Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Other ML1208704852012-04-0303 April 2012 Regulatory Audit Scheduled to Begin 5/7/2012 in Support of the License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Other ML12185A2122012-07-18018 July 2012 Request for Additional Information, License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: RAI ML12275A0132012-09-27027 September 2012 Application for Order Approving Transfers of Licenses and Conforming License and ESP Amendments Project stage: Request W3F1-2012-0064, Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request2012-09-27027 September 2012 Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request Project stage: Response to RAI W3F1-2012-0083, 90-Day Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 8052012-10-16016 October 2012 90-Day Response to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 Project stage: Response to RAI ML13072A0632013-03-22022 March 2013 Request for Additional Information, Round 2, License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: RAI ML13129A1502013-05-10010 May 2013 Request for Supplement of Review Schedule and Interim Milestones, License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Other ML13157A0622013-06-26026 June 2013 Request for Additional Information, Round 3, License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: RAI W3F1-2013-0048, Supplement to NFPA 805 License Amendment Request (LAR)2013-12-18018 December 2013 Supplement to NFPA 805 License Amendment Request (LAR) Project stage: Supplement ML14023A2792014-01-23023 January 2014 Notice of Meeting with Entergy Operations, Inc., to Discuss Waterford Unit 3 License Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Meeting PMNS20140175, Notice of Meeting with Entergy Operations, Inc., to Discuss Its National Fire Protection Association (NFPA) 805 License Amendment Request Supplement Changes for the Waterford Steam Electric Station, Unit 32014-01-24024 January 2014 Notice of Meeting with Entergy Operations, Inc., to Discuss Its National Fire Protection Association (NFPA) 805 License Amendment Request Supplement Changes for the Waterford Steam Electric Station, Unit 3 Project stage: Meeting W3F1-2014-0025, Updated Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR)2014-06-11011 June 2014 Updated Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Project stage: Response to RAI ML14232A0262014-09-15015 September 2014 Continuation of Enforcement Discretion, License Amendment Request to Adopt NFPA Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Other ML14350A2122014-12-22022 December 2014 Regulatory Audit Plan; January 12-14, 2015 Audit in Support of the Amendment Request to Adopt NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 Edition Project stage: Other ML15022A2392015-02-0606 February 2015 Request for Additional Information- National Fire Protection Association Standard NFPA 805 Project stage: RAI W3F1-2015-0015, Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request2015-03-12012 March 2015 Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request Project stage: Response to RAI W3F1-2015-0024, Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR)2015-04-10010 April 2015 Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Project stage: Response to RAI W3F1-2015-0025, Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Waterford Steam Electric Station, Unit 3 (Waterford 3)2015-05-14014 May 2015 Responses to Request for Additional Information Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Waterford Steam Electric Station, Unit 3 (Waterford 3) Project stage: Response to RAI ML15182A3462015-07-13013 July 2015 Request for Additional Information - National Fire Protection Association Standard NFPA 805 Project stage: RAI ML15197A2292015-07-21021 July 2015 Request for Additional Information Regarding National Fire Protection Association Standard 805 Project stage: RAI ML15239A7392015-08-31031 August 2015 Summary of Public Meeting with Entergy Operations, Inc. to Discuss Main Control Room Abandonment Regarding NFPA-805 License Amendment Request Project stage: Meeting W3F1-2015-0078, Revised Implementation Item Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR)2015-09-24024 September 2015 Revised Implementation Item Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Project stage: Request W3F1-2015-0081, Request for Additional Information (RAI) Clarification Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR)2015-10-13013 October 2015 Request for Additional Information (RAI) Clarification Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Project stage: Request W3F1-2015-0085, Transfer of License and Conforming Amendment2015-10-29029 October 2015 Transfer of License and Conforming Amendment Project stage: Other W3F1-2016-0003, Revised Licensing Actions and Implementation Items Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR)2016-01-18018 January 2016 Revised Licensing Actions and Implementation Items Regarding Adoption of National Fire Protection Association Standard NFPA 805 License Amendment Request (LAR) Project stage: Request 2013-06-26
[Table View] |
Text
From:
Kalyanam, Kaly Sent:
Friday, February 03, 2012 10:15 AM To:
STEELMAN, WILLIAM J Cc:
BENNETT, STEVE A
Subject:
Acceptance Review Report for ME7602 DATE: FEBRUARY 3, 2012 TO: WILLIAM STEELMAN
SUBJECT:
WATERFORD STEAM ELECTRIC STATION, UNIT 3 - ACCEPTANCE REVIEW REPORT FOR LICENSE AMENDMENT REQUEST TO ADOPT NFPA-805, PERFORMANCE-BASED STANDARD FOR FIRE PROTECTION FOR LIGHT WATER REACTOR GENERATION STATION (2001 EDITION. (TAC NO. ME7602).
DOCKET NO. 50-382 LICENSE NO. NPF-38
Dear Mr. Steelman:
By letter dated November 17, 2011, (Agencywide Documents Access and Management System (ADAMS) Accession No. ML113220230, (portions of Enclosure 1 that contain Security-Related Information withheld under Section 2.390 of Title 10 of the Code of Federal Regulations (CFR))), as supplemented by letter dated January 26, 2012 (ADAMS Accession No. ML12027A049), Entergy Operations Inc. (the licensee),
requested the U.S. Nuclear Regulatory Commission (NRC) staffs approval of an amendment to the Waterford Steam Electric Station, Unit 3.
The proposed License Amendment Request would permit the licensee to adopt NFPA-805, Performance-Based Standard for Fire Protection for Light Water Reactor Generation Station (2001 Edition). This fire protection licensing basis complies with the requirements of 10 CFR 50.48(a) and (c). and the guidance in Revision 1 of Regulatory Guide 1.205, Risk Informed Performance-Based Fire Protection for Existing Light-Water Nuclear Power Plants.
The purpose of this letter is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staff=s acceptance review of this amendment request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with of 10 CFR 50.90, an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required. This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the staff to proceed with its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. If additional information is needed for the staff to complete its technical review, you will be advised by separate correspondence.
If you have any questions, please contact the undersigned, at (301) 415-1480.
Kaly N. Kalyanam Project Manager, ANO-1 and 2; Waterford 3 NRR/DORL/LPL4 Email: kaly.kalyanam@nrc.gov