ML120030321
ML120030321 | |
Person / Time | |
---|---|
Site: | LaSalle |
Issue date: | 01/19/2012 |
From: | Nicholas Difrancesco Plant Licensing Branch III |
To: | Exelon Generation Co |
DiFrancesco N, NRR/DORL/LPL3-2, 415-1115 | |
Shared Package | |
ml120030332 | List: |
References | |
TAC ME7496, TAC ME7495 | |
Download: ML120030321 (25) | |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 January 19, 2012 LICENSEE: Exelon Generation Company, LLC FACILITY: LaSalle County Station, Units 1 and 2
SUBJECT:
SUMMARY
OF DECEMBER 7, 2011, PUBLIC MEETING WITH EXELON GENERATION COMPANY, LLC REGARDING THE PROPOSED EXTENDED POWER UPRATE LICENSE AMENDMENT REQUEST FOR LASALLE COUNTY STATION, UNITS 1 AND 2 (TAC NOS. ME7495 AND ME7496)
On December 7, 2011, a Category 1 public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Exelon Generation Company, LLC (EGC, the licensee) at the NRC Headquarters, Two White Flint North, 11545 Rockville Pike, Rockville, Maryland. The purpose of the meeting was to discuss a planned Extended Power Uprate (EPU) licensee amendment request (LAR) for LaSalle County Station, Units 1 and 2 (LaSalle). A list of attendees is provided as Enclosure 1.
During the meeting, EGC informed the NRR staff of their plans to submit a LAR for a 12.5 percent increase in licensed thermal power for LaSalle in the 3rd Quarter of 2012. The meeting discussion focused on review standards for annulus pressurization loads and emergency core cooling system (ECCS) net positive suction head (NPSH) analysis. The licensee presented slides contained in Enclosure 2 and discussed a pre-application checklist enclosed in the public meeting notice (Agencywide Documents Access and Management System (ADAMS) Accession No. ML113200075).
The meeting piloted the use of the Nuclear Energy Institute (NEI) developed pre-application checklist. The purpose of the pre-application meeting using the NEI checklist is for NRC staff and the licensees to reach common understanding of the regulatory criteria and standards to be applied in the review of significant licensing actions with a goal of enhancing the effectiveness and efficiency of the review process. A series of LaSalle EPU pre-application meetings are being planned for additional technical area topics. During each subsequent pre-application meeting, the NEI checklist will be used to support discussions. Additional information about the NEI checklist pilot process may be found in public meeting summary from November 2, 2011 (ADAMS Accession No. ML113210594).
The following actions were agreed to between the NRC and the EGC prior to submission of the LaSalle EPU LAR.
Summary of Follow-up Actions
- EGC and the NRC achieved an understanding of the methodology being proposed for use for determination of break Mass and Energy release and annulus pressurization calculations. The NRC acknowledged that the use of the Transient Reactor Analysis Code - G (TRACG) methodology was an acceptable approach.
- The TRACG evaluation for use in break Mass and Energy release and annulus pressurization calculations should also have a description identifying the differences in application of TRACG at LaSalle compared to its application in the economic simplified boiling-water reactor safety analysis and Grand Gulf's EPU application. EGC agreed to
- 2 provide a summary of the differences along with a justification for use of the methodology in the EPU application.
- Based on recent Advisory Committee on Reactor Safeguards comments associated with the use of American National Standards Institute and American Nuclear Society (ANSIIANS) 58.2-1988 for evaluating jet impingement loads, the NRC staff noted that the use of this standard as it applies to the proposed EPU may be inappropriate. The NRC staff also noted that ANSIIANS 58.2-1988 is a withdrawn standard.
- EGC and the NRC achieved an understanding regarding the proposed methodology used to determine the ECCS NPSH. EGC's approach and use of current guidance was considered to be acceptable.
