Letter Sequence Supplement |
|---|
TAC:ME2531, Clarify Application of Setpoint Methodology for LSSS Functions (Approved, Closed) |
Administration
- Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance, Withholding Request Acceptance
- Meeting, Meeting
|
MONTHYEARGNRO-2009/00022, 2009-03 - NRC Written Examination Grade Report in Accordance with NUREG 1021, Revision 92009-03-0909 March 2009 2009-03 - NRC Written Examination Grade Report in Accordance with NUREG 1021, Revision 9 Project stage: Request ML0931404632009-11-0303 November 2009 License Amendment Request Regarding Power Range Neutron Monitoring System Upgrade Project stage: Request ML0934100662009-12-10010 December 2009 Acceptance Review of License Amendment Request for Power Range Neutron Monitoring System - Includes Revised Schedule for Completion Based on Late Submittal Project stage: Acceptance Review ML0931707702009-12-10010 December 2009 Request for Withholding Information from Public Disclosure - 10/1/2009 Affidavit Executed by E. Schrull, GE-Hitachi Nuclear Energy Americas LLC Project stage: Withholding Request Acceptance ML1000703852010-01-15015 January 2010 Request for Additional Information, License Amendment Request for Power Range Neutron Monitoring System Project stage: RAI ML1004308252010-02-0808 February 2010 Responses to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI ML1010902452010-04-22022 April 2010 Request for Additional Information Power Range Neutron Monitoring System Project stage: RAI ML1011901252010-05-0404 May 2010 Request for Additional Information, Round 3, License Amendment Request for Power Range Neutron Monitoring System Project stage: RAI ML1013805412010-05-17017 May 2010 Entergy Operations, Inc. - E-mail Attaching EOI and GE-Hitachi Nuclear Energy Presentation Slides and Affidavit Related to Meeting on May 25, 2010 Regarding Grand Gulf Nuclear Station, Unit 1 Project stage: Meeting ML1013805152010-05-17017 May 2010 GE-Hitachi Nuclear Energy Americas LLC Affidavit of Edward Schrull Request to Withhold from Public Disclosure, Enclosure 1 to GEH Letter GG-PRNM-168777-EC065, Grand Gulf Prnm Upgrade Project - Presentation for May 25, 2010, NRC Meeting Project stage: Meeting ML1014100942010-05-18018 May 2010 Responses to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI ML1013805592010-05-24024 May 2010 Request for Withholding Information from Public Disclosure Project stage: Withholding Request Acceptance ML1013804212010-05-25025 May 2010 Entergy Operations, Inc. and GE-Hitachi Nuclear Energy Slide Presentation for May 25, 2010 - NRC RAIs Regarding GGNS Prnm System LAR (Non-Proprietary) Project stage: Other ML1014703852010-05-25025 May 2010 Licensee Slides from 5/25/10 Meeting to Discuss Response to Requests for Additional Information on License Amendment Request for Digital Power Range Neutron Monitoring System (Nonproprietary Version) Project stage: Response to RAI ML1014704032010-05-25025 May 2010 Affidavit for 5/25/10 NRC Meeting to Discuss Response to Requests for Additional Information on License Amendment Request for Digital Power Range Neutron Monitoring System Project stage: Response to RAI GNRO-2010/00040, Responses to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System2010-06-0303 June 2010 Responses to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI ML1015202692010-06-0909 June 2010 5/25/2010 Summary of Meeting with Entergy Operations, Inc., to Discuss the Licensees Response to NRC Staffs Request for Additional Information Dated 5/4/2010 Installation of a Digital Power Range Neutron Monitoring System Project stage: RAI ML1018001492010-06-18018 June 2010 Schedule for Responding to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Request ML1017904372010-06-30030 June 2010 0000-0102-0888-RI, Plant-Specific Responses Required by Numac Prnm Retrofit Plus Option III Stability Trip Function Topical Report, (NEDC-3241OP-A) Project stage: Other ML1016703442010-07-0202 July 2010 Request for Withholding Information from Public Disclosure - GE-Hitachi Nuclear Energy Americas LLC Affidavit Dated 6/2/2010 Project stage: Withholding Request Acceptance ML1021500292010-07-29029 July 2010 Responses to NRC Request for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI ML1021404062010-08-10010 August 2010 Request for Withholding Information from Public Disclosure, E. Schrull, GE-Hitachi Nuclear Energy Americas LLC Affidavit Dated 7/23/2010 Project stage: Withholding Request Acceptance GNRO-2010/00064, Response to NRC Request for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System2010-09-29029 September 2010 Response to NRC Request for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI ML1027307312010-10-14014 October 2010 Request for Withholding Information from Public Disclosure, 9/28/2010 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC Project stage: Withholding Request Acceptance GNRO-2010/00075, Response to NRC Request for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System2010-12-13013 December 2010 Response to NRC Request for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI GNRO-2010/00070, Response to NRC Request for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System2010-12-14014 December 2010 Response to NRC Request for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI ML1111704242011-04-27027 April 2011 E-mail, Request for Additional Information, Round 4, License Amendment Request for Power Range Neutron Monitoring System Project stage: RAI ML1111704322011-04-27027 April 2011 Request for Additional Information, Round 4, License Amendment Request for Power Range Neutron Monitoring System Project stage: RAI GNRO-2011/00032, Responses to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System2011-05-0303 