ML11116A141

From kanterella
Jump to navigation Jump to search
IR 05000461-11-009, on 03/18/11, Clinton Power Station, Routine Triennial Fire Protection Baseline Inspection
ML11116A141
Person / Time
Site: Clinton Constellation icon.png
Issue date: 04/25/2011
From: Robert Daley
Engineering Branch 3
To: Pacilio M
Exelon Generation Co
Loretta Sellers
References
IR-11-009
Download: ML11116A141 (24)


See also: IR 05000461/2011009

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

2443 WARRENVILLE ROAD, SUITE 210

LISLE, IL 60532-4352

April 25, 2011

Mr. Michael J. Pacilio

Site Vice-President, Exelon Generation Company, LLC

President and Chief Nuclear Officer (CNO), Exelon Nuclear

4300 Winfield Road

Warrenville IL 60555

SUBJECT: CLINTON POWER STATION FIRE PROTECTION TRIENNIAL BASELINE

INSPECTION NRC INSPECTION REPORT 05000461/2011009(DRS)

Dear Mr. Pacilio:

On March 18, 2011, the U.S. Nuclear Regulatory Commission (NRC) completed a triennial

fire protection inspection at your Clinton Power Station (CPS). The enclosed inspection

report documents the inspection results, which were discussed on March 18, 2011, with

Mr. F. Kearney and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

Based on the results of this inspection, one NRC-identified finding of very low safety

significance was identified. The finding involved a violation of NRC requirements. However,

because of the very low safety significance, and because the issue was entered into your

corrective action program, the NRC is treating the issue as a Non-Cited Violation (NCV) in

accordance with Section 2.3.2 of the NRC Enforcement Policy.

If you contest the subject or severity of these NCVs, you should provide a response within

30 days of the date of this inspection report, with the basis for your denial, to the U.S. Nuclear

Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with

a copy to the Regional Administrator, U.S. Nuclear Regulatory Commission - Region III,

2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement,

U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector

Office at Clinton Power Station. In addition, if you disagree with the cross-cutting aspect

assigned to any finding in this report, you should provide a response within 30 days of the date

of this inspection report, with the basis for your disagreement, to the Regional Administrator,

Region III, and the NRC Resident Inspector at Clinton Power Station.

M. Pacilio -2-

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter,

its enclosure, and your response (if any), will be available electronically for public inspection in

the NRC Public Document Room or from the Publicly Available Records System (PARS)

component of NRC's Agencywide Documents Access and Management System (ADAMS),

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA/

Robert C. Daley, Chief

Engineering Branch 3

Division of Reactor Safety

Docket No. 50-461

License No. NPF-62

Enclosure: Inspection Report 05000461/2011009

w/Attachment: Supplemental Information

cc w/encl: Distribution via ListServ

U.S. NUCLEAR REGULATORY COMMISSION

REGION III

Docket No: 50-461

License No: NPF-62

Report No: 05000461/2011-009(DRS)

Licensee: Exelon Generation Company, LLC

Facility: Clinton Power Station

Location: Clinton, IL

Dates: February 16 through March 18, 2011

Inspectors: Z. Falevits, Senior Reactor Inspector, Lead

A. Dahbur, Senior Reactor Inspector

R. Winter, Senior Reactor Inspector

L. Kozak, Senior Reactor Analyst

Observers: J. Hafeez, Reactor Engineer in Training

Approved by: R. Daley, Chief

Engineering Branch 3

Division of Reactor Safety

Enclosure

SUMMARY OF FINDINGS

IR 05000461/2011009(DRS); 02/16/2011 - 03/18/2011 Clinton Power Station, Routine Triennial

Fire Protection Baseline Inspection.

This report covers an announced triennial fire protection baseline inspection. The inspection

was conducted by Region III inspectors. One Green finding was identified by the inspectors.

The finding was considered a Non-Cited Violation (NCV) of NRC regulations. The significance

of most findings is indicated by their color (Green, White, Yellow, or Red) using Inspection

Manual Chapter (IMC) 0609, Significance Determination Process (SDP). Findings for which

the SDP does not apply may be (Green) or be assigned a severity level after NRC management

review. The NRCs program for overseeing the safe operation of commercial nuclear power

reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated

December 2006.

A. NRC-Identified and Self-Revealed Findings

Cornerstone: Mitigating Systems

  • Green. A finding of very low safety significance and associated NCV of Clinton Power

Station Unit 1 Operating License NPF-62, Section 2.F was identified by the inspectors

for the licensee's failure to ensure fire doors were closed and latched. Specifically,

during a walkdown of fire area CB-1e 737 General Access Area, fire door 1DR1-432

located between fire area CB-1e and D-6 Emergency Diesel 2 Room, was found

unlatched/not fully closed. The door was a 3-hour fire rated door credited for fire barrier

between the two fire areas. Site personnel closed the door when it was found open and

the door remained fully closed when challenged. The issue was entered into the

licensee corrective action program as AR 01187906.

The inspectors determined that this finding was more than minor because the finding

affected the Mitigating Systems cornerstone attributes of protection against external

factors (Fire) and affected the cornerstone objective of ensuring the capability of the

system to respond to events to prevent undesirable consequences. This finding

was of very low safety significance (Green) based on answering Yes to Question 7 of

Task 1.3.2. of Appendix F of IMC 0609. The inspectors did not identify a cross-cutting

aspect associated with this finding because the underlining cause of unlatched door was

indeterminate during the inspection. (Section 1R05.b(1))

B. Licensee-Identified Violation

No violations of significance were identified.

1 Enclosure

REPORT DETAILS

1. REACTOR SAFETY

Cornerstones: Initiating Events and Mitigating Systems

1R05 Fire Protection (71111.05T)

The purpose of the fire protection triennial baseline inspection was to conduct a design

based, plant specific, risk-informed, onsite inspection of the licensees fire protection

programs defense-in-depth elements used to mitigate the consequences of a fire. The

fire protection program shall extend the concept of defense-in-depth to fire protection in

plant areas important to safety by:

  • preventing fires from starting;
  • rapidly detecting, controlling and extinguishing fires that do occur;
  • providing protection for structures, systems, and components important to safety

so that a fire that is not promptly extinguished by fire suppression activities will not

prevent the safe shutdown of the reactor plant; and

  • taking reasonable actions to mitigate postulated events that could potentially cause

loss of large areas of power reactor facilities due to explosions or fires.