- Agreement was achieved regarding the use of 21 percent uncertainty when performing EPU ECCS NPSH calculations. It was noted that the uncertainty value may be impacted by Boiling-Water Reactor Owner's Group (BWROG) evaluations currently underway for non-containment accident pressure plants. Also, there may be an elimination of the "Maximum Erosion Zone" requirement. EGC agreed to address any final results of the BWROG evaluation prior to submittal in the application.
- EGC and the NRC achieved an understanding that the EPU application would address mixed core analysis or provide justification for excluding.
The meeting notice and agenda are available under ADAMS Accession No. ML113200075.
The public was invited to observe the meeting. No members of the public were in attendance.
Public Meeting Feedback forms were not received.
Please direct any inquiries to me at 301-415-1115, or Nicholas.DiFrancesco@nrc.gov.
Sincerely, ~
~LJ~~
Nicholas DiFrancesco, Project Manager Plant licenSing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374
Enclosures:
- 1. List of Attendees
- 2. Licensee Handout cc w/encl: Distribution via ListServ
LIST OF ATTENDEES DECEMBER 7,2011, PUBLIC MEETING WITH EXELON GENERATION COMPANY, LLC REGARDING THE PROPOSED EXTENDED POWER UPRATE LICENSE AMENDMENT REQUEST FOR LASALLE COUNTY STATION, UNITS 1 AND 2 NRC Jake Zimmerman Exelon Nicholas DiFrancesco Kenneth Ainger Araceli T. Billoch Colon Kevin Borton William Jessup John Rommel John Huang Harold Vinyard Ogbonna Hopkins Tim Byam John Tsao Vikram Shah Tom Alexion Terry Simpkin Sheldon Stuchell Faramarz Pournia Greg Casto Stevie Du Pont Rick Plasse Rick Stattel David Rahn GE-Hitachi TaiHuang Curt Robert Ahsan Sallman Bruce Hagemeier Tony Ulses Sara Ruddy Garry Armstrong Muhammad Razzaque Nageswara Karipineni Enclosure 1
Exelon Nuclear LaSalle County Station Pre-Application Meeting Extended Power Uprate December 7, 2011 F,nclosure 2
Introductions
Exelon Team
- Kenneth Ainger - Project Management Director, EPU
- Kevin Borton - Power Uprate Licensing Manager
- John Rommel - Power Uprate Engineering Director
- Harold Vinyard - LaSalle Engineering Director
- Tim Byam - Power Uprate Lead Licensing Engineer
- Vikram Shah - Power Uprate Senior Engineering
. Manager
- Terry Simpkin - LaSalle Regulatory Assurance Manager
- Faramarz Pournia - Power Uprate Project Manager
- Stevie Du Pont - Power Uprate Licensing Engineer Exelon0 Nuclear
Agenda and Meeting Purpose
- Introduce LaSalle EPU Staff
- Describe NEI Pre-Submittal Meeting Pilot
- Present LaSalle Extended Power Uprate Schedule and Approach
- Describe Key Aspects of Technical Evaluations and Obtain Feedback
- Annulus Pressurization Loads
- Discuss Potential Topics for Future Meetings Exelon@
Nuclear
NEI Pilot - Pre-submittal Meetings
- Purpose is to enhance License Amendment Request pre-submittal meetings
- Reach a common understanding on the regulatory criteria and standards to be applied during the NRC review of the proposed changes
- Identify potential application issues that can be addressed during the application conceptual phase that will reduce acceptance review time, requests for additional information, and application review time
- Process
- Pilot Checklist is used to focus on applicable review criteria, codes, standards, justification required for use of a new analytical method, applicability of a precedent, or feasibility of a desired schedule in order to reach alignment with the NRC
- NRC meeting notice and meeting summary will docket the expectations and outcomes of the alignment in order to greatly reduce the risk and uncertainty associated with future application acceptance and NRC review
- LaSalle specific checklist focus
