Order (Revising Deadlines for Certain Mandatory Disclosures Hearing File Production, and Dispositive Motions.)
ML111040376
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 04/14/2011
From: Karlin A
Atomic Safety and Licensing Board Panel
To:
SECY RAS
References
RAS 19914, 50-275-LR, 50-323-LR, ASLBP 10-900-01-LR-BD01
Download: ML111040376 (4)


Text

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION ATOMIC SAFETY AND LICENSING BOARD Before Administrative Judges:

Alex S. Karlin, Chairman Nicholas G. Trikouros Dr. Paul B. Abramson In the Matter of Docket Nos. 50-275-LR and 50-323-LR PACIFIC GAS & ELECTRIC COMPANY ASLBP No. 10-900-01-LR-BD01 (Diablo Canyon Nuclear Power Plant, Units 1 April 14, 2011 and 2)

ORDER (Revising Deadlines for Certain Mandatory Disclosures, Hearing File Production, and Dispositive Motions)

The Initial Scheduling Order (ISO) in this proceeding established, inter alia, deadlines for the parties and the NRC Staff to make initial mandatory disclosures pursuant to 10 C.F.R.

§ 2.336, and for the NRC Staff to produce the hearing file pursuant to 10 C.F.R. § 2.1203(a).

ISO (Sept. 15, 2010) at 4-5 (unpublished). Subsequently, the Staff advised us that its environmental review would be delayed. On January 19, 2011, the Board revised the deadlines for making initial mandatory disclosures and providing the hearing file for Contentions EC-4 and TC-1. 1 These deadlines are now May 16, 2011, or thirty days after the Commission ruling on the contention, whichever is first to occur. Id. at 2.

The ISO also established ultimate deadlines for dispositive motions. For contentions based on 10 C.F.R. Part 51 or the National Environmental Policy Act, the ultimate deadline for dispositive motions was set at June 1, 2011. ISO at 17. For any other contention or issue, the 1

Licensing Board Order (Extending Deadline for Certain Mandatory Disclosures) (Jan. 19, 2011) at 1-2 (unpublished).

ultimate deadline for such motions was set at May 1, 2011. Id. at 17-18. These deadlines were based, in part, on the Staffs estimates concerning the timing of its safety and environmental reviews. Id. at 17 n.25, 18 n.26.

At this time the Board considers it prudent to revise the foregoing deadlines as follows.

The new deadlines for initial mandatory disclosures and production of the hearing file related to Contentions for EC-4 and TC-1, respectively, are September 30, 2011, or thirty days after the Commission ruling on the contention, whichever is first to occur.

Meanwhile, given recent events and potential delays associated with the Applicants and Staffs schedules herein, the ultimate deadlines for filing dispositive motions are temporarily lifted. 2 We expect to establish appropriate deadlines for such motions at a later date.

It is so ORDERED.

FOR THE ATOMIC SAFETY AND LICENSING BOARD

_________/RA/______________________

Alex S. Karlin, Chairman ADMINISTRATIVE JUDGE Rockville, Maryland April 14, 2011 2

See Letter from David A. Repka, Counsel for PG&E, to Licensing Board (Apr. 12, 2011) at 1-2.

UNITED STATES OF AMERICA NUCLEAR REGULATORY COMMISSION In the Matter of )

)

PACIFIC GAS AND ELECTRIC COMPANY ) Docket Nos. 50-275-LR and 50-323-LR

)

(Diablo Canyon Nuclear Power Plant, )

Units 1 and 2) )

CERTIFICATE OF SERVICE I hereby certify that copies of the foregoing ORDER (REVISING DEADLINES FOR CERTAIN MANDATORY DISCLOSURES, HEARING FILE PRODUCTION, AND DISPOSITIVE MOTIONS) have been served upon the following persons by the Electronic Information Exchange.

U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Atomic Safety and Licensing Board Panel Office of the General Counsel Mail Stop: T-3F23 Mail Stop: O-15D21 Washington, DC 20555-0001 Washington, DC 20555-0001 Alex S. Karlin, Chair Edward L. Williamson, Esq.

E-mail: alex.karlin@nrc.gov E-mail: edward.williamson@nrc.gov Susan Uttal, Esq.

Nicholas G. Trikouros E-mail: susan.uttal@nrc.gov E-mail: nicholas.trikouros@nrc.gov Maxwell Smith, Esq.

E-mail: Maxwell.smith@nrc.gov Paul B. Abramson Lloyd Subin, Esq.

E-mail: pba@nrc.gov E-mail: lloyd.subin@nrc.gov paul.abramson@nrc.gov Megan Wright, Esq.

E-mail: megan.wright@nrc.gov Jonathan Eser, Law Clerk Brian Newell, Paralegal E-mail: jonathan.eser@nrc.gov E-mail: bpn1@nrc.gov OGC Mail Center E-mail: OGCMailCenter@nrc.gov U.S. Nuclear Regulatory Commission U.S. Nuclear Regulatory Commission Office of Commission Appellate Adjudication Office of the Secretary of the Commission Mail Stop: O-16C1 Mail Stop: O-16C1 Washington, DC 20555-0001 Washington, DC 20555-0001 OCAA Mail Center Hearing Docket E-mail: ocaamail@nrc.gov E-mail: hearingdocket@nrc.gov

2 Docket Nos. 50-275-LR and 50-323-LR ORDER (REVISING DEADLINES FOR CERTAIN MANDATORY DISCLOSURES, HEARING FILE PRODUCTION, AND DISPOSITIVE MOTIONS)

Winston & Strawn, LLP Harmon, Curran, Spielberg, and Eisenberg Counsel for PG&E Counsel for San Luis Obispo Mothers 101 California Street For Peace San Francisco, CA 94111-5802 1726 M Street, N.W., Suite 600 David A. Repka, Esq. Washington, DC 20036 E-mail: drepka@winston.com Diane Curran, Esq.

Tyson Smith, Esq. dcurran@harmoncurran.com E-mail: trsmith@winston.com Carlos Sisco, Senior Paralegal E-mail: CSisco@winston.com Winston & Strawn, LLP 1700 K Street, NW Washington, DC 20006 Rachel Miras-Wilson, Esq.

E-mail: rwilson@winston.com San Luis Obispo Mothers for Peace 1123 Flora Road Arroyo Grande, CA 93420 Jill ZamEk, Esq.

jzk@charter.net

[Original signed by Nancy Greathead]

Office of the Secretary of the Commission Dated at Rockville, Maryland this 14th day of April 2011