The inspectors evaluation focused on the design, operational status, and material

condition of the reactor plants fire protection program, post-fire safe shutdown systems

and B.5.b mitigating strategies. The objectives of the inspection were to assess

whether the licensee had implemented a fire protection program that: (1) provided

adequate controls for combustibles and ignition sources inside the plant; (2) provided

adequate fire detection and suppression capability; (3) maintained passive fire protection

features in good material condition; (4) established adequate compensatory measures

for out-of-service, degraded, or inoperable fire protection equipment, systems or

features; (5) ensured that procedures, equipment, fire barriers, and systems exist so that

the post-fire capability to safely shut down the plant was ensured; (6) included feasible

and reliable operator manual actions when appropriate to achieve safe shutdown; and

(7) identify fire protection issues at an appropriate threshold and ensured these issues

were entered into the licensees problem identification and resolution program.

In addition, the inspectors review and assessment focused on the licensees post-fire

safe shutdown systems for selected risk significant fire areas. Inspector emphasis was

placed on determining that the post-fire safe shutdown capability and the fire protection

features were maintained free of fire damage to ensure that at least one post-fire safe

shutdown success path was available. The inspectors review and assessment also

focused on the licensees B.5.b related license conditions and the requirements of

10 CFR 50.54(hh)(2). Inspector emphasis was to ensure that the licensee could

maintain or restore core cooling, containment, and spent fuel pool cooling capabilities

utilizing the B.5.b mitigating strategies following a loss of large areas of power reactor

facilities due to explosions or fires. Documents reviewed are listed in the Attachment to

this report.

2 Enclosure

The fire areas/fire zones and B.5.b mitigating strategies selected for review during this

inspection are listed below and in Section 1R05.6. The fire areas/fire zones and B.5.b

mitigating strategies selected, constitute four inspection samples and four inspection

samples, respectively, as defined in Inspection Procedure 71111.05T.

Fire Zone Description

A-3f Division 2 Switchgear Room

CB-1e General Access Area

CB-2 Division 2 Cable Spreading Room

CB-3a Auxiliary Electrical Equipment Room

.1 Protection of Safe Shutdown Capabilities

a. Inspection Scope

For each of the selected fire areas, the inspectors reviewed the fire hazards analysis,

safe shutdown analysis, updated final safety analysis report (UFSAR), and supporting

drawings and documentation to verify that safe shutdown capabilities were properly

protected.

The inspectors reviewed the licensees procedures and programs for the control of

ignition sources and transient combustibles to assess their effectiveness in preventing

fires and in controlling combustible loading within limits established in the fire hazards

analysis. The inspectors performed plant walkdowns to verify that protective features

were being properly maintained and administrative controls were being implemented.

The inspectors also reviewed the licensees design control procedures to ensure that the

process included appropriate reviews and controls to assess plant changes for any

potential adverse impact on the fire protection program and/or post-fire safe shutdown

analysis and procedures.

b. Findings

No findings were identified.

.2 Passive Fire Protection

a. Inspection Scope

For the selected fire areas, the inspectors evaluated the adequacy of fire area barriers,

penetration seals, fire doors, electrical raceway fire barriers, and fire rated electrical

cables. The inspectors observed the material condition and configuration of the installed

barriers, seals, doors, and cables. The inspectors reviewed approved construction

details and supporting fire tests. In addition, the inspectors reviewed license

documentation, such as NRC safety evaluation reports, and deviations from NRC

3

Enclosure

regulations and the National Fire Protection Association (NFPA) standards to verify that

fire protection features met license commitments.

The inspectors walked down accessible portions of the selected fire areas to observe

material condition and the adequacy of design of fire area boundaries (including walls,

fire doors, and fire dampers) to ensure they were appropriate for the fire hazards in the

area.

The inspectors reviewed the installation, repair, and qualification records for a sample of

penetration seals to ensure the fill material was of the appropriate fire rating and that the

installation met the engineering design.

b. Findings

1) Failure to Ensure Fire Door was Closed and Latched

Introduction: A finding of very low safety significance (Green) and associated NCV of

License Condition 2.F, Fire Protection, was identified by the inspectors for the licensee's

failure to ensure that fire door 1DR1-432, located between the Division 2 emergency

diesel generator (EDG) room (D 3-9) and control building corridor (D 3-13), was closed

and latched. The door provided a 3-hour fire barrier between these two separate fire

areas.

Description: On March 14, 2011, during a plant walkdown of the 737 Control Building,

General Access Area, fire door 1DR1-432 was observed not to be fully latched. When

noted, site personnel closed the door and the door remained closed/latched when it was

challenged. The door was a 3-hour fire rated door credited for fire barrier between the

two fire areas as discussed below.

Section 3.4.1.5 Fire Zone CB-1e; Elevation 737 and 751 General Access Area, of the

Appendix E of the fire protection report indicated that the portion of the south wall

adjacent to the diesel generators rooms were 3-hour fire rated. The zone included

Division 1 and 2 electrical cables and diesel generator associated motor control centers.

In the event of a fire in this fire zone, safe shutdown can be achieved using Method 2

and 3 as described in the safe shutdown analysis. An ionization fire detection system

and an automatic wet pipe sprinkler system were provided in this zone where cables for

both divisions were located.

Section 3.5.6.1 Fire Zone D-6a; Elevation 737 Division 2 Diesel Generator Room,

indicated that this zone housed the Division 2 diesel generator and its associated

support cables and equipment. Therefore, a fire in this zone may affect equipment relied

upon for method 2 safe shutdown due to fire damage. This fire zone was protected by

an automatic carbon dioxide (CO2) fire suppression system actuated by thermal

detectors.