May 2011 Responses to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI ML1113204932011-05-12012 May 2011 E-mail, Request for Additional Information, Round 5, License Amendment Request for Power Range Neutron Monitoring System Project stage: RAI GNRO-2011/00038, Responses to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System2011-05-16016 May 2011 Responses to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI GNRO-2011/00039, Responses to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System2011-05-26026 May 2011 Responses to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI GNRO-2011/00042, Responses to NRC Requests for Additional Information Re License Amendment Request for Power Range Neutron Monitoring System2011-05-31031 May 2011 Responses to NRC Requests for Additional Information Re License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI ML1113905962011-06-0202 June 2011 Request for Withholding Information from Public Disclosure, 4/28/2011 Affidavit Executed by E. Schrull, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00032 Project stage: Withholding Request Acceptance ML1113906562011-06-0202 June 2011 Request for Withholding Information from Public Disclosure, 5/11/2011 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00038 Project stage: Withholding Request Acceptance GNRO-2011/00044, Responses to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System2011-06-13013 June 2011 Responses to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI ML1117402132011-06-23023 June 2011 Email, Request for Additional Information, Round 6, License Amendment Request for Power Range Neutron Monitoring System Project stage: RAI GNRO-2011/00045, Supplemental Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System2011-06-28028 June 2011 Supplemental Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Supplement GNRO-2011/00057, Response to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System2011-07-22022 July 2011 Response to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI GNRO-2011/00066, Response to NRC Request for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System2011-09-28028 September 2011 Response to NRC Request for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI GNRO-2011/00089, Response to NRC Request for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System2011-10-18018 October 2011 Response to NRC Request for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System Project stage: Response to RAI GNRO-2011/00090, Supplemental Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System (TAC No. ME2531) - Software Evaluation Report2011-10-26026 October 2011 Supplemental Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System (TAC No. ME2531) - Software Evaluation Report Project stage: Supplement GNRO-2011/00091, Supplemental Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System (TAC No. ME2531) – V&V Summary Test Report2011-11-0808 November 2011 Supplemental Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System (TAC No. ME2531) – V&V Summary Test Report Project stage: Supplement GNRO-2011/00110, Supplemental Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System (TAC No. ME2531) – V&V Summary Test Report2011-12-0101 December 2011 Supplemental Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System (TAC No. ME2531) – V&V Summary Test Report Project stage: Supplement ML1204406022012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 5/19/2011 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00039 Project stage: Withholding Request Acceptance ML1204406602012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 11/29/2011 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00110 Project stage: Withholding Request Acceptance ML1204406532012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 11/3/2011 Affidavit Executed by E. Schrull, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00091 Project stage: Withholding Request Acceptance ML1204406462012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 10/20/2011 Affidavit Executed by E. Schrull, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00090 Project stage: Withholding Request Acceptance ML1204406382012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 9/22/2011 Affidavit Executed by J. Harrison, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00066 Project stage: Withholding Request Acceptance ML1204406272012-02-27027 February 2012 Request for Withholding Information from Public Disclosure, 7/21/2011 Affidavit Executed by E. Schrull, GE-Hitachi Nuclear Energy Americas LLC, Attachment 1 to GNRO-2011/00057 Project stage: Withholding Request Acceptance 2010-07-29
[Table View] |
Text
When the Attachment is removed from this letter, the entire document is NON-PROPRIETARY.
The Attachment contains PROPRIETARY information.
GNRO-2011/00110 December 1, 2011 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555
SUBJECT:
Supplemental Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System (TAC No. ME2531) -
V&V Summary Test Report Grand Gulf Nuclear Station, Unit 1 Docket No. 50-416 License No. NPF-29
REFERENCES:
- 1. Entergy Operations, Inc. letter to the NRC (GNRO-2009/00054),
License Amendment Request - Power Range Neutron Monitoring System Upgrade, November 3, 2009 (ADAMS Accession No. ML093140463)
- 2. Entergy Operations, Inc. letter to the NRC (GNRO-2011/00057),
Response to NRC Requests for Additional Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System (TAC No. ME2531), July 22, 2011 (ADAMS Accession No. ML112061524)
- 3. Entergy Operations, Inc. letter to the NRC (GNRO-2011/00090),
Supplemental Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System (TAC No.