- Verify methodology and approach used for analyses of Annulus Pressurization Load
=
Background===
- LaSalle Original License
- Unit 1 licensed 19821 Unit 2 licensed 1983
- Original Licensed Thermal Power (OLTP) of 3323 MWt per unit
- LaSalle Previous Uprates
- Stretch Power Uprate of 50/0 in 2000 to 3489 MWt
- MUR Uprate of 1.6% in 2010 to 3546 MWt
- Current Licensed Thermal Power (CL TP) of 3546 MWt
- Projected Power Uprate level of 3988 MWt (increase -12.5% of current licensed power or 120% of original licensed power)
Exelon Nuclear
Schedule Overview NRC Communication Schedule
- 2nd Pre-Submittal Meeting: Target February 2012
- 3rd Pre-Submittal Meeting: Target April 2012
- Final Pre-Submittal Meeting: Target June 2012 EPU Implementation Schedule
- Submit LAR: Target 3rd QTR 2012
- Unit 2 Implementation: 2nd QTR 2015 (Outage L2R15)
- Unit 1 Implementation: 1st QTR 2016 (Outage L 1 R16)
Steam Dryer Evaluation could impact above schedule Exelon Nuclear
- LAR will meet criteria in NRC RS-001, "Review Standard for Extended Power Uprates"
- Evaluations supporting the LAR were performed using Constant Pressure Power Uprate (CPPU) Licensing Topical Report (NEDC 33004P-A) (commonly called CLTR)
- Fuel related evaluations were performed to the guidance in NRC-approved NEDC-32424P-A (commonly called ELTR1)
- Safety issues identified in EL TR1 that should be addressed in a plant-specific EPU license amendment request are addressed in the LaSalle Specific Power Uprate Safety Analysis Report (PUSAR) (NEDC-33603P)
- For generically evaluated issues - the PUSAR references the NRC-approved generic evaluations in either ELTR1 or ELTR2 (NEDC-32523P-A)
- No Submittals Linked to Proposed EPU Submittal
- Incorporated Past RAls Exelon Nuclear
EPU LAR Approach Exelon's submittal will include
- Cover Letter and Amendment Request
- Attachments
- Description/Evaluation of Proposed Changes including No Significant Hazards Consideration
- Markup of Operating License and Technical Specifications
- Markup of Technical Specifications Bases and Technical Requirements Manual (Information Only)
- Power Uprate Safety Analysis Report (PUSAR) (non- proprietary, proprietary, and affidavit)
- Regulatory Commitments
- Supplemental Environmental Report
- List of Modifications
- EPU Startup Test Plan
- Grid Stability Study
- PRA Report
- Flow Induced Vibration (FIV) Piping and Component Evaluation
- Instrument Setpoint Calculations Affected by EPU
- Steam Dryer Evaluation (High Cycle Fatigue Report) (non-proprietary, proprietary, and affidavit)
Exelon@
Nuclear
-- t/)
t/)
-co~
c:
<< t/)
-c co o -'=
..J CO c: -'=
o CO tJ)
E s
N
~
- l t/)
t/)
~
Q) s-a.
t/)
- l
Annulus Pressurization (AP) Loads Analysis Purpose
- Verify methodology and approach used for analyses of Annulus Pressurization Load
- Perform the EPU break mass and energy release (M&E) and pressurization calculations for the annulus pressurization using the GEH TRACG computer code
- TRACG based M&E release methodology for the AP loads will address GEH corrective action of the Safety Communication SC09-01 Methodology
- Current CLTP Methodology
- NEDO-24548, Annulus Pressurization Load Adequacy Evaluation
- Computer Code: RELAP41 MOD 3
- EPU Methodology
- NEDE-32176P, Revision 4, TRACG Model Description
- NEDE-32177P, Revision 3, TRACG Qualification
- NEDE-33083P-A, TRACG Application for ESBWR, October 2005
- NEDE-33440P, Revision 2, TRACG ESBWR Safety Analysis - Additional Information, March 2010
- Computer Code: TRACG V.04
Annulus Pressurization (AP) Load~ Analysis Overview
~
High line com
~T~'----- "",.,','.,.. ".-,--.----..- ..-.. ".. . ,..,'.. --,
I~~-----r========'-
~20
~ 15
~ 10t----/
u:
I
'on :: I~::
n I"
i
'" 10E.()3 1.0E.Q2 1.OE-01 tOE+OO 1.0E+01 'i ~ ~ r;'a,,;~ r;' '\ ;; ,,:,..