The inspectors were concerned that with the door left unlatched, a fire could spread

between the two fire areas. The inspectors noticed that the licensee currently has an

open item in their corporate corrective action program to develop and implement a plan

to reinforce with site workers the need to challenge fire doors and write condition reports

if doors do not self close and latch.

4

Enclosure

On March 15, 2011, the inspectors questioned the licensee if a condition report was

written to document the issue related to the door being found open during the plant

walkdown on March 14, 2011. Subsequently, the licensee issued AR 01187906. The

inspectors were concerned that the licensee was not timely in entering this issue into

their corrective action program.

Procedure 9601.05 Visual Inspection of Closed Fire Doors, was last completed on

March 13, 2011, at which time door 1DR1-432 was verified closed and latched.

Analysis: The inspectors determined that the licensees failure to ensure a 3-hour fire

door was closed and latched was contrary to Licensee Condition 2.F. and was a

performance deficiency. The finding was determined to be more than minor because it

was associated with the Mitigating System cornerstone attribute of Protection Against

External Factors (Fire) and affected the cornerstone objective of ensuring the availability

of systems that respond to initiating events to prevent undesirable consequences (i.e.,

core damage). Specifically, the failure to ensure that a 3-hour rated fire door was closed

and latched between Fire Areas D-6 and CB-1e degraded the defense and depth

element of the fire protection program. In the event of a fire in the EDG room (Fire Area

D-6), the fire could spread to the control building corridor (CB-1e) and could have

complicated safe shutdown of the plant.

In accordance with IMC 0609, Significance Determination Process, Attachment

0609.04, Phase I - Initial Screening and Characterization of Findings, Tables 3b the

inspectors determined the finding degraded the fire protection defense-in-depth

strategies. Therefore, screening under IMC 0609, Appendix F, Fire Protection

Significance Determination Process, was required. Based on Table 1.1-1 of Appendix F

and Table A2.2 of Attachment 2 of Appendix F, the inspectors determined that the

finding affected the fire confinement category and the barrier was moderately degraded

because the door was not latched. Since the EDG room has a curb included in the wall

between the two fire areas that could contain the fuel oil available in the EDG, the

inspectors determined that in the event of a fire in the EDG room, the affect of a hot gas

layer was the only concern for the adjacent fire area CB-1e. The inspectors determined

that the finding was of very low safety significance (Green) because the inspectors

answered Yes to Question 7 of Task 1.3.2 Supplemental Screening for Fire

Confinement Findings. In addition, Table 2.3.2 of IMC 0609, Appendix F, showed that

for a 2MW fire in the EDG room, the zone of influence in the adjacent room (CB-1e) for

damage to thermoset cables was 13.3 feet in height and 6.7 feet in radial distance. The

Division 1 cables were located in cable trays and conduits installed near a wide ceiling

area in CB-1e; therefore, the cables of concern were outside the zone of influence and

would not be directly affected by a fire in the EDG room (Fire Area D-6). The inspectors

also determined that the finding only affected one of the defense-in-depth elements of

the fire protection program; because both fire areas had fully functional automatic fire

detection and suppression systems.

The licensee entered this issue into their corrective action program on March 15, 2011,

a day after the door was found unlatched and after the inspectors prompted the licensee

to issue a corrective action document. The inspectors did not identify a cross-cutting

aspect associated with this finding because the underlining cause of unlatched door was

indeterminate during the inspection.

5

Enclosure

Enforcement: Clinton Power Station Unit 1 Operating Licensee Condition 2.F.

required the licensee to implement and maintain in effect all provisions of the

approved fire protection program as described in the Final Safety Analysis Report

(UFSAR), as amended, and as approved in the Safety Evaluation Report (NUREG-

0853), dated February 1982 and Supplemented Numbers 1 through 8. The Clinton

Power Station UFSAR, Appendix E, Fire Protection Evaluation Report, Section 3.4.1.5,

Fire Zone CB-1e, stated, in part, that the portion of the south wall adjacent to the EDG

rooms is 3-hour fire rated. Section 3.1.2.2.9, Fire Doors, of Appendix E, stated, in part,

that access opening in the fire barrier walls is closed with fire rated doors or equivalent.

Contrary to the above, on March 14, 2011, the licensee failed to ensure that the 3-hour

fire rated door 1DR1-432, located in the portion of the south wall between the EDG room

(Fire Area D-6) and the control building corridor (Fire Area CB-1e) was closed and

latched. Because this violation was of a very-low-safety significance and because it was

entered into the licensees Corrective Action Program as AR 01187906, this violation is

being treated as an NCV, consistent with Section 2.3.2 of the NRC enforcement policy.

(NCV 05000461/2011009-01, Failure to ensure fire door was closed and latched)

.3 Active Fire Protection

a. Inspection Scope

For the selected fire areas, the inspectors evaluated the adequacy of fire suppression

and detection systems. The inspectors observed the material condition and

configuration of the installed fire detection and suppression systems. The inspectors

reviewed design documents and supporting calculations. In addition, the inspectors

reviewed license basis documentation, such as, NRC safety-evaluation reports,

deviations from NRC regulations, and NFPA standards to verify that fire suppression and

detection systems met license commitments.

b. Findings

No findings were identified.

.4 Protection from Damage from Fire Suppression Activities

a. Inspection Scope

For the selected fire areas, the inspectors verified that redundant trains of systems

required for hot shutdown would not be subject to damage from fire suppression

activities or from the rupture or inadvertent operation of fire suppression systems

including the effects of flooding. The inspectors conducted walkdowns of each of the

selected fire areas to assess conditions such as the adequacy and condition of floor

drains, equipment elevations, and spray protection.

b. Findings

No findings were identified.

6

Enclosure

.5 Alternative Shutdown Capability

a. Inspection Scope

The inspectors reviewed the licensees systems required to achieve alternative safe

shutdown to determine if the licensee had properly identified the components and

systems necessary to achieve and maintain safe shutdown conditions. The inspectors

also focused on the adequacy of the systems to perform reactor pressure control,

reactivity control, reactor coolant makeup, decay heat removal, process monitoring, and

support system functions.