ME2531) - Software Evaluation Report, October 26, 2011 (ADAMS Accession No. ML113081234)
- 4. Entergy Operations, Inc. letter to the NRC (GNRO-2011/00091),
Supplemental Information Pertaining to License Amendment Request for Power Range Neutron Monitoring System (TAC No.
ME2531) - V&V Summary Test Report, November 8, 2011 (ADAMS Accession No. ML113130070)
Dear Sir or Madam:
In Reference 1, Entergy Operations, Inc. (Entergy) submitted to the NRC a license amendment request (LAR), which proposes to revise the Grand Gulf Nuclear Station (GGNS)
Technical Specifications (TS) to reflect the installation of the digital General Electric-Hitachi Entergy Operations, Inc.
P. O. Box 756 Port Gibson, MS 39150 Michael A. Krupa Director, Extended Power Uprate Grand Gulf Nuclear Station Tel. (601) 437-6694
GNRO-2011/00110 Page 2 of 3 (GEH) Nuclear Measurement Analysis and Control (NUMAC) Power Range Neutron Monitoring System (PRNMS).
In Reference 2, Entergy submitted to the NRC staff a response to a Request for Additional Information (RAI) pertaining to verification and validation (V&V) of software used in PRNMS.
In Reference 2, Entergy committed to provide to the NRC: (1) a software evaluation report; and (2) a V&V summary test report. The software evaluation report was submitted via Reference 3 as NEDC-33688P, Grand Gulf Nuclear Station Power Range Neutron Monitor Previously Developed Software Analysis and Report. NEDC-33688P documents the evaluation and analysis of previously developed software used in PRNMS since the NRCs approval of GEH Licensing Topical Report NEDC-32510P-A, Nuclear Measurement Analysis and Control Power Range Neutron Monitor (NUMAC PRNM) Retrofit Plus Option III Stability Trip Function, October 1995. It also documents the extent of independent module and integration testing required.
In Reference 4, Entergy submitted the companion V&V summary test report as GEH Report NEDC-33692P, Grand Gulf Nuclear Station Power Range Neutron Monitor V&V Test Summary Report. NEDC-33692P provides a summary of the V&V test program applied to PRNMS software used in the GGNS system. The results of the independent module and integration testing as determined in NEDC-33688P (the software evaluation report) are summarized in NEDC-33692P.
However, as discussed in various sections of NEDC-33692P, testing of the PRNMS 2-Out-Of-4 Logic Modules Programmable Logic Device (PLD) had not been completed at the time NEDC-33692P was submitted; therefore, it was not included in the report. This testing has since been completed and NEDC-33692P has been revised to reflect it. NEDC-33692P, Rev. 1 is provided in the attachment to this letter.
GEH considers NEDC-33692P, Rev. 1 to be proprietary in its entirety and, therefore, requests it be withheld from public disclosure in accordance with 10 CFR 2.390. The associated affidavit is also provided in the attachment. Because the entire report is proprietary, a non-proprietary, redacted version is not provided, as allowed by NRC Information Notice 2009-07, Withholding of Proprietary Information from Public Disclosure.
The No Significance Hazards Determination and the Environmental Consideration provided in Reference 1 are not impacted by this submittal.
This letter contains no new commitments.
If you have any questions or require additional information, please contact Mr. Guy Davant at (601) 368-5756.
I declare under penalty of perjury that the foregoing is true and correct; executed on December 1, 2011.
Sincerely, MAK/ghd
GNRO-2011/00110 Page 3 of 3
Attachment:
GEH Report NEDC-33692P, Grand Gulf Nuclear Station Power Range Neutron Monitor V&V Test Summary Report (GEH Proprietary Information) cc:
Mr. Elmo E. Collins, Jr.
Regional Administrator, Region IV U. S. Nuclear Regulatory Commission 612 East Lamar Blvd., Suite 400 Arlington, TX 76011-4005 U. S. Nuclear Regulatory Commission ATTN:
Mr. A. B. Wang, NRR/DORL (w/2)
ATTN:
ADDRESSEE ONLY ATTN:
Courier Delivery Only Mail Stop OWFN/8 B1 11555 Rockville Pike Rockville, MD 20852-2378 State Health Officer Mississippi Department of Health P. O. Box 1700 Jackson, MS 39215-1700 NRC Senior Resident Inspector Grand Gulf Nuclear Station Port Gibson, MS 39150