Tlmo (Me; e..., ~qu .,,""" ,**fO)"01~ :!
"I.--..;, *X Mass I energy Annulus pressure Displacements, Piping and release vs. time vs. time accel erations, component forces, stresses, loads, stress, moments and fatigue, and response spectra accelerations Exelon Nuclear
Annulus Pressurization Loads Analysis Methods Comparison
'cltP***Method Mass and Energy Release Generic NEDO- TRACG 04 Note 1 24648 Annulus Pressurization Loads RELAP4IMOD 3 TRACG 04 Note 2 Jet Loads ANSI 176 (draft) ANSI/ANS 68.2- Same method, Old 1988 standard superseded.
Pipe Whip Restraint PDA PDA Same Dynamic Structural Analysis SAP4G07 SAP4G07 Same
- Note 1 - The TRACG 04 allows the calculation of mass and energy (M&E) release rates to include the physical attributes of the piping system for both rated and off-rated conditions. TRACG eliminates unphysical and artificially imposed jumps in mass and energy. Providing estimates of M&E at off-rated and rated conditions addresses the concerns identified in GEH Safety Communication SC 09-01, Annulus Pressurization Loads Evaluation, dated June 8, 2009
- Note 2 - The use of the TRACG 04 vessel component together with a fine mesh model (336 nodes) of the LaSalle annulus provides a more detailed annulus pressurization response than the analysis of record, which uses a coarse node (35 node) RELAP 4/MOD 3 model.
Exelon0 Nuclear
Annulus Pressurization (AP) Loads Analysis Summary
- The application of TRACG for both the mass and energy release analysis and the annulus pressurization analysis is appropriate to provide a response frequency used in all downstream load analyses
- SC 09-01 will be addressed by analyzing the pipe breaks considered in the LaSalle design and licensing basis at various rated and off-rated operating conditions with bounding conditions being used in the downstream analysis
- Confirm NRC agreement that the above approach to calculation of AP Loads is acceptable Exelon Nuclear
-->a tJ) tJ)
-co J:
co c:
<< J:
(/)
J:
(/) E
- 11. co Z
(/) -->
~
U U
w
Purpose:
Verify methodology and Exelon's approach to perform NPSH analysis for a non-CAP credit plant is in accordance with NRC's expectations, and draft regulatory guidance Methodology
- SECY 11-0014, Use of Containment Accident Pressure in Analyzing Emergency Core Cooling System and Containment Heat Removal System Pump Performance in Postulated Accidents
- Event-specific analyses determine containment response
- Suppression Pool Temperature
- Event-specific NPSH a determined for each applicable event/pump
- Time in Maximum Erosion Zone Exelon Nuclear
ECCS NPSH Analysis Key Assumptions
- No Containment Accident Pressure
- Deterministic analysis with conservative inputs for DBA-LOCA, ASDC and Small Break LOCA.