The inspectors conducted selected area walkdowns to determine if operators could

reasonably be expected to perform the alternate safe-shutdown procedure actions and

that equipment labeling was consistent with the alternate safe shutdown procedure. The

review also looked at operator training, as well as consistency between the operations

shutdown procedures and any associated administrative controls.

b. Findings

No findings were identified.

.6 Circuit Analyses

a. Inspection Scope

The inspectors reviewed the licensees post-fire safe shutdown analysis to verify that the

licensee had identified both required and associated circuits that may impact safe

shutdown. On a sample basis, the inspectors verified that the cables of equipment

required achieving and maintaining hot shutdown conditions, in the event of fire in the

selected fire zones, had been properly identified. In addition, the inspectors verified

whether these cables had either been adequately protected from the potentially adverse

effects of fire damage, mitigated with approved manual operator actions, or analyzed to

show that fire-induced faults (e.g., hot shorts, open circuits, and shorts to ground) would

not prevent safe shutdown. In order to accomplish this, the inspectors reviewed

electrical schematics and cable routing data for power and control cables associated

with each of the selected components.

In addition, the adequacy of circuit protective coordination for the safe shutdown

systems electrical power and instrumentation busses was evaluated. The inspectors

also evaluated cable trays that contained both safe shutdown and non-safe shutdown

cables for proper circuit protection to ensure that cables were protected by a proper

protective device in order to preclude common enclosure concerns.

1) Review of Licensees Multiple Spurious Operations (MSOs) Circuit Analyses In

Accordance with Guidance in Regulatory Guide 1.189, Revision 2

Background

In October 2009 the NRC issued guidance in Regulatory Guide 1.189, Fire Protection

for Nuclear Power Plant, Revision 2, to identify acceptable methods for resolving issues

7

Enclosure

related to circuits required for post-fire safe shutdown and circuits important to post-fire

safe shutdown. Equipment required for post-fire safe shutdown (credited train) must use

one of the three methods identified in 10 CFR Part 50, Appendix R, Section III.G.2 to

protect the circuits located within the same fire area from damage, including single and

multiple spurious operations (MSOs). For important to post-fire safe shutdown circuits,

the licensee may use operator manual actions if the licensee demonstrates they can be

shown to be feasible and reliable or resolve issues using other analysis methods

including fire modeling.

In May 2009, the NRC issued Enforcement Guidance Memorandum 09-002,

Enforcement Discretion for Fire-Induced Circuit Faults, which described the conditions

limiting enforcement discretion during the resolution of the fire protection concerns

involving MSOs. The EGM limited the enforcement discretion to three years from the

date of issuance of RG 1.189, Revision 2: (1) six months following the issuance of

RG 1.189, Revision 2, for licensees to identify non-compliances related to multiple fire-

induced circuit faults, place the non-compliances into their corrective action program and

implement compensatory measures for the non-compliances and (2) three years

following the issuance of RG 1.189, Revision 2, for licensees to complete the corrective

actions associated with non-compliant multiple fire-induced circuit faults. The

enforcement discretion would not be granted to identified non-compliances that are

found to be willful or findings that the Reactor Oversight Process Significant

Determination Process would evaluate as (Red) or categorized at Severity Level I.

Inspection Effort

During this inspection, the inspectors reviewed representative sampling of single and

multiple spurious issues throughout the plant to verify:

  • The licensee successfully addressed single and multiple spurious issues in a way

that met regulations;

  • The licensee properly classified equipment required for safe shutdown and

equipment important for safe shutdown;

  • The adequacy of the licensees evaluation of multiple spurious actuations, in

accordance with Regulatory Guide 1.189 and NEI 00-01, Revision 2; and

  • The adequacy of the licensees compensatory actions taken for identified non-

compliances.

The inspectors reviewed the licensees post-fire safe shutdown analysis to verify that

the licensee had identified both required and important circuits that could impact safe

shutdown. The inspectors reviewed the Clintons expert panel results for the potential

fire-induced operations of component supported safe shutdown at CPS. The expert

panel performed this review in accordance with RG 1.189 and Guidance provided in

NEI 00-01 Revision 2. The purpose of the expert panel was to review the applicable

industry developed Generic BWR Owners Group List of MSOs for applicability to CPS.

The expert panel was also tasked with considering plant specific MSOs similar to those

in the Generic List, but not specifically listed. The expert panel identified MSOs as

applicable to CPS and provided recommendations to resolve these issues. The

8

Enclosure

inspectors reviewed a sample of MSO scenarios identified by the expert panel as

potential non-compliances requiring further evaluations to determine corrective action

needed.

The inspectors verified that the safe shutdown cables had either been adequately

protected from the potentially adverse effects of fire damage, mitigated with approved

compensatory measures, or analyzed to show that fire-induced faults (e.g., hot shorts,

open circuits, and shorts to ground) would not prevent safe shutdown. In order to

accomplish this, the inspectors reviewed piping and instrumentation diagrams (P&IDs),

electrical schematics and logic diagrams, Safe Shutdown flow diagrams and cable

routing data sheets associated with each of the selected safe shutdown components. In

addition, the adequacy of electrical circuit protective coordination for the reviewed safe

shutdown systems components was evaluated by sampling.

The licensee initiated 27 ARs to document the identified non-conforming MSO

scenarios. In addition, the licensee implemented alternate compensatory measures as a

form of documented operator rounds as justified by the fire protection engineering

evaluation EC-EVAL 379435, GL 86-10 Evaluation: Use of Alternate Compensatory

Measures Related to Multiple Spurious Operations (MSOs), Revision 1. The inspectors

reviewed a sample of the nonconforming MSO scenarios identified by the licensee. The

inspectors noted that the licensee has not completed the analyses and evaluations of

the identified non-conforming MSOs. The licensee was in the process of determining

the appropriate long term corrective actions needed to address these findings. The

documents and ARs reviewed by the inspectors are listed in the Attachment to this

report. The licensee plans to identify and complete corrective actions to address the

identified MSOs prior to November 2, 2010, (the end of the enforcement discretion

period per EGM 09-002). The licensee evaluated the identified MSO scenarios for

potential significance and determined that none of the 27 identified MSOs were

considered to be risk significant.

b. Findings

No findings were identified.

2) Review of Licensee Actions to Address a Post-Fire Safe Shutdown MSO Scenario

Documented in NRC URI 461/2005-006-01(DRS)

(Open URI 461/2005-006-01(DRS): During the 2005 FP inspection, the NRC inspectors

performed an independent review of post-fire safe shutdown circuit analysis, using the

guidance and criteria provided in NRC Regulatory Issue Summary (RIS) 2004-003,

Revision 1, Risk-Informed Approach for Post-Fire Safe Shutdown Circuit Inspections,

dated December 29, 2004. The inspectors postulated a fire in the Division III

switchgear room, located in Fire Zone CB-5a, and determined that it could result in

multiple fire-induced electrical circuit faults in the control logic cables used in the

Division III High Pressure Core Spray (HPCS) Pump 1E22-C001 and discharge

Valve 1E22-F004 control logic. The inspectors determined that postulating such

multiple spurious faults could impair the capability to shut off the HPCS pump and stop

it from continually injecting and overfilling the reactor pressure vessel (RPV).

9

Enclosure

The licensee documented in calculation IP-0532, 10 CFR Part 50, Appendix R,

Compliance Assessment, that any and all spurious operations or failures shall be

evaluated and that the spurious actuations or failures are not required to be

evaluated simultaneously except for high/low pressure interface components.

However, the licensee also documented that they did consider the potential for

concurrent/simultaneous spurious actuations or failures in the Appendix R analysis for

the ECCS system automatic initiation instrumentation logic network, as well as the

high/low pressure interface components.

At the time of the inspection, the inspectors determined that documented evidence

was not available to show that the licensee considered the potential hot shorts, shorts

to ground and open circuits, postulated by the team, in the multi-conductor control

cables used in the control logic of HPCS pump 1E22-C001 and pump discharge valve

1E22-F004.

On June 8, 2005, the licensee, RIII, and NRR fire protection staff members conducted a

conference call to further discuss the concerns raised by the team. The NRC requested

that the licensee evaluate the postulated scenarios provided by the team and determine

if CPS can achieve and maintain safe shutdown in Fire-Zone CB-5a if HPCS injection

cannot be stopped, and if CPS is within their licensing basis considering the electrical

faults and fire-induced actuations of HPCS components. The licensee entered this issue

in their Corrective Action Program under CR 00343489, dated June 13, 2005.

During this current inspection, the team reviewed the licensees response to address the

NRC finding documented in the URI. The team noted that the licensee had identified a

similar finding during their MSO analysis and evaluation of automatic initiation logic

instrumentation logic cables related to the high drywell pressure or low RPV level

instrument loop logic. On April 7, 2010, the licensee initiated AR 01053529, MSOPS

Scenario 2U - Spurious HPCS/HPCI Operation, to document this similar finding to the

one documented in the NRCs URI. The AR stated that further work was needed to

resolve the Safe Shutdown Analysis (SSA) that evaluated the potential for spurious

HPCS initiation due to fire damage to the initiation logic, instrumentation wiring, pump

breaker wiring, and injection valve wiring and ensure the new regulatory requirements

(i.e., RG 1.189, R2) are addressed.

Subsequently, on February 8, 2011, the licensee issued AR 01172335, RVW Identifies

Design Basis Issue for Spurious HP Operation, and Event Notification (EN) No. 46603,

to document an unanalyzed condition identified by the licensee. The EN reported that

an SSA assumed operator action to locally depress the HPCS internal trip plunger to trip

the pump breaker in response to a fire in the MCR and continuous operation of the

pump, could not be performed as stated in the written procedure. The unanalyzed

condition involved a postulated scenario where, in the event of a MCR fire, the HPCS

will continuously inject into the RPV due to fire-induced faults and instrument logic cable

damage, and place the Main Steam Safety Relief Valves (MSSRVs) and their associated

tailpipes in an unanalyzed condition for the stresses expected during the two-phase flow

event. The licensee promptly initiated a confirmatory analysis to evaluate this issue and

implemented compensatory measures for potential non-conforming MSOs until the

analysis is complete.

10

Enclosure

Unresolved item (URI) 461/2005-006-01(DRS) remains open pending review of results

of the licensees confirmatory analysis of the stresses expected on the MSSRVs and

their associated tailpipes. These stresses could potentially occur during the HPCS

injection and a two-phase flow event as a result of multiple fire-induced faults in the

instrument logic cables (refer to licensee MSO Scenario No. 2U) or in the HPCS pump

and valve control logic cables (refer to NRC URI).

.2 Communications

a. Inspection Scope

The inspectors reviewed, on a sample basis, the adequacy of the communication system

to support plant personnel in the performance of alternative safe shutdown functions and

fire brigade duties. The inspectors verified that plant telephones, page systems, sound

powered phones, and radios were available for use and maintained in working order.

The inspectors reviewed the electrical power supplies and cable routing for these

systems to verify that either the telephones or the radios would remain functional

following a fire.

b. Findings

No findings were identified.

.3 Emergency Lighting

a. Inspection Scope

The inspectors performed a plant walkdown of selected areas in which a sample of

operator actions would be performed in the performance of alternative safe shutdown

functions. As part of the walkdown, the inspectors focused on the existence of sufficient

emergency lighting for access and egress to areas and for performing necessary

equipment operations. The locations and positioning of the emergency lights were

observed during the walkdown and during review of manual actions implemented for the

selected fire areas.

b. Findings

No findings were identified.

.4 Cold Shutdown Repairs

a. Inspection Scope

The inspectors reviewed the licensees procedures to determine whether repairs were

required to achieve cold shutdown and to verify that dedicated repair procedures,

equipment, and material to accomplish those repairs were available onsite. The

inspectors also evaluated whether cold shutdown could be achieved within the required

time using the licensee's procedures and repair methods. The inspectors also verified

that equipment necessary to perform cold shutdown repairs was available onsite and

properly staged.

11

Enclosure

b. Findings

No findings were identified.

.5 Compensatory Measures

a. Inspection Scope

The inspectors conducted a review to verify that compensatory measures were

in place for out-of-service, degraded or inoperable fire protection and post-fire safe

shutdown equipment, systems, or features (e.g., detection and suppression systems,

and equipment, passive fire barriers, pumps, valves or electrical devices providing safe

shutdown functions or capabilities). The inspectors also conducted a review on the

adequacy of short term compensatory measures to compensate for a degraded function

or feature until appropriate corrective actions were taken.

b. Findings

No findings were identified.

.6 B.5.b Inspection Activities

a. Inspection Scope

The inspectors reviewed the licensees preparedness to handle large fires or explosions

by reviewing one or more mitigating strategies as identified below. This review ensured

that the licensee continued to meet the requirements of their B.5.b related license

conditions and 10 CFR 50.54(hh)(2) by determining that:

  • Procedures were being maintained and adequate;
  • Equipment was properly staged, maintained, and tested;
  • Station personnel were knowledgeable and could implement the procedures; and
  • Additionally, inspectors reviewed the storage, maintenance, and testing of B.5.b

related equipment.

The inspectors reviewed the licensees B.5.b related license conditions and evaluated

selected mitigating strategies to ensure they remain feasible in light of operator training,

maintenance/testing of necessary equipment and any plant modifications. In addition,

the inspectors reviewed previous inspection reports for commitments made by the

licensee to correct deficiencies identified during performance of Temporary Instruction

(TI) 2515/171 or subsequent performances of these inspections.

The B.5.b mitigating strategies selected for review during this inspection are listed

below. Note: The off-site and onsite communications, notifications/ERO activation,

initial operational response actions, and damage assessment activities identified in

Table A.3-1 were evaluated during the review of the Command and Control

Enhancements Strategy.

12

Enclosure

NEI 06-12, Selected for

Revision 2 Licensee Strategy (Table) Review

Section

2.2 SFP Makeup - Internal Strategy (Table A.2-1) Selected

3.2.2 to 3.2.5 Command and Control Enhancements (Table A.3-1) Selected

BWR Enhancement Strategy No. 3 Utilize Feedwater

3.4.3 and Condensate (Table A.5-3) Selected

BWR Enhancement Strategy No. 8 Manually Open

3.4.8 Containment Vent Lines (Table A.5-8) Selected

b. Findings

No findings were identified.

4. OTHER ACTIVITIES

4OA2 Problem Identification and Resolution (71152)

a. Inspection Scope

The inspectors reviewed the licensees Corrective Action Program Procedures and

samples of corrective action documents to verify that the licensee was identifying issues

related to the fire protection program at an appropriate threshold and entering them in

the corrective action program. The inspectors reviewed selected samples of condition

reports, design packages, and fire protection system non-conformance documents.

b. Findings

No findings were identified.

4OA6 Management Meetings

.1 Exit Meeting Summary

The inspectors presented the inspection results to Mr. F. Kearney and to other members

of the licensee staff on March 18, 2011, and during subsequent telephone calls with

licensee representatives on March 24, 2011, and on April 13, 2011. The licensee

acknowledged the issues presented.

The inspectors confirmed that none of the potential report input discussed was

considered proprietary.

4OA7 Licensee-Identified Violations

No violations were identified.

ATTACHMENT: SUPPLEMENTAL INFORMATION

13

Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

F. Kearney, Site Vice-President

M. Kanavos, Plant Manager

R. Zadislski, Manager, Nuclear Oversight Manager

T. Chalmers, Director, Operations

R. Frantz, Regulatory Assurance

K. Baker, Sr. Manager, Design Engineering

G. Mosley, Engineering Programs Manager

S. Fatora, Maintenance Director

C. Dunn, Shift Operations Superintendent

J. Ruth, Operations Training Manager

J. Ufert, Fire Marshall

Nuclear Regulatory Commission

B. Kemker, Senior Resident Inspector

LIST OF ITEMS OPENED, CLOSED AND DISCUSSED

OPENED

05000461/2011009-01; Failure to Ensure Fire Door was Closed and

NCV

Latched.(Section 1R05.2.b(1))

Closed

05000461/2011009-01; Failure to Ensure Fire Door was Closed and Latched.

NCV

(Section 1R05.2.b(1))

Discussed

05000461/2005006-01; Review of Licensee Action to Address a Post-Fire Safe

URI

Shutdown MSO Scenario. (Section 1R05.2b(2))

LIST OF DOCUMENTS REVIEWED

The following is a list of documents reviewed during the inspection. Inclusion on this list does

not imply that the NRC inspectors reviewed the documents in their entirety, but rather, that

selected sections of portions of the documents were evaluated as part of the overall inspection

effort. Inclusion of a document on this list does not imply NRC acceptance of the document or

any part of it, unless this is stated in the body of the inspection report.

ANALYSES, CALCULATIONS AND STANDARDS

Number Description or Title Date or Revision

480 ESF SWGR Breakers and Associated Upstream 12

19-AN-04

eRelay Setting

IP-M-0471 Safe Shutdown Equipment Selection 2

EE-01.00 Safe Shutdown Cable Selection 1

H600.Y35 Automatic Sprinkler, FP Hydraulics, Auxiliary Bldg 0

H706.B01 Automatic Sprinkler, FP Hydraulics, Control Bldg 1

Automatic Sprinkler, FP Hydraulics, Auxiliary Electric 1A

H727.B02

Equipment Room

CONDITION REPORTS (ARs) ISSUED DURING INSPECTION

Number Description or Title Date or Revision

RVW Identifies Design Basis Issue for Spurious Hp

01172335 02/08/2011

Operation

01175632 NRC FP Insp. -- Paint Chips in Floor Drain 781 Control Bldg 02/15/2011

01176329 B.5.B Pump Implementation Strategy Enhancement 01/13/2011

NRC FP Triennial IDD - TSC Copy of 4303.01F001 not

01176370 02/16/2011

Readily Available

NRC FP Triennial IDD - B.5.B Pump Operating Procedure

01176393 02/16/2011

not Staged at Pump Location

NRC FP Triennial IDD - Enhance B.5.B Strategies per

01176407 02/16/2011

Procedure

4303.01 for RCIC Verification

01177009 1FP02E NRC FP Triennial IDD - Enhance 4303.01P009 02/17/2011

01177205 Status of Cable Cannot be Determined 02/18/2011

01177206 Construction ERA Wood in Cable Tray 02/18/2011

01180184 NRC FP TRI - FECN Not Posted 02/25/2011

01180220 Suppression Effects Calc Weaknesses 02/25/2011

2011 FP Triennial Issue Regarding BOP UPS 1IP06E and

01181956 03/01/2011

1IP07E

01181876 NRC FP TRI - Cable Pull Box Number is Incorrect 03/01/2011

NRC FP TRI ID - USAR App E 3.4.3.1 Fire Detection

01183043 03/03/2011

Incorrect

01183546 NRC FP TRI ID - Enhancement to 4003.01C002 03/03/2011

01186553 FP Licensing Basis Documents not Readily Available 03/03/2011

01187430 NRC FP TRI ID - Lanyard on Cable Tray Hanger 03/14/2011

1 Attachment

Number Description or Title Date or Revision

01187435 NRC FP TRI - Thermo-Leg Cable Tray Discrepancies 03/14/2011

01187906 NRC FP TRI - Div. 2 DG Fire Door Found Unlatched 03/15/2011

01188547 NRC FP TRI - Housekeeping Above AB Battery Rooms 03/16/2011

01188935 NRC FP TRI - Drawings Identified Again as Having

03/17/2011

Incorrect

01188952 NRC FP TRI - Margin Discussion is Missing from Sprinkler

03/17/2011

Calc

Elevation Description

CONDITION REPORTS (ARs) REVIEWED DURING INSPECTION

Number Description or Title Date or Revision

01053529 Evaluate HPCS MSO April 7, 2010

01053473 MSOPS 2L - Spurious RH Min. Flow Close With Spurious April 7, 2010

Pump Start

01053407 MSOPSUse of Alternate Compensatory Measures for MSO April 7, 2010

00985851 Coordinate Fleet Actions for RG 1.189/NEI 00-01 October 29, 2009

01053473 MSOPS 2L - Spurious RH Min Flow Close with Spurious Pump October 07, 2010

Start

01053538 MSOPS 2Y - RCIC Test Flow to CST Stop/Throttle Vlvs Flow April 07, 2010

Diversion

01029032 NOS ID Unauthorized BISCO Seal Penetration February 11, 2010

01135002 FP FASA Walkdown Identified Improperly Breached Nov. 3, 2010

Penetration

01149954 ILL61BP06E Safe S/D Pathway Light Trickle Chg Lamp not lit Dec. 8, 2010

01153758 Fire Doors not Kept Closed Dec 17, 2010

01172335 RVW Identifies Design Basis Issue for Spurious HP Operation February 8, 2011

DRAWINGS

Number Description or Title Date or Revision

E26-1003-03A-E1 Electrical Installation Aux Bldg El 781 3 AG

Fire Detection System, Aux Bldg Switchgear Floor A

E26-1003-03A-FP

Plan El 781 0

Fire Detection System, Aux Bldg Switchgear Floor A

E26-1003-03A-FP

Plan El 790 0

Pre-Fire Plan, Auxiliary Building, Containment Pipe 1

Fire Zone A-3F

Penetration, El. 364- 0

Fire Zone CB-1e Pre-Fire Plan, 737 Control Building, General Access 6a

Fire Zone CB-1e Pre-Fire Plan, 751 Control Building, HVAC Mezzanine 6

Pre-Fire Plan, 781 Control Building Div 2 Cable 5a

Fire Zone CB-2

Spreading Room

Pre-Fire Plan, 781 Control Building Auxiliary Electrical 7a

Fire Zone CB-3a

Equipment , Inverter and Battery Rooms

M05-1039; sh, 008 P&ID Fire Protection (FP) Turbine Bldg AL

M05-1056 sh. 002 P&ID Plant Service Water AL

2 Attachment

Number Description or Title Date or Revision

Key Diagram, Control Building MCC G and H W

E02-0AP24

(0AP56E and 0AP57E)

M05-1075 P&ID - Residual Heat Removal (RH) AW

Residual Heat Removal Shutdown Cooling Upper K

E02-1RH99

Pool Valves 1E12-F037A and 1E12-F037B

E30-1003-04A- Electrical InstallationControl Bldg Cable Spreading AF

E1 Room

E03-0AP56E External Wiring Diagram - Control Building MCC G M

(0AP56E)

E02-0AP24 Key Diagram - MCC G and H (0AP56E and 0AP57E) 1

CPS-SSD-LOG- Containment and Reactor Vessel Monitoring System 2

301 Safe Shutdown Logic Diagram

CPS-SSD-LOG- Reactor Core Isolation Cooling Safe Shutdown Logic 2

102 Diagram

M05-1079 P&ID Reactor Core Isolation Cooling (RCIC) AJ

MODIFICATIONS/ENGINEERING CHANGES

Number Description or Title Date or Revision

EC 383184 Design Bases Issues for Spurious HP Operations 0

Fire Protection With Alternate Comp Measures for 0

EC 383133

Spurious HPCS Ops.