- Vendor supplied NPSHr 3% curves
- 21 % uncertainty for NPSHreff for DBA-LOCA, ASDC and Small Break LOCA events
- Assumes minimum Suppression Pool Inventory (level) for all events
- All events are evaluated at 102 % of EPU power Exelon Nuclear
ECCS NPSH Analysis Preliminary Results Event Pump NPSHa NPSHreff Margin (Feet) (Feet) (Feet)
OSA-LOCA RHR 18.8 16.9 1.9 OSA-LOCA HPCS 19.7 6.1 13.6 OSA-LOCA LPCS 19.0 2.4 16.6 ASOC RHR 17.8 16.9 0.9 ASOC HPCS 17.5 6.1 11.4 ASOC LPCS 18.0 2.4 15.6 SSO RHR 19.2 14.0 5.2 SSO RCIC Analysis in Progress SBO HPCS 18.9 5.0 13.9 ATWS RHR 32.4 14.0 18.4 App R RHR 25.9 14.0 11.9 AppR HPCS 25.7 5.0 20.7 AppR LPCS 26.1 2.0 24.1
=
NPSHreft values consistent with draft guidance (NPSHreff NPSHr3% + uncertainties) including 21 % uncertainty for Design Basis Events and 0% uncertainty for non-Design Basis Events No modifications are required to achieve the above results Exelon Nuclear
- Exelon's approach to perform NPSH analysis is in accordance with NRC expectations and draft guidance
- Demonstrates that adequate positive margin exist for ECCS/RCIC pumps
- Demonstrates that ECCS/RCIC pumps will perform their safety functions
Future EPU Meeting Topics and Schedule
- Follow-up EPU Meetings
- Proposed Topics
- Steam Dryer Strategy and FIV Analysis
- Impact and Changes to Human Factors
- Impact on Primary Containment internal pressure (P a)
- Ultimate Heat Sink Analysis
- Setpoint Calculations
- Alternate Source Term Analysis
- Next meeting target February 2012 Exelon Nuclear
Meeting Summary
- Pilot Alignment and Outcome
- Discussion
- Checklist Mark-up
- Critique Exelon Nuclear
Acronym List
- ASDC - Alternate Shut Down Cooling
- CAP - Containment Accident Pressure
- CLTP - Current Licensed Thermal Power
- DBA - Design Basis Accident
- EPU - Extended Power Uprate
- ESBWR - Economic Simplified Boiling Water Reactor
- GEH - General Electric - Hitachi
- LAR - License Amendment Request
- LOCA - Loss of Coolant Accident
- LPCS - Low Pressure Core Spray
- LTR - Licensing Topical Report
- MWt - Mega Watts thermal
- NEI- Nuclear Energy Institute
- NPSH - Net Positive Suction Head
- NPSHa - Net Positive Suction Head available
- NPSHr - Net Positive Suction Head required
- NPSHreff - Effective Net Positive Suction Head required
- PUR - Power Uprate
- RAI - Request for Additional Information
- SBO - Station Black Out
- SC - GEH Safety Communication
- SECY - Commission Papers (Written issues papers the NRC staff submits to the Commission to inform them about policy, rulemaking, and adjudicatory matters)
Exelon Nuclear
The public was invited to observe the meeting. No members of the public were in.attendance.
Public Meeting Feedback forms were not received.
Please direct any inquiries to me at 301-415-1115, or Nicholas.DiFrancesco@nrc.gov.
Sincerely, IRA!
Nicholas DiFrancesco, Project Manager Plant Licensing Branch 111-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-373 and 50-374
Enclosures:
- 1. List of Attendees
- 2. Licensee Handout cc w/encl: Distribution via ListServ DISTRIBUTION:
PUBLIC RldsNrrDorlLpl3-2 Resource RidsRgn3MailCenter Resource LPL3-2 R/F RidsNrrPMLasalle Resource ASnyder. EDO Region III RidsNrrAdro Resource RidsOgcMailCenter Resource RidsNrrDori Resource RidsOpaMaii Resource Package Accession No. Ml120030332 Meeting Notice ML113200075 Meetlng
. S ummary ML120030321 NRC-001 OFFICE DORULPL3-2 PM DORULPL3-2/LA DORULPL3-2/BC DORULPL3-2/PM NAME NDiFrancesco SRohrer(BTully for) JZimmerman NDiFrancesco DATE 1/17112 1117112 1/18/12 1/19/12