GL 86-10 Evaluation: Use of Alternate Compensatory 001

EC 379435 Measures Related to Multiple Spurious Operations

(MSO)

3822.04C003 Quarterly B.5.b Equipment Checklist 1d

3822.04C006 Quarterly OCA/NTD Fire Cage Checklist 2e

9277.11C001 Hose Replacement Checklist 24b

9601.05C001 Closed Fire Door Inspection Checklist 31a

9601.06C001 Semi-Annual Fire Door Operability Checklist

CC-AA-201 Plant Barrier Control Program 8

OP-AA-201-009 Control of Transient Combustible Materials 11

OP-MW-201-007 Fire Protection System Impairment Control 7

PROCEDURES

Number Description or Title Date or Revision

3822.04C003 Quarterly B.5.b Equipment Checklist 1d

3822.04C006 Quarterly OCA/NTD Fire Cage Checklist 2e

9277.11C001 Hose Replacement Checklist 24b

9601.05C001 Closed Fire Door Inspection Checklist 31a

9601.06C001 Semi-Annual Fire Door Operability Checklist 30c

CC-AA-201 Plant Barrier Control Program 8

OP-AA-201-009 Control of Transient Combustible Materials 11

3 Attachment

Number Description or Title Date or Revision

OPOP-MW-201- 7

Fire Protection System Impairment Control

007

9601.05 Visual Inspection of Closed Fire Doors March 13, 2011

4303.01P020 Emergency Confirmation of Reactor Scram 0a

WORK ORDERS

Number Description or Title Date or Revision

01162683 01 9601.01C003 Accessible Group 1 Penetration Fire August 17, 2009

Seal Inspections

01170437 01 9601.01C009 Inaccessible Group 1 Penetration Fire January 07, 2010

Seal Inspections

01170408 01 9601.01C003 Accessible Group 1 Penetration Fire April 13, 2010

Seal Inspections

01354876 04 Install BISCO Seal CB-781-09-1063 TS-EC 380713 September 17, 2010

Number Description or Title Date or Revision

AR 01056005-02 2010 Focused Area Self-Assessment November 18, 2010

Fire Protection Safe Shutdown Analysis Clinton

USAR Apx. F Power Station Unit 1 14

NEI 00-01 Apx.

G Generic List of MSOs 2

ATI 1165189 Perform CCA on TCFZ Issues February 15, 2011

Report an Unanalyzed Condition Concerning HPCS

EN No. 46603 Injection Scenario February 15, 2011

Slice Version 7.6 Cable Tabulation-Main File (S101-1) Pg. HP 14 September 29, 2010

CPS-SSD-LOG- HPCS SRV and Containment Spray and Initiation

302 Safe Shutdown Logic Diagram 2

E02-1HP99 High Pressure Core Spray (HP) (NSPS) (1E22-

Sh.5 1050) G

E02-1HP99 High Pressure Core Spray (HP) (NSPS) (1E22-

Sh.6 1050) D

E02-1HP99 High Pressure Core Spray (HP) (NSPS) (1E22-

Sh.7 1050) L

E02-1HP99 High Pressure Core Spray (HP) (NSPS) (1E22-

Sh.110 1070) H

High Pressure Core Spray (HP) HPCS Suction

E02-1HP99

Valve (1E22-F001) and HPCS Pump Disch Valve

Sh.501 J

(1E22-F004)

4 Attachment

LIST OF ACRONYMS USED

ADAMS Agencywide Documents Access and Management System

AR Action Request

CFR Code of Federal Regulations

CO2 Carbon Dioxide

CPS Clinton Power Station

DRS Division of Reactor Safety

EDG Emergency Diesel Generator

EN Event Notification

ESF Engineered Safety Features

HPCS High Pressure Core Spray

IMC Inspection Manual Chapter

IR Inspection Report

kV KiloVolt

MCC Motor Control Center

MCR Main Control Room

MSO Multiple Spurious Operations

MSSRV Main Steam Safety Relief Valves

NCV Non-Cited Violation

NEI Nuclear Energy Institute

NFPA National Fire Protection Association

NRC U.S. Nuclear Regulatory Commission

NUREG NRC Technical Report

PARS Publicly Available Records

P&ID Piping and Instrumentation Diagram

RIS NRC Regulatory Issue Summary

RPV Reactor Pressure Vessel

SDP Significance Determination Process

SER Safety Evaluation Report

SPAR Standardized Plant Analysis Risk

SRA Senior Reactor Analyst

SRP Standard Review Plan

SSA Safe Shutdown Analysis

UFSAR Updated Final Safety Analysis Report

URI Unresolved Item

5 Attachment

M. Pacilio -2-

of this inspection report, with the basis for your disagreement, to the Regional Administrator,

Region III, and the NRC Resident Inspector at Clinton Power Station.

In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter,

its enclosure, and your response (if any), will be available electronically for public inspection in

the NRC Public Document Room or from the Publicly Available Records System (PARS)

component of NRC's Agencywide Documents Access and Management System (ADAMS),

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA/

Robert C. Daley, Chief

Engineering Branch 3

Division of Reactor Safety

Docket No. 50-461

License No. NPF-62

Enclosures: Inspection Report 05000461/2011009(DRS)

w/Attachment: Supplemental Information

cc w/encl: Distribution via ListServ

DISTRIBUTION:

See next page

DOCUMENT NAME: G:\DRSIII\DRS\Work in Progress\-CLINTON IR 2011- 009 FPI ZXF

Final.docx

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy

OFFICE RIII DRS RIII DRS RIII

NAME ZFalevits:ls RDaley

DATE 04/25/11 04/25/11

OFFICIAL RECORD COPY

Letter to Mr. Michael J. Pacilio from Mr. Robert C. Daley dated April 25, 2011.

SUBJECT: CLINTON POWER STATION FIRE PROTECTION TRIENNIAL BASELINE

INSPECTION NRC INSPECTION REPORT 05000461/2011009(DRS)

DISTRIBUTION:

Daniel Merzke

RidsNrrDorlLpl3-2 Resource

RidsNrrPMClinton Resource

RidsNrrDirsIrib Resource

Cynthia Pederson

Steven Orth

Jared Heck

Allan Barker

Carole Ariano

Linda Linn

DRSIII

DRPIII

Patricia Buckley

Tammy Tomczak

ROPreports